Sunteți pe pagina 1din 6

Failure Analysis of Micro-hydroelectric sites in the

Province of lfugao, Philippines

Mahmoud Kabalan, Diane Tamir, Dr. Pritpal Singh


Electrical and Computer Engineering Department
Villanova University
Villanova, PA, USA
Mahmoud.kabalan@villanova.edu

Abstract- Micro-hydroelectric power has the promise of PHIUPPINES


supplying clean renewable energy for remote communities at a
cost-effective price. However, previous attempts of
implementation suffered from a high failure rate and proved to be
unsustainable. This paper presents a failure analysis of multiple
micro hydroelectric sites that were built in the province of Ifugao,
Philippines. The analysis was done by completing field trips to the
failed sites and performing a technical examination of the
neglected hydroelectric facilities. Moreover, interviews with
multiple community members and officials were held to
understand the social, culture and economic context of these
systems. The interviews also focused on including female
community members to get a gender neutral overview of the
community. The study showed that multiple technical, economic
and social factors can lead to the failure of the implementation of
this technology. A relatively successful micro-hydroelectric system
in the province is highlighted to provide a comparison with the
other failed sites. The aim of the paper is to provide an insight on
the best practices for the future development of micro­
hydroelectric systems. The study showed that a sustainable micro­
Figure 1: Map of the Philippines
hydroelectric system should address the three pillars of
sustainability - social, economic and technical. rural electrification or developments projects. These projects
face similar challenges and hurdles to ensure that they are
Keywords-micro hydroelectricity; failure analysis; rural
sustainable.
development; social and economic factors

I. INTRODUCTION
II. ABATAN MrCRO HYDROELECTRIC SYSTEM
Micro hydroelectricity is a technology well suited for rural
The first failed system is located in the village of Abatan in
electrification projects [1]. However, this technology suffers
Hungduan, Ifugao. Abatan is a small community with around 50
from a high failure rate in such a setting [2]. The sustainability
households. The micro hydroelectric system was constructed by
of these systems rely on multiple social, economic and technical
a local NGO in the year 1998 with an installed rated capacity of
factors that are complex and dynamic [3-10]. The authors 21 kW. Once the system was installed, the community was
wanted to comprehend these factors by studying three failed solely responsible for troubleshooting and system repairs. The
and one successful micro hydroelectric sites in Ifugao. The NGO did not provide any training or technical support for the
three failed sites are in the villages of Abatan, Bokiawan and community. The system functioned for two years with
Maggok while the successful one is in Hapao. The province of maintenance being carried out by untrained community
Ifugao is located in north of the Philippines (Figure 1) and is members who were eager to keep the system operational. By the
known for its mountainous terrain and numerous rivers and year 2000, the system broke down since the community could
streams [11]. The aim of the study was to gain experience and not afford the cost of repairs anymore. The provincial electric
insight before embarking on an effort to develop a new micro utility, IFELCo (Ifugao Electric Cooperative), reached the
hydroelectric site in the province of Ifugao. The following community around a year after the system broke down.
paper presents an overview of the sites studied and the lessons
Four elected operators were responsible for collecting the
learned from these trips. The infonnation gathered here is based fees from the participating households. The community decided
on interviews with the local government officials or community on a fee of IPhp/watt/month for each household based on their
members responsible for running and operating these systems. capability to pay. These operators were not paid but were
Although the failure analysis is done for micro hydroelectric exempt from the electricity consumption fee set by the
systems, the insights and lessoned learned can be applied to any community. The collected funds were used for system

2014 IEEE Canada International Humanitarian Technology Conference - (IHTC)


978-1-4799-3996-1/14/$31.00 ©2014 IEEE
maintenance which consisted mostly of lubricating the bearings voltage and frequency of the generator could not be controlled
with occasional repairs to the generator and turbine. and the system's exact operating point would vary.

The installed electrical lines were not compatible with the The system ultimate failure was when the turbine, its
power system. The quality of the electricity deteriorated as the bearings and all its fittings broke. The community was unable to
distance from the household to the powerhouse increased due to give us a clear picture on what caused that major system failure.
line losses. The voltage drop was so significant that households The community did not attempt to repair the system because
far from the powerhouse were not capable of using light bulbs they lacked the funds and because plans for connecting to
at times. The main usage of the electricity was for lighting IFELCo were already in place. Despite all the hard work and
purposes. The most common light bulb was the 25 Watt costs given by the community, the community would
incandescent bulb that is dim and does not provide adequate recommend this system to another un-electrified village since
lighting for reading. However, the community claimed that having poor quality electricity is better than none
sound systems were used in special occasions such as
community gatherings. The powerhouse has been abandoned III. BOKLAWAN MICRO HYDROELECTRIC SYSTEM
for almost a decade. The powerhouse is now completely covered The second failed system is located in Bokiawan in the
with overgrown forest and the inside of the powerhouse is now municipality of Kiangan, Ifugao. The system was designed and
filled with mud that is five inches deep. installed in 1999 by the same local NGO mentioned above and
funded by the municipal and provincial government. The power
rating of the installed system was 10 kW. At the time of the
installation, the system supplied power to 22 households,
however that number decreased to 10 due to high maintenance
costs and low power quality. The system is not operational as of
late2011 after a typhoon destroyed a section of the flow channel.
The community used the electricity for lighting and re-charging
cell phones. Each household was allowed two light bulbs only.

The NGO was the only entity in contact with the community
and coordinated all construction efforts. The community's
contribution was in the form of free labor throughout the
construction of the system. The NGO's personnel purchased the
required system materials and components such as generator,
electric lines, transformers, etc. However, the original turbine
was constructed at the office of the NGO. Moreover, there were
Figure 2: Map of the municipalities in the province of plans to have a rice mill installed at the powerhouse; however
Ifugao these plants were never implemented due to lack of funds.
The micro-hydroelectric system suffered from multiple
The management of the micro-hydro system was the
technical problems throughout its short life span. The
responsibility of the Bokiawan Farmers Association once the
implementation of the system design was carried out by un­
NGO left the village. The association was in charge of running,
specialized individuals and resulted in major system flaws. The
repairing, and collecting maintenance and usage fees from the
penstock leading into the turbine was at a very steep angle
community. The Bokiawan Farmers Organization was an
causing an excessive head lose. Moreover, the pipe diameter
existing local group formed to build and maintain the vital
decreased from 8 to 6 inches inside the powerhouse and caused
irrigation canals used in rice farming.
more pipe-losses. The turbine was not constructed properly
which caused the shaft to break in three separate occasions. The An engineer provided training on basic system maintenance
original design had a 1.5 inch diameter shaft that was welded to and electrical connections. No training or aid was given to the
each side of the runner of a typical cross flow turbine design. farmers regarding business planning, business development, or
After the first failure of the turbine, the shaft diameter was the fmancial management of the system. The Farmers
increase to two inches. The final design had a two inch diameter Association together with the community decided on a fee of 10
shaft going through the runner with the runner being welded Php per light bulb per month. This fee was selected by
onto the shaft. considering the spending capability of the community. The fee
covers regular maintenance which is mainly bearings
During system operation, a bearing inside the generator
lubrication. Additional funds were collected from each
broke causing the rotor to brush against the stator which resulted
household when a component of a system broke down and
in short-circuiting the generator. Consequently, the generator
needed to be replaced.
was rewound twice because the short circuit caused it to burn
out twice. The fust time the generator was rewound in a shop in There were many problematic areas in the design or
nearby town of Lagawe while the second time the community implementation of the mechanical and electrical components of
rewound it on site. Moreover, the system had neither an the micro-hydro system. The penstock feeding into the
electronic nor a mechanical governor or speed controller which powerhouse is 8 inches in diameter; however its diameter
meant that the speed of the generator and turbine could not be decreases to 6 inches inside the powerhouse. Moreover, the gate
controlled. With the absence of any control mechanism, the valve is placed on the 6 inch pipe and not on the 8 inch pipe. The
6 inch gate valve was not able to withstand the pressure of the 8
inch pipe and it started to leak. In addition, the turbine was not Additional working days given by locals were then compensated
fixed properly to the floor of the powerhouse so the operators with a daily wage. However, due to poor management, some
piled rocks on the turbine casing to limit the vibrations. Since laborers were paid and some continued to work for free. This
the turbine had no by-pass, the operators' only choice was to wage inequity stirred up the community's disapproval towards
wedge a metal rod into the runner pulley to stop the turbine from the system management.
rotating as water passes through it. This placed excessive stress
The installation of the electrical lines was supervised by a
on the runner and shaft of the turbine and caused damage to both.
civil engineer. Step-up and step-down transformers were
The runner needed to be replaced between 5 and 10 times due to
purchased to reduce the line losses; however these were
twisting and broken runner blades. Additional system repairs
unsuccessfully installed. Contrary to basic electrical
that were made included changing the bearings of the turbine
transmission and distribution techniques, the step-down
and the carbon brush of the generator.
transformer was installed in the powerhouse while the step-up
As for the electrical components, the size of the generator transformer was placed close to the village. Once these
was inaccurately sized. First, a 10 kW generator was first transformers were erroneously installed, the electric system
installed however, in an attempt to increase system capacity a 30 performance degraded as expected. After carrying the heavy
kW generator was bought. When that generator was installed, transformers across the mountainous terrain and rice fields, the
the generator/turbine assembly was not able to rotate due to locals were disheartened and decided to leave the transformers
improper sizing of the new generator. That generator is still in in the rice fields. This engineering mistake caused the
the comer of powerhouse unused since it was purchased more community to further lose trust in the NGO's staff.
than 10 years ago. Moreover, the system has no speed control or
The Maggok Sustainable Electric Cooperative (MAGSEC)
governor to control the rotation speed in order to produce proper
was formed to run and maintain the hydroelectric system. The
voltage and frequency levels. Furthermore, the electrical
positions in the cooperative were elected by the community and
distribution system was implemented in a bizarre fashion. Two
included four directors, a manager, secretary, treasurer,
transformers were purchased, a 30kVA step up transformer and
lineman/collector, and three operators. Out of these positions,
5kVA step down which are mismatched. Furthermore, these
only the linemen and the operators were paid. The lineman
transformers were installed right next to each other at the
received training for maintaining the electrical lines and the
powerhouse without the basic understanding of how these
household connections while the three operators were trained in
transformers work. These transformers had no advantage or
basic maintenance of the turbine and generator. MAGSEC
contribution to the overall system performance and were a poor
charged new consumers a 50 Php (US $1) connection fee and
investment.
the cost of the connection lines to their house. A flat rate of
Nevertheless, the system was able to produce electric energy 50Php/month is paid per household for the electricity regardless
adequate only for lighting purposes and cell phone charging. of the quantity of electricity consumed. This rate was agreed
The system stopped operating after a typhoon destroyed the upon by general assembly on how much locals can afford to pay
water canal by triggering multiple landslides in September 2011. for electricity. This rate is too low to cover the expenses needed
These landslides destroyed about lkm of canal in three spots, to maintain, repair and run the systems.
with one landslide going all the way down to the river.
The community used the electricity for lighting and charging
The local electric utility provider, IFELCo, extended its lines cell phones. Each household was allowed a maximum of three
to reach the village of Bokiawan around 2009. With the micro­ bulbs, but every household paid the same flat monthly rate
hydro site currently not operating, the community is left with the regardless. Moreover, many had appliances like televisions and
sole option of connecting to the public electricity grid. radios and some had power tools like wood planers. There is also
Currently, households pay over 100 Php/ month for basic one refrigerator in the town hall shop purchased recently but is
lighting and sell phone charging which some households are not operational due to the low quality electricity.
struggling to meet. Since the utility grid reached Bokiawan, the
The system fust failed in 2007 one year after construction,
community purchased two refrigerators, 10 TVs and some other
when the turbine cracked under the pressure of the water. It was
appliances for personal usage. However, no income generating
then taken to Kiangan to be welded back together. Since then,
activities or livelihood projects resulted from the electricity.
the community has always had problems with the runner,
IV. MAGGOK MICRO HYDROELECTRIC SYSTEM especially with the blades breaking off. They have also
experienced many problems with the generator, which required
The third and last failed site visited is the village of Maggok
constant repairs and replacements. The fust generator purchased
in the municipality ofHungduan. The system installation started
in 2006 is a 15 kW unit while the second generator purchased in
in 2005 with a rated capacity of 25 kW. This system was again
December 2008 is a 20 kW unit. The community has never
designed and constructed by the same NGO as the first two
received constant and good quality electricity. This is not only
systems above. The project funding was provided by the local
because of the poor turbine design providing inconsistent
government and foreign aid organizations. Construction was
rotation, but because of the poor electrical distribution system
finally completed in August 2006 providing electricity to 80
and lack of transformers.
households until the turbine's first failure in 2007.
During a field trip to the powerhouse in 2009, the gate valve
The construction of the micro-hydro system was completed
was leaking heavily and causing the powerhouse to flood. There
in about 8 months. The community provided free labor during
were no transformers in the system and the electrical lines gauge
construction in the amount of five working days per household.
was too small resulting in significant line losses (estimated at
more than 40%). Moreover, there is no speed control or connected their households by themselves to the electric system.
regulation between the turbine and generator which causes the However, this process was not planned or controlled and caused
generator voltage level to be lower than its rated output. electricity demand to exceed the supply resulting in low quality
Vibrations were felt from the turbine when standing in the electricity.
powerhouse since the foundation wasn't properly laid. The
After the 3kW system was completed in 1997, an
turbine and generator broke frequently leaving the community
organization was formed to manage and maintain the micro­
with blackouts for weeks at a time. The funds collected from the
hydro system. The organization comprised of members from the
community were not enough to pay for repairs and maintenance.
two communities being served; Hapao and Baang. Once the
Some households refused to pay the flat rate due to limited
second system was operational, the former organization was
resources and/or dissatisfaction with the quality of light.
split in two yielding one organization for Hapao and one for
Eventually, the community lost faith in the system and few cared
Baang. These two organizations have coordination meetings
to contribute efforts for repairs.
since both systems share the same operator and powerhouse.
A strong typhoon wiped out the sedimentation tank along The operator turns the system on at night and off in the morning
with the entire rock bed it was resting on. This has left the on a daily basis. So far there was no conflict reported between
community without electricity since October 2011. Meanwhile, the two communities served by the system.
the community has made efforts to repair this problem but have
The fIrst decision that the organization took was to set the
not made much progress due to a lack of funds and the time
electricity consumption fee. The decision was taken by
needed to tend to their crops.
consensus between the community members based on their
In 2009, efforts began to rehabilitate the gate valves, turbine, ability to pay. The fee was a flat monthly rate of 20 pesos for
generator, and Electrical distribution system. However, these each household; however payment is not consisted since some
efforts have been largely unsuccessful and suffered multiple households cannot afford the fee year round. Moreover, the
delays due to funding and coordination problems. The organization had to control the number of households
community has been without electricity since the end of 2011. connecting to the system and stopped allowing more to join to
The locals have lost all faith in the micro hydroelectric system maintain electricity quality. The organization would direct the
and are hoping for the national electric grid to reach their operator to forcefully disconnect households that are illegally
community soon. connected. The organization divides the 20 Php fee as follows:
10 Php goes to maintenance, 7Php goes to the operator, and 3
V. HAP AO MICRO HYDROELECTRIC SYSTEM Php goes to the collector. Regular maintenance only covers
The operating micro hydroelectric system was found in the lubrication of the pulleys and a small percentage of repairs.
village ofHapao which is in the municipality of Hungduan. The Further funding is solicited from the community and the
system was design and constructed by experienced faculty of a government when additional repairs are needed such as buying
university. The implementation was completed over two phases. new belts. If problems or repairs cannot be addressed by the
In 1997, a 3kW system was installed to provide power to the community, the organization contacts the university faculty that
households in Hapao and Baang. Baang and Hapao are two usually visits to evaluate the problems and attempt to fIx them
communities that are separated by a large stream and are U.N. free of charge.
World Heritage sites since 1995. In 2005, the system capacity
Electricity is mostly used for lighting with one to three bulbs
was augmented by installing a new 5kW micro hydroelectric
per household. Good quality of light is reported when 5w bulbs
system to account for the increased energy demand. After the
are used, but the lights usually dim or turn off between the hours
5kW system became operational, the electrical lines were
of 6pm and lOpm when demand is at its peak. There is no limit
separated so that the 5kW system provided power to Baang
or monitoring on the amount of electricity consumed. Some
while the 3kW system provided power to Hapao.
households have TVs but rarely use them because they don't
The faculty prepared the designs for both systems and turn on due to low voltage. TVs can be turned on during off­
oversaw the implementation stage which was completed by free peaks hours once most of the community has gone to sleep and
labor from the community. The construction of each phase took turned their lights off. Some skilled laborers have also tried
around one month and was completed in the same respective using power tools for carpentry and carving but the tools did not
years; 1997 and 2005. In 2005, a new tank and penstock were work with the low power quality. Aside for the poor quality, the
constructed while the new turbine and generator were housed in system is reliable, and is only down for about two to three days
the same powerhouse next to the 3kW turbine/generator that was per month for maintenance.
installed in 1997. The 3kW and 5kW systems are totally
The system is currently in good structural shape with two
independent from one another since each system has a separate
intake tanks, a sturdy penstock and a powerhouse with a solid
tank and penstock and supplies energy to a different
construction. There are minimal vibrations in the powerhouse
neighborhood. The local government funded the construction of
since the foundations of turbine and generator set in the concrete
the powerhouse and the purchase of a back-up generator while
floor. The penstock enters the powerhouse close to the ground
the university covered all other costs of the system.
and is set in the concrete eliminating the need for extra supports
The faculty did not provide any technical training to the under the gate valve. Both systems have not suffered any major
community during or after system construction and electromechanical malfunctions that caused extended
implementation. No professional linemen oversaw the linking of downtime. The 5kW generator was replaced once while the
the electric distribution network so community members turbine was swapped with an improved turbine. Other
occasional maintenance included replacing bearings, pulleys most appropriate if the end use is lighting and cell phone
and the generators' carbon brushes. charging and are affordable. On the other hand, micro
hydroelectricity provides enough power for the development of
At the time of the field trip, only the 5kW system was
small businesses and industrial applications but are a significant
operating while the 3kW system was inactive because the belts
connecting the turbine to the generator snapped. The community investment.

is currently in the process of purchasing replacement belts. The second layer of sustainability in rural development
Multiple gear ratios were used on the 5kW turbine generator projects is financial. A sustainable system must be able to
assembly to speed up the generator to rotate at a higher velocity. survive financially without the constant need for external
The generator is rated to produce electricity at 220V; however it funding for system maintenance. This requires a self-sustaining
is producing electricity at around l30V. That is due to the fact system coupled with a proper organization structure. Previous
that the generator's shaft speed is much less than its rated speed studies have shown that income generating activities are vital
of 3600 rpm (revolutions per minute). The pulley system, with in ensuring sustainable rural development projects [12].
its present gear ratio, is not sufficient to increase the speed of the Accordingly, these projects need to be coupled with income
turbine's revolution up to the rated speed of the generator. generating activities to maximize sustainability and impact on
Consequently, the output voltage is almost half its rated value the local economy and quality of life. Moreover, the community
since the generator's output voltage is almost proportional to its requires training on the basic financial and management skills
shaft speed. Increasing the pulley ratio is impractical because needed to properly manage such projects.
that would de-stabilize the mechanical assembly between the
Finally, the social issues must be addressed. Social aspects
turbine and generator. The electric lines extend directly from the
are the most complex to fully comprehend. Those rural
generator to the community without utilizing transformers to
development or rural electrification projects should not disrupt
raise the voltage level. With the generator producing 130V
the intricate social dynamics of these communities. Any
electricity, we estimate that line loses would be too high which
disruptions might lead to losing the trust of the community such
causes the power quality issues reported earlier. The authors
as the case of Maggok.
discussed the matter with the university faculty. The decision to
buy the 3600 rpm generator was due to the superior quality and CONCLUSION
VII.
performance of this unit. The faculty informed us that units there
were few reliable units with a rated speed of 1800 rpm at the
time of construction. The study above presented a failure analysis for micro
hydroelectric systems in Ifugao. The lessons learned can be
VI. DISCUSSION
applied to other rural electrification projects. Insuring the
The field studies of the above four micro hydroelectric sustainability of such projects might be difficult. However,
systems provide a general overview of the challenges facing the certain steps can be taken to improve the chances of the survival
implementation of this technology in Ifugao. The sustainability of these projects.
of these systems relies on social, economic and technical Acknow ledgment
factors. The technical aspect is the foundation on which
sustainability is built. NGOs participating in such projects The work done in this paper was funded by Halloran
should insure that they possess the proper capacity, technical Philanthropies. The authors are grateful for that financial
skills and experience to participate in such endeavors. It can be support.
seen that a faulty system design and implementation destines
REFERENCES
the project for failure in such a setting. A defective system
would require significant funding to fix the errors which is [I] R. Waddell and P. Bryce, "Micro-hydro systems for small communities,"
Renewable Energy, vol. 16, pp. 1257-1261, lI/ 1999.
prohibitive in rural development projects were funds are
[2] M. M. Vergel, "Inventory of eleven (II) micro-hydropower sites in
limited. However, the lack of funds also require shortcuts in the
province ofTfugao to determine 'as-is' condition and recommendation for
technical designs of such projects. A balance between the improvement. ," 2005.
essential and the unessential system components is required and [3] N. U. Blum, R. Sryantoro Wakeling, and T. S. Schmidt, "Rural
is challenging to find. Studies need to be done on the most electrification through village grids-Assessing the cost competitiveness
of isolated renewable energy technologies in Indonesia," Renewable and
effective "no-frill" designs that lower system costs but do not
Sustainable Energy Reviews, vol. 22, pp. 482-496, 6// 2013.
sacrifice performance. Consequently, the issue is tied to the
[4] W. Drinkwaard, A. Kirkels, and H. Romijn, "A learning-based approach
capacity and expertise of the participating organization (NGO, to understanding success in rural electrification: Insights from Micro
government, etc.) in such projects. As the three failed systems Hydro projects in Bolivia," Energy for Sustainable Development, vol. 14,
showed, the NGO had no experience in properly designing and pp. 232-237, 9// 2010.
implementing a micro hydroelectric system. In contrast, the [5] A. Gurung, O. P. Gurung, and S. E. Oh, "The potential of a renewable
energy technology for rural electrification in Nepal: A case study from
experienced university faculty built two systems that are still
Tangling," Renewable Energy, vol. 36, pp. 3203-3210, Il!I 2011.
operational to this day.
[6] C. Kirubi, A. Jacobson, D. M. Kammen, and A. Mills, "Community­
Moreover, the goal of the organization must be clear at the Based Electric Micro-Grids Can Contribute to Rural Development:
start of such rural electrification projects. The ultimate goal of Evidence from Kenya," World Development, vol. 37, pp. 1208-1221, 7//
the project would dictate the most applicable technology. For 2009.

example, solar photovoltaic panels and small batteries are the [7] A. A. Lahimer, M. A. Alghoul, K. Sopian, N. Amin, N. Asim, and M. T.
Fadhel, "Research and development aspects of pico-hydro power,"
Renewable and Sustainable Energy Reviews, vol. 16, pp. 5861-5878, 10// [10] M. Kabalan, D. Tamir, P. Singh, "Community Engagement for the
2012. Development of a Micro-hydroelectric site in Ifugao, Philippines," in
[8] M. M. Rahman, 1. V. Paatero, and R. Lahdelma, "Evaluation of choices lEEE-fHTC, Montreal, Canada, 2014. Accepted for publication

for sustainable rural electrification in developing countries: A [II] P. N. S. Office, "2010 Census of Population and Housing," 2013.
multicriteria approach," Energy Policy, vol. 59, pp. 589-599, 8// 2013. [12] ITDO, " BEST PRACTICES FOR SUSTAINABLE DEVELOPMENT.
[9] D. Palit and A. Chaurey, "Off-grid rural electrification experiences from OF MICRO HYDRO POWER FINAL SYNTHESIS REPORT" 2000.
South Asia: Status and best practices," Energy for Sustainable
Development, vol. 15, pp. 266-276, 9// 2011.

S-ar putea să vă placă și