Sunteți pe pagina 1din 26

Preliminary Investigation

of the Potential impacts at


the HYDRO ALUNORTE
Refinery SUMP 45
downstream areas
Located in
Barcarena, PA

Volume 1 of 1

Confidential

Report for: Alumina


do Norte da Brasil
S.A. (Hydro
Alunorte)
Barcarena, PA

Feb 2018

Enviro-Tec do Brasil Consultoria


e Tecnologia Ambiental Ltda.

Hydro Alunorte-032/18
Note

This report was prepared by Enviro-Tec do Brasil Consultoria e Tecnologia Ambiental


Limitada for Alumina do Norte do Brasil S.A. (HYDRO ALUNORTE) Barcarena,
PA. This report represents the best judgment of Enviro-Tec according to the
information available at the time of its preparation.

This report must be read in its entirety. It is important that the reader understands that
the activities performed during this evaluation were limited to the specific objectives
established in the corresponding proposal. These activities were not implemented to
provide a full characterization of all the environmental impacts that may exist in the
Plant. This report does not constitute a legal opinion. No person has been authorized by
Enviro-Tec to provide any representation with respect to the content of this report.

Any use of this report made by third parties, or in trust, or any decision to be taken on
the basis thereof, is the sole responsibility of such third parties. Enviro-Tec is not liable
for damages suffered by any third party arising from decisions or actions taken based on
this report.

i
Table of contents

1.0 Introduction ....................................................................................... 01


1.1 Project History ............................................................................ 01

1.2 Elaboration of the Action Plan ..................................................... 03

2.0 Procedure for surveys and the collection of samples .................... 05

2.1 Preparations and Safety Precautions Implemented..................... 05

2.2 Soil samples collected for pH analysis…………………………… 05

2.3 surface water and sediments sample Collection ....................... 06

3.0 CONCLUSION AND RECOMMENDATIONS………………………….. 09

ii
1.0 Introduction

This Preliminary Investigation of the Potential impacts at the HYDRO ALUNORTE


Refinery SUMP 45 downstream areas (Figure 1-1) was prepared by Enviro-Tec do
Brasil Consultoria e Tecnologia Ambiental Limitada (ENVIRO-TEC) for Alumina do
Norte do Brasil S.A. (HYDRO ALUNORTE) Barcarena, PA. The objective of this
report is to document all procedures performed during the Preliminary Investigation
activities of the corresponding results.

1.1 Project History

During the night on February 16th to 17th, 2018 intense rains were registered in the
region of Barcarena, PA (231mm in 10 hours), which resulted in an overflow of the Rain
Water Storage Basin (SUMP 45). The rain water from this part of the Refinery is
considered clean without any contact with the Refinery Production Areas, where caustic
soda is the main contaminant. The website climate-data.org indicates that the average
volume of rainfall for the entire month of February is approximately 365mm. As a
consequence of this overflow, the rain water was directed to the piping next to the
vegetation of the Murucupi river. On the morning of February 19th, 2018, HYDRO
ALUNORTE conducted an evaluation of the environmental conditions of the
downstream areas of SUMP 45 until the Murucupi river, using internal resources, to
determine whether there has been any environmental impact associated with this
incident. More specifically, this internal assessment was performed in order to:
 Assess whether the reddish color effluent reached the vegetation and
subsequently the Murucupi River;
 Investigate the quality of the soil along the path of preferential flow of water between
the pipe and the Murucupi river;
 To evaluate the quality of surface waters of the Murucupi river (pH, electrical
conductivity and temperature);

To meet these objectives, the HYDRO ALUNORTE environmental technician walked


along the preferred path of drainage of surface water (controlled by the topographic
gradient in the area until the Murucupi river. Collected a series of 5 samples of surface
soil, equally distributed along this path (Figure 1-2), for the analysis of pH and electrical
conductivity. These results are presented below:

Point 1 Point 2 Point 3 Point 4 Point 5


pH 7,04 6,7 6,28 5,97 5,66
Conductivity 33.8 17.9 10.97 9.61 10.26
electrical (µs/cm)

1
Venezuela Suri. FG Oceano
olômbia Guy.
. Atlântico
Macapá

Manaus . .
Barcaren a Belém
São Luís
. .
Fortaleza
Natal
.
..
Recif e
Brasil Maceió

Salvador.
Peru .
Cuiab á .
Bolívia
Goiânia . BRASíLIA

Belo Horizonte. . Vitória

C Poços de Caldas .. .
h Paraguai .
Sã o Paulo Rio de Janeiro
Oceano i Curitiba
Pacífico l Porto Oceano
e
Argentina
.
Ale gre Atlântico Hydro Alunorte
Uruguai
1.000 km
1,000 milhas

Hydro Alunorte

Scale (m): 0
800 1600

Prepared for: Hydro Alunorte


Title: Figure 1-1
Barcarena,PA
Map of the location of the
Project ID: Hydro Alunorte-032/18 Hydro Alunorte Plant
Barcarena, PA - Brazil
Prepared by: Jeffey W. Fortner DATA: Feb 2018 Scale: As indicated revision No.: 0
SUMP 45

Preferential flow path

Prepared for: Hydro Alunorte, Barcarena, PA Title: Figure 1-2

Location of soil samples collected by HYDRO


Project ID: Hydro Alunorte-032/18 ALUNORTE on 02.19.18
Along the Preferred Path downstream from
the SUMP 45
Prepared by: Jeffrey W. Fortner DATA: Feb 2018 Scale: As indicated revision No.: 0
The HYDRO ALUNORTE environmental technician reported that,"The pH of the
water body had the result of 5.62 whose value is within the pattern established by
CONAMA 357 of 2005 which states the classification of the water bodies. The
temperature showed the value of 26.4C°, this result also lies within the limits set by
CONAMA. Finally, the electrical conductivity presented a result of 204 µs/cm. The
results showed that there was no contamination by bauxite residue in the Murucupi
river."

2
Through the observations and the results recorded in the field, HYDRO ALUNORTE
concludes that, "the vegetation has not suffered change or contamination due to
effluent from the SUMP 45 area piping. In addition, there was no evidence of
contamination or alteration in the color of the water of the Murucupi River. However,
with the circulation of false information in communities around the refinery, HYDRO
ALUNORTE decided to hire Enviro-TEC to perform this Environmental Investigation
to confirm the conditions of the area downstream of the SUMP 45 and the Murucupi
River."

1.2 Preparation of the Sampling Plan

The sampling plan of this preliminary investigation was based on the information of the
incident supplied by HYDRO ALUNORTE and remarks made by the Enviro-TEC
professional during a visit in the area on February 20th, 2018. During this visit, a small
area in the vicinity of the piping outlet with evidence of red dust characteristic of water
flow with mud (Figure 1- 3). A hole was observed in this area (Temporary Basin - Figure
1-4) which was excavated by HYDRO ALUNORTE soon after the event of the incident
with the objective to capture and return the drainage water to the Refinery rainwater
management system. Then, the Enviro-TEC Environmental Engineer followed the
preferred path of drainage of runoff waters of this area, controlled by the topographic
gradient, until the Murucupi River. Along the path, the environmental conditions of
natural vegetation and points of sampling conducted by HYDRO ALUNORTE the
previous day were observed . Pictures of these points and natural conditions observed
are shown in Figures 1-5 to 1-8. Evidences of the passage of muddy water were not
identified along that path, in addition to the area already indicated earlier around the
piping outlet. At the arrival point of the Murucupi River, the river water was transparent,
and even a little whitish color characteristic of natural soils of the area.

With the objective of confirming the representativeness of the data obtained by


HYDRO ALUNORTE on February 19th, 2018, Enviro-TEC recommended the
expansion of the sampling program, as follows:
 Collect a sample of water in a Temporary Basin and analyze for pH, conductivity,
turbidity, salinity, temperature, Eh and total dissolved solids.
 Collect a soil sample in the piping outlet (0.0-0.1m) - Analyze for pH;
 Collect 5 samples equally distributed within the area with red visible impact (0.0-
0.1m). In the same points collect 5 samples more for the same analyzes (0.5-0.6m).
 Collect 5 samples equally distributed along the outer perimeter of the area with red
visible impact (0.0-0.1m). These points must be removed approximately 3m from
the boundary of the red, visible impact on soils apparently not impacted. In the
same points collect 5 samples more for the same analyzes (0.5-0.6m).

3
Prepared for: Hydro Alunorte, Barcarena, PA Title: Figure 1-3

Piping outlet area with evidence of overflow


Project ID: Hydro Alunorte-032/18 water
from SUMP 45
DATA: Feb 2018 Scale: As indicated revision No.: 0
Prepared by: Jeffrey W. Fortner
Prepared for: Hydro Alunorte, Barcarena, PA Title: Figure 1-4
Temporary Basin for Collection and
Return
Project ID: Hydro Alunorte-032/18 Rainwater excavated by HYDRO
ALUNORTE

Prepared by: Jeffrey W. Fortner DATA: Feb 2018


Scale: As indicated

revision No.: 0
Prepared for: Hydro Alunorte, Barcarena, PA Title: Figure 1-5

Project ID: Hydro Alunorte-032/18 Natural conditions of the Preferred Path of runoff
of Rainwater
In point 2 sampled by HYDRO ALUNORTE
Prepared by: Jeffrey W. Fortner DATA: Feb 2018 Scale: As indicated revision No.: 0
Prepared for: Hydro Alunorte, Barcarena, PA Title: Figure 1-6

Project ID: Hydro Alunorte-032/18 Natural conditions of the Preferred Path of runoff
of Rainwater
In point 3 sampled by HYDRO ALUNORTE
Prepared by: Jeffrey W. Fortner DATA: Feb 2018 Scale: As indicated revision No.: 0
Prepared for: Hydro Alunorte, Barcarena, PA Title: Figure 1-7

Project ID: Hydro Alunorte-032/18 Natural conditions of the Preferred Path of runoff
of Rainwater
In point 4 sampled by HYDRO ALUNORTE
Prepared by: Jeffrey W. Fortner DATA: Feb 2018 Scale: As indicated revision No.: 0
Prepared for: Hydro Alunorte, Barcarena, PA Title: Figure 1-8

Project ID: Hydro Alunorte-032/18 Natural conditions of the Preferred Path of runoff
of Rainwater
In point 5 sampled by HYDRO ALUNORTE
Prepared by: Jeffrey W. Fortner DATA: Feb 2018 Scale: As indicated revision No.: 0
 Collect 5 samples in line (0.0-0.1m) in point 2 (Figure 1 from the HYDRO report).
This line must be oriented perpendicular to the direction of potential flow for
drainage with the center of the line in point 2. These soil samples must be
analyzed for pH.
 Collect 5 samples in line (0.0-0.1m) in point 3 (Figure 1 from the HYDRO report).
This line must be oriented perpendicular to the direction of potential flow for
drainage with the center of the line in point 3. These soil samples must be
analyzed for pH.
 Collect 5 samples in line (0.0-0.1m) in point 4 (Figure 1 from the HYDRO report).
This line must be oriented perpendicular to the direction of potential flow for
drainage with the center of the line in point 4. These soil samples must be
analyzed for pH.
 Collect 5 samples in line (0.0-0.1m) in point 5 (Figure 1 from the HYDRO report).
This line must be oriented perpendicular to the direction of potential flow for
drainage with the center of the line in point 5. These soil samples must be
analyzed for pH.
 Collect 3 samples of surface water and sediments from the Murucupi River, including
1 set aligned with point 5, 1 whole directed approximately 20m upstream of Point 5
and 1 guided set to about 20m downstream of Point 5. Each sample of surface water
must be analyzed for pH, conductivity, turbidity, salinity, temperature, Eh and total
dissolved solids, and each sample of sediment must be analyzed for pH.

This sampling program is focused on the characterization of the potential impacts after
the piping outlet and only along the surface that has the greatest risk to be impacted, and
does not represent a characterization of the potential impacts between SUMP 45 and the
piping. If signs of contamination in this portion of the study (particularly in the area
impacted visibly at the piping outlet) could not be identified, we can consider that the
conditions between SUMP 45 and the piping are similar. All these analyzes must be
carried out in the field with Enviro-TEC instruments, duly calibrated. In the event of
identification of pH values > 9.0, Enviro-TEC recommends the collection of samples for
laboratory analyzes (metals, sulfate and alkalinity).

4
2.0 Procedure for surveys and the collection of samples

This section provides a detailed description of the procedures and methodologies


applied by the Enviro-TEC team while performing the collection of the
environmental samples for analyzes, as recommended.

2.1 Implemented Preparations and Safety Precautions

Prior to the commencement of the drilling activities in each location, a rigorous process
of excavation liberation was performed along with the Authorized Professional from
HYDRO ALUNORTE. The objective of this liberation process is to confirm that each
marked point is free of obstacles and dangers, from air on the surface and underground.
Thus, representatives from each HYDRO ALUNORTE department responsible for the
process lines and piping; lines and main drainage piping (rain water, sanitary water and
effluents);, septic tanks and reservoirs; and the networks of air, gas, power and
telecommunications were involved in evaluating and releasing of each point before its
implementation.

Besides the excavation liberation process, Enviro-TEC has produced in conjunction


with HYDRO ALUNORTE an analysis of Risk Prevention Analysis ("APR") detailed
by professionals of Enviro-TEC and HYDRO ALUNORTE, with the purpose to identify
and communicate all potential risks associated with the various activities carried out by
Enviro-TEC, as well as to identify the risks and specific precautions to each of the
operational areas that were designated for the implementation of surveys, as well as the
corresponding precautions that would be applied to minimize these risks.

In addition, Safety Daily Dialogs (DDS), documented by professionals of Enviro-


TEC at the start of day were performed. The purpose of the DDS was to highlight
and/or update, for the Enviro-TEC professionals, what specific precautions relevant
to the activities of each day, as well as assess the physical/mental state of each
employee before the start of the project activities for each day.

The gauge Hanna Phem soil HI99121, used to measure the pH directly on soils, and
the Horiba U-52 meter, used for the measurements of pH, electrical conductivity,
turbidity, temperature, salinity, Eh and total dissolved solids in the water, were duly
calibrated with original calibration solutions of manufacturers of these instruments
immediately before the commencement of the sampling activities.

2.2 Surface Soil samples collected for pH analysis

On February 22nd, 2018, Enviro-TEC collected 41 soil samples in areas downstream of


SUMP 45, distributed according to the established sampling plan. Each soil sample was
collected with a two inches manual auger

5
of diameter, constructed of stainless steel, and properly cleaned. The soil was removed
from the auger using a clean spoon, also made of stainless steel, and placed in a clean
stainless steel bowl, where the pH measurement of the soil in the sample was
performed with the instrument Hanna Phem, duly calibrated. All the information of
measures, including the results were recorded in the field book, as shown in Table 2-
1. All equipment have been properly cleaned/decontaminated with distilled water
between the samples. The location of each of these soil samples is presented in Figures
2-1A and 2- 1B.

A review of data obtained indicated that the higher pH value detected was associated
to the sample SO-01 (7.82) of the surface soil collected at the piping outlet. The
concentrations of pH in the soil around the reddish area presented values between 4,79-
6.50 and concentrations of pH in soils collected along the outer perimeter, not reddish,
presented values between 4,94-6,40, indicating no difference in the quality of the soil
inside and outside the reddish area. The concentrations of pH in soils collected in the
downstream lines vary between 4,80-7,33, also, without evidence of environmental
impact.

These results indicate that the rain water overflow from SUMP 45 and discharged to
the forest downstream area of SUMP 45 were not contaminated by the HYDRO
ALUNORTE industrial process and did not cause any negative impact in the quality
of the soil which were in contact with the rain water.

2.3 Surface water and sediments sample Collection

Supporting the rainwater effluent quality assessment which originated from the reddish
area, ENVIRO-TEC collected a sample from the Temporary Basin (Sample SW-01) and
measured the following parameters using the Horiba U-52 instrument, duly calibrated:
pH, electrical conductivity, dissolved oxygem, turbidity, salinity, temperature, Eh and
total dissolved solids. The results of these analyzes are presented below:

Point pH Electrical Dissolved Turbidity Temperature Salinity Eh Total


conductivity Oxygen Dissolved
Solids
(mS/cm) (mg/l) (NTU) (°C) (%) (mV) (g/l)
SW-01 6,07 0,150 4,45 544 28,5 0,05 264 0,095

These results are consistent with rain water without evidence of chemical
contamination.

In support of the evaluation of the quality of Murucupi River, and to determine whether
there is evidence of impact on the water quality and/or sediments in the river associated
with industrial activities of HYDRO ALUNORTE, Enviro-TEC has collected 3 sets of
samples of surface water and sediments along the course of the river, including a

6
Line 02

Line 04

Line 03

Line 05

Muruc
upi River

Tempor
ary Basin

Prepared for: Hydro Alunorte, Barcarena, PA Title: Figure 2-1A = Soil Collection Points P-01 to P-05 sampled
by HYDRO ALUNORTE
Location of soil samples, surface water On 02.19.18.
Project ID: Hydro Alunorte-032/18
and sediment collected by Enviro-TEC = surface water samples collection Points
(02.22.18) and Sediments
Prepared by: Jeffrey W. Fortner DATA: Feb 2018 Scale: As indicated revision No.: 0
Preferential flow
path
Reddish
Area SW-02
Line 02 SED-02

20m
Piping Line 04
Tempor
ary Basin
SW-03
SW- SED-03
01 Line 03
Identification of sampling points: 20m

SO-16 SO-15 SO-14 SO-13 SO-12 SO-07A/07B SO-08A/08B


Line 05
Line 02

2m 2m 2m 2m
SW-04
SED-04
SO-21 SO- SO-19 SO-18 SO-17 SO-03A/03B
SO-02A/02B
20 Line 03 SO-09A/09B

2m 2m 2m 2m
SO-01
SO-04A/04B
SO-26 SO-25 SO-24 SO-23 SO-22
Line 04 SO-05A/05B

2m 2m 2m 2m
SO-06A/06B

SO-31 SO- SO-29 SO-28 SO-27


SO-10A/10B
30 Line 05 Murucupi River Flow

2m 2m 2m 2m SO-11A/11B
Figura 2-1B
Prepared for: Hydro Alunorte, Barcarena, PA Title:

Project ID: Hydro Alunorte-032/18 Location of soil samples, surface water and
sediment collected by Enviro-TEC
(02.22.18)
Prepared by: Jeffrey W. Fortner DATA: Feb 2018 Scale: As indicated revision No.: 0
Table 2 -1: Results of soil and sediment analyzes
Location Sample Date of Time of Sample Analysis Temperatur
Point collection Analysis Interval result e
pH
(°C)
Piping outlet SO-01 2/23/2018 11:10 0,0 - 0,1m 7,82 26,9
Reddish Area SO-02A 2/23/2018 11:10 0,0 - 0,1m 6,40 27,2
Reddish Area SO-02B 2/23/2018 11:15 AM 0,5 - 0,6m 5,85 28,0
Reddish Area SO-03A 2/23/2018 11:17 AM 0,0 - 0,1m 5,40 28,0
Reddish Area SO-03B 2/23/2018 11:20 AM 0,5 - 0,6m 5,20 28,3
Reddish Area SO-04A 2/23/2018 11:21 AM 0,0 - 0,1m 5,56 27,0
Reddish Area SO-04B 2/23/2018 11:23 AM 0,5 - 0,6m 4,79 27,1
Reddish Area SO-05A 2/23/2018 11:30 AM 0,0 - 0,1m 5,90 26,1
Reddish Area SO-05B 2/23/2018 11:32 AM 0,5 - 0,6m 6,01 25,3
Reddish Area SO-06A 2/23/2018 11:35 AM 0,0 - 0,1m 6,50 26,3
Reddish Area SO-06B 2/23/2018 11:36 AM 0,5 - 0,6m 5,15 26,0
External perimeter SO-07A 2/23/2018 11:40 AM 0,0 - 0,1m 4,94 27,0
External perimeter SO-07B 2/23/2018 11:43 AM 0,5 - 0,6m 5,77 26,8
External perimeter SO-08A 2/23/2018 11:45 AM 0,0 - 0,1m 5,87 27,9
External perimeter SO-08B 2/23/2018 11:45 AM 0,5 - 0,6m 5,73 27,1
External perimeter SO-09A 2/23/2018 11:48 AM 0,0 - 0,1m 6,11 27,4
External perimeter SO-09B 2/23/2018 11:48 AM 0,5 - 0,6m 5,85 27,1
External perimeter SO-10A 2/23/2018 11:50 AM 0,0 - 0,1m 5,72 26,4
External perimeter SO-10B 2/23/2018 11:50 AM 0,5 - 0,6m 5,97 26,3
External perimeter SO-11A 2/23/2018 11:52 AM 0,0 - 0,1m 6,40 26,1
External perimeter SO-11B 2/23/2018 11:52 AM 0,5 - 0,6m 5,59 25,7
Line 02 SO-12 2/23/2018 12:08 PM 0,0 - 0,1m 6,60 26,8
Line 02 SO-13 2/23/2018 12:09 PM 0,0 - 0,1m 7,18 26,4
Line 02 SO-14 2/23/2018 12:10 PM 0,0 - 0,1m 7,33 26,8
Line 02 SO-15 2/23/2018 12:11 PM 0,0 - 0,1m 6,74 27,3
Line 02 SO-16 2/23/2018 12:12 PM 0,0 - 0,1m 6,53 26,8
Line 03 SO-17 2/23/2018 12:15 PM 0,0 - 0,1m 6,22 26,2
Line 03 SO-18 2/23/2018 12:15 PM 0,0 - 0,1m 5,47 26,2
Line 03 SO-19 2/23/2018 12:18 PM 0,0 - 0,1m 6,29 26,2
Line 03 SO-20 2/23/2018 12:20 PM 0,0 - 0,1m 6,01 26,1
Line 03 SO-21 2/23/2018 12:20 PM 0,0 - 0,1m 5,62 25,9
Line 04 SO-22 2/23/2018 12:20 PM 0,0 - 0,1m 5,32 25,2
Line 04 SO-23 2/23/2018 12:23 PM 0,0 - 0,1m 4,88 25,1
Line 04 SO-24 2/23/2018 12:25 PM 0,0 - 0,1m 4,80 25,1
Line 04 SO-25 2/23/2018 12:27 PM 0,0 - 0,1m 5,25 25,1
Line 04 SO-26 2/23/2018 12:28 PM 0,0 - 0,1m 4,82 25,2
Line 05 SO-27 2/23/2018 12:30 PM 0,0 - 0,1m 5,38 25,7
Line 05 SO-28 2/23/2018 12:30 PM 0,0 - 0,1m 5,39 25,8
Line 05 SO-29 2/23/2018 12:31 PM 0,0 - 0,1m 5,46 25,8
Line 05 SO-30 2/23/2018 12:32 PM 0,0 - 0,1m 5,72 25,5
Line 05 SO-31 2/23/2018 12:33 PM 0,0 - 0,1m 5,59 25,4
Murucupi River - SED-02 2/23/2018 12:36 PM 0,0 - 0,1m 6,42 25,6
Downstream
Murucupi River - SED-03 2/23/2018 12:40 PM 0,0 - 0,1m 4,55 25,9
Point 5
Murucupi River - SED-04 2/23/2018 12:53 PM 0,0 - 0,1m 5,19 26,0
Upstream

7
Sample at the point where the preferred path of drainage has intersected the river; a
sample located approximately 20m upstream from this point; and a sample located about
20m downstream of the same point.

To maximize the representativeness of the samples, the sampling program was started at
the furthest point downstream of the river and continued in the direction of flow to the
point further upstream. The same way, the samples of surface water were always
collected before the collection of the sample of sediments. The water quality of the
Murucupi River was measured directly, with the placement of the Horiba probe straight
into the river. A summary of the measurements recorded in the three points is presented
below:

Point pH Electrical Dissolved Turbidity Temperature Salinity Eh Total


conductivity Oxygen Dissolved
Solids
(mS/cm) (mg/l) (NTU) (°C) (%) (mV) (g/l)
SW-02 5,15 0,095 1,25 203 26,9 0,00 320 0,062
SW-03 5,19 0,098 1,20 150 26,8 0,00 318 0,064
SW-04 5,20 0,100 0,53 180 26,2 0,00 318 0,065

These results of the river water do not present any evidence of negative impact on their
quality. The only parameter that drew attention are the low values of dissolved oxygen.
However, these low values of dissolved oxygen are highly consistent with the
groundwater flush.

The collection of sediments at each point of the river was performed with the manual
auger and the pH of sediment analyzes used the same process of measures from the
soil. The pH results of these sediments are presented in Table 2-1 and indicated the
same range of variation of soils with concentrations of 4,55-6,42.

8
3.0 CONCLUSION AND RECOMMENDATIONS

On days 16th to 17th of February 2018, an out of the ordinary heavy rain event occurred.
As a consequence, the HYDRO ALUNORTE rainwater capture system limit was
overcome, causing an overflow on SUMP 45. These effluents overflowed from SUMP
45 originated in areas of low risk of contact with process liquor and did not have the
characteristics of the process liqueurs or bauxite waste.

The characterization of the overflow of the downstream area from the piping outlet to
the Murucupi River, was investigated by Enviro-TEC on February 22nd, 2018, and
there was no evidence of significant environmental impact associated with this
overflow event. A small reddish area, with mud visually present on the surface, was
the only evidence found of the flow of effluents from rain water. A series of multi-level
samples were collected within the reddish area; along the outer perimeter of the reddish
area; and along the preferred path of drainage from this area to the Murucupi River,
and all these 41 soil samples showed the same range of pH, without differentiation of
areas - including the reddish area.

As a result of these soil investigation activities, ENVIRO-TEC has concluded that no


evidences were identified which suggests that the stormwaters which overflowed
SUMP 45, and subsequently drained to the wooded area donwgradient of SUMP 45,
were contaminated by Hydro Alunorte's Industrial Process and no residual impacts to
soil quality along the stormwater drenage flowpath were detected.

In addition to assess potential impacts on soil quality between SUMP 45 and the
Murucupi River, Enviro-TEC also evaluated the quality of the waters and sediments
from Murucupi River. In this case, 3 sets of samples of surface water and sediments
along the course of the river were collected, including a sample at the point where the
preferred path of drainage has intersected the river; a sample located approximately
20m upstream of this point; and a sample located about 20m downstream of the same
point.

The results of the river water quality do not present any evidence of negative impact
on the quality. The only parameter that drew attention are low values of dissolved
oxygen. However, these low values of dissolved oxygen are highly consistent with the
groundwater flush. The results of the analyzes of pH of sediments indicated the same
range identified in the soils investigated, with concentrations of pH between 4,55-
6,42.

To minimize the potential risk of impact in the investigated area, Enviro-TEC


recommends the removal of the drainage piping. In addition, HYDRO ALUNORTE

9
Must expand the capacity of SUMP 45 and conduct a general review of the capacity of
the rainwater management system.

10

S-ar putea să vă placă și