KKATT Consult

CNOOC UGANDA LIMITED KKATT Consult Limited

CONSULTANCY SERVICES FOR RESETTLEMENT HOUSES,


DESIGN REVIEW AND CONSTRUCTION SUPERVISION

PROJECT DAILY REPORT

REPORT DATE: 27th-10-2017


REPORT TO: CNOOC Uganda Limited
PREPARED BY: Omar Hassan
Contents
1.0 WORK DONE TODAY .................................................................................................................... 3
1.1 Activities executed today................................................................................................................. 3
1.1 Problems faced today: ................................................................................................................ 3
2.0 WORKERS ON CONSTRUCTION SITE TODAY............................................................................... 4
3.0 EQUIPMENT ON SITE ................................................................................................................... 4
4.0 MATERIALS ON SITE .................................................................................................................... 4
5.0 RAIN RECORD THIS MONTH ............................................................................................................. 4
6.0 PHOTOS OF “WORK PROGRESS AND ISSUES ON SITE” TODAY .................................................. 5
6.1 General site activities: ................................................................................................................... 5
6.2 Substructure:................................................................................................................................ 5
7.0 MAJOR QHSE ISSUES ON SITE: ...................................................................................................... 6
7.1 Quality Issues ............................................................................................................................ 6
7.2 Health Issues ................................................................................................................................... 6
7.3 Safety Issues ................................................................................................................................... 6
7.4 Environment Issues .................................................................................................................... 6
8.0 SOCIAL ISSUES ON SITE .............................................................................................................. 6

2
1.0 WORK DONE TODAY

1.1 Activities executed today.


Activity Location

Main house  Trimming of foundation edges and Foundation edges of main


removal of top vegetable soil layer House 1st block and 2nd block
2.95mx5.7mx0.3m=5.04m3 for 2 houses
=10.08 m3
4.63mx2.45mx0.3m =3.40m3 (for 2 houses
=6.8 m3)

1.1 Problems faced today:


Problem Location/Description
Weather
N/A

Machinery break Lack of fuel on site .


down

Other
N/A

3
2.0 WORKERS ON CONSTRUCTION SITE TODAY
Company Personnel Nationality Comment
0 Chinese No representative on site
CNOOC
0 Ugandan No representative on site
KKATT
1 Uganda Mainly technical personnel (Omar Hassan )
Consult
X Team Leader Paul Mwirumubi
 Project Manager Patrick B Haines
X Site Engineer Magambo Andrew

Network X Quality Controller Hendrick Venter


Civil
X Senior foreman Sam Mutabazi
Engineering 6 Uganda
Contractor’s X Senior foreman Joseline Byambandwa
Ltd.
 Machine operator 1

 Carpenters 2

 Helpers 2
Total 7

3.0 EQUIPMENT ON SITE


Number Working
S.N. Item Quantity on site Remark
today
1) Backhoe Cat 428 1 1 Foundation excavations
Preparing for block
2) Motor mixer 1
manufacture
Preparing for block
3) Block making machine 1
manufacture
Preparing for block
4) Generator 1
manufacture

4.0 MATERIALS ON SITE


S.N. Item Quantity on site
Sand 50tons
1)
Stone Dust 20tons
2)
Iron Sheets 150pcs
3)

5.0 RAIN RECORD THIS MONTH


Month October 2017
Date 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Rainfall(mm)

4
Date 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Rainfall(mm) 0

6.0 PHOTOS OF “WORK PROGRESS AND ISSUES ON SITE” TODAY


6.1 General site activities:

Photo 1:Removing of top weak soil within foundations Photo 2:Trimmed foundations and removed top vegetable soil

6.2 Substructure:

Photo 3.Excavated Foundation for 2nd site House block only Photo 4: Machine idle for today .

5
7.0 MAJOR QHSE ISSUES ON SITE:
Present Comment
Issue
Situation
7.1 Quality Issues
  
7.2 Health Issues
  
  
7.3 Safety Issues
  
7.4 Environment Issues
  
  

8.0 SOCIAL ISSUES ON SITE


Social Issue Present Situation Comment
  
  
  