Sunteți pe pagina 1din 3

p12-14.

qxd 04/08/2005 17:09 Page 1

PLANT SAFETY

The Train 7 Fire at PETRONAS’ LNG Complex, Bintulu, Malaysia


Norrazak Hj. Ismail, MLNG Tiga Sdn Bhd, PETRONAS and Thomas Roy Stuart, Foster Wheeler Energy Ltd, Malaysia

A major fire occurred in 2003 in the exhaust system of the propane compressor gas turbine in the first train
(train 7) of the MLNG Tiga project. The authors describe the consequences of the accident, the analysis
of the causes, the management of the plant recovery process, and the re-design of the system in
both train 7 and train 8 to ensure enhanced integrity and increased safety.

T
he PETRONAS LNG Complex in lems encountered. In accordance with the the exhausts of the main turbine drivers The natural gas escaping from the
Bintulu, Malaysia covers a land area recovery plan, the facility managed to of the refrigeration compressors. Hot oil regeneration coil mixed with the air inside
of 276 hectares and with a com- resume its normal operation in April for general heating duties and hot natural the WHRU that was still at a very high
bined production capacity of about 23 mil- 2004, three weeks ahead of the original gas for regeneration of dryers recover the temperature, near the normal operating
lion tonnes per annum (Mtpa), it is the target of seven months. exhaust heat with the use of heat exhaust temperature of 570 °C. High
world's largest LNG export facility in a exchanger coils. The exhaust gas from the pressure leaking gas, mostly methane
single location. It is made up of three LNG Overview of the Train 7 C3 GT passes through an exhaust plenum (CH4+), only required 4% volume in air to
plants (see Figure 1): Fire Incident and then splits in a Y piece to enter the reach its lower flammability limit and auto
„ Malaysia LNG Sdn Bhd (Trains 1, 2 and In March 2003, Train 7 of MLNG Tiga two halves of the Waste Heat Recovery ignition temperature of 537 °C. This was
3), which began operation in 1983. plant had started its operation. It had suc- Unit (WHRU). Each half contains a achieved and led to an explosion inside
„ Malaysia LNG Dua Sdn Bhd (Trains 4, cessfully passed its performance test in regeneration gas coil and 5 hot oil coils. A the WHRU.
5, and 6), which began operation in June 2003 and was soon to be offered for schematic of the arrangement is shown
1994 provisional acceptance to the owner. Two in Figure 3. Damages Occurred
„ Malaysia LNG Tiga Sdn Bhd (Trains 7 months later, the Propane Compressor The regeneration coil has an inlet and „ The WHRU ducting was damaged
and 8), which began operation in 2003. Gas Turbine (C3 GT) exhaust system of outlet header with 32 tubes connecting beyond repair
them, each tube with a U bend at the top. „ The hot oil coils were damaged beyond
The entire regeneration coil, including the repair
headers, is housed within the WHRU „ The regeneration coils were recoverable
duct. Under normal operation, the duct, „ The gas turbine plenum was extensive-
which is refractory lined, reaches temper- ly damaged
atures in excess of 500 °C. „ The housing around the compressor /
Prior to the incident, unbeknown to turbine was extensively damaged
the operations personnel, a crack had „ The compressor was undamaged but
developed in the joint between the tube needed to be stripped down for
and header of the regeneration gas coil. examination
This leakage was not obvious to the „ The turbine moved on its base but only
Operator from the instrumentation sustained damage to ancillary equip-
arrangement but could be detected on the ment. It required disassembly for
instrument records during subsequent internal inspections
investigations. „ The building suffered superficial
The propane compressor and turbine damage
experienced a trip that was unrelated to „ No injury occurred to any personnel.
the gas leakage. This resulted in fuel
gas to the turbine shutting off and the Recovery Process
turbine speed running down before In an effort to recover production safely in
Figure 1: Overview of the PETRONAS LNG complex stopping. The procedure was then for the quickest possible time, it was decided
the turbine to go into a slow rotation of to establish multiple teams to tackle the
6 rpm using the barring motor, which various challenges. The teams included:
successfully occurred. Because of the „ Initial Investigation Team to find the
rotation of the turbine blades and the root cause
chimney effect of the turbine exhaust „ Business Recovery Team
stack, air was drawn in through the tur- „ Interim Production Study Team
bine and into the exhaust duct. During „ Demolition Team
slowing down (about 14 minutes), the „ Engineering Team to develop a safe
oxygen (O2) content rose from 14% in redesign
normal operation to 21% by the intake of „ Reconstruction Team
fresh air through the gas turbine air „ Re-HAZOP Team
intake compressor „ Insurance Claim Group

Figure 3: Side View of MLNG Tiga C3 GT, WHRU, Exhaust System, and Incinerator

Figure 2: Top View of MLNG Tiga C3 GT Exhaust Plenum Damage

The MLNG Tiga project has a total Train 7 was involved in a fire incident
annual capacity of 7.8 Mtpa for two (Figure 2). It occurred on 16 August 2003
trains, which are among the largest ever at 22:21 hours and led to a temporary
built. The application of several signifi- shutdown of the train. After thorough
cant innovative ideas makes this project investigation and analysis, appointed
one of the most significant achievements teams identified the specific damages
in the LNG industry. A fire at the MLNG that had occurred and developed a step-
Tiga plant in August 2003, however, by-step recovery process to ensure that
forced a temporary shutdown for repairs. the Train 7 could resume operation
This article provides a thorough analysis quickly and safely.
of the incident and the enhanced modifi- The design utilised within the MLNG
cations instigated in resolving the prob- Tiga plant seeks to recover the heat from

LNG journal July/August 2005 page 12


p12-14.qxd 04/08/2005 17:09 Page 2

LNGjournal
The participating personnel were from duration for reconstruction of Train 7 to allow this operating mode were imple- team to place and expedite orders for
the following: WHRU section was twelve months, main- mented and the revised target for interim replacement parts. Critical items were
„ Owner : MLNG Tiga ly due to the long delivery of the replace- production was set at seven months. regularly air freighted. The purchase
„ Operator: MLNG ment hot oil coils. The original coils could A large number of equipment items order for WHRU ducting was placed
„ EPCC Contractor: JGC / KBR / SIME not be reused due to the extensive dam- were associated with the GE / Nuovo with Ishikawa Heavy Industries (IHI)
„ Project Management Consultant: Foster age. Analysis by the Interim Production Pignone compressor turbine arrange- within a very short schedule as agreed.
Wheeler / OGP Technical Services Team concluded that by sharing hot oil ment, particularly the exhaust arrange- The WHRU ducting was completed on
„ Technical Services: Shell Global Solu- from Train 8, Train 7 could operate near ment on the turbine outlet. Nuovo time and was transported by a specially
tions International to its full capacity. Piping modifications Pignone established a special task force chartered ship travelling non-stop from
Whilst the plant had
commenced operation,
contractually it still
remained the EPCC Con-
tractor's responsibility
to repair the damage.

We make successful
1. technology
However, the majority
of the costs were recover-
able against the owner's
Construction All Risks
Insurance.
natural gas projects
As soon as access was
possible to the regeneration
as easy as....
2. experience
coil, the crack between the
tube and header was
observed and extensive stud-
ies conducted into the design
of the coil. During normal
operation the coil undergoes
several heating and cooling
cycles per day and high
stresses occur. However, the
area where the failure hap-
pened has relatively low
stress factors.
A section of the coil was
3. execution
sent to The Welding Insti-
tute in the United Kingdom
for analysis. The tube to
header joint was section-
alised and examined. It
could be clearly seen from a
connection adjacent to the
failed weld that the root
pass had not been carried
out correctly. Several other
such joints were examined
and found to be poorly
welded. The failed weld
connection was maintained
by a very small section of
weld that was sufficient to
withstand hydrostatic pres-
sure test but not the cyclic
stresses induced during
operation as shown in Fig-
ure 4. This type of weld
cannot be fully tested using
radiographs, whilst Ultra-
sonic Testing (UT) is not n competitive rowing, This “reinvestment” in our people
suitable for use with incol-
loy material. The inadequa-
I each stroke has three parts—
drive, finish, recovery. How each
and services gives us the flexibility
to deliver the same high level of
cy of the weld could have
been determined during the crewmember performs deter- support simultaneously to
inspection of the root weld. KBR Energy and Chemicals is a division of Halliburton. mines if the crew finishes first projects worldwide.
The redesign team select- © 2005 Halliburton. All rights reserved.
in a race…or merely finishes.
ed the use of nipolets
Contact KBR today and start a
between the header and
tubes to allow easier welding For 40 years, KBR has competed discussion on how, working
and full radiographic testing in the race to meet the world's together, we can pull your gas
of each joint. The original onshore and offshore gas monetization efforts in the
Gas Monetization Headquarters
design of welding is shown development needs. Our three right direction.
601 Jefferson Avenue
in Figure 5 and the new Houston, Texas USA 77002-7990 part approach—develop leading
design is shown in Figure 6. Tel: 713.753.2000 • Fax: 713.753.5353
Additional springs were technologies, share experience
added to the coil supports to United Kingdom and knowledge among our
eliminate the high stresses M.W. Kellogg Limited personnel, execute the project,
experienced elsewhere in the Kellogg Tower repeat—has helped KBR build
coil (the U bend at the top of Greenford Road
the coil). Greenford UB6 OJA United Kingdom one of the deepest engineering
The original estimated Tel: 44.208.872.7000 • Fax: 44.208.872.7272 talent pools in the industry.

LNG journal July/August 2005 page 13


p12-14.qxd 04/08/2005 17:09 Page 3

PLANT SAFETY

because the regeneration coil will always


be depressurised during a C3 GT trip or
shutdown.
When the C3 GT is starting up an
explosive mixture can form if a fully pres-
surised Regeneration Coil is leaking. This
is due to lower C3 GT Exhaust Gas flow
and higher oxygen content in the WHRU.
For this reason a permissive is provided
whereby the regeneration coil can only be
pressurised once the C3 GT reaches 95% of
its full operating speed.

Conclusion
The inspection plan for the regeneration
coil was adequate but due to the complex-
ity of the weld details and the critical
Figure 4: Cross Sectionalised between the Tube and Header of the
Original Weld Figure 5: Original Welding Design between the Header and Tubes nature of the equipment, additional sur-
veillance should have been carried out in
the fabrication workshop. The redesign of
HAZOP team recommended that consid- the mass flowrate through the regenera- the tube to header connection is vastly
eration should be given to locating the coil tion coil to vary quickly between approx- superior to the original design and facili-
header and connection outside the waste imately 0-1400 tonnes/day. For this tates the application of Non Destructive
heat recovery duct. reason the mass flow differential input Examination (NDE) reducing the need for
C3 GT Trip or shutdown: With refer- to the new safeguarding system is tem- day-to-day surveillance.
ence to Figure 7, when the C3 GT trips or porarily inhibited until steady flow The damages of the Train 7 fire inci-
shuts down the new safeguarding sys- resumes. This inhibition only lasts dent at the Petronas LNG Complex were
tem automatically closes valves A to D, for a few minutes of the 8-hour Drier repaired successfully. Instead of the esti-
thus preventing further Regeneration Bed cycle. mated twelve months of the recovery
Gas and Purge Gas entering the regener- Low pressure: Once the pressure drops process, Train 7 managed to be brought
ation coil. Next valve E is opened, allow- to a low enough level (approximately 70% back into production within seven
ing the regeneration coil to fully depres- of the normal operating pressure, as meas- months. The multiple teams established
surise to flare. Extra isolation is provid- ured by P1) the new safeguarding system in the recovery process shared the
ed as inlet valves FC1 and FC2 are also initiates the same response as flow differ- common objective of getting the plant
Figure 6: Improved Welding Design that closed. The check valve provides suffi- ential instrument (FD). Again, if P1 con- onto line quickly and safely again.
use Nipolets between the Header and cient extra isolation on the regeneration tinues to indicate falling pressure, hence a These teams, who were made up of
Tubes coil outlet. leaking regeneration coil, manual depres- the best members from each organisa-
tion, worked together in an environment
where information was shared freely
Japan to Bintulu. Owner's spare parts with an excellent spirit of co-operation.
were utilised within the rebuild wherev- It saved a lot of time, energy and cost
er they were available. as duplication of effort was appropriate-
The co-operation of all parties was ly avoided. Decisions were made quick-
essential to complete the project and the ly and followed up with the most suit-
success was measured by an efficient and able actions.
safe start-up three weeks ahead of the The outcome of the investigations pro-
target. vided an improved welding design of the
regeneration coil and also a new safe-
The Re-Hazop Analysis guarding system that not only is useful
The MLNG Tiga LNG liquefaction train for rebuilding of Train 7, but was also of
design utilises Propane Compressor Gas use for Train 8. These modifications were
Turbine (C3 GT) Exhaust Gas duty to immediately incorporated into the adja-
regenerate the Drier Beds. C3 GT cent Train 8 that was ready to enter serv-
Exhaust Gas passes through a WHRU, ice and later made to Train 7 prior to its
which contains the Regeneration Coil restart. Besides the long hours of work,
(heat exchanger used to provide the nec- the teams also took ownership of the
essary heat input for regenerating the dri- Figure 7: Regeneration Coil Isolation and Depressurising problem. This helped to expedite the
er beds). When the C3 GT trips and there recovery of Train 7 and the facility man-
is a Regeneration Coil tube leak an explo- aged to resume its normal operation safe-
sive mixture can form in the WHRU. The High flow differential: Figure 7 shows a surisation would then follow. ly three weeks ahead of the original tar-
Re-HAZOP team recommended a new flow differential instrument (FD), which Start up/Shutdown: The question of get of seven months. Currently, both
safeguarding system such that, in the measures the difference between regener- when to pressurise the regeneration coil Train 7 and 8 are in operation producing
event of a hazardous situation arising, ation coil inlet and outlet mass flowrate. If had to be addressed as part of the new a total annual capacity of 7.8 Mtpa as the
the regeneration gas in the coil should be the differential exceeds approximately safeguarding system design. This is design intends. „
isolated (using existing motorised valves) 15% the new safeguarding system auto-
and then vented from the coil (via a new matically initiates the closure of valves A
relief system). Depressurisation of the to D as per the C3 GT trip or shutdown Norrazak Hj. Ismail is the General Man- Roy Stuart is a Senior Project Manager
regeneration coil was initiated by a C3 scenario where extra isolation is provided ager for PETRONAS Malaysia LNG Tiga with Foster Wheeler. He has an Honours
GT trip or shutdown; or by high differen- by inlet valves FC1 and FC2 and the outlet Sdn. Bhd. He has a Bachelor of Science in Degree in Mechanical Engineering from
tial flow between the inlet and the outlet check valve. Chemical Engineering from the University Loughborough University, England and is a
of the regeneration coil; or by the loss of However, in this case valve E remains of East London, England. He has been Chartered Engineer and Member of the Insti-
pressure in the regeneration coil. The closed unless the operator chooses to man- tution of Mechanical Engineers. He has 20
with PETRONAS for 20 years in the gas
new system employed the existing ually depressurise the regeneration coil. years experience in the Oil and Gas Con-
business and for the last 13 years in LNG
process instrumentation around the The operator monitors the new regenera- tracting Industry, completing projects for
Projects as Process/Commissioning and
regeneration coil. tion coil inlet pressure instrument (P1); if many of the major oil companies. From 2002
Start-up Manager for Malaysia LNG Dua until 2004, he resided in Bintulu, Malaysia
These modifications were immediately it indicates falling pressure, hence a leak-
Plant Project. In 1995 he was appointed where he was the Project Manager of the
incorporated into the adjacent Train 8 that ing regeneration coil, manual depressuri-
General Manager for Malaysia LNG Tiga Project Management Consultant for the con-
was ready to enter service in two months sation would then follow.
Project. struction of Train 7 and Train 8 of the
time and later made to Train 7 prior to its As the Drier Bed sequence proceeds,
restart. For future designs, the Re- transitions between certain steps allow Malaysia LNG Tiga Project.

LNG journal July/August 2005 page 14

S-ar putea să vă placă și