Documente Academic
Documente Profesional
Documente Cultură
discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/259292030
CITATIONS READS
0 260
2 authors, including:
Ramli Nazir
Universiti Teknologi Malaysia
116 PUBLICATIONS 320 CITATIONS
SEE PROFILE
All content following this page was uploaded by Ramli Nazir on 14 December 2013.
Abstract
The paper presents the history of ground improvement work adopted in the campus development
for Universiti Tun Hussein Onn, Batu Pahat, Johor. Due to the limitation of construction cost,
ground improvement work is to be limited for roads and parking lot only. 11 numbers of
boreholes and 13 numbers of CPT tests were performed to established soil parameters needed for
the design works. Excessive long term settlement was the major concern for the area due to the
existing of soft soil within the area. In order to minimize the long term settlement, ground
treatment would be required. Various ground treatment methods had been assessed and it was
decided to use surcharge and Prefabricated Vertical Drain (PVD) method for the soft soil
treatment due to its financial value and simplicity in its works. Real time prediction using
Asaoka’s Observatory Procedure shows a reliable agreement for prediction of settlement in
ground improvement works for soft soil.
1. Introduction
Universiti Teknologi Tun Hussein Onn is located in Parit Raja, about 25km to the east of Batu
Pahat Town. The area is considerably flat with existing ground level ranges generally between
1.2m to 2.4m above Sea Level. The construction begins in 2007 within an area of 145 Ha. It
comprises of construction for the Library and Chancellery, Faculty of Civil Engineering and
Environment, Faculty of Electrical and Electronic Engineering, Faculty of Technology
Information and Multimedia, Faculty of Mechanical Engineering and Manufacturing, Faculty of
Technical Education and Lecture Hall. The existing area which is to be developed has a Reduce
Level varies from +1.4m to +1.8m in the open area. A propose final platform level will be RL
2.5m since flood contributed by Sungai Semberong and Sungai Simpang Kanan was estimated to
be at highest level of +2.3m. However as a centre of attraction, the Library building will be
placed on a higher level than others at a R.L of +3.5m. The layout plan for the development area
is as shown in Figure 1.0.
2013 International Congress on Engineering and Information, Bangkok, Thailand. 26th Jan -28th Jan 2013
2. Subsurface Conditions
Prior to the ground improvement work a site investigation scheme was performed throughout the
propose development area. The scheme suggested comprises of 11 boreholes and 13 CPT point
with Dissipation test from selected boreholes and CPT point respectively and laboratory test on
extracted samples. The laboratory testing includes strength and settlement parameters and also
physical testing. The subsoil information from the development area is divided into 3 zones. Base
from the overall soil profile cross section i.e:
i) Zone A (Profile BH1,BH2 and BH11)
ii) Zone B (Profile BH8, BH4, BH7)
iii) Zone C (Profile BH5, BH6, BH10)
Generally, the soil layer can be described as below:-
Water level that has been monitored through boreholes ranged from 0m to 0.5m below the ground
surface. The water levels are slightly erratic initially but stabilized during most of the monitoring
period. To minimize the future settlement of the platform for infrastructure such as roads, parking
and open area after the completion of the development, subsoil treatment is necessary due to the
existence of soft layer within the development area. Figure 2.0 shows a typical cross section of
boreholes acquired during the site investigation work.
(a) (b)
(a) (b)
Figure 7 : Typical reading for Magnetic extensometer (a) and Menard Pressuremeter
installed in pre bore hole.
Instrument Type: Inclinometer Location : Primary Ring Road (Zone A)
Instruments ID : IN 1 Top of Tube RL : 2.3752 mRL
In Logger ID : 0001 Total Length of Tube Installed: 30.0 m
Inclinometer CD Cumulative Displacement (mm) Against Depth (m)
0
D Towards Site Entrance Towards Worker
BarrackC
1
2
3
4
5
Remarks 6
Commisioning on 7
8
02/10/07 9
Surcharge removed 10
13/05/08 11
12
13
14
15
Depth (m)
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
-300 -250 -200 -150 -100 -50 0 50 100 150 200 250 300
Cumulative Displacement (mm)
2/10/2007 9/10/2007 23/10/2007 30/10/2007 6/11/2007
12/11/2007 19/11/2007 27/11/2007 4/12/2007 11/12/2007
18/12/2007 27/12/2007 31/12/2007 8/1/2008 15/1/2008
21/1/2008 28/1/2008 5/2/2008 14/2/2008 18/2/2008
26/2/2008 3/3/2008 11/3/2008 18/3/2008 25/3/2008
1/4/2008 14/4/2008 28/4/2008
Embankment stability in terms of settlement and slope instability will be observed through the
settlement plate via Temporary Bench Marking point and Inclinometer respectively. This will
provides a real time performance observation during improvement period. At the initial stage, a
total settlement predicted to occurs are 800mm, 486mm and 572mm for Zone A, Zone B and
Zone C respectively. These values are inclusive of elastic settlement that occurs immediately
after the filling is place on the improved site. Base from observational procedure by
Asaoka(1978) the average value of settlement obtained from the analysis are as shown in Table
2.
Table 2: Prediction of Settlement using Asaoka’s Observation Procedure and Terzaghi
One Dimension Consolidation.
At average all zones shows a settlement between 420mm and 490mm. In most cases, the
settlement from back analysis shows that Asaoka’s plots is lower than predicted except for Zone
B. The different in reading is expected, since the use of an analytical solution such as Terzaghi
one dimensional consolidation is not always effective factors concerning settlement magnitudes
in which sometimes it is quite uncertain in engineering practices. Figure 9 and 10 shows selected
typical results for Asaoka’s plot representing the zones. SP6 representing Zone A, while SP8 is
representing Zone B. Finally SP9 and SP10, is representing Zone C.
6.0 Conclusions
The whole area of the development sits on soft clay which is highly compressible. Due to
construction time constrain, a ground improvement need to be done to expedite the settlement
process of the area. A task of less than six month was given to improve the site before other
infrastructure works will be commencing. Surcharge method incorporated with PVD was used as
a ground improvement programs. The method was selected due to its simplicity and economical
in comparison with other available method within the region. The work was done by stages
starting from Zone A until Zone C. Settlement at each zone reached its final value within a period
of 5months from the day of the ground improvement work started. The surcharge height used
was 2.5m for both Zone A and B and 2.75m for Zone C. The final settlement occurs were
490mm, 400mm and 254mm for Zone A, Zone B and Zone C respectively. Geotechnical
instrument were installed to monitor the performance of subsoil. Back analysis based on
settlement monitoring results predicted using Asaoka’s Observatory method shows a reliable
agreement with Terzaghi’s one dimensional consolidation. It was thought to be useful to
understand the history of the development site before any settlement prediction is done to
eliminate overestimating of surcharge materials which might incurs to extra cost in construction.
2013 International Congress on Engineering and Information, Bangkok, Thailand. 26th Jan -28th Jan 2013
Figure 10 : Typical value of Asaoka’s plot for settlement prediction
2013 International Congress on Engineering and Information, Bangkok, Thailand. 26th Jan -28th Jan 2013
7.0 Acknowledgement
The authors’ wishes to thank to all personnel involve during the construction and
monitoring of the ground improvement on site. Appreciation is to be given to UTHM,
JKR and Ecovest Sdn. Bhd. for allowing publishing the data available.
8.0 References
[1] Asaoka, A. 1978. Observational Procedure of Settlement Prediction. Soils and Foundations,
Vol. 18, No. 4, Dec. 1978. Japanese Society of Soil Mechanics and Foundation Engineering.
pp. 87- 101
[2] Hansbo, S. 1979. Consolidation of clay by band-shaped prefabricated drains. Ground
Engineering, July, Vol. 12, No.5.
[3] Hansbo, S. 1981. Consolidation of fine-grained soils by prefabricated drains. Proceedings,
10th International Conference on Soil Mechanics and Foundation Engineering, Vol. 3,
Stockholm.
[4] Terzaghi, K. 1948. Teorethical Soil Mechanics. John Wiley and Sons, New York.