Jeddah Municipality
Engineering Management Consultancy
Contract No 19/005/001/0604/03/00/4
Revision History
Rev Date Description Author Checker Approver
1 15-July-13 AT BD BD
This report has been prepared for Jeddah Municipality in accordance with the terms and conditions of appointment for Engineering
Management Consultancy (EMC) Contract dated 16 April 2011. Hyder Consulting Middle East Ltd (31444) cannot accept any
responsibility for any use of or reliance on the contents of this report by any third party.
Document Management
Hyder Consulting Middle East Ltd
CONTENTS
Document Management
Hyder Consulting Middle East Ltd Page i
Document Management
Hyder Consulting Middle East Ltd Page ii
1 Electronic Filing System
Project filing can be done in hard copy or electronically. All documentation containing original
signature must be kept in softcopy. The filing structure for the EMC project is set up as follows:
Document Management
Hyder Consulting Middle East Ltd Page 2
1.2 Pre-Award (Undefined Projects)
Information on all the client queries, technical advice requests and possible projects are to be
kept in a separate drive using the folder structure below. It is a working folder for each
department
Document Management
Hyder Consulting Middle East Ltd Page 3
1.3 Document Control Folder (EMC)
The filing structure below is mainly used by the document control department to store all the
information exchanged by the EMC team and data sent out by the team
Document Management
Hyder Consulting Middle East Ltd Page 4
1.3.2 C-handbook
All EMC team administration documents, forms and templates are stored here
1.3.4 G-Submissions
1.3.5 R-Register
Document Management
Hyder Consulting Middle East Ltd Page 5
1.3.6 L-Reference Library
Used to store all Design Manuals, and other reading material that can be used and are useful
1.3.7 M-Minutes
Used to store all meeting minutes sorted into the different types of meetings
Document Management
Hyder Consulting Middle East Ltd Page 6
2 Procedural Workflows
2.1 Incoming Documents
START
DC to log submittal
in register
Document Management
Hyder Consulting Middle East Ltd Page 7
3 Document Numbering
All documents received and produced by the EMC team shall be assigned a specific document
number. This will allow the document controller to register and track that particular document,
package or submittal. The format for the document number will be as follows:
Sequential Number
Document Type
Department / Discipline
Project ID Number
Project ID (“414XXXXXXXXXX “)
The project ID is to be assigned either by the PMO, Planning or Contracts Department. The
project ID Coding is based upon the PMO document “JM-PMO-DOC-PRO-002” which is part of
their document control guidelines
Table 1.1
EMC Engineering Management Consultant
CMS Construction Management Services
JMA Jeddah Municipality / Amanah
OMS Operations and Maintenance Services
PMO Project Management Office
ACE Moharram Bakhoum
SPL Saudi Arabian Parsons Ltd
*acronyms to be added as required
Table 1.2
ADM Administration DRN Drainage PCS Project Controls
ARC Architectural ELC Electrical PMT Project Management
B&P Budgeting and Planning GEO Geotechnical QAC Quality Assurance
B&T Bridges and Tunnels HDR Hydraulics / Hydrology RDS Roads
COM Contract Management HSE Health Safety STR Structural
CIV Civil HVA Heat, Vent, AC TEL Telecommunication
C&R Civil and Roads LTG Lighting TRN Transportation
DOC Document Control MEC Mechanical URP Urban Planning
Document Management
Hyder Consulting Middle East Ltd Page 8
Document Type (“REP”)
Indicates which type of document
Table 1.3
MAN Manual FDN Final Design INV Invoice
MOM Minutes of Meeting DTL Detail ORG Organizational Chart
B Schedule /
0RPT Report FRM Form SCH
Programme
1 Monthly Progress
BOQ Bill of Quantities SPC Specification MPR
Report
–CNT Contract STD Standard EMX Email
PRQ Prequalification REF Reference TRX Transmittal
I RFP Request for Proposal REG Register LTR Letter
n AB As Built TRN Technical Note / Study MEM Memo
dCAL Calculation BDT Budget DRG Drawing
i
CD Concept Design EOH Expression of Interest
DD Detail Design EST Cost Estimate
0
Sequential Number
At the end of every document number is a 3 digit number that indicates the sequential number
of the document
*note all folders and filename will follow the document numbering system shown above.
1. Upon receipt of the document(s) they are checked for the following
Document is signed and is meant for Hyder
There is a content list and pages are numbered
Submittal is registered in the Amanah system (CTS)
2. Receive sheet and first page is stamped with appropriate date
3. Document is scanned and is saved under U:\EMC\B-Incoming Data\B10 Misc\For
Translation and given the file name “MM-DD-YYYY Amanah Ref”
4. Submittal is recorded in the incoming document register under the “Translate” tab with the
following information a) Amanah reference 3XXXXXXXXX b) date of receipt
5. Documents are handed to translators for interpretation
6. After Translation document is given back to Document Controller and incoming document
register is updated with appropriate information
7. The scanned file is moved to the appropriate location
Document Management
Hyder Consulting Middle East Ltd Page 9
8. The Hyder Action-Translation sheet is created and is attached at the top of the submittal
9. The document controller will distribute the submittal to the appropriate department or Team
Leader for their review and action
The diagram shows the flow of the document upon receipt of the document controller
Document Management
Hyder Consulting Middle East Ltd Page 10
4.2 Reviewing and Tracking Documents
Upon receipt of a document or submittal, several processes are in place to help the team all the
documents that has been received for review and comments
In order to ensure that no data is lost or misplaced all the documents received by the EMC team
are scanned and stored in the network. There are 2 main storage areas for the documents
The structure of the network is design to organize all the files in to folders and to group related
documents either by project or document type. It is the responsibility of the department head,
project leader or the document controller to ensure that the documents are in the correct
location at all times. They are also responsible to name the files appropriately ( see document
numbering Section 3 )
A hard copy filing system shall be maintained in accordance to the structure used for the
electronic files. It should mirror the structure for the electronic filing system. Due to the limited
space not all documents are kept as hard copies
Reviewing client requests and queries is one of the EMC’s functions. During the study and
review process these documents are kept by Hyder and are returned to the client as an
attachment along with the design review report or letter. Hard copies are not kept by the EMC
team
The team uses electronic copies of documents as the primary way to store their information so it
is important to backup these files to avoid losing critical information. The whole network is
backed up daily and a shadow copy of the network of up to 1 week can be accessed to retrieve
lost information. Backups are stored off site
There are several ways to locate an issue. Via date, location or amanah reference number
1. Search the incoming document register using the criterias date, amanah reference, or
subject, date receieved
2. The spread sheet can also be filtered
3. A link is provided in the spreadsheet that points to the exact location of the scanned copy of
the issue and all related documents
4. The register is divided into disciplines for easy distinction
5. If a document is not with any engineer it is under translation. Refer to incoming document
register
6. All scanned issue are located in the B-Incoming Date folder
Document Management
Hyder Consulting Middle East Ltd Page 1
4.3 Handling of Special Documents
4.3.1 Prequalification Documents
1. Prequalification documents are received via Courier, thru JM, via EMC_JeddahMunicipality
email or thru Mr. Aasif Variava. There should be 2 copies and 1 Electronic copy
2. Document is recorded in the Incoming Document Register and the PQQ Submission list
is updated
3. Electronic Copy is copied in two locations *
U:\EMC\L-Reference Library\L09 Supplier
U:\Prequalification\PQQ Consultant Submissions
4. 1 copy is kept in the Prequalification Cabinet and the other copy is handed over to the
engineer for review
Document Control is responsible for assisting in the timely submission and the final preparation
of the Monthly report for submission to Worley Parsons. DC will assist the planning department
to prepare the document
1. Planning department to collate all information needed in the report and placed in
U:\EMC\F-Reports-and Photos\F01-Reports\F01.1 Monthly Report
2. An appropriate Report Number will be given by DC
3. A folder is created in the above mentioned location
4. DC will combine all sections into a single pdf and produce 2 disc and 5 hard prints
5. A letter is created and submitted to Worley parsons
6. The Out Document Register.is updated
These steps are applied when preparing both the English and Arabic versions of the report
Document Management
Hyder Consulting Middle East Ltd Page 2
Fig 1.4
DC categorized (Cat.) as :
1. Letter
2. Drawings
3. Report
Amanah System must be Issue official doc. (Ref. from the Amanah & Close the status & file
Amanah
updated as “Sent” in CTS. Register) as per the standard & Other / Archive the Doc.
signed by DM / Nominee.
Document Management