○ Core tasks

PIC Ary Wahyudi 081293564353


Chiko Akbar Sobari 087780393524l

1. SAFETY.
-. Apply safety Iron Rule (use PPE).
-. Do not working without check the Panel condition first (such as voltage source at panel) and put on
safety tag at panel door (ILS).
-. Always do finger point before and after working.

2. TBM.
-. Place infront of Main Electrical Room SteelMaking Plant, time: 07:45 AM.
-. Tools preparation check (if not ready, prohibited to work).
-. Work permit published and distribute to workers (for High risk Job).

3. Working Step Implementation.


- . Fabrication and install greeting

○ Quality requirements
4. After working.
-. Safety check arround area.
-. Cleaning arround area.

5. Tools and MSPE.


-. Personal tool (Box set), cable roll, grinding, welder and drill.
-. Safety Gear (Hand gloves,mask, and safety glasses)

6. Material
-. Greeting, mesin las , gerinda dll
-.

7. Request worker

○ tidy work/Tools and MSPE(Safety)


Please try to maintain tidy work-field
by doing clean up after maintanence work.

○ Core tasks

PIC Ary Wahyudi PT.KP ELECTRIC MAINTENANCE (081293564353)

Chiko Akbar Sobari PT. POSCO ICT INDONESIA (087780393524)

1. SAFETY.

-. Apply safety Iron Rule (use PPE).

-. Do not working without check the Panel condition first (such as voltage source at panel) and put on
safety tag at panel door (ILS).
-. Always do finger point before and after working.

2. TBM.

-. Place infront of Main Electrical Room SteelMaking Plant, time: 07:45 AM.

-. Tools preparation check (if not ready, prohibited to work).

-. Work permit published and distribute to workers (for High risk Job).

3. Working Step Implementation.

- . Power off and Install Grounding Cable from Panel MCC

-. Checking Residual Voltage On Panel and Terminal Box Motor

-. Rebolting Motor area Boiler and GCT

○ Quality requirements

4. After working.

-. Safety check arround area.

-. Cleaning arround area.

5. Tools and MSPE.

-. Personal tool (Box set), Wrench,Ratchet, and Torque Keys

-. Safety Gear (Hand gloves,mask, and safety glasses)

_oa_dis
Note : SAFETY FIRST
○ Core tasks
PIC Ary Wahyudi 081293564353
Vicky Immanuel

1. SAFETY.
-. Apply safety Iron Rule (use PPE).
-. Do not working without check the Panel condition first (such as voltage source at panel) and put on
safety tag at panel door (ILS).
-. Always do finger point before and after working.

2. TBM.
-. Place infront of Main Electrical Room SteelMaking Plant, time: 07:45 AM.
-. Tools preparation check (if not ready, prohibited to work), tool set.
-. Work permit published and distribute to workers (for High risk Job).

3. Working Step Implementation.


- Check and cleaning field instrument (pressure, level and temperature) GCT silo.

○ Quality requirements
4. After working.
-. Safety check arround area.
-. Cleaning arround area.

5. Tools and MSPE.


-. Personal tool (Box set).
-. Safety Gear (Hand gloves,mask, and safety glasses)

○ tidy work/Tools and MSPE(Safety)


Please try to maintain tidy work-field
by doing clean up after maintanence work.
_oa_dis
Core tasks
PIC Ary Wahyudi 081293564353
Arman 087808910207

1. SAFETY.
-. Apply safety Iron Rule (use PPE).
-. Do not working without check the Panel condition first (such as voltage source at panel) and put on
safety tag at panel door (ILS).
-. Always do finger point before and after working.

2. TBM.
-. Place infront of Main Electrical Room SteelMaking Plant, time: 07:45 AM.
-. Tools preparation check (if not ready, prohibited to work), tool set.
-. Work permit published and distribute to workers (for High risk Job).

3. Working Step Implementation ( 27 September 2017 )


- Measuring suport panel.
- Fabrication support panel
- Install Panel.

4. Working Step Implementation ( 03 October 2017 )


- Measuring suport line pipe.
- Fabrication support pipe
- Install Pipe and conduit flexible.

5. Working Step Implementation ( 10 October 2017 )


- Install Pipe and conduit flexible.
- Pulling cable.

6. MATERIAL
- PANEL.
- PIPE CONDUIT AND FLEXIBLE 32mm
- U BALL.
- ANGLE.

○ Quality requirements
7. After working.
-. Safety check arround area.
-. Cleaning arround area.

8. Tools and MSPE.


-. Trafo welding machine, Grinding, Drilling.
-. Safety Gear (Hand gloves,mask, and safety glasses)

○ tidy work/Tools and MSPE(Safety)


Please try to maintain tidy work-field
by doing clean up after maintanence work.
Contact Person
PTKP : Saut Daniel 081221007834
M. Riswan Maulana 082122498499
ICT : Tri Nova 087871711697

o Safety Action and Condition (Emergency Call: Safety Master each plant)
1. Apply Safety Iron Rule (Use PPE, Body harness, etc)
2. Do not working without check the Panel condition first
(Such as Voltage source at panel) and Put on safety tag at panel door (ILS)
3. Always do Finger Point before and after working

Contact Person
PTKP : Saut Daniel 081221007834
M. Riswan Maulana 082122498499
ICT : Tri Nova 087871711697

o Safety Action and Condition (Emergency Call: Safety Master each plant)
1. Apply Safety Iron Rule (Use PPE, Body harness, etc)
2. Do not working without check the Panel condition first
(Such as Voltage source at panel) and Put on safety tag at panel door (ILS)
3. Always do Finger Point before and after working

○ Core tasks

1.TBM First (Place : Steel Making Plant, Time : 08:00 AM)


1.1 Tools Preparation check (If not Ready, prohibited to work)
1.2 Short briefing about Work description, precaution and safety risks
1.3 Work permit published and distribute to workers (for High risk job)

2.Working Step Implementation


2.1 TBM on work area and explain potential hazard
2.2 Moving AC Geared Motor (Teeming Travelling Motor) from Motor Warehouse to CMF
2.3 Overhaull AC Geared Motor
2.4 Check condition of (bearing, bearing housing, coil, grease etc)
2.5 Change any parts if necessary
2.6 Do running test (load and no load test)
2.7 Send user the result test

3.After Working
3.1 Safety check arround area
3.2 Cleaning arround area

Tools & MSPE


1. Personal Tool (Tool Box Set, Key Set, Majun, Brush,)
2. Safety Gear (Insulation gloves, mask, & googles if need)

○ Quality requirements
Makesure all of condition motor already good

○ tidy work/Tools and MSPE(Safety)


Please try to maintain tidy work-field by doing clean up after maintanence work

SAFETY FIRST!!!