Sunteți pe pagina 1din 4

HELSINKI, FINLAND

Central Wastewater Treatment


in Helsinki
Going Underground
The Viikinmaki central wastewater
treatment plant in Helsinki, Finland,
commissioned in the early 1990s,
was the largest underground facility
of its kind. It was also very success-
ful. So much so, that it is currently
being extended with the addition of
some 200,000 cu m of space to
accommodate denitrification filters
and extra treatment lines.
The extension has to be squeezed
into an area with low rock cover that
is close to surface development.
Hence, particular care has to be taken
with drilling and blasting, and with
rock reinforcement.
For the extreme drilling accuracy
required, contractor YIT used a new
Atlas Copco Rocket Boomer XL3 C
with COP 1838HF rock drills. The
faster drilling rate of the high fre-
quency machines combined with the
computer control of the drillrig
resulted in very efficient excavation.
Additionally, some 60,000 m of rock-
Wastewater was pumped from the old Atlas Copco Rocket Boomer XL3 C
bolts were installed using an Atlas
Copco Boltec 435 SH. treatment plants to the new central treat- drilling at Viikinmaki.
ment plant, and nearly 20 km of new sewer
tunnels was built. The treated water is led
Centralization of Treatment out to sea through an outfall tunnel, built in
the mid-1980s, and discharged into the sea
Helsinki’s first wastewater treatment plants through a rock shaft, opening in the sea
were built in the 1910s. New plants were bottom near the island of Katajaluoto,
progressively added to the system as the 8 km from the southern tip of Helsinki.
population grew, until there were eleven
plants in operation by the beginning of the Rock Engineering
1970s. This figure had dropped to eight by
the mid-1980s, however, as the first steps Several factors favoured Viikinmäki as the
towards centralization were taken. ideal location for the new plant. It was
This development coincided with the centrally situated with respect to the older
completion of a feasibility study, which treatment plants. The area was undevel-
examined the possibility of replacing all oped, and it was high enough to allow a
the existing plants with one central treat- single pumping stage from treatment to
ment plant built underground in rock. The outfall, even though it was underground.
goal was to construct a single technically All the wastewater and sludge treatment
and economically efficient plant capable of units are located underground in rock. The
raising treatment efficiency, while also plant’s efficient layout and the excellent
meeting tough environmental restrictions. construction properties of the hard granite
The city council gave the go-ahead for and mica gneiss bedrock also helped to
the project in 1986, and construction of ensure a cost-effective solution. Further-
the Viikinmaki plant started early the more, the rock cover also provides a stable
following year. ambient temperature for the treatment

FACE DRILLING 53
HELSINKI, FINLAND

25 mm diameter were installed to a


typical depth of 4 m, and a total area of
199,000 sq m was shotcreted.
A network of drains was installed under
the shotcrete to channel dripwater to the
treatment process. Similarly, drainage mats
were placed between the rock and the con-
crete walls of the basins, with a layer of
macadam. Water leakage from the entire
treatment plant has been extremely low,
only about 200 lit/min.
Extensive rock mechanical calculations
were performed at the planning stage to
estimate the amount of rock movement, if
any, that excavation would produce. Every
effort was made to ensure the stability of
the rock, and to predict any changes likely
to be caused by excavation.
Several extensometers were used to
measure movements at critical points in
the roof and pillars during excavation and
construction. The loads placed on the
reinforcement structures, and changes to
the stress state of the rock, were also moni-
tored. Precision levelling was also used to
Location of Viikinmaki wastewater plant all year round, despite the adverse monitor movements in the rock surface
treatment plant and outfall. surface conditions during winter. above ground. The calculated and mea-
The rock engineering aspects of the sured results corresponded closely with
central treatment plant were unusually each other. Rock movements continue to
challenging due to the plant’s exception- be monitored regularly.
ally large size and the widely varying
bedrock conditions. The total tunnel Design of Extension
volume excavated was 1,000,000 cu m.
Rock cover over the plant is zoned for new For nearly half a decade, the treatment
housing estates and is at minimum 10 m. plant served mainly to reduce BOD and
In dipping areas housing is not allowed. phosphorus from waste water. In 1997,
There the halls are very near the rock sur- extra equipment was installed to facilitate
face, with a minimum rock cover of only 50% nitrogen removal.
4 m. These areas are also characterized by Initially, the total population to be
weakness zones which vertically traverse served was 750,000 inhabitants. Since
the rock caverns. The span of the process original commissioning in 1993, the popu-
halls, 17-19 m, is also exceptionally large lation in the area has increased by some
with respect to the various thicknesses of 10,000, while the treatment requirements
the rock cover. The halls are separated by have become stricter.
10-12 m-thick pillars. Helsinki Water is undertaking an ongo-
Rock mechanical dimensioning calcula- ing project to extend the treatment process
tions were used to ensure the stability of to meet the stricter requirements, especial-
the caverns. The large scope of the project ly regarding nitrogen, which has to be
also placed a high priority on optimizing reduced by 70%. The required 200,000 cu m
worksite arrangements and logistics, the extension to the Viikinmaki plant will
distribution of contracts and the disposal of house de-nitrification filters and additional
the excavated rock. treatment lines.
The treatment process used is a typical
Support and Stability activated sludge process. Wastewater
organics are degraded by digesting sludge
The excavated caverns were reinforced first in four digesters, and then combusting
with grouted rebar bolts and steel fibre the digester gas to generate heat and elec-
reinforced shotcrete. About 55,000 bolts of tricity. The energy thus recovered adds up

54 FACE DRILLING
HELSINKI, FINLAND

to roughly 50% of the total electricity con-


sumption and 100% of the heat require-
ment of the entire plant.
The main designer and process designer
was Plancenter Ltd.
Lack of available space necessitated the
filling of old access tunnels with concrete,
and using rock masses as close as possible
to the margins of the hill. The existing
plant employs gravity discharge, and so the
new facilities had to take account of its
elevation. Helsinki City Geotechnical
Division was the tunnelling designer, with
engineering firm Rockplan Ltd as subcon-
sultant.
The two new treatment lines are parallel
with the old existing ones. The filter
cavern and related facility cavern are
transversely positioned, at the ends of the
sewage treatment lines.

Excavation
being carried out by Suomen Malmi Excavation to house one of the Viiki
Rock Mechanics Technology Ltd was (SMOY) and Geotek Oy, while ground- denitrification chambers.
selected to measure and calculate the rock water level monitoring is the responsibility
stress using an overcoring technique. Rock of Helsinki City Geotechnical Division.
sample drilling, measure-while-drilling Residential houses, a school and streets
(MWD), TV imaging, seismic sounding, are being built simultaneously with the
and radar were also employed. Propagation construction of the sewage plant, imposing
of blasting vibration was studied using test limitations on underground blasting and
blasts. The two principal stresses were support work. Building is only allowed
found to be horizontal, with magnitudes of where the rock cover exceeds 10 m.
8 MPa and 3 MPa. The third principal stress The excavation contractor for the
is vertical, and its magnitude is 1 MPa. All 200,000 cu m extension was YIT
principal stresses are compressive. Construction Ltd. Their contract com-
Systematic monitoring of the movements menced in May, 2000 and was completed
of the rock mass, and the rock quality, are in January, 2002, and was valued at Section of the Viikinmaki plant.

FACE DRILLING 55
HELSINKI, FINLAND

hydraulic double-dampening system absorbs


and dissipates the shockwaves from the
rock, while establishing the best possible
contact for the drillbit. The reversible
rotation motor gives high torque, and rota-
tion speed is easily adjustable to match
changing rock conditions. The low profile
of the rock drill permits close drilling to
the sidewall, with only 2 degrees of look-
out angle. Nitrogen charged accumulators
reduce vibrations and wear on hydraulic
components.
Between July and September, 2001, the
Rocket Boomer XL3 C drilled 42,500 m in
203 percussion hours, an average penetra-
tion rate of 140 m/percussion hour.

Rock Reinforcement
An Atlas Copco Boltec 435 SH was used for
drilling and installation of some 60,000 m of
grouted steel rockbolts. YIT also placed
some 6,500 cu m of shotcrete and conducted
Isometric plan of the Viikinmaki €5.6 million. Because of proximity to the cement grouting where necessary. Some
wastewater treatment plant.
operating sewage plant, flexible airtight disused sewage tunnels and access adits
blasting barriers of wooden beams secured were filled with 4,200 cu m of concrete to
by steel cables were installed. Initially, rehabilitate the rock area for reuse.
these were found to be too flexible, and All excavated rock has been crushed
had to be braced with profile steel. and used in earth construction, where it
replaces natural gravel. Initially, the crush-
Computer Based Drilling ing was carried out on the surface, but as
soon as there was space enough under-
YIT employed an Atlas Copco Rocket ground, the crushing operations were
Boomer XL3 C with ABC Total to drill moved into a tunnel. Some 500,000 t of
some 250,000 m of blastholes. This is a rock was crushed underground using a
fully-computerized hydraulic tunnelling rig mobile crusher. The crusher capacity of
with high reaching Eagle console for huge 2,000 t/day over two shifts limited the rate
cross sections up to 179 sq m, and ideally of rock excavation, despite optimum work-
suited to conditions at Viikinmaki. It is site arrangements.
fitted with Atlas Copco’s innovative Rig The bedrock is mostly hard and crys-
Control System (RCS) with interactive talline, but the extension site is crossed by
operator control panel with full-colour dis- a fractured zone, affecting three of the tun-
play of the computer-based drilling nels, which have a span of 17 m and a roof
system, which includes auto-collaring and thickness of only 2-3 m. Here, rockbolting
anti-jamming protection. of roofs and walls was carried out in fans
A major feature of this drillrig was that it from two directions, while the excavation
was one of the first to be equipped with the advanced in small increments.
HF version of Atlas Copco’s successful The excavation was completed in early
COP 1838 rock drill. The COP 1838HF has 2002. The filter cavern will be commis-
a higher impact rate than the popular ME sioned in late 2003, and the additional
version, delivering more frequent blows at treatment line in late 2004. ■
almost the same impact energy. The result is
up to 20% faster drilling in the 43-51 mm Acknowledgements
hole range.
The long, slender piston of the COP The editor is grateful to Janne Lehto and
1838 series permits high impact energy to Veikko Koponen of YIT Construction Ltd
be utilized, while considerably increasing for their inputs and assistance with revision
the service life of the drill steel. A of this article.

56 FACE DRILLING

S-ar putea să vă placă și