Sunteți pe pagina 1din 3

FLOORS AND SCREEDS

(Photo: Mike Amodeo (Contractors) Ltd.)


Floor slabs, lasers and levels
buildings. The Government also outlawed
Modern buildings may have main structural frames of precast or in-situ standard fee scales and promoted fee
concrete, or steel but they almost always have concrete floors. These may competition.
As a consequence, architects and
be cast in-situ on temporary formwork, or concrete topping cast on precast
engineers are often appointed on ‘design
concrete planks, or concrete cast on profiled steel sheeting. They are so only’ contracts where they do not inspect
familiar that it is tempting to take their design and specification for granted. the contractor’s work and only visit site
However, the past 20–30 years have seen revolutions in procurement, when requested. Structural engineers
contracts and construction methods which have combined to create a therefore have fewer opportunities to
situation where standard design assumptions and specifications are no longer visit site and see how their designs are
appropriate and could even be dangerous. Alasdair N Beal of Thomasons constructed.
Contractors have also changed: few now
reports.
carry out site work themselves. Instead
they commonly divide projects into
‘work packages’ and let these to specialist
n the 1970s and early 1980s, when contractor had to make allowances in levels subcontractors, restricting their own

I most current codes of practice were


being written, construction projects
were organised differently from today.
for formwork movement or structural
deflection. Temporary tamping rails were
set up on the soffit shuttering to level the
role to planning and co-ordination. Some
take care to discuss and co-ordinate the
subcontractors’ work carefully but others
Contracts were usually consultant-led – a concrete. Most floors had a tamped surface, simply split the project into packages and
client employed an architect and structural with a screed finish. Power finishing was leave the subcontractors to sort things out
engineer to design the building, obtain generally only applied to ground-bearing on-site.
tenders, appoint the contractor and inspect warehouse slabs. Floors cast on metal
the work on-site, with fees from standard decking were tamped level between screed Performance specifications
RIBA and ACE scales. Reinforced concrete rails set up on steel beam lines. Project specifications have also changed:
was built by the main contractor’s own clients can no longer rely on architect’s
labour, or by subcontract joiners, steelfixers Design-and-build contracts and engineer’s drawings to define their
and concretors. Since the early 1980s, contractor-led design- requirements, so they now rely on
The architect’s and engineer’s drawings and-build contracts have been heavily performance specifications. This has
specified finished structure levels and the promoted and are now used for most new affected floor levels and tolerances; instead

www.concrete.org.uk SEPTEMBER 2011 concrete 15


FLOORS AND SCREEDS

of the project architect and engineer struck – and the contractor controls these.

(Photo: Propex Concrete Systems.)


specifying these to suit the design and It is not clear how compliance with
construction method, these are now often the new specification is supposed to be
decided by clients or project managers using checked. If the levels on drawings are
generic specification clauses. As a result, finished levels, these can be checked any
specifications often require upper floors time after completion but how can pre-
in an office to be constructed to the same strike concrete levels be checked? Checking
tolerances as a warehouse floor (eg, surface after the formwork has been struck would
±15mm relative to datum). lead to endless arguments about whether
discrepancies were caused by construction
Laser levels and construction errors or post-strike deflection. To avoid
Laser levels have revolutionised warehouse this, the client would have to check pre-
floor construction since the 1980s; instead strike levels, which would have to be after
of long strips tamped between road forms, curing protection is removed from the
large areas are cast in a single pour, levelled hardened concrete but before the formwork
by laser level. Once the technique is is struck. On a busy site it may be impossible
mastered it is faster and cheaper, so it has to do this without delaying construction.
now spread to upper floors. To cut cost and
weight, these are also often power-finished Composite floors on metal decking
instead of screeded. BS 5950-4(3) draws attention to the extra
Laser levelling is ideal for constructing concrete dead load caused by decking
a ground-bearing warehouse floors with deflection but the possibility of extra
a flat surface. Blinding level variations weight caused by steel beam deflection is
do not matter as long as the required not mentioned, presumably because laser-
minimum concrete thickness is achieved levelling was not in use when it was written.
and the concrete is laid on solid ground, More recent guides such as Concrete Society
so movement during concreting or after Good Concrete Guide 5(4) and SCI Advisory
striking formwork is not a problem. Desk Note AD344(5) do draw attention to the
Upper floors are different. Tight level issue but leave it to clients, engineers and
tolerances are not as important but the slab contractors to work out their own solutions.
thickness must be right: if it is too thin, it In Eurocodes, the problem is even worse:
loses strength, stiffness and fire resistance makes decking and beams deflect, requiring the possibility of beam deflection increasing
and if it is too thick, the extra weight could extra concrete to make up the surface the weight of concrete is not mentioned
overload the supporting structure. Also level, which then causes further deflection, in BS EN 1994-1-1 Cl. 9.3.2(6) and BS EN
upper floors are either cast on temporary requiring yet more concrete. Second, the 1991-1-6 Table 4.2 reduces the allowance
formwork or on metal decking and steel steel frame also has a level tolerance of for construction loads from 1.5kN/m² to
beams that deflect, so there is more to ±10mm, so if beams are low, the slab will be 0.75kN/m²(7).
consider than just levelling the concrete thicker: 10mm of extra concrete increases In practice, floor slabs are rarely
surface relative to datum. the weight on the metal decking and beams constructed using the method assumed
When the concrete is levelled using by 0.24kN/m². If these factors were not by BS 5950-4 (tamping from screed rails).
tamping rails, these are measured off the allowed for in the design, a vicious circle Instead, they are either laid to constant
soffit formwork, so the slab has a constant can develop where adding extra concrete to thickness or else the surface is laser-levelled
thickness: if the formwork is low, the slab try to level the slab leads to overstressing or relative to datum. The former method gives
surface will also be low and vice versa. If even structural collapse. good control of dead load and structural
the soffit is precambered, the top surface thickness but produces greater surface
will follow the same profile and if the slab is Discussion – in-situ concrete slabs undulations than past practice, particularly
supported on steel beams that sag under the Changing levels on drawings from ‘finished if beam deflections are high. The latter
weight of concrete, the slab top surface will levels’ to ‘pre-strike levels’ certainly makes method gives a level surface but can lead to
also sag. life easier for the concrete subcontractor: large thickness variations and a dead load
A laser-levelled floor is different: its top instead of having to estimate precambers much higher than the theoretical value
surface level is set relative to the datum. and adjust levels so that the finished slab is calculated from BS 5950-4. If the contractor
Therefore if the shuttering is high, this will at the correct level, he simply lays concrete uses laser levelling but the potential extra
make the slab too thin and if it is low, the to the levels on the drawings and his job is dead load has not been allowed for in the
slab will be too thick. done. design, the consequences may be disastrous.
However, the change creates problems Clients, sheeting manufacturers and
In-situ concrete floor specifications for everyone else. For following trades such concrete contractors will all say that this
Modern specifications are also changing as bricklayers or ceiling fixers the pre-strike is a design issue. However, engineers
how floor levels are specified: for directly levels are irrelevant – they have to work cannot solve the problem either. As it is
finished floors, NSCS Version 3(1) says that to the levels after formwork is removed. not mentioned in BS 5950-4, many are still
levels on drawings are finished levels, after Similarly, client specifications quote levels unaware of it and in any case they often
striking formwork, but for screeded floors and tolerances for the completed structure. have no say in two of the most important
they are pre-strike levels. NSCS Version 4(2) It could be argued that engineers’ issues – the client’s specification of level
takes this further, stating that all levels on drawings should now specify ‘pre-strike’ tolerances and the contractor’s construction
drawings should be considered as pre-strike rather than ‘finished’ slab levels, allowing method. The fragmented nature of modern
levels. for deflection of the structure. However, design and construction makes it a difficult
in addition to bringing obvious scope for problem for any one party to solve. However,
Discussion – slabs on metal decking confusion, it should remembered that if the industry fails to find a solution, there
For laser-levelled slabs laid on steel beams deflection after casting is not just affected by is a risk that a major accident may occur.
and metal decking, two further factors come the design; it is also depends on formwork An industry-wide solution is needed that
into play. First, the weight of the concrete rigidity and the concrete age when it is defines standard options for constructing

16 concrete SEPTEMBER 2011 www.concrete.org.uk


FLOORS AND SCREEDS

these floors, each with compatible standard

(Photo: SMD Ltd.)


specification clauses and design guidance.
Defining industry-standard options would
(a) encourage a more rational approach
to specifications by clients and their
advisers, (b) clarify issues for engineers and
promote consistent design approaches and
(c) ensure that contractors’ construction
methods are compatible with the design and
specification.

Proposed specifications and


design guidance
Two standard options are proposed for
composite concrete slabs cast on metal
decking. Each specifies a construction
method, specification and design guidance
that are compatible and suitable for use
together. In both cases, mechanised plant
should not be used to lay the concrete unless
the contractor has checked that the decking
and supporting structure can safely support
its weight.

Option 1: ‘Constant thickness’ (c) Design guidance would be to revert to the principle that
specification (i) Floor self-weight quoted in levels on drawings are required levels of
This produces a floor slab which has manufacturers’ literature must include the finished structure, with the contractor
constant thickness along supporting beams allowance for additional concrete being responsible for making the necessary
and is level between them. This gives the thickness caused by sheeting deflection. allowances during construction to ensure
lightest, most economical structure. It is (ii) design decking and structure for that these are achieved.
suitable where absolute level is not critical. additional 0.6kN/m² dead load to cover Where precambering is needed to achieve
Alternatively, a screed may be applied to concrete ponding caused by beam the required levels (eg, on longer spans),
produce a level floor surface within close deflection. it may be necessary to level the surface or
tolerances. (iii) limit total cumulative dead load dipping to check concrete thickness instead
(a) Construction method: lay concrete to deflection of primary and secondary of laser levelling. ●
constant thickness, either by tamping beams to a maximum of 25mm.
from screed rails or by ‘dipping’ to check Acknowledgements:
concrete thickness. A higher deflection limit would increase Thanks are due to Barry Watts (Thomasons), Rob
(b) Specification the weight of concrete on the sheeting and Smith (Cidon Construction) and Dan Williams
(i) Level of top surface at column structure. The limit of 25mm is proposed as (SMD) for their assistance.
positions ±15mm. a reasonable compromise.
(ii) Slab thickness on beam lines These standard options are suitable for
±10mm. most buildings and should be adopted References
(c) Design guidance where possible, in the interests of consistent 1. CONSTRUCT. National Structural Concrete
(i) If screed is to be applied, calculated practice and construction safety. Where Specification. Third Edition, The Concrete
dead load should allow for increased they are not used, the client, engineer and Society, Camberley, 2004.
mid-span screed thickness. contractor must agree on a specification, 2. CONSTRUCT. National Structural Concrete
Specification. Fourth Edition, The Concrete
(ii) Steel beams may be precambered to design assumptions and construction Centre, Camberley, 2010.
reduce deflection. method and ensure that these are 3. BRITISH STANDARDS INSTITUTION, BS 5950.
compatible with one another. Structural use of steelwork in building. Part 4 –
Option 2: ‘Constant level’ Code of practice for design of composite slabs
with profiled steel sheeting. BSI, London, 1994,
specification In-situ concrete floors withdrawn.
Produces a floor slab with a level top As discussed, the change in NSCS Version 4 4. CONCRETE SOCIETY. Good Concrete Guide
surface but close tolerances are difficult to to make levels on architects’ and engineers’ 5 – Composite concrete slabs on steel decking.
achieve. It results in a heavier, less drawings ‘pre-strike’ rather than ‘finished’ Concrete Society, Camberley, 2008.
5. STEEL CONSTRUCTION INSTITUTE, Advisory Desk
economical structure than Option 1. is ill-conceived: it causes problems for Note AD344. Levelling techniques for composite
(a) Construction method: check steel following trades, it is incompatible with floors. New Steel Construction, April 2010,
beam levels; adjust target slab level standard project specifications (which Vol.18, No.4, pp.36–38.
to maintain correct thickness around generally specify level tolerances for the 6. BRITISH STANDARDS INSTITUTION, BS EN 1994-
1-1. Eurocode 4. Design of composite steel and
columns; laser level concrete surface. finished structure) and it makes checking concrete structures. Part 1 – General rules and
(b) Specification clauses compliance with the specification rules for buildings. BSI, London, amended 2009.
(i) Level of slab top surface (all points) impossible. It is therefore impractical, 7. BRITISH STANDARDS INSTITUTION, BS EN 1991-
±15mm. inappropriate and unenforceable. 1-1. Eurocode 1. Actions on structures. General
actions. Part 6 – Actions during execution. BSI,
(b) Slab thickness around columns This clause of NSCS Version 4 should be London, amended 2008.
±10mm. reconsidered. The most practical solution

Publications, Advice Sheets,


Technical Reports and more:
Visit: www.concretebookshop.com

www.concrete.org.uk SEPTEMBER 2011 concrete 17

S-ar putea să vă placă și