Documente Academic
Documente Profesional
Documente Cultură
Presented By :
Client: Swiss Re Akshay Aman
Project Manager: RWG Associates
Charu Kumari
Architect: Foster and Partners
Structural Engineer: Arup
Manisha Nimesh
Building Services Engineer: Hilson Moran Partnership Sharda Bhagat
Cost consultant: Gardiner & Theobold Vikram Bengani
Disclaimer
BUILDING OF THE GHERKIN Second IRA bombing. St. Mary Axe street
facade of Baltic exchange was completely
The beginning of the Gherkin's birth starts in 1992 as an blown off. APRIL 1993
explosion rocked the financial district of London. The
Provisional IRA detonated an explosive device near the Baltic
Exchange and catastrophically injured the building. The
building was torn down and city officials decided to put a
larger tower in its place. Foster started working on the
The Gherkin began as a much larger building that was dubbed Millennium Tower right after English
the "Millennium Tower" but which failed to materialise. The Heritage accepted demolition of the
original design of the building raised fears that it could The Baltic Exchange.(MARCH 1996)
negatively impact air traffic from Heathrow. There were also London Millennium Tower(400m)
concerns that it may interfere with the sight-lines of St. Paul's planning application. August 1996
Dome from certain parts of the city. Once the original design
was shot down, Norman Foster created the scaled-down
version that now sits at 30 St Mary Axe.
Construction began in 2001 and the Gherkin was finished in
Entire project of the Millennium Tower abandoned when it was decided that
December of 2003. It didn't open for the public until almost
Swiss Re will buy the site from Kvaerner on condition that planning permission
half of a year later.
to knock down Baltic exchange was granted. Late 1997
In response to Norman Foster's Millennium Tower and 30 St
Mary Axe Proposal, the English Heritage supported newer
buildings, but perceived threat of tall buildings. SAVE Britain's
Heritage also played a heavy opposition role over Swiss Re hinted that unless it was allowed to
construction of any new architecture. build Norman Foster's distinctive circular tower
With demand for space for new offices, Swiss Re claimed
('the Gherkin') on the site of the old Baltic
that it should be allowed to build "the Gherkin" on the
Exchange, it would take itself, its jobs and its
site, with economic benefit of its jobs, and a huge
huge investment in the UK economy back to
investment in the UK economy back to mainland Europe.
mainland Europe. Early 1998
• Total = 64,470 m²
• Office 46,450 m2
• Retail 1,400 m2
•Office floor-floor: 4.15 m
•Gross superstructure floor area (incl. lightwells): 74,300 m2
•Tower Structural Steelwork
•Total weight of steel (from Arup Xsteel model): 8,358
tonnes of which:
Ground floor and first floor consist of reception and a series The design provides column-free floor space, light and views,
of shops at outer edge of the building with the arcade. and incorporates many sustainable building design features.
Third to sixteenth floor is the office of swiss re insurance Spiralling light wells allow the maximum amount of sunlight
company. to flood the interiors.
There are private dining area at 38-40 floors. Atria between the radiating fingers of each floor link
together vertically to form a series of informal break-out
The basement is used for the parking (only two wheelers , no spaces. Each floor rotates 5 degrees from the one below.
four wheelers are allowed in the parking).
6TH FLOOR PLAN
21ST FLOOR PLAN
33RD FLOOR PLAN
39TH FLOOR PLAN
40TH FLOOR PLAN
FRAMING PLANS
Footers Come here @ 10pts Footers Come here @ 10pts Footers Come here @ 10pts Leave This Empty !
12
Background of "diagrid" structure
The early era, tall building relied on portal frame and fix
joint to resist lateral and wind load. Latter the structure
build higher, more load and forces have to consider in the
structure. Additional bracing in the form of diagonal placed
in between the structure to take the lateral load. Portal
frames are insufficient in the lateral forces for the tall
building. Diagonal bracing make the structure resist wind
forces instead creating stronger frame connection.
Brace tube Structure
The braced tube structure John Hancock Building in Chicago was Brace Tube Structure
designed by Fazlur Kahn in, 1968. John Hancock Building,
Chicago
Diagrid tower is model as vertical cantilever. The size of diagonal grid is defined by
the dividing tower height into series of modules.
Diagrid “tube” does not have the sufficient strength to achieve stability in the
structure. Ring beam connection to the floor edge can tied diagrid with the floor and
the core.
Normally multiple floors interesting with each long diagonal of the grid, these
intersections will occur at the nodes as well as the several instances along the
diagonal.
When the diagonal bracing extends over several stories, each floor’s edge beam can
frame into the diagonal members providing connection the core to support the floor
edge beam.
“diagrid is a series of triangle that combine gravity and
lateral support into one, making the building to be stiff,
efficient, and lighter than a traditional high rise”
The base of the building have to designed to resist moment while the top have to
resist the shear force. As a result, the foundation of a diagrid system is more
concentrate on a point to reach stability
The diagonal members in diagrid carry shear and moment. The optical angle of
the diagrid will dependent on the building height and module. The expected
optimal angle for diagonal members for diagrid structure will fall in the range of
60° to 70°.
“ a pure steel diagrid tower doesnot require a core for lateral resistance ”
Diagrid nodes
(i) diagrid structure sit external and the envelope or curtain wall will clad on floor
structure,
(ii) diagrid structure sit internal and the envelope have to clad on the diagrid.
There are two main joint for the diagrid structure: welding or
bolting. This have to rely on the what appearance require for
the design. for example when the structure to be expose,
welding cans provides better aesthetic value.
Somehow, if the structure are to be clad or concealed like Welding joint for the Swiss Re
Hearts Tower, the diagrid can choose to bolted on site for Tower interior
speed erection.
Vertical Load
The gravity and vertical load from the building will distribute toward the apex of the
diagonal structure. Somehow, it will affected by the height and angle of the
diagonal.
The vertical forces will be divide/disperse into the other diagonal member.
Compression and tension result in the diagonal will transfer into the bottom
section.
Lateral Load
the lateral load happened toward the "flange" of the structure receiving directional
wind load. this will result the lateral load into two part; windward and leeward.
DEMERITS OF DIAGRIDS:
1) As of yet, the Diagrid Construction techniques are not thoroughly explored.
2) Lack of availability of skilled workers . Construction crews have little or no
experience creating a DiaGrid skyscraper.
3) The DiaGrid can dominate aesthetically, which can be an issue depending upon
design intent.
4) It is hard to design windows that create a regular language from floor to floor.
5) The DiaGrid is heavy-handed if not executed properly.
Diagrid (diagonal + grid) is a design for constructing large buildings with steel that
creates triangular structures with diagonal support beams. It requires less structural
steel than a conventional steel frame.Hearst Tower in New York City, designed by
Sir Norman Foster, reportedly uses 21 percent less steel than a standard design.
The Diagrid also obviates the need for large corner columns and provides a better
distribution of load in the case of a compromised building.
The perimeter ‘diagrid’ structure The perimeter steel structural solution was developed
specifically for this building in order to address the issues generated by the unusual geometry in
a manner that was fully integrated with the architectural concept and generated the maximum
benefit for the client.
The final solution was one of a number of approaches that were assessed in detail for overall
structural efficiency, internal plannning benefits, buildability, cost and risk. The design avoids
large cantilevers and keeps the light-wells free of floor structure by inclining the perimeter
columns to follow the helical path of the six-fingered floors up through the building.
The hoops also turn the diagrid into a very stiff triangulated shell, which provides excellent
stability for the tower. This benefit of the diagrid means that the core does not need to resist
wind forces and can be designed as an openplanned steel structure providing adaptable internal
space.
Foundation loads are also reduced compared with a building stabilised by the core.
STRUCTURAL ELEVATION
41
DIAGRID SYSTEM
INTERLOCKING DETAILS
A-frame • Aluminum coated tube steel • series
of two-stories-high, end to end arrangement. •
one full diamond is four-stories tall.
Footers Come here @ 10pts Footers Come here @ 10pts Footers Come here @ 10pts Leave This Empty !
43
DIAGRID SYSTEM
INTERLOCKING DETAILS
Footers Come here @ 10pts Footers Come here @ 10pts Footers Come here @ 10pts Leave This Empty !
44
0.02 - 0.06
coarse
mm
M 0.006 - 0.02
Fine medium
SILT mm
soils
0.002 -
fine
0.006 mm
CLAY < 0.002 mm
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year
Month of year
01 02 03 04 05 06 07 08 09 10 11 12 1-12
ELEVATORS IN BUILDING
FIRE FIGHTING METHODS:
• Swiss Re falls within the guidance of inner London Section 20 requirements for fire
safety.
The spiral lightwell
• Every sixth floor , the atria feature gardens which control and purify air movements as
arrangement allows for a fire
well as dividing the building into fire compartments.
escape strategy based on a
• The unusual light well arrangement leads to a fire escape strategy based on a variation
variation of phased evacuation.
of phased evacuation.
The building is divided into fire
• In this case all six floors linked by a set of light wells are evacuated in the case of a fire on
safety zones at every sixth and
any one of them.
second floor . this allows for
• Where only two floors are linked then those two constitute the first phase. So the light
the evacuation of one area at a
wells are designed following the guidance for simultaneous evacuation, which allows
time as opposed to a whole
them to be open to the accommodation.
building at once.
• Because the light well base floors are protected by sprinklers on the overhanging soffits
above, they can be used as office space too.
• A system of smoke curtains form smoke reservoirs in the light wells, and others delay the
transport of smoke from accommodation into the light wells.
• Natural ventilation is used for smoke clearance for the light wells and the accommodation.
• The building is sprinkle red, including arrays of window sprinklers on part of the façade of levels 2 and 3, to protect a glazed opening in the
compartment floor of level 4, directly above.
• However sprinklers have not been fitted in the 12m high domed space that forms the very top of the building.
• The Tower has two firefighting shafts with dedicated lifts.
• The use of dedicated smoke detectors in each lobby which cause the vent to open in that lobby, as well as at the top of the smoke shaft and the
top of the stair.
• During a fire temperatures can be such that the window glazing may break and thus allow cool air to enter and hot gas to escape.
• Alternatively, temperatures may be such that the fire has not engulfed a large area and is not severe enough to actually break the glass.
• In both cases the temperature reached in the compartment and the duration of a fire is dependent on the amount of ventilation, and it is
assumed that sprinkler activation has not prevented the fire from growing.
Architectural style
21st century contemporary iconic design
sustainable design features:
• maximising natural daylight and ventilation;
VENTILATION: AIR MOVEMENT THROUGH THE LIGHTWELL • minimising heating and cooling through a ventilated double-skin façade.
SUSTAINABLITY : THE GHERKIN
The tower is aerodynamically designed to reduce wind load on the structure,
whilst the lower part tapers so that wind wraps around the tower.
The six fingers of accommodation on each floor, configured with light wells
in between, maximize daylight penetration.
The façade design with advance glazing technologies, ventilated cavities and
blinds , provides up to 85% solar protection.
Gas is the main fuel used hence it will only generate half the carbon
emission.
Overall energy serving is up to 50%.
The façade consists of two layers of glass (the outer one double-glazed)
enclosing a ventilated cavity with computer-controlled blinds. A system of
weather sensors on the outside of the building monitors the temperature,
wind speed and level of sunlight, closing blinds and opening window panels
as necessary.
The building's shape maximises the use of natural daylight, reducing the
need for artificial lighting and providing impressive long-distance views even
from deep inside the building
The glass panels in the atriums are also tinted to reduce glare
and solar gain
THE SERVICE
CORE THE ELEVATORS- 18
PASSENGER LIFTS
THE OFFICE
AREA
THE CORE
The core takes a portion of the
vertical gravity loads and is a
secondary structure to the diagrid.
Provides rigidity
Resists torsion
Core area at centre
Increases stiffness
This building has a core 9 meters wide and 36 meters long split into
five separate sections to provide additional strength
MATERIALS
• 35 km of steel, 10 thousand tons were used to build the Swiss Re
• 24,000 square meters of glass were used for the exterior of the
building, equivalent to five football fields.
• The building was designed to use recycled or recyclable materials
whenever possible
• The glazing to the office areas consist of a double –glazed outer and a
single –glazed inner screen.
• Sandwiched in between is the ventilated cavity which reduces heating and
cooling requirements.
• The solar-control blinds intercept solar gain before it enters the office
environment.
Gherkin London.
Windows open on the
outer skin to allow air
to enter the cavity
Distance between each floor:4200mm
between the inner and
Each closed steel frame height: 16800mm
outer skin.
Each glass height: 4200mm
Other than one curved , other glass are all flat.
TOWER STRUCTURAL STEEL WORK
The heart consists of a solid block of steel of 240 by 140
mm.
Steel in foundation:
• 750mm diameter straight-shafted piles into London clay
• Number of piles: 333
• Total length of piles: 9km
• Total design capacity: 117,000 tonnes
Because of site restrictions and in order to create a monolithic foundation, all piles and pile
caps were poured in one day.
Façade material:
• Despite its curved shape, there is actually only 7,429 glass panes for external skin(recycled
one piece of curved glass – the lens at the top of glass) made from intersecting tubular steel
the building which is 2.4m in diameter and weighs sections which give vertical support to the
250kg. floors, rendering them column free. The grid is
highly resistant to wind loading and weighs
• The glass dome at the top of the building provides 2,500
360 degree views of London
EXTERNAL CLADDING SYSTEM
An aerodynamic
form, reducing
effects of wind
Wind load
The overall cylindrical shape allows for the wind
to move around the building.
How does this shape effect the horizontal wind
loads?
• Decreased buffeting
• Reduced vibrations
• Diminished fluttering
CONNECTIONS
Diagrid
• There is a special connector that transfers
loads, both vertically and horizontally at
the “nodes” which are rigid monolithic
and welded together.
• Rigid node connections at intersecting
members.
Core
• Rigid connections of steel beams and
columns.
NATURAL VENTILATION AND LIGHTING SYSTEM
Differing air pressures and double skin façade allow for natural ventilation
•Six spiralling light wells allow daylight to flood down onto the floors
•Windows and blinds are computer controlled
•Solar blinds to reclaim or reject heat
•Windows open when external temperature is between 20°C and 26°C and
wind speed is less than 10 mph
The shafts are essentially light wells in that light travels through these
wells and naturally light the six radial fingers of the building.
Sources
http://www.archinomy.com/case-
studies/669/30-st-mary-axe-the-gherkin-
london
https://prezi.com/sxt_dfdzmijt/case-study-
for-the-gherkin/
http://www.webpages.uidaho.edu/arch504u
kgreenarch/casestudies/swissre1.pdf
http://www.coopersfire.com/system/files/pri
vate/CaseStudy_The_Gherkin.pdf
http://skyscrapercenter.com/building/30-st-
mary-axe/2369
http://faculty.arch.tamu.edu/media/cms_pa
ge_media/4433/30StMaryAxe_1.pdf
http://faculty.arch.tamu.edu/media/cms_page_media/4433/30StMaryAxe_1.pdf
http://brandondonnelly.com/post/67910871416/who-knew-gherkins-were-so-aerodynamic
http://www.greendesignetc.net/Buildings_09/Building_Shen_Yuming_paper.pdf
http://www.engagingplaces.org.uk/teaching%20resources/art63639
http://www.engagingplaces.org.uk/teaching%20resources/art63639
http://www.archinomy.com/case-studies/669/30-st-mary-axe-the-gherkin-london
http://www.building.co.uk/30-st-mary-axe-a-gherkin-to-suit-all-tastes/3111783.article
http://www.sustainablebuild.co.uk/sustainable-building-around-world.html
http://www.skyscrapernews.com/swiss.htm
http://www.fosterandpartners.com/projects/30-st-mary-axe/gallery/
http://www.slideshare.net/adadarmon/swiss-re-building-london