Sunteți pe pagina 1din 1

Unit 1 outage activities

1.) Coal A temp Tx voltage dropped 11HHE03CT101 (by construction team)


2.) Windbox #1 pressure root valve 1 ea nut missing 11HLA50CP103 (by mech comm. Team)
3.) WTR flow Tx manifold leakage 11LAB60CF101/102, 11LAE10CF101, 11LAE20CF101 (by
construction team)
4.) Soot Blower main steam flow tubing H/L reversed 11HCB10CF101/102 (by construction
team)
5.) Soot blower PCV re-calibration 11HCB01AA101
6.) Soot Blower PLC main graphic color modification – standby from red to green, moving from
green to red.
7.) Loop Seal Blower anti-surge valve opening flow to be modified by MR. Hu of SFW
Pre-surge set value 20,000 m3/h
17-18,000 m3/h

8.) Drum level electronic indicator right side root valve stem broken (by mechanical team)
-Steam line 1st valve 11HAD01AA329
9.) Coal feeder/ Bottom Ash screw cooler sealing air flushing
-SA to IA line flushing, rotameter cleaning

10.) Fly ash slide gate cable attached 11HDG11AA002 (by construction team)

11.) SA air nozzle rear right upper 11HLB80AA101 to be recalibrated

12.) SCAH drain vessel LT H tubing 11HCL10CL102

13.) Feed water flow range

14.) Limestone slide gate front right 11HRB14AA001 open limit switch

15.) Backpass Hopper level switch electronic fuse blown out 11HNA30CL202/204

16.) Fly Ash Hopper Level switch, 17-feb slide gate full open, high alarm x/scr speed 40%

17.) SA Fan Key Phasor, 11HLB21CY009 and ID Fan Key phasor, 11HNC10CY009 troubleshooting.

Currently both zero reading.