Sunteți pe pagina 1din 19

Published on Planning Planet (http://www.planningplanet.

com)
Home > Forum > What is the S-Curve, and how do calculate the work progress..

What is the S-Curve, and how do calculate


the work progress..
By Mai Tawfeq
Created 28 Mar 2011 - 13:59
Submitted by Mai Tawfeq on Mon, 2011-03-28 13:59

For all planners are keep asking about S-Curve

the Artical has been written By: David Garland

Introduction

The first time most project managers become aware of the existence of S-curves is when
they are requested by the client or senior management to include one in their next progress
report. The following explains what the mysterious S-curve is, why it is an important project
management tool, and how to generate one.

Editor's Note:

The S-curve is a powerful project management control tool. Why it is the shape it is, how to
use it and "Max's Rule of Thumb" for drawing it as a part of the project planning activity are
all described in Chapter 10 of A Management Framework for Project, Program and
Portfolio Integration [1]. You can also find more information on this web site by entering "S-
curve" or "Resource loading" into the site search engine field.

What is an S-curve?
An S-curve is defined as:

"A display of cumulative costs, labor hours or other quantities plotted against time. The name
derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the
middle, which is typical of most projects. The beginning represents a slow, deliberate but
accelerating start, while the end represents a deceleration as the work runs out."[1] [2]

Types of S-curves

There are a variety of S-curves that are applicable to project management applications,
including:

Man Hours versus Time S-curve


Costs versus Time S-curve
Baseline S-curve
Actual S-curve
Target S-curve
Value and Percentage S-curves

Each of these is described in the following pages.

Resource Consumption
Man Hours versus Time S-curve

The Man Hours versus Time S-curve is appropriate for projects that are labor intensive. It
shows cumulative man hours expended over time for the duration of the project. As man-
hours are a product of manpower and working hours, these may be adjusted together or
individually in an attempt to keep the project on schedule. Projects may require additional
man-hours to finish on time due to low productivity, delays and disruptions, rework,
variations, etc.

By: David Garland

What is the S-Curve, and how do calculate the work progress..

Introduction

The first time most project managers become aware of the existence of S-curves is when
they are requested by the client or senior management to include one in their next progress
report. The following explains what the mysterious S-curve is, why it is an important project
management tool, and how to generate one.

Editor's Note:

The S-curve is a powerful project management control tool. Why it is the shape it is, how to
use it and "Max's Rule of Thumb" for drawing it as a part of the project planning activity are
all described in Chapter 10 of A Management Framework for Project, Program and
Portfolio Integration [1]. You can also find more information on this web site by entering "S-
curve" or "Resource loading" into the site search engine field.

What is an S-curve?
An S-curve is defined as:

"A display of cumulative costs, labor hours or other quantities plotted against time. The name
derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the
middle, which is typical of most projects. The beginning represents a slow, deliberate but
accelerating start, while the end represents a deceleration as the work runs out."[1] [2]

Types of S-curves

There are a variety of S-curves that are applicable to project management applications,
including:
Man Hours versus Time S-curve
Costs versus Time S-curve
Baseline S-curve
Actual S-curve
Target S-curve
Value and Percentage S-curves

Each of these is described in the following pages.

Resource Consumption
Man Hours versus Time S-curve

The Man Hours versus Time S-curve is appropriate for projects that are labor intensive. It
shows cumulative man hours expended over time for the duration of the project. As man-
hours are a product of manpower and working hours, these may be adjusted together or
individually in an attempt to keep the project on schedule. Projects may require additional
man-hours to finish on time due to low productivity, delays and disruptions, rework,
variations, etc.

Figure 1: Man Hours versus Time S-curve

Costs versus Time S-curve

The Costs versus Time S-curve is appropriate for projects that contain labor and non-labor
(e.g. material supply / hire / subcontract) tasks. It shows cumulative costs expended over
time for the duration of the project, and may be used to assist in the calculation of the
project's cash flow, and cost to complete.

Figure 2: Costs versus Time S-curve

Progress Tracking
Baseline S-curve

Prior to project commencement, a schedule is prepared outlining the proposed allocation of


resources and the timing of tasks necessary to complete the project within a set time frame
and budget. This schedule is referred to as the Baseline Schedule. From this schedule, a
Baseline S-curve is generated. This S-curve reflects the planned progress of the project. If
the project requirements change prior to commencement (e.g. change of scope, delayed
start), the Baseline Schedule may require revision to reflect the changed requirements.
Figure 3: Baseline S-curve

Target S-curve

Following project commencement, modification of the Baseline Schedule is usually required.


Changes are continually made to the Production Schedule (which is originally the same as
the Baseline Schedule). The production schedule reflects the actual progress of the project to
date, and any revisions made to tasks yet to commence or not yet completed. From this
schedule, a Target S-curve may be generated. This S-curve reflects the ideal progress of the
project if all tasks are completed as currently scheduled. In an ideal world, the Target S-curve
will meet the Baseline S-curve at the end of the project (On Time, On Budget) or finish below
and to the left of the Baseline S-curve (Early, Under Budget). In reality, it is not uncommon
for the Target S-curve to finish above and to the right of the Baseline S-curve (Late, Over
Budget).

Figure 4: Target S-curve

Actual S-curve

The production schedule is updated on a regular basis throughout the duration of the project.
These updates include the revision of percentage complete for each task to date. Using this
information, an Actual S-curve may be generated. This S-curve reflects the actual progress of
the project to date, and may be compared with the Baseline and Target S-curves to
determine how the project is progressing. During the project, the Actual S-curve will terminate
at the Cut Off Date. This is the date the Production Schedule was last updated. At the
completion of the project, the Actual S-curve will meet the Target S-curve.

Figure 5: Actual S-curve

Value and Percentage S-curves

S-curves may be graphed as absolute values (i.e. Man Hours or Costs) versus Time, or as
percentage values versus Time. Value S-curves are useful for determining Man Hours or
Costs expended to date, and Man Hours or Costs to complete. Percentage S-curves are
useful for calculating the project's actual percentage complete against target and baseline
percentage complete, and for calculating the project's percentage growth (or contraction).

Using S-curves
Why Use an S-curve?

S-curves are an important project management tool. They allow the progress of a project to
be tracked visually over time, and form a historical record of what has happened to date.
Analyses of S-curves allow project managers to quickly identify project growth, slippage, and
potential problems that could adversely impact the project if no remedial action is taken.

Determining Growth
Comparison of the Baseline and Target S-curves quickly reveals if the project has grown
(Target S-curve finishes above Baseline S-curve) or contracted (Target S-curve finishes
below Baseline S-curve) in scope. A change in the project's scopes implies a re-allocation of
resources (increase or decrease), and the very possible requirement to raise contract
variations. If the resources are fixed, then the duration of the project will increase (finish later)
or decrease (finish earlier), possibly leading to the need to submit an extension of time claim.

Figure 6: Calculating Project Growth using S-curves

Determining Slippage

Slippage is defined as:

"The amount of time a task has been delayed from its original baseline schedule. The
slippage is the difference between the scheduled start or finish date for a task and the
baseline start or finish date. Slippage can occur when a baseline plan is set and the actual
dates subsequently entered for tasks are later than the baseline dates or the actual durations
are longer than the baseline schedule durations".[2] [3]

Comparison of the Baseline S-curve and Target S-curve quickly reveals any project slippage
(i.e. the Target S-curve finishes to the right of the Baseline S-curve). Additional resources will
need to be allocated or additional hours worked in order to eliminate (or at least reduce) the
slippage. An extension of time claim may need to be submitted if the slippage cannot be
eliminated or reduced to an acceptable level.

Figure 7: Calculating Project Slippage using S-curves

Determining Progress

Comparison of the Target S-curve and Actual S-curve reveals the progress of the project
over time. In most cases, the Actual S-curve will sit below the Target S-curve for the majority
of the project (due to many factors, including delays in updating the production schedule).
Only towards the end of the project will the curves converge and finally meet. The Actual S-
curve can never finish above the Target S-curve. If the Actual S-curve sits above the Target
S-curve at the Cut Off Date, the Production Schedule should be examined to determine if the
project is truly ahead of schedule, or if the Production Schedule contains unrealistic
percentage complete values for ongoing tasks.

Figure 8: Calculating Project Progress using S-curves


Generating S-curves
Project Benchmarks

Percentage S-curves may be used to calculate important project benchmarks on an ongoing


basis, including:

Project percentage growth (Target and Baseline S-curves)


Project percentage slippage (Target and Baseline S-curves)
Actual percentage complete against Target percentage complete to date
Actual percentage complete against Baseline percentage complete to date

How is an S-curve Generated?

To generate a Baseline S-curve, a Baseline Schedule is required.


The Baseline Schedules should contain the following information for each task:

Baseline Start Date, Finish Date


Baseline Man Hours and/or Costs

To generate Actual and Target S-curves, a Production Schedule is required.


The Production Schedules should contain the following information for each task:

Actual Start Date, Finish Date


Actual Man Hours and/or Costs
Actual Percentage Complete

Worked Example

To better understand how S-curves are generated, consider a simple project comprising
three tasks.
A Baseline Schedule prepared using MS Project for this project is shown below.

Figure 9: Sample Baseline Schedule

Baseline Man Hours versus Time S-curve

To generate a Baseline Man Hours versus Time S-curve, two sets of calculations are
performed.
The first set of calculations is performed for each task in the Baseline Schedule.

1. Calculate the duration in days for each task


i.e. Baseline Duration = Baseline Finish Date - Baseline Start Date + 1
2. Calculate Man Hours per day for each task
i.e. Baseline MHs per Day = Baseline Man Hours / Baseline Duration

These calculations are shown in the following table.


Figure 10: Baseline S-curve Calculation 1 of 2

The second set of calculations is performed for each day in the Baseline Schedule.

1. Calculate the total Man Hours per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours per Day for all tasks.

These calculations are shown in the following table.

Figure 11: Baseline S-curve Calculation 2 of 2

The S-curve is constructed by assigning the Dates to the X Axis, and the YTD values to the
Y Axis.
The resulting Baseline Man Hours versus Time S-curve is shown below.

Figure 12: Baseline Man Hours versus Time S-curv

Actual versus Target


Target Man Hours versus Time S-curve

To generate the Actual and Target S-curves, a Production Schedule is required. A Production
Schedule for this project is shown below.

Figure 13: Production Schedule

To generate a Target Man Hours versus Time S-curve, two sets of calculations are
necessary. The first set of calculations is performed for each task in the Production Schedule.

1. Calculate the duration in days for each task


i.e. Duration = Finish Date - Start Date + 1
2. Calculate Man Hours per day for each task
i.e. MHs per Day = Man Hours / Duration

These calculations are shown in the following table.

Figure 14: Target S-curve Calculation 1 of 2


The second set of calculations is performed for each day in the Production Schedule.

1. Calculate the total Man Hours per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours per Day for all tasks.

These calculations are shown in the following table:

Figure 15: Target S-curve Calculation 2 of 2

The resulting Target Man Hours versus Time S-curve is shown below.

Figure 16: Target Man Hours versus Time S-curve

Actual Man Hours versus Time S-curve


To generate an Actual Man Hours versus Time S-curve, two sets of calculations are
performed, but before these calculations may be performed, the Cut Off Date needs to be
defined. This is the date the Production Schedule was last updated. For this example a Cut
Off Date of 3rd November 2008 will be used.

The first set of calculations is performed for each task in the Production Schedule.

1. Determine the Task Status: Complete, Ongoing, Not Started.


Complete: Tasks that have a Finish Date prior to the Cut Off Date.
Ongoing: Tasks that have commenced and have a Finish Date on or after the Cut Off
Date.
Not Started: Tasks that have a Start Date after the Cut Off Date.
2. Calculate the Duration to Date based on the Task Status.
Complete: Duration To Date = Finish Date - Start Date + 1
Ongoing: Duration To Date = Cut Off Date - Start Date + 1
Not Started: Duration To Date = 0.
3. Calculate Man Hours to Date for Complete and Ongoing Tasks.
i.e. Man Hours to Date = Man Hours x % Complete / Duration to Date.

These calculations are shown in the following table.

Figure 17: Actual S-curve Calculation 1 of 2

The second set of calculations is performed for each day in the Production Schedule up to
the Cut Off Date.

1. Calculate the total Man Hours to Date per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours to Date per Day for all tasks.
These calculations are shown in the following table.

Figure 18: Actual S-curve Calculation 2 of 2

The resulting Actual Man Hours versus Time S-curve is shown below.

Figure 19: Actual Man Hours versus Time S-curve

The Baseline, Actual, and Target S-curves are usually combined, as shown below.

Figure 20: Man Hours versus Time S-curves

Analysis

S-curve Analysis

Initial examination of the S-curves generated above reveal the following about the status of
the project.

The project has grown in scope. (The Target S-curve finishes above the Baseline S-
curve)
The project has slipped. (The Target S-curve finishes to the right of the Baseline S-
curve)
The project is behind schedule. (The Actual S-curve sits below the Target S-curve at
the Cut Off Date)

Project Growth

Analysis of the Baseline and Target S-curve data reveals the project has grown in scope by
12 man-hours, or 14.29%.

i.e. Growth = Target MHs - Baseline MHs = 96 - 84 = 12


i.e. Growth % = (Target MHs / Baseline MHs - 1) x 100% = (96 / 84 - 1) x 100% =
14.29%

Project Slippage

Analysis of the Baseline and Target S-curve data reveals the project has slipped by 1 day, or
20.00%.

i.e. Slippage = Target Duration - Baseline Duration = 6 - 5 = 1


i.e. Slippage % = (Target Duration / Baseline Duration - 1) x 100% = (6 / 5 - 1) x 100%
= 20.00%
Project Progress

According to MS Project, based on the Production Schedule the project is 50% complete. MS
Project calculates percentage complete based on durations, and does not take into account
man-hours assigned to each task. Analysis of the Actual and Target S-curve data reveals the
project is 53.13% complete as of the Cut Off Date, while the project should be 59.38%
complete.

i.e. Actual % Complete = (Actual YTD Man Hours @ Cut Off Date / Target Man Hours)
x 100% = (51 / 96) x 100% = 53.13%
i.e. Target % Complete = (Target YTD Man Hours @ Cut Off Date / Target Man Hours)
x 100% = (57 / 96) x 100% = 59.38%

Conclusion
Project status

The project will finish late and over budget compared to the Baseline Schedule. Progress to
date (i.e. the Cut Off Date) is behind schedule compared to the Production Schedule.
Detailed analysis of the project is required to determine why the project will be completed late
and over budget. Project growth and/or slippage may be due to a number of factors, including
underestimation of effort in the Baseline Schedule, low productivity, rework, variations
(approved or not), etc.

In this example, variations may need to be raised to account for the extra man hours
expended, and an extension of time claim raised for the later than planned completion. The
Production Schedule may need review to ensure tasks have been updated accurately
(especially with respect to true percentage complete values), and ongoing and future tasks
may require revising.

Generating S-curves

Some software scheduling packages automatically generate S-curves. On the other hand,
some (including MS Project) do not. In this case, a third party software application is required
to process the Baseline and Production Schedule data to generate the required S-curves.

Midori Media's myPM SCG S-curve Generator is an MS Windows application that integrates
with MS Excel to generate the various types of S-curves discussed above. MS Project users
will need to export their schedule data to an MS Excel file (easily accomplished using MS
Project's File Save As option). myPM SCG processes the resulting export file, and creates an
MS Excel Output file containing the required S-curves. These may be copy-pasted to MS
Word for inclusion in Project Progress Reports.

The value of S-curves


The S-curve is an important but often overlooked and misunderstood project management
tool. A variety of S-curves exist, the most common being Man Hours versus Time, and Costs
versus Time. By creating a Baseline Schedule, a Baseline S-curve can be generated.
Baseline S-curves provide a basis on which to compare a project's actual status to its
planned status. They may also assist in the planning of manpower and financial resources
required to complete the project.

A Production Schedule allows Actual and Target S-curves to be generated. These allow the
progress of a project to be monitored, and quickly reveal any divergence from the Baseline
Schedule. S-curves may also be used to determine project growth, slippage, and progress to
date.

Figure 1: Man Hours versus Time S-curve

Costs versus Time S-curve

The Costs versus Time S-curve is appropriate for projects that contain labor and non-labor
(e.g. material supply / hire / subcontract) tasks. It shows cumulative costs expended over
time for the duration of the project, and may be used to assist in the calculation of the
project's cash flow, and cost to complete.

Figure 2: Costs versus Time S-curve

Progress Tracking
Baseline S-curve

Prior to project commencement, a schedule is prepared outlining the proposed allocation of


resources and the timing of tasks necessary to complete the project within a set time frame
and budget. This schedule is referred to as the Baseline Schedule. From this schedule, a
Baseline S-curve is generated. This S-curve reflects the planned progress of the project. If
the project requirements change prior to commencement (e.g. change of scope, delayed
start), the Baseline Schedule may require revision to reflect the changed requirements.

Figure 3: Baseline S-curve

Target S-curve

Following project commencement, modification of the Baseline Schedule is usually required.


Changes are continually made to the Production Schedule (which is originally the same as
the Baseline Schedule). The production schedule reflects the actual progress of the project to
date, and any revisions made to tasks yet to commence or not yet completed. From this
schedule, a Target S-curve may be generated. This S-curve reflects the ideal progress of the
project if all tasks are completed as currently scheduled. In an ideal world, the Target S-curve
will meet the Baseline S-curve at the end of the project (On Time, On Budget) or finish below
and to the left of the Baseline S-curve (Early, Under Budget). In reality, it is not uncommon
for the Target S-curve to finish above and to the right of the Baseline S-curve (Late, Over
Budget).

Figure 4: Target S-curve

Actual S-curve

The production schedule is updated on a regular basis throughout the duration of the project.
These updates include the revision of percentage complete for each task to date. Using this
information, an Actual S-curve may be generated. This S-curve reflects the actual progress of
the project to date, and may be compared with the Baseline and Target S-curves to
determine how the project is progressing. During the project, the Actual S-curve will terminate
at the Cut Off Date. This is the date the Production Schedule was last updated. At the
completion of the project, the Actual S-curve will meet the Target S-curve.

Figure 5: Actual S-curve

Value and Percentage S-curves

S-curves may be graphed as absolute values (i.e. Man Hours or Costs) versus Time, or as
percentage values versus Time. Value S-curves are useful for determining Man Hours or
Costs expended to date, and Man Hours or Costs to complete. Percentage S-curves are
useful for calculating the project's actual percentage complete against target and baseline
percentage complete, and for calculating the project's percentage growth (or contraction).

Using S-curves
Why Use an S-curve?

S-curves are an important project management tool. They allow the progress of a project to
be tracked visually over time, and form a historical record of what has happened to date.
Analyses of S-curves allow project managers to quickly identify project growth, slippage, and
potential problems that could adversely impact the project if no remedial action is taken.

Determining Growth

Comparison of the Baseline and Target S-curves quickly reveals if the project has grown
(Target S-curve finishes above Baseline S-curve) or contracted (Target S-curve finishes
below Baseline S-curve) in scope. A change in the project's scopes implies a re-allocation of
resources (increase or decrease), and the very possible requirement to raise contract
variations. If the resources are fixed, then the duration of the project will increase (finish later)
or decrease (finish earlier), possibly leading to the need to submit an extension of time claim.
Figure 6: Calculating Project Growth using S-curves

Determining Slippage

Slippage is defined as:

"The amount of time a task has been delayed from its original baseline schedule. The
slippage is the difference between the scheduled start or finish date for a task and the
baseline start or finish date. Slippage can occur when a baseline plan is set and the actual
dates subsequently entered for tasks are later than the baseline dates or the actual durations
are longer than the baseline schedule durations".[2] [3]

Comparison of the Baseline S-curve and Target S-curve quickly reveals any project slippage
(i.e. the Target S-curve finishes to the right of the Baseline S-curve). Additional resources will
need to be allocated or additional hours worked in order to eliminate (or at least reduce) the
slippage. An extension of time claim may need to be submitted if the slippage cannot be
eliminated or reduced to an acceptable level.

Figure 7: Calculating Project Slippage using S-curves

Determining Progress

Comparison of the Target S-curve and Actual S-curve reveals the progress of the project
over time. In most cases, the Actual S-curve will sit below the Target S-curve for the majority
of the project (due to many factors, including delays in updating the production schedule).
Only towards the end of the project will the curves converge and finally meet. The Actual S-
curve can never finish above the Target S-curve. If the Actual S-curve sits above the Target
S-curve at the Cut Off Date, the Production Schedule should be examined to determine if the
project is truly ahead of schedule, or if the Production Schedule contains unrealistic
percentage complete values for ongoing tasks.

Figure 8: Calculating Project Progress using S-curves

Generating S-curves
Project Benchmarks

Percentage S-curves may be used to calculate important project benchmarks on an ongoing


basis, including:

Project percentage growth (Target and Baseline S-curves)


Project percentage slippage (Target and Baseline S-curves)
Actual percentage complete against Target percentage complete to date
Actual percentage complete against Baseline percentage complete to date

How is an S-curve Generated?


To generate a Baseline S-curve, a Baseline Schedule is required.
The Baseline Schedules should contain the following information for each task:

Baseline Start Date, Finish Date


Baseline Man Hours and/or Costs

To generate Actual and Target S-curves, a Production Schedule is required.


The Production Schedules should contain the following information for each task:

Actual Start Date, Finish Date


Actual Man Hours and/or Costs
Actual Percentage Complete

Worked Example

To better understand how S-curves are generated, consider a simple project comprising
three tasks.
A Baseline Schedule prepared using MS Project for this project is shown below.

Figure 9: Sample Baseline Schedule

Baseline Man Hours versus Time S-curve

To generate a Baseline Man Hours versus Time S-curve, two sets of calculations are
performed.
The first set of calculations is performed for each task in the Baseline Schedule.

1. Calculate the duration in days for each task


i.e. Baseline Duration = Baseline Finish Date - Baseline Start Date + 1
2. Calculate Man Hours per day for each task
i.e. Baseline MHs per Day = Baseline Man Hours / Baseline Duration

These calculations are shown in the following table.

Figure 10: Baseline S-curve Calculation 1 of 2

The second set of calculations is performed for each day in the Baseline Schedule.

1. Calculate the total Man Hours per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours per Day for all tasks.
These calculations are shown in the following table.

Figure 11: Baseline S-curve Calculation 2 of 2

The S-curve is constructed by assigning the Dates to the X Axis, and the YTD values to the
Y Axis.
The resulting Baseline Man Hours versus Time S-curve is shown below.

Figure 12: Baseline Man Hours versus Time S-curv

Actual versus Target


Target Man Hours versus Time S-curve
To generate the Actual and Target S-curves, a Production Schedule is required. A Production
Schedule for this project is shown below.

Figure 13: Production Schedule

To generate a Target Man Hours versus Time S-curve, two sets of calculations are
necessary. The first set of calculations is performed for each task in the Production Schedule.

1. Calculate the duration in days for each task


i.e. Duration = Finish Date - Start Date + 1
2. Calculate Man Hours per day for each task
i.e. MHs per Day = Man Hours / Duration

These calculations are shown in the following table.

Figure 14: Target S-curve Calculation 1 of 2

The second set of calculations is performed for each day in the Production Schedule.

1. Calculate the total Man Hours per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours per Day for all tasks.

These calculations are shown in the following table:


Figure 15: Target S-curve Calculation 2 of 2

The resulting Target Man Hours versus Time S-curve is shown below.

Figure 16: Target Man Hours versus Time S-curve

Actual Man Hours versus Time S-curve


To generate an Actual Man Hours versus Time S-curve, two sets of calculations are
performed, but before these calculations may be performed, the Cut Off Date needs to be
defined. This is the date the Production Schedule was last updated. For this example a Cut
Off Date of 3rd November 2008 will be used.

The first set of calculations is performed for each task in the Production Schedule.

1. Determine the Task Status: Complete, Ongoing, Not Started.


Complete: Tasks that have a Finish Date prior to the Cut Off Date.
Ongoing: Tasks that have commenced and have a Finish Date on or after the Cut Off
Date.
Not Started: Tasks that have a Start Date after the Cut Off Date.
2. Calculate the Duration to Date based on the Task Status.
Complete: Duration To Date = Finish Date - Start Date + 1
Ongoing: Duration To Date = Cut Off Date - Start Date + 1
Not Started: Duration To Date = 0.
3. Calculate Man Hours to Date for Complete and Ongoing Tasks.
i.e. Man Hours to Date = Man Hours x % Complete / Duration to Date.

These calculations are shown in the following table.

Figure 17: Actual S-curve Calculation 1 of 2

The second set of calculations is performed for each day in the Production Schedule up to
the Cut Off Date.

1. Calculate the total Man Hours to Date per Day for all tasks.
2. Calculate the Year To Date Total for Man Hours to Date per Day for all tasks.

These calculations are shown in the following table.

Figure 18: Actual S-curve Calculation 2 of 2

The resulting Actual Man Hours versus Time S-curve is shown below.
Figure 19: Actual Man Hours versus Time S-curve

The Baseline, Actual, and Target S-curves are usually combined, as shown below.

Figure 20: Man Hours versus Time S-curves

Analysis

S-curve Analysis

Initial examination of the S-curves generated above reveal the following about the status of
the project.

The project has grown in scope. (The Target S-curve finishes above the Baseline S-
curve)
The project has slipped. (The Target S-curve finishes to the right of the Baseline S-
curve)
The project is behind schedule. (The Actual S-curve sits below the Target S-curve at
the Cut Off Date)

Project Growth

Analysis of the Baseline and Target S-curve data reveals the project has grown in scope by
12 man-hours, or 14.29%.

i.e. Growth = Target MHs - Baseline MHs = 96 - 84 = 12


i.e. Growth % = (Target MHs / Baseline MHs - 1) x 100% = (96 / 84 - 1) x 100% =
14.29%

Project Slippage

Analysis of the Baseline and Target S-curve data reveals the project has slipped by 1 day, or
20.00%.

i.e. Slippage = Target Duration - Baseline Duration = 6 - 5 = 1


i.e. Slippage % = (Target Duration / Baseline Duration - 1) x 100% = (6 / 5 - 1) x 100%
= 20.00%

Project Progress

According to MS Project, based on the Production Schedule the project is 50% complete. MS
Project calculates percentage complete based on durations, and does not take into account
man-hours assigned to each task. Analysis of the Actual and Target S-curve data reveals the
project is 53.13% complete as of the Cut Off Date, while the project should be 59.38%
complete.

i.e. Actual % Complete = (Actual YTD Man Hours @ Cut Off Date / Target Man Hours)
x 100% = (51 / 96) x 100% = 53.13%
i.e. Target % Complete = (Target YTD Man Hours @ Cut Off Date / Target Man Hours)
x 100% = (57 / 96) x 100% = 59.38%

Conclusion
Project status

The project will finish late and over budget compared to the Baseline Schedule. Progress to
date (i.e. the Cut Off Date) is behind schedule compared to the Production Schedule.
Detailed analysis of the project is required to determine why the project will be completed late
and over budget. Project growth and/or slippage may be due to a number of factors, including
underestimation of effort in the Baseline Schedule, low productivity, rework, variations
(approved or not), etc.

In this example, variations may need to be raised to account for the extra man hours
expended, and an extension of time claim raised for the later than planned completion. The
Production Schedule may need review to ensure tasks have been updated accurately
(especially with respect to true percentage complete values), and ongoing and future tasks
may require revising.

Generating S-curves

Some software scheduling packages automatically generate S-curves. On the other hand,
some (including MS Project) do not. In this case, a third party software application is required
to process the Baseline and Production Schedule data to generate the required S-curves.

Midori Media's myPM SCG S-curve Generator is an MS Windows application that integrates
with MS Excel to generate the various types of S-curves discussed above. MS Project users
will need to export their schedule data to an MS Excel file (easily accomplished using MS
Project's File Save As option). myPM SCG processes the resulting export file, and creates an
MS Excel Output file containing the required S-curves. These may be copy-pasted to MS
Word for inclusion in Project Progress Reports.

The value of S-curves


The S-curve is an important but often overlooked and misunderstood project management
tool. A variety of S-curves exist, the most common being Man Hours versus Time, and Costs
versus Time. By creating a Baseline Schedule, a Baseline S-curve can be generated.
Baseline S-curves provide a basis on which to compare a project's actual status to its
planned status. They may also assist in the planning of manpower and financial resources
required to complete the project.

A Production Schedule allows Actual and Target S-curves to be generated. These allow the
progress of a project to be monitored, and quickly reveal any divergence from the Baseline
Schedule. S-curves may also be used to determine project growth, slippage, and progress to
date.
Planning, Scheduling & Programming Discussion [4]
Planning, Scheduling & Programming Discussion
By accessing any further pages of this website you agree to be bound by our Planning Planet
T&C's
Copyright © 2015 Planning Planet - ( Run by Volunteer Planners for Planners ) - Contact Us
PPAdmin@planningplanet.com

Source URL: http://www.planningplanet.com/forums/planning-scheduling-programming-discussion/502846/what-


s-curve-and-how-do-calculate-work-prog

Links:
[1] http://www.maxwideman.com/papers/framework_book/contents.htm
[2] http://www.maxwideman.com/guests/s-curve/what.htm#1
[3] http://www.maxwideman.com/guests/s-curve/using.htm#2
[4] http://www.planningplanet.com/forums/planning-scheduling-programming-discussion

S-ar putea să vă placă și