HASUKI PROJECT June 15, 2013

DAILY DRILLING PROGRESS JR 75

COORDINATES CORING (m) CORE LENGTH CORE LOST Sample


DATE HOLE ID PLAN HOLE RUN CORE REC (M) REC (%) TOTAL DEPTH/ DAY REMARKS
EAST NORTH ELV FROM TO TOTAL (M) (M) Number
14-Jun-13 Mobilization from Malili to Location
15-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 1 0 0.37 0.37 0.37 0.22 0.15 41 0.37 Moving and start drilling
16-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 2 0.37 1.57 1.2 1.2 0.5 0.7 58 continue drilling
3 1.57 3.07 1.5 1.5 1.24 0.26 17
4 3.07 4.57 1.5 1.5 0.45 1.05 70 5.70
5 4.57 5.62 1.05 1.05 0.43 0.62 59
6 5.62 6.07 0.45 0.45 0.35 0.10 22
17-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 7 6.07 7.12 1.05 1.05 0.05 1.00 95 Trouble with Transportation, continue drilling
8 7.12 8.62 1.50 1.50 0.00 1.50 100 3.00
9 8.62 9.07 0.45 0.45 0.01 0.44 98
18-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 10 9.07 10.57 1.50 1.50 0.03 1.47 98 Continue drilling
11 10.57 12.07 1.50 1.50 0.00 1.50 100
4.50
12 12.07 12.77 0.70 0.70 0.00 0.70 100
13 12.77 13.57 0.80 0.80 0.12 0.68 85
19-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 14 13.57 15.07 1.50 1.50 0.27 1.23 82 Continue drilling
15 15.07 16.57 1.50 1.50 0.00 1.50 100
16 16.57 17.22 0.65 0.65 0.05 0.60 92
5.70
17 17.22 18.07 0.85 0.85 0.00 0.85 100
18 18.07 18.67 0.60 0.60 0.01 0.59 98
19 18.67 19.27 0.60 0.60 0.00 0.60 100
20-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 20 19.27 20.17 0.90 0.90 0.00 0.90 100 Continue drilling
21 20.17 21.07 0.90 0.90 0.05 0.85 94 3.30
22 21.07 22.57 1.50 1.50 0.72 0.78 52
21-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 23 22.57 23.22 0.65 0.65 0.06 0.59 91 Continue drilling
1.35
24 23.22 23.92 0.70 0.70 0.05 0.65 93 Core barrel trouble
22-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 - Stand by - core barrel trouble
23-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 25 23.92 25.42 1.5 1.5 0.45 1.05 70 Continue drilling
26 25.42 26.32 0.9 0.9 0.05 0.85 94
27 26.32 27.07 0.75 0.75 0.35 0.4 53 4.95
28 27.07 28.37 1.3 1.3 0.1 1.2 92
29 28.37 28.87 0.5 0.5 0 0.5 100
24-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 30 28.87 30.07 1.2 1.2 0.27 0.93 78 Continue drilling
31 30.07 30.27 0.2 0.2 0 0.2 100 2.7 Core barrel trouble
32 30.27 31.57 1.3 1.3 0 1.3 100
25-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 Stand by - Repair Core Barrel
26-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 33 31.57 33.07 1.5 1.5 0.06 1.44 96 Continue drilling
34 33.07 34.57 1.5 1.5 0 1.5 100
6
35 34.57 36.12 1.55 1.55 0 1.55 100
36 36.12 37.57 1.45 1.45 0 1.45 100
27-Jun-13 HS 1 Hole 1 282,581.00 9,686,261.00 37 37 37.57 39.12 1.55 1.55 0 1.55 100
38 39.12 40.32 1.2 1.2 0.03 1.17 98 Finish Hole HS 1
HS 1R Hole 1 282,582.00 9,686,261.00 37 1 0 1.4 1.4 1.4 0.26 1.14 81 6.22 Start drill Hole HS 1R, (Re drill)
2 1.4 2.85 1.45 1.45 0.66 0.79 54
3 2.85 3.47 0.62 0.62 0.02 0.6 97
28-Jun-13 HS 1R Hole 1 282,582.00 9,686,261.00 37 4 3.47 4.87 1.4 1.4 0.28 1.12 80 Continue drill
2.6
5 4.87 6.07 1.2 1.2 0.35 0.85 71 Finish hole, Rig down, Prepare move to HS 2, plan Hole 2
29-Jun-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 Moving to HS 2, Plan Hole 2
30-Jun-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 Stand by (waiting new plan hole 2),
Moving from plan hole 2 to new plan hole 2
1-Jul-13 New plan Hole 2 282,565.00 9,686,367.00 33 'Greaves' Rig Engine Trouble (Cannot Start), Hole Trouble
2-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 1 0 0.81 0.81 0.81 0 0.81 100 Hole trouble move back to plan hole 2
2 0.81 1.58 0.77 0.77 0 0.77 100 Start drilling
3.08
3 1.58 2.57 0.99 0.99 0 0.99 100
4 2.57 3.08 0.51 0.51 0 0.51 100
3-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 5 3.08 4.58 1.5 1.5 0.14 1.36 91 Continue drill
6 4.58 5.23 0.65 0.65 0.03 0.62 95
7 5.23 6.08 0.85 0.85 0.03 0.82 96 4.5
8 6.08 6.82 0.74 0.74 0.07 0.67 91
9 6.82 7.58 0.76 0.76 0.06 0.7 92
4-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 10 7.58 8.1 0.52 0.52 0.04 0.48 92 Continue drill
11 8.1 8.56 0.46 0.46 0.02 0.44 96
12 8.56 9.08 0.52 0.52 0.05 0.47 90
4.5
13 9.08 10.05 0.97 0.97 0.27 0.7 72
14 10.05 11.03 0.98 0.98 0.08 0.9 92
15 11.03 12.08 1.05 1.05 0 1.05 100
5-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 16 12.08 13.58 1.5 1.5 0.22 1.28 85 Continue drill
17 13.58 14.73 1.15 1.15 0.15 1 87 3.35
18 14.73 15.43 0.7 0.7 0 0.7 100
6-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 19 15.43 16.53 1.1 1.1 0 1.1 100 Continue drill
20 16.53 17.38 0.85 0.85 0 0.85 100
21 17.38 18.08 0.7 0.7 0 0.7 100 4.1
22 18.08 18.78 0.7 0.7 0.09 0.61 87
23 18.78 19.53 0.75 0.75 0.05 0.7 93
7-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 24 19.53 21.08 1.55 1.55 0.28 1.27 82 Continue drill
25 21.08 22.58 1.5 1.5 0 1.5 100 4.43
26 22.58 23.96 1.38 1.38 0 1.38 100
8-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 27 23.96 25.06 1.1 1.1 0.03 1.07 97 Continue drill
28 25.06 25.58 0.52 0.52 0 0.52 100
29 25.58 26.74 1.16 1.16 0.11 1.05 91 4.03
30 26.74 27.23 0.49 0.49 0 0.49 100
31 27.23 27.99 0.76 0.76 0 0.76 100
9-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 32 27.99 28.58 0.59 0.59 0.04 0.55 93 Trouble and Repair Rig Engine
2.09
33 28.58 30.08 1.5 1.5 0 1.5 100 Continue drill
10-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 34 30.08 31.58 1.5 1.5 0.1 1.4 93 Continue drill
35 31.58 33.08 1.5 1.5 0.02 1.48 99 4.25
36 33.08 34.33 1.25 1.25 0.11 1.14 91
11-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 37 34.33 35.83 1.5 1.5 0.1 1.4 93 1.5 Continue drill - Core barrel Trouble (core catcher Trouble),
12-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 Drilling trouble, - Repair Core barrel (core catcher) at Malili
13-Jul-13 HS 2 Hole 2 282,559.00 9,686,359.00 40 38 35.83 36.71 0.88 0.88 0.12 0.76 86 Continue drill
39 36.71 37.58 0.87 0.87 0.07 0.8 92 3.25 Holes collapse, stop-finish drill
40 37.58 39.08 1.5 1.5 0.1 1.4 93 Rig down, move to Plan Hole 4, (HS 3)
14-Jul-13 HS 3 Hole 4 282,562.00 9,686,461.00 34 1 0 0.61 0.61 0.61 0.06 0.55 90 Continue move, Setting Rig
2 0.61 1.58 0.97 0.97 0.12 0.85 88 Start Drill
3 1.58 3.08 1.5 1.5 0.8 0.7 47 Stop drill till 21.30 WITA (Over Time)
6.43
4 3.08 4.58 1.5 1.5 1.14 0.36 24
5 4.58 6.08 1.5 1.5 0.33 1.17 78
6 6.08 6.43 0.35 0.35 0 0.35 100
15-Jul-13 HS 3 Hole 4 282,562.00 9,686,461.00 34 7 6.43 7.13 0.7 0.7 0.05 0.65 93 Continue drill
8 7.13 7.58 0.45 0.45 0.04 0.41 91 Stop drill till 21.30 WITA (Over Time)
9 7.58 9.08 1.5 1.5 0.4 1.1 73
7.15
10 9.08 10.58 1.5 1.5 0.3 1.2 80
11 10.58 12.08 1.5 1.5 0 1.5 100
12 12.08 13.58 1.5 1.5 0 1.5 100
16-Jul-13 HS 3 Hole 4 282,562.00 9,686,461.00 34 13 13.58 15.08 1.5 1.5 0 1.5 100 Continue drill
14 15.08 16.58 1.5 1.5 0.1 1.4 93 Stop drill till 21.30 WITA (Over Time)
15 16.58 18.08 1.5 1.5 0 1.5 100
16 18.08 19.58 1.5 1.5 0 1.5 100
12
17 19.58 21.08 1.5 1.5 0 1.5 100
18 21.08 22.58 1.5 1.5 0 1.5 100
19 22.58 24.08 1.5 1.5 0.02 1.48 99
20 24.08 25.58 1.5 1.5 0.05 1.45 97
17-Jul-13 HS 3 Hole 4 282,562.00 9,686,461.00 34 21 25.58 27.08 1.5 1.5 0 1.5 100 Continue drill
22 27.08 28.58 1.5 1.5 0 1.5 100 Stop drill till 21.30 WITA (Over Time)
23 28.58 30.08 1.5 1.5 0.14 1.36 91 7.5
24 30.08 31.58 1.5 1.5 0 1.5 100
25 31.58 33.08 1.5 1.5 0 1.5 100
18-Jul-13 HS 3 Hole 4 282,562.00 9,686,461.00 34 26 33.08 34.58 1.5 1.5 0 1.5 100 Continue drill
27 34.58 36.08 1.5 1.5 0 1.5 100 Gear Box, Bearing Trouble
5.5
28 36.08 37.58 1.5 1.5 0 1.5 100 Stop drill
29 37.58 38.58 1 1 0.02 0.98 98
19-Jul-13 Repair Gear Box
20-Jul-13 Move to HS 4, Plan Hole 7
21-Jul-13 HS 4 Hole 7 282,559.00 9,686,570.00 38 1 0 1.58 1.58 1.58 0.13 1.45 92 1.58 Continue Move, Start drill
22-Jul-13 HS 4 Hole 7 282,559.00 9,686,570.00 38 2 1.58 3.08 1.5 1.5 0.7 0.8 53 Continue drill
3 3.08 4.58 1.5 1.5 0.62 0.88 59 Over Time till 21.00 WITA
6
4 4.58 6.08 1.5 1.5 0.37 1.13 75
5 6.08 7.58 1.5 1.5 0.3 1.2 80
23-Jul-13 HS 4 Hole 7 282,559.00 9,686,570.00 38 6 7.58 9.08 1.5 1.5 0.7 0.8 53 Continue drill
7 9.08 10.58 1.5 1.5 1 0.5 33 Over Time till 21.00 WITA
6
8 10.58 12.08 1.5 1.5 0.4 1.1 73
9 12.08 13.58 1.5 1.5 0.4 1.1 73
24-Jul-13 HS 4 Hole 7 282,559.00 9,686,570.00 38 10 13.58 15.08 1.5 1.5 0.55 0.95 63 Continue drill
11 15.08 16.58 1.5 1.5 0.7 0.8 53 4.5 Over Time till 21.00 WITA
12 16.58 18.08 1.5 1.5 0.5 1 67
25-Jul-13 HS 4 Hole 7 282,559.00 9,686,570.00 38 13 18.08 19.58 1.5 1.5 0.72 0.78 52 Continue drill
14 19.58 21.08 1.5 1.5 0.8 0.7 47 4.5
15 21.08 22.58 1.5 1.5 0.79 0.71 47
26-Jul-13 HS 4 Hole 7 282,559.00 9,686,570.00 38 Trouble with fuel ( No Solar)
27-Jul-13 HS 4 Hole 7 282,559.00 9,686,570.00 38 16 22.58 24.08 1.5 1.5 0.65 0.85 57 Continue drill
17 24.08 25.58 1.5 1.5 0.85 0.65 43 Over Time till 22.00 WITA
6
18 25.58 27.08 1.5 1.5 0.43 1.07 71
19 27.08 28.58 1.5 1.5 0.25 1.25 83
28-Jul-13 HS 4 Hole 7 282,559.00 9,686,570.00 38 20 28.58 30.08 1.5 1.5 0.21 1.29 86 Continue drill
21 30.08 31.58 1.5 1.5 0.75 0.75 50 4.5
22 31.58 33.08 1.5 1.5 0.8 0.7 47
29-Jul-13 HS 4 Hole 7 282,559.00 9,686,570.00 38 23 33.08 34.58 1.5 1.5 0.12 1.38 92 Continue drill
2.5
24 34.58 35.58 1 1 0.2 0.8 80 Gear Box trouble (trouble with bearing Gear Box), Stop drill
30-Jul-13 Demobilization Rig, from site location to near village,
(Patikala Village)

Grand Total 159.63 26.38 133.25 159.63

PT. HASUKI PT. DANMAR EXPLORINDO


DAYLI REPORT

Hole ID : TMJ HOLE 1


Coordinate
East 668999 weel site Mr Tias Bayureksa
North 9819350 master drilling Mr Agus
elevation 73 m

CORING (m) CORE LENGTH CORE LOST CORE REC REC TOTAL DEPTH
DATE RUN REMARKS
FROM TO TOTAL (M) (M) (M) (% ) (per Day)
31-01-2014 8 3.8 4,0 0,2 0,2 0,2 100
9 4,0 6,50 2,50 0,3 2,20 0,3 12
10 6,50 7,95 1,45 0,23 1,22 0,23 15
11 7,95 8,85 0,9 0,70 0,2 0,70 77
12 8,85 14,90 6,05 14,90 lost cure
1/2/2014 13 14,90 15,40 0,5 0,40 0,10 0,40 80
14 15,40 16,90 1,50 0,17 1,33 0,17 11
15 16,90 17,40 0,5 0,50 0 0,50 100 17,40
2/2/2014 16 17,40 18,50 1,10 0,50 0,60 0,50 45
17 18,50 19,70 1,20 100 0,20 100 83 19,70
3/2/2014 18 19,70 21,10 1,40 1,40 0 1,40 100
19 21,10 23 1,90 1,46 0,44 1,46 76 23
4/2/2014 20 23 24,5 1,5 1,48 0,2 1,48 98 24,5
5/2/2014 pipa terjepit
6/2/2014 pipa terjepit
7/2/2014 pipa terjepit
8/2/2014 21 24,5 25 0,50 0,50 0 0,50 100 25
9/2/2014 22 25 26,5 1,50 1,50 0 1,50 100
23 26,5 26,95 0,45 0,43 0,2 0,43 95 26,95
10/2/2014 perbaikan
11/2/2014 24 26,95 28,30 1,35 1,23 0,12 1,23 91
25 28,30 28,70 0,40 0,29 0,11 0,29 72 28,30
12/2/2014 26 28,70 29,20 0,50 0,48 0,02 0,48 98 29,20
muping
DAYLI REPORT
Hole ID : TMJ HOLE II
Coordinate
East weel site Mr Tias Bayureksa
North master drilling Mr Agus
elevation
3
CORING (m) CORE LENGTH CORE LOST CORE REC
DATE RUN (M)
FROM TO TOTAL (M) (M)
13-02-2014
1 0 9,5
2 9,5 12
14-02-2014 3 12 13,50 1,5
4 13,50 15,50 2 0,28 1,7 0,28
5 15,50 16,25 0,75 0,20 0,55 0,20
6 16,25 17,75 1,50 1,37 0,13 1,37
15-02-2014 7 17,75 19,25 1,50 1,45 0,5 1,45
8 19,25 19,95 0,70 0,70 0,70
9 19,95 20,15 0,20 0,17 0,3 0,17
10 20,15 20,65 0,50
16-02-2014 11 20,65 20,99 0,34 0,15 0,19 0,15
12 20,99 22,49 1,50 1,32 0,18 1,32
13 22,49 22,49 0,15 0,8 0,7 0,8
14 22,64 23,04 0,40 0,22 0,18 0,22
17-02-2014 15 23,04 26,40 3,36 3,36 3,36
18-02-2014 16 26,40 27,70 1,30 1,25 0,5 1,25
17 27,70 29,20 1,50 1,50 1,50
18 29,20 30,20 100 100 100
19 30,20 31,70 1,50 1,50 1,50
Mr Tias Bayureksa

TOTAL
REC DEPTH REMARKS
(% ) (per Day)
muping
soil
soil
13,50
14
26
91 17,75
96
100
85
20,65 core lost
44
88
53
55 23,04
100 26,40
96
100
100
100 31,70
DAYLI REPORT
Hole ID : TMJ HOLE III
2
Coordinate
East weel site Mr Tias Bayureksa
North master drilling Mr Agus
elevation

CORING (m) 0 CORE LOST CORE REC REC


DATE RUN (M)
FROM TO TOTAL (M) (M) (% )
19-02-2014
20-02-2014 1 0 3 3 0,10 2,90 0,10 3
2 3 4,50 1,50 0,10 1,40 0,10 6
3 4,50 5,90 1,40 100 0,40 100 71
4 5,90 7,30 1,40 1,40 1,40 100
5 7,30 8 0,80 0,80 1,40 100
6 8 9,20 0 0,60 0,60 0,60 50
7 9,20 9,50 0,30 0,30 0,30 100
21-02-2014 8 9,50 10,90 1,40 1,37 0,3 1,37 97
9 10,90 12,5 1,60 1,46 0,14 1,46 91
10 12,5 14 1,50 1,60 1,60 100
11 14 15 100 0,96 0,4 0,96 96
12 15 16,50 1,50 1,8 0,42 0,72 72
13 16,50 16,90 0,40 0,40 100 100
14 16,90 17,50 100 1,10 100 100
15 17,90 18,60 0,70 0,67 0,3 0,67 95
16 18,60 19,70 1,10 100 0,10 100 90
17 19,70 21,20 1,50 1,30 0,20 1,30 88
18 21,20 22 0,80 0,78 0,2 0,78 98
TOTAL
DEPTH REMARKS
(per Day)
muping

9,50
iron ore
iron ore
iron ore
iron ore
iron ore

17,50

21,20
22