Preliminary design
Perhitungan beban
Beban mati
Bridge Weight = 4110 kg
Runway Bridge = 66 kg/m ( IWF 400x200x8x13)
Beban hidup
Crane capacity = 5000 kg
P berat crane ( weight hoist) = 555 kg
P hook block weight = 50 kg
P foot walk = 100 kg
P crane sadle / trolley = 100 kg +
= 5805 kg
7038 1 2 1
Mfactored = 2(4,5) × (4,5 − 2) + 8 x 66 x 4,52 x 1,2
= 12712,5 kg.m
λ
Vultimate = P × (2 − L)
1000
= 7038 × (2 − 4500)
= 12512 kg
o Cek rasio terhadap lebar ( flange)
𝑏 𝐸 𝐸
≤ 0,38 √𝐹𝑦 ≤ 1,00 √𝐹𝑦
𝑡
100 200000 200000
13
≤ 0,38 √ 450
≤ 1,00 √ 450
ℎ 𝐸 𝐸
≤ 3,76 √𝐹𝑦 ≤ 5,70 √𝐹𝑦
𝑡
342 200000 200000
8
≤ 3,76√ 450
≤ 5,70 √ 450
= 1076944 mm4
𝐼𝑥 23700 x 104
Sx = = 200
= 1185000 mm3
𝑦0
Zx = bt (d-t) + 0,25wh2
= 1240128 mm3
ℎ2 𝑏3 t (400−13)2 𝑥 2003 x 13
Cw = =
24 24
= 6,489 x 1011
400−13
ho = 2
= 193,5 mm
1 1
𝐼𝑦 2 1740 𝑥 104 2
ry = (𝐴) = ( 84,1 𝑥 102 )
= 45,49 mm
= 475312,5 N = 47531,25 kg
Rn = 0,9 x 47531,25
= 42778,125 Kg
ℎ⁄
= 𝐿𝑏 𝑡𝑤 ≤ 2,3
⁄𝑏𝑓
342⁄
8
= 4500⁄ ≤ 2,3
200
= 1,9 ≤ 2,3
3
𝐶𝑟 𝑡𝑤 3 𝑡𝑓 ℎ⁄
𝑡𝑤
Rn = [1 + 0,4 (𝐿𝑏 ) ] , Cr = 6,62 x 106 MPa
ℎ2 ⁄𝑏𝑓
342⁄ 3
6,62 𝑥 106 𝑥 83 𝑥 13 8
= [1 + 0,4 (4500⁄ ) ]
3422 200
= 388916,68 N = 38891,7 Kg
Vn = 0,6 x fy x Aw x Cv
Aw = 2 ht
= 2 x (342) x 8
= 5472 mm2
ℎ 𝐾𝑣 𝐸
Cv2 Jika ≤ 1,1 √ Kv = 5
𝑡𝑤 𝐹𝑦
342 5 𝑥 200000
≤ 1,1 √
8 450
42,75 ≤ 51,85
Cv2 =1
Vn1 = 0,6 x fy x Aw x Cv
= 0,6 x 450 x 5472 x 1
= 1477440 N
= 14774 kg
Vu ≤ Ø Vn1
12512 kg ≤ 0,9 x 14774 kg
12512 kg ≤ 13296,6 kg OK
Menghitung Reaksi
R = ½ x q x L2 + V
= ½ x 66 x 4,52 + 12512
= 13848,5 kg
= 13,85 ton