Sunteți pe pagina 1din 3

Table of content

General
1. Table of Content
2. Project Quality Plan
3. Project Organization Chart & Certificates
4. WPS & PQR
5. Painting Qualification Test ( PQT)
6. Approval Drawing (As Built)
 Temporary Works Pile Turn Support Back Frame
 Temporary Works Bulk Off-Loading Facility Working Platform
7. ITP (Inspection Test Plan)
 Temporary Works Pile Turn Support Back Frame
 Temporary Works Bulk Off-Loading Facility Working Platform
8. List Welder & Certificate
9. NDT Procedure
1.9.1 MT Procedure
1.9.2 NDT List and Personal Certificate
10. Load Test Procedure (for Working Platform)
11. Blasting & Painting Procedure
12. Equipment Calibration List & Certificate
13. Manufacture Certificate

TEMPORARY WORKS PILE TURN SUPPORT BACK FRAME

Fabrication Report
14. Welding Map and Welding Traceability
15. Material Receiving Inspection Report & Certificate
16. Fit-up Report, Visual Inspection Report and Dimensional Check Report
17. NDT Report
18. Welding Repair Report ( if any )
19. Blasting & Painting Report
20. Inspection Release Note (IRN)
TEMPORARY WORKS BULK OFF-LOADING FACILITY WORKING PLATFORM

Fabrication Report
14. Welding Map and Welding Traceability
15. Material Receiving Inspection Report & Certificate
16. Fit-up Report, Visual Inspection Report and Dimensional Check Report
17. NDT and Load Test Report
18. Welding Repair Report ( if any )
19. Blasting & Painting Report
20. Inspection Release Note (IRN)

S-ar putea să vă placă și