Documente Academic
Documente Profesional
Documente Cultură
OF RBIDHTI'IAL BUIIDING
BACHELOR 0F TECHNOLOGY
IN
BY
NYEAR
DECLARATION CERTIFICATE
CONTENTS
1 INTRODUCTION
2 METHODOLODGY
3 SPECIFICATION
4 CHAPTER I PLANNING
5 CHAPTERII ANALYSIS
7 CHAPTER IV ESTIMATION
8 CHAPTER V MANAGEMENT
Introduction
Shelter is one of the basic needs for Habitation. In this project, I have
completed the Planning. Analysis. Design and Estimation of a Residential Building of
(ZBHKl two flats in Chennai. Kuratur (Near Avadt). The Project is completed with
reference to the Indian Standard codes in planning. 1 has used AutoCAD. Revit.
Sweet Home 3D software for Plan. Elevmion, Interior and [interior design is with
reference to National Building Code 2005 completed. Analysis of the stmctum is done
in manual as well as using STAAD Pro Vi8 software. Designing of structural
components are carried out using Indian Standard Code (Given in reference) in Limit
state Method. Estimation is completed by using rates from Schedule of Rana (20l5-
20l6) by Public Work Department. Management of contraction is very much
Important hence we need shelter with good Quality in appreciative cost and time.
Here I have med Critical Path Method as well u PERT Analysis with Probability for
Time and Cost Management (Timeouts Trade off).
METHODOLDGY
The Methodology Followed For Completing the Mini Project Was Given Below
SPECIFICATION
l Slab:
A flat piece of concrete. Typically med as a walking surface. But may also serve as a
load
Heating device as in slit homes. It also acts as a beam but thick is less and width is
mole what compare to beam.
Design Consideration:
Among the design function that needs to be taken in consideration for construction of
ground floor slab is
When the slab is supported on all the four edges , and when the ratio of the long span
to short span is huge (>2) bending takes place along one the span , such as slab is
known as a one way slab.
When the slab is supported on all the four edges, and when the ratio of the long span
to
Short span is small bending takes place along both the span. Such as ski: is known as:
two way slab.
2 BEAMS:
Simply supported beam supported freely at the two cocks on walls or column. In
actual practice. No bum mu freely on the supports (walk or columns).
Fixed beam:
Fixed beam both ends of the beam re rigidly fixed into the supports. Also, Main
reinforcement ham and stirrups are provided.
Cantilever beam:
Cantilever beam is fixed in a wall (1' column a one end and the other end is free, it is
called Cantilever beam. It has tension zone in the top side and commission zone in the
beam side.
Continuous beam :
Continuous beam ‟u supported on more than two supports. This beam is more
economical for any span length.
R.C.C. Beams:
Concentrated Load.
Uniformly Distributed boat.
Uniformly Varying Loads.
Arbitrary Loading.
3 LINTELS:
Lintel is a bean supporting the load of masonry above it which is transmitted to the
adjacent wall portion ova which it is laid. The bearing of lintel the baring of lintel
ham should be the minimum of the following:
(1) l00 mm
(4)
CLASSIFICATION OF LINTELS:
Lintel is classified into the following types according to the materials used in their
construction:
(2)Stone lintels
(3)Brick lintels
(5)Steel lintels
These are the oldest types of lintel. At present, they are not used expect in hilly
regions where timber is chiefly available.
(2)Stone lintel
These are commonly used in none masonry. The least thickness of the stone lintel is a
about 75 mm and as thumb rule. Thickness is taken as at least 1 mm per 10 mm length
of the span of opening.
(3)Brick lintels
These lintels are not structurally strong, and they are used only when the opening is
small (less than 1m) and loads are light
The depth of brick lintels varies from l00 mm to 200 mm. depending upon the span.
These lintels are commonly med time this. They have high rigidity. fire resistance and
are simple in construction.
R„C.C lintels are available as precast units. Precast R.C.C lintels are preferred for
small spam up to 2 meters Generally 1:2:4 concrete is used in the construction of
these lintels. The depth of lintel and the amount of the reinforcing is governed by the
intensity of load. The type of support and the span.
For the cast-in-situ lintels which are quite common, form work is required for
construction.
(5)Steel lintels
There lintels are provided when the opening is large and where the super-imposed
loads are heavy. Rolled see] joints are med either singly or in combination of two or
three units. S
COLUMN:
Column is a vertical structural member. it transmits the load from ceiling/roof slab
and beam. Including itself-weight to the foundation. Columns may he subjected to a
pure compressive load. R.C.C. columns are the most widely used now-a-days.
R.C Column concrete has a high compressive strength and a low tensile
strength .Hence. Theoretically concrete should need no reinforcement when it
is subjected to compression. Reinforcements are provided in order to reduce
the size of column, though a column is mainly a compression member'. it
liable to some moment due to eccentricity of loads or transfer loads or due to
its slenderness. Such moments may occur in any direction and so it is
necessary to provide reinforcement near all face of the column. These
reinforcements form the longitudinal steel. In order to maintain the position of
the longitudinal reinforcement and a ko to prevent their buckling which may
cause splitting of concrete. it is necessary to provide traverse reinforcement in
the form of lateral ties or spirals at close pitch. The tram verse reinforcement
also assists in confining the concrete.
A column may be classified on the basis of its shape. Its slenderness ratio. The
manner loading and the type of lateral reinforcement provided. A column may leave a
section which may be square, rectangle. Circular or a desire polygon Depending on
the slenderness ratio. Column may be a short or long column.
The slenderest ratio of column is the ratio of the elective length of the column to its
last lateral dimension. A column whose slenderness ratio exceeds l2 is a long column.
A column whose slenderness ratio does not exceed the above limit is a short column.
l STAIR CASE:
Stair cases are used in almost all buildings A staircase consist of a number of steps
arranged in a series. With landing at appropriate locations. For the purpose of giving
access to different floors of a building. The width of a staircase may depend on the
purpose for which it is provided. And may generally vary between lm for residential
buildings to 2m for public buildings. A flight is the length of the staircase situated
between two landings. The number of steps in a flight may vary between 3 to l2. The
rise of a step and the tread should be proportioned that it gives conformable access.
Generally the sum of the plus twice the rise is kept bout 5(X)mm and the product of
the trend and the rise is kept about 40000 to 42000. In residential buildings. The rise
may vary between 150 mm to l80mm and trend between 200 to 250mm. in public
buildings, rise is kept between 120 to l50mm and tread between 200 to 300mm.
(3) Half turn stair (open newel type or open well stair)
Footings:
l. Shallow foundations:
It has smaller' depth limited to the width of footing. It spreads the load from
superstructure on a larger am of soil so that stress intensity is reduced to a value
which can be carried safely by soil. They are classified as isolated and combined
footing and combined footings.
An isolated footing supports one well or one column. A wall footing is continuous
strip, either flu or stepped which distribute the load of wall on the soil. An isolated
footing supporting a single column is commonly used where the load on Coolum are
small and are not closely spaced. They are squared, rectangular, circular or of other
shapes
A combined footing supports two or more column. They may classify 5 those which
supports two columns and those which support more than two columns. Combined
footing supporting two columns may be used for column on property lines. Such
footings may be rectangular, trapezoidal or T shaped in plan or may consist of
isolated footing connected with a narrow beam.
2. Deep foundations:
When the top layer of the soil is too weak to support the structure on the shallow
foundation. the depth of foundation is increased till more suitable soil is found to
support the structure. Such a foundation '3 turned as deep foundation becomes of its
large depth. Different types of deep foundation are pile and well foundation.
Baring capacity of soil is the maximum intensity of the load or pressure developed
under the foundation without causing failure of soil and in settlement of
superstructure supported on foundation.
DESIGN OF SLAB
DATA
FLOOR FINISH:
1 KN/m2
TYPE OF SLAB
DEPTH
SPAN/DEPTH=25
DEPTH = 174 mm
D= 200mm
EFFECTIVE SPAN
LOAD CALCULATION
LIMITING MOMENT
REINFORCEMENT
24.523x 106 = 0.87 x 415 x Ast X 200 (1-415 x Ast /20 x 1000 x 200)
Ast = 814.90mm2
DISTRIBU‟HON
Pt = (100XAst)/bd=0.4523
KTc > Tv
DATA
DIMENSION: 5.9m
DEPTH
SPAN/ DEPTH = 12
d = 600 mm
EFFECTIVE SPAN
LOAD CALCULATION
LIMITING MOMENT
Mu < Mu lim
REINFORCEMENT
130.27 X106 = 0.87 X 415 X Ast X 600 (1- 415 X Ast / 20 X 600 X 300 )
KTc < Tv
Vu s= Vu -(Tc X bd)
DEPTH
SPAN/DEPTH= 15
DEPTH = 350Mm:
d= 400 mm
EFFECTIVE SPAN
LOAD CALCULATION
LIMITIM MOMENT
Mu< Mu lim
REINFORCEMENT
Ast = 572.73mm2
Tc = 0.4806N/ mm2
DESIGN OF COLUMN
DATA
Fck=20 N/mm2
SLENDERNESS RATIO:
L/D=3.2/0.3 = l0.66
MINIMUM ECCENTRICITY
LIMITING MOMENT
Mu<Mu lim
REINFORCEMENT
Asc = 720mm2
LATERAL TIES:
2)Spacing
Generally =300mm
DESIGN OF FOUNDATION
DATA
BACE AREA
Length= 2.2m
2
Af= 2.2 X2.2 =4.84m
BENDING MOMENT
2
BM= [ qa X B X (B-d) ] /8=188.43 KN-m
REINFORCEMENT
DEPTH
SPAN/DEPTH = 20
DEPTH = 70mm
EFFECTIVE SPAN
LOAD CALCULATION
LIMITING MOMENT
Mu < Mu lim
REINFORCEMENT
Ast = 36.86mm2
DESIGN OF STAIRCASE
DATA
DIMEVSION
No of Riser = 3200/160=20
No of tread = 10-1=9
Going = 300X9=2.7m
DESIGN OF FLIGHT
Span = 3.57 m
Depth
Pt = 0.4%
2
al=1.32 For Fs = 240N/mm
D= l40+20= 160mm
LOAD CAICUIATION
ULTIMATE MOMENT
Limiting Moment
2
Mu lim = 0.138 X Fck X b X d = 54.096 KN-m
Mu < Mu lim
REINFORCEMENT
Distribution Reinforcement
Pl=100xa70noooxn4o-o.47%
CHAPTER V (MANAGEMEN'D
The Critical Path Method (CPM) is one of several related techniqtm for doing project
planning. CPM is for projects that are made up of a number of individual “activities”
If some of the activities require other' activities to finish before they can start. Then
the project becomes a complex web of
edivitia.
PERT is a network mays‟ technique which is used to determine the tin: it will take to
complete a complex pieces.
Z =(190-180.11)/13.479 = 0.733
From Log table Probability = l 0.7673 = 0.2327 Project to be completed after 190
days is 23.27% '9 Project to be completed before 160 days: 2 =(160-180.110)/13.479
= -1.491 From Log table Probability = 0.0681 Project to be completed before 160
days is 6.81% 6 Project to be completed between 160 In 190 days Probability =
10232700681 = 0.6992 Project to be between 160 days to 190 days is 69.92% 9
Number of days for completion of project with 90% probability me Log Table 128
4[(009-008) X (0.90-0.8997) / (69015-08997) = 1.281667 Days = 180.ll+1.281667 X
13.429 = 197.32 Number of days for completion with 90% probability is 197.32 =
198 Days
REFERENCES
IS CODES USED:
I. IS 456 :2000 “Phin and Reinforced Caterer -code of practice“ Fourth Rev'nion
section 3 (claims I9, 23, 26) section 4(33)
7. IS 29“ (Pm IlSecZ) I979 “Cock of Practice for Design And Consmxlion of Pile
Fomchions"