SABIC Mega Housing Package 6, (Infrastructure & Villas)

Method Statement For Asphalt Roads Construction and Completion


MS.No. 07 , Date : 22-Feb-2018, Rev. 1 Page 0 of 7

KINGDOM OF SAUDI ARABIA


Project :
SABIC Mega Housing , Phase 4, Package 6
( Infrastructure & Villas ),
Mutrafiah Locality , Jubail Industrial City
CONTRACT NO. EPC-LS-16-SABIC—018-IK-Package -6

FOR

THIS MOS IS RAISED IN RESPONSE TO RC NCR. Rev. 1


SABIC Mega Housing Package 6, (Infrastructure & Villas)
Method Statement For Asphalt Roads Construction and Completion
MS.No. 07 , Date : 22-Feb-2018, Rev. 1 Page 1 of 7

Table of Content

1. SCOPE OF WORK
01.1 General Description
01.2 Plant And Equipment
01.3 Materials
01.4 Site Planning & Preparation
01.5 Procedure For Asphalt Roads Construction and Completion
01.6 Organization, Responsibility & Supervision

2. QUALITY CONTROL

3. HEALTH AND SAFETY CONSIDERATION

4. ENVIRONMENTAL ISSUES

5. APPENDICES

6. WARRENTY
SABIC Mega Housing Package 6, (Infrastructure & Villas)
Method Statement For Asphalt Roads Construction and Completion
MS.No. 07 , Date : 22-Feb-2018, Rev. 1 Page 2 of 7

MEHTOD STATEMENT
ASPHALT ROADS RECTIFICATION AND COMPLETION

1. SCOPE OF WORK

01.1 General Description

To enumerate procedure for construction of asphalt roads driveways, walkway and


parking in accordance with the lines, grades, locations and typical sections & layout
shown on the Approved Drawings, and in conformance with these Specifications at
proposed Project Construction.

Furnishing and delivery of roads approved fill materials, aggregate subbase,


aggregate base type, asphalt concrete base course and surface course etc. Other
secondary materials precast curbstone, concrete cast in place, interlock pavers, tiles,
pavement marking and signs as shown in the layout

The contractor will furnish all labour, materials, tools and equipment required to
complete the works in conformance with these specifications.

That including the following:

 Pre-survey work to the construction area as per roads layout.


 Informing to Surrounding Persons.
 Raise RFI to evidence.
 Prevention during and after construction.

01.2 Plant And Equipment

Trucks (For Aggregate Base Course, Soil Fill)


Asphalt Mixer
Concrete Mixer & Pump
Roller and other Compactors
Showel , Wheel Loader, Skip Loader, Fork lift
Water Tankers & other Vehicles
Safety Barrier & Signs
Applicable Technicians and PPE

Workmanship and Certified operators from road work specialized contractor for
satisfactory work as recommended standards will be completed.

01.3 Materials
The following materials are required to complete the above mentioned works..

 Filling Materials, Aggregate Base Course


 Asphalt Aggregate Base & Top Course
SABIC Mega Housing Package 6, (Infrastructure & Villas)
Method Statement For Asphalt Roads Construction and Completion
MS.No. 07 , Date : 22-Feb-2018, Rev. 1 Page 3 of 7

 Construction Water
 Concrete Cast in Place
 Precast Concrete Curbstone, Pavers/Tiles
 Sand for Bedding and Cement Mortar etc.
 Safety barrier, lighting, warning tape and PPE.

01.4 Site Planning & Preparation

To work as a team that support site management plan as per schedule, the work area
to be confirmed according to priority basis. The work will be organized by responsible
engineer/supervisor with proper arrangement of manpower, equipment, materials,
approved drawings and standard construction method in view of quality and safety.

Communications on site by means of mobile, telephones etc.


Lay down area designated to stock different materials and stock pile of backfill
materials and aggregates base course recommended locations at site.

01.5 Procedure For Asphalt Roads Rectification and Completion

Project internal local and residential asphalt roads driveways works are constructing
into two stages as recommended by the RC representative and Project Management
(PMT). The Contractor is following the procedure and construction of roads
completion and other appurtenant works in reference with Royal Commission
specification and standards as drawings, PMT approved documents and
recommendations.

General survey and cleaning and leveling the ground locations where asphalt roads
and walkways to be constructed. Exactly survey marking of coordinates and center
line for asphalt road ways, curbstone edges and tiled walkways as per dimension
shown in the approved drawings. The roads widths as per the approved drawings
are.

Residential Asphalt Road driveway width 6.60m


Residential Asphalt Road driveway width 11.60m (With Parking Lane)
Local Asphalt Road driveway width 12.60m (With Parking Lane)

Construction of roads in two stages as per suitability of site internal access, fist stage
completes roads upto asphalt base course only and remaining work of roads will be
completed in second stage after a period when the traffic movement will less on site
area. All the balance work of roads like parking lane, curbs walkways with asphalt top
surface course will be done in second stage to have the roads in condition at time of
project handover.

CONSTRUCTION OF ROADS STAGE - I


Construction of Roads Stage – I Includes the following work steps, refer to the
attached drawing sketch Stage – I. In this stage of road construction all fill upto grade
level, aggregate base course and asphalt base course will completed without top
surface course, curbs and walkways.

1. Subgrade : Fill material upto grade level (Subgrade).


2. Aggregate Subbase : Laying of Aggregate Subbase ( 250 mm Thick ) and
covering 50cm margin more than the required road widths on both sides.
SABIC Mega Housing Package 6, (Infrastructure & Villas)
Method Statement For Asphalt Roads Construction and Completion
MS.No. 07 , Date : 22-Feb-2018, Rev. 1 Page 4 of 7

3. Aggregate Base : Laying of Aggregate Base Type ( 200 mm Thick ) to the


required width of road.
4. Asphalt Concrete Base Course : Laying of Asphalt Concrete Base Course ( 70
mm Thick ) to the required top surface road width ( Upto curbs locations on both
sides).
5. Asphalt road parking lane, top surface course and relevant works underground
utilities, roads walkways, curbs & Interlock concrete pavers will be completed in
Stage – II after a period when the traffic movement will be less on site in order to
avoid damages.

CONSTRUCTION OF ROADS STAGE - II


Construction of Roads Stage – II : Includes the following work steps, refer to the
attached drawing sketch Stage – II (Normal Roads and With Parking Lane) . In this
stage it is proposed to lay the asphalt top surface course of road and concrete curbs
other all pertaining works underground utilities work, walkways and inter lock pavers
etc.

6. Curbs Fixing ( Normal Roads ) : To fixing curbs with foundation exact to road
width, cutting straight edge and remove loose edge 10cm in road width of asphalt
base course and aggregate etc. as shown in the drawing sketch Stage II (Roads
Without Parking).
7. Asphalt Base Course (Roads With Parking Lane) : Similarly cut and remove
loose edge 10cm width at earlier laid Asphaltic Concrete Base Course to continue
course layer at parking lane areas with full width of road upto curbs as shown in
the drawing sketch Stage II With Parking Lane.
8. Walkway : Complete underground work of walkways utilities manholes and light
pole bases etc. Then construction of walkways curbs, interlock pavers as
mentioned in the drawings.
9. Asphalt Top Surface Course : Lastly to lay Asphalt Concrete Surface Course
( 50 mm Thick Top Layer ) over earlier laid asphalt base course and other
required areas as indicated in the drawings with RC standards.
10. Road Finishing Works : Complete road marking and traffic signs as indicated on
the drawing.
11. Remove all unwanted materials, construction equipments and cleaning of roads
for inspection and initial acceptance for handover.

01.6 Organization, Responsibility & Supervision

Project Manager
To allocate duties and responsibilities & overall coordination with SABIC PMT, Royal
Commission (RC) and Contractor personnel / utility departments site team..

Project Engineer
To ensure duties and responsibilities & overall coordination with PMT engineers,
Royal Commission (RC) representative has been done. The required documents,
drawings, Construction Method and materials are approved. Monitor the work
schedule to start and finish on time with QC inspection, permits and Contractor
personnel with assigned team

Construction Manager
SABIC Mega Housing Package 6, (Infrastructure & Villas)
Method Statement For Asphalt Roads Construction and Completion
MS.No. 07 , Date : 22-Feb-2018, Rev. 1 Page 5 of 7

To prepare method statement, assign duties, arrangement of manpower/equipment,


monitor works on project sites, liaisonning with PMT, RC representative, engineers
and other.

Quality Control Manager


Prepare Quality Control Plan/ITP, allocates duties and works to QC Engineers,
overall implementation of quality plan, submittals prepare & review and managing
inspections, coordinates with PMT engineers.

HSE Manager
Planning safety, tool box meeting conduction, implementation of safety & security
plan, monitor safety works, equipments and PPE on site, liaisonning with PMT, site
team, safety officers.

2. QUALITY CONTROL

 The Contractor shall be responsible for the quality of work.


 Quality Assurance All materials and equipments procured for construction and
fabrications.
 Conduct inspections of works with SABIC PMT representatives to meet quality
requirements.
 Witness and hold point signature of responsible parties associated with ITP.

3. HEALTH AND SAFETY CONSIDERATIONS

A. All works undertaken in relation to this Specification are to be completed in full


accordance with the respective health and safety requirements established by the
following:

1. Kingdom of Saudi Arabia


Legislation, Regulation, Standards and Codes.
2. SABIC PMT / Royal Commission Regulations
Standards, Contractual Conditions, and Health and Safety Systems.
3. Contractor Health and Safety Standards and Systems as accepted by the SABIC
E & PM / Royal Commission.

B. In the absence of any of the above, best accepted industry practice shall be
employed throughout.

Risk Assessment
Protective and Safety Equipment
Contractual Requirements
Information to Personnel
Emergency Procedures
Permitting Requirements

4. ENVIRONMENTAL ISSUES

Environmental Impact Assessment


SABIC Mega Housing Package 6, (Infrastructure & Villas)
Method Statement For Asphalt Roads Construction and Completion
MS.No. 07 , Date : 22-Feb-2018, Rev. 1 Page 6 of 7

The Health safety environment plan is based on SABIC E&PM / Royal Commission
guidelines, safety is the responsibility of all and the site project manager will monitor
all spheres of operation, & will strive to achieve the safety objectives by means of
efficient management control.

5. APPENDICES

The following documents are attached to this method statement.


Approved Material Submittal.
Roads Kep Plan ( Sectors A7 & A10 ) – Drawing No. 714-100-20TR-CE-050
Roads Typical Cross Sections (Sectors A7 & A10) – Drawing No. 714-100-20TR-CE-
522
Road Construction Drawing Sketch Stage - I
Road Construction Drawing Sketch Stage - II
Road Construction Drawing Sketch Stage - III

6. WARRENTY

All Asphalt Roads Construction are executed as per approved layout drawings and
materials in reference with standards of Royal Commissions and SABIC. Project
work is guaranteed as per contract agreement from date completion of project or
preliminary hand over.

***