Documente Academic
Documente Profesional
Documente Cultură
2010
This page intentionally left blank.
table of contents
Acknowledgments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Project Framework. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Project Timeline. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Functional Integration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Space Needs Update. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Design Narratives
Architectural Narrative. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Concept Diagrams. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
Concept Floor Plans. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
Site and Landscape Narrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
Site Plan. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Civil Narrative. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Structural Narrative. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
Mechanical Narrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
Electrical Narrative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
Code Summary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
Systems Diagrams. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
Exhibits (under separate cover)
Exhibit A: Cost Estimate
Exhibit B: Full Space List
Exhibit C: Conditions Survey
Exhibit D: Topographic Survey
Exhibit E: Geotechnical Overview
Exhibit F: Haz-Mat Report
Exhibit G: Phase 1 Environmental Report
Over the past few years a paradigm shift has The project has three key goals: Outreach
been occurring at the Alaska State Libraries, Initial outreach efforts included stakeholder
• Construct a new building that will protect
Archives and Museums. A dream for a new facil- interviews with representatives of 35 groups
Alaska’s collections while integrating the
ity that would integrate the three units is becom- statewide and an email poll of other state
library, archives and museum.
ing a reality. Simultaneously, the workings of libraries, archives and museums regarding their
the Division are becoming more integrated on • Improve service delivery and program of-
expansion projects. A project fact sheet outlined
a daily basis. These changes have Alaska on tar- ferings through integration of the three
the project need and approach. A project bro-
get to become an international leader in service groups.
chure was distributed with presentations to the
delivery for libraries, archives and museums. • Create an integrated digital portal for access annual meeting of the Alaska Historical Societies
This report summarizes the process that led to to information. and Museums Alaska.
where we are, presents the concepts that arose
from the process, and sets a course that will lead More recently, a series of public workshops and
Building Space Requirements discussions with staff has led to development
to a new Library, Archives and Museum Facility.
After extensive user interviews with staff mem- of an updated list of space requirements and a
At heart, this project is about protecting Alas- bers and stakeholders, the space requirements concept design for the new facility.
ka’s treasures. The existing collections of the have been updated and described in detail. In
Alaska Libraries, Archives and Museums are full summary, the new facility will include the follow- Over the next several months continued state-
of those treasures. Many, if damaged, are irre- ing components. wide outreach will be employed to educate citi-
placeable, yet they are housed in buildings that zens about the project and to generate feedback
can no longer adequately protect them. The • 124,000 sf new construction on the design concepts.
storage facilities are beyond their useful life and • 80 basement level parking stalls
beyond capacity. There are additional treasures
within the State and beyond that will eventually • 40 surface parking stalls
find their way into the collections. This project • site development and landscaping
promises to produce a facility capable of receiv-
ing and protecting valuable artifacts. Alaska
deserves to see the existing and future collec-
tions preserved for generations to come.
ECI/HYER :: THA ARCHITECTURE
project
FRAMEWORK
Mission
The mission of the Alaska Division of Libraries, Archives and Museums is to preserve Alaska’s cultural heritage and to facilitate access to information and
resources for research and lifelong learning.
In keeping with this mission to better protect and share our collections and to improve our programs and services, the division is working towards consoli-
dating and integrating the work of its three sections: the State Library, the State Archives and the State Museums. A new building should help us to work
more efficiently and effectively for Alaskans.
Next Steps
• Fall - Winter 2010 - 2011 • Fall - Winter 2011 - 2012
Schematic design Final construction documents
Statewide outreach campaign Initiate construction contract for long-lead
items, utilities and advanced site work
Contractor selection
• Spring 2012 - Summer 2014
• Spring - Summer 2011
Construction
Design development
• Fall 2014
Finalize construction timeline
Grand Opening
Secure project funding for construction
10
ECI/HYER :: THA ARCHITECTURE
SPACE NEEDS
update
Through numerous stimulating discussions Historical Collection (Library) have the most The preservation of these collections benefits
with the Executive Committee, staff and the issues with potential contamination. An isola- all Alaskans, a small child may develop a lifelong
Design Team, a collaborative method of working tion room will be used by these two sections interest in history by visiting the Museum; an
emerged. This will be facilitated by an integra- and by Archives when necessary. The Museum intern for a State Senator may look for prec-
tion of spaces in the new facility. Together the needs a direct access from the loading dock into edent in the State Archives.
Library, Archives, Museum, Administration and the Exhibit area for touring shows. Library and
Each section currently “explains” its collections
Technical and Imaging Services explained to the Archives also need a convenient way to bring
through a different catalog system. The end
Design Team what services they provide to the materials into the processing area from receiv-
goal of any cataloging system is clear collection
State and how work is accomplished within their ing. The loading/receiving area begins the back
access.
current space. From these meetings surfaced an of house integration of the sections.
understanding of what each section shares and When visiting the new building looking for infor-
Material preservation involves the treatment of
where potentially conflicting differences exist in mation on a subject, the public should be able to
objects for contaminants, repair and storage. All
the program requirements. It is important that see what is available from each of the sections
sections have some level of paper conservation,
the design and program create space that allows without having to run to different locations and
so an area to serve this need has been added
collaboration in new and yet unidentified ways. be confused by numerous cataloging methods.
to the program. Storage has different security
As the sections develop an understanding of
Each section collects, preserves, explains, inter- and environmental requirements for the various
what resources each has, they will better assist
prets, shares and communicates. Within each collections. The Museum collection requires the
patrons in their search for information. The staff
of these areas are both nuanced and notice- highest level of security. The Museum, Archives
is also looking at ways to make cataloging more
able procedural distinctions. The Design Team and Historical Collections all require specific
transparent. These issues impact the building
worked with the user group to understand all and similar environmental controls. Informa-
program in a number of ways.
the possible areas of integration that should be tion Service’s (Library) Collection is browsable
considered during the programming process and and has the lowest security and environmental Upon coming into the new facility it will be evi-
to find ways of addressing technical variations. demands. The various collections also grow or, dent where to enter the Museum Exhibit area
potentially, contract at different rates. A large and how to access the other collections. There
Collecting is done both through outreach result-
secure storage area shared between Archives will be one entrance to a reading/research room
ing in donations and through systematic collect-
and the Historical Collection gives potential for to serve Information Services, the Historical
ing and purchasing. New materials are evaluated
the line between these sections to move as stor- Collection and Archives. A service desk will be
for issues that must be addressed prior to being
age needs change. attended by staff who can direct patrons to
entered into the collection. The Museum and
items in all the collections or to another staff
12
ECI/HYER :: THA ARCHITECTURE
SPACELISTSUMMARYSHEET NetSF TotalGrossSF
14
ECI/HYER :: THA ARCHITECTURE
ARCHITECTURAL.
NARRATIVE
16
ECI/HYER :: THA ARCHITECTURE
Sustainable Design cooling will be handled primarily through natural
ventilation and economizer cooling. The more
Energy conservation is a primary concern for
highly controlled spaces in the museum and
the State Library, Archives and Museum Project.
storage spaces will likely require some means of
Maximizing the benefits of natural lighting and
mechanical cooling.
minimizing energy loss are achievable goals.
At the outset of the project, staff and patrons To ensure the success of these strategies, staff
expressed a strong desire to provide daylit and operations personnel will be comfortable
spaces and to minimize long-term operating with the design direction and should be part of
costs. Space planning and the design of the the start-up and testing phases of the project.
building “skin” will be carefully coordinated to Emphasis will be given to building systems that
take advantage of daylight. The goal moving for- can be easily maintained and operated by local historic Juneau dock forms
ward will be to integrate time-tested “passive” personnel.
and “low-tech” strategies with the economical
and complementary use of new technologies in Materials and Methods
an effort to save energy while at the same time In all areas of construction, emphasis will be
providing for the well-being of patrons. Deci- placed on materials and assemblies that provide
sions will be guided by real data based on energy low-tech and economical construction. This
modeling of the building. means of careful planning is based on standard
The energy-efficiency strategy will primarily focus material units that facilitate little construction
on the building “skin.” Roof and walls will have waste. Durable materials and assemblies will
continuous insulation without thermal bridges be favored over those that are complicated and
and will be a vast improvement over traditional have high maintenance. Wherever practical, fin- inspiration sketch
construction assemblies. Other assemblies, like ish materials will be avoided, allowing structural
windows, will be thermally “broken” and will materials to be expressed thus minimizing over-
be triple-glazed where appropriate. Since cool- all material consumption.
ing loads in southeast Alaska are relatively light,
18
ECI/HYER :: THA ARCHITECTURE
... The site layout reflects the fan of the docks that
historically occupied the site, and the roof form is
reminiscent of the wing and feathers of a bird in flight ...
Loading
Elev.
W Security
Wd. Crate Ed. Classroom Off.
Wood Iso.
Stor. Storage Coll. Museum
Work Volunteer Cafe
Sup. Staff
Shop M M Lock.
Elev.
Conf. Conf. Auditorium
W
Clean
Lobby
Shop
UP Vest.
3D
Con.
Cons.
Supply Store
Wet Lab Museum
Photo Lobby
Wet Lab
Secure Storage
Storage Pro-
cessing 2D
Con. Museum
Exhibit
M W
Col. Disp.
Ex.
Stor.
Coll.
Sup.
Building Support
Library Space
Roof 0 20 40 80’
Elev. 0 20 40 80’
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M M Elev.
W
DN
Service
Special Desk
Processing
Projects
Video
Conf. Research
Room
Reading
Secure Room
Storage
Microform
Storage
Readers
LAM
Offices
Roof
Terrace
Staff
Storage
Building Support
Library Space
0 20 40 80’
HC
Elev.
HC
HC
HC
Parking
Mechanical
24
ECI/HYER :: THA ARCHITECTURE
SITE & LANDSCAPE.
NARRATIVE
Site Context and Location Site Conditions surface parking and loading facilities are relo-
cated to the north side of the building and will
Situated at the confluence of important natural The site is built on rock fill that dates from the
accommodate up to two tractor trailers and two
borders and urban corridors, the site presents city’s hard-rock mining period. The fill is porous
smaller delivery vehicles. Public parking is under
opportunities to create connections, to link the and is subject to inundation by tidal waters.
the building.
waterfront to the site, to further develop the Generous precipitation and maritime conditions
arboretum, and to create a public plaza as an make this area conducive to growing plants from
important outdoor space. most parts of Alaska. Prevailing winds enter the
Pedestrian Circulation and Entrance
site from the southeast with the occasional Taku Plaza
Located between the Gastineau Channel and
winds coming from the northeast. Pedestrian access to the site will come primar-
Mount Juneau, the site occupies an area that
ily from the east with clear views into the entry
was once a tidal beach. A spillway or tailrace The area to the east of the site is typified by a
plaza. This east access from downtown and the
from an historic hydroelectric plant and a shop- lack of clear connectivity and scattered parking
State Office Building will be further strengthened
ping center form the western boundary to the lots, in spite of being a major pedestrian pas-
by the plaza’s future extension into the eastern
site. Egan Drive, an important highway, along sageway. The tailrace on the west side of the
parcel across Whittier Street.
with a restaurant, hotel and radio station forms site is partially exposed with the power com-
the southern boundary, with the waterfront one pany planning on completing the piping within The other important pedestrian access to the
block further south. The eastern site boundary the next four years. Currently, tour buses enter site is from the south. Pedestrian access over
is Whittier Street, which separates the museum the site and pull directly to the building entry. A Egan Drive is addressed with a path that can
site from a collection of surface parking lots, collection of trees and shrubs with interpretive connect to a proposed pedestrian bridge that
Willoughby Street, the State Office Building and signs forms an arboretum on-site. will link the existing waterfront path to a north-
downtown Juneau. Immediately north of the south pedestrian path. This passage will provide
site is a motel, restaurant and Willoughby Street Vehicular Access and Circulation an opportunity for tourists to cross the highway
where the outline of the beach is still somewhat This plan proposes to relocate the bus drop-off to the site. The path will continue north through
visible. Two well used pedestrian corridors serve zone to the Whittier Street edge. This move will a naturalized corridor along the western site
the site: between the State Office Building and allow the site to reclaim its frontage as a plaza boundary connecting to Willoughby Street.
the shopping center (east-west) and from the and event space, keeping buses close to the
waterfront to the museum (south to north). street for easy arrival and departure. The staff
Landscape
The entry plaza is designed to be low mainte-
nance, safe and flexible enough to accommo-
3
date a variety of event programs and uses, and
1 to be an elegant and enjoyable public space. This
entry plaza is seen as a first step towards creat-
ing a public open space and arboretum that later
expands towards the east to create additional
1 New LAM building public space and to continue uniting the district.
2 State Office Building The plaza landscape will represent a balance of
plantings and hardscape, reflecting local materi-
3 proposed pedestrian mall
als and textures. Due to the rock fill at the site,
Mall Concept -- Interim Build-out trees will be placed in a raised planting area sup-
ported by stone and good topsoil. Sightlines are
maintained throughout the planted areas by the
use of low growing herbaceous plants. Raised
plantings will define paths within the plaza space
2 and provide ample topsoil depth for trees and
other plants.
The arboretum will be a lightly forested zone
on the south side of the museum, providing an
3
entry to the north-south trail. On the north side
of the building, tree plantings will buffer the staff
1
entry and parking area. Plaza paving and planter
designs will reflect the glacial activity typical
of the region: exposed rock faces; scored and
grooved paving surfaces will provide a sense of
detail and directionality. Seating and other fur-
nishings will further reflect the rock outcrops
found in the nearby mountains and the forms of
dugout canoes.
Mall Concept -- Full Build-out
26
ECI/HYER :: THA ARCHITECTURE
y Ave
n ue
CONCEPT
Wil
lough
b
Site Plan
Wh
ittie
r S
tre
6 3
et
9
4
2 8
1
8
5
1 building footprint
5
2 entry plaza
4 bus drop-off
5 pedestrian trails
5 6 service/maintenance area
7 staff parking
venue
Egan A 8 art/sculpture
Introduction elevator, parking garage and other uses. Domes- AJ rock fill are often referred to as outwash and
tic/fire water supply and sanitary sewer system glacio-marine deposits. These soils commonly
The proposed Library Archives Museum project
will be supplied through the CBJ public utilities. consist of gray to brownish light gray sand with
site is on property owned by the State of Alaska.
gravel with pockets of fine sand/silt deposits
ECI/Hyer provided R&M the LAM Concept Design The topographic survey prepared for the site
some of which offer low bearing values.
Full Report on September 2, 2010 to assist in reveals that Lots 4, 5, and 6 are developed as
preparing the civil concept narrative. Site topo- the existing State of Alaska Museum. With the
graphic survey has been previously been per- exception of the museum building and the tem-
Ground Water
formed by our firm and included as an Exhibit to porary annex, Lots 4, 5 and 6 are relatively flat Ground water at this site will be dependent
the concept narrative report. and are covered by lawn areas, landscaping, upon the tide level of Gastineau Channel and
sidewalks, an asphalt paved access road and most likely fluctuate within the tide range on
The proposed LAM Building is located adjacent any given day. Structural foundation members
parking areas accessing Whittier Street. Lots 9
to Willoughby Avenue to the north and to the and site construction activities below elevation
and 12 FR are predominantly developed as fairly
east by Whittier Avenue, both which is City and +20’ mean lower low water would be influenced
level gravel surfaced parking areas accessing
Borough of Juneau (CBJ) maintained and owned by the tide. Dewatering the project site during
onto Willoughby Avenue.
paved roadways. To the northwest is located construction is important. Mitigation methods
private developed property including the Drift- The following is our conceptual civil design for controlling construction surface and ground-
wood Lodge and Salvation Army Church. To the based on our understanding of the Project. Site water include but are not limited to:
south lie the Prospector Hotel and the KTOO civil issues will be further refined to determine
Radio building. To the west lie the Alaska Electric the most economical and intelligent solutions 1. All below-grade portions of the building are
Light and Power (AEL&P) Gold Creek Tailrace for the Project during the Schematic and Design properly water and moisture-proofed by
Flume and Foodland Shopping Center. The legal Development design phases. waterproofing the below grade foundation
description of the LAM property is Lots 4, 5, 6, 9 walls and placement of a plastic vapor bar-
and 12 Front (FR), Block Sixty Six (66), Tidelands Site Geology and Soils rier below the floor slabs.
Addition to the CBJ. Preliminary research of general site geology and 2. Surface water is effectively isolated from
The LAM Building proposal consists of a ground soils on adjacent properties indicates that the entering all soils below foundation footings
floor, upper floor and lower level below grade site was originally an alluvial soils formed by Gold and floor slabs.
parking structure. The facility will include spaces Creek. The alluvial soils were filled with mine tail-
3. Surface grading is accomplished in a man-
for museum, archives, auditorium, meeting ings waste rock from the Alaska Juneau (AJ) Mine
ner that will positively divert surface water
rooms, offices, restrooms, mechanical room, from the 1910 through 1940’s. The depth of this
runoff away from the structure.
material varies. The granular deposits below the
30
ECI/HYER :: THA ARCHITECTURE
required for the installation in either option. All Strategically placed storm drain structures with
wastewater generated from this site would be 12” CPP gravity storm piping between them
treated at the CBJ wastewater treatment plant. will drain the drop-off zone, hard-scape areas,
access roads and sidewalks. Roof drains would
Storm Water System be routed to the ground surface and routed
Storm drain systems exist within Willoughby away from the building foundation walls. Foun-
Avenue and Whittier Street. It is assumed for dation drains would be routed to storm drain
this concept narrative that site storm drainage catch basins/manholes if elevations are found
will be designed to be routed to each of these to be adequate. The lower level parking garage
areas. An 18” CPP storm drain line with curb will require a storm drain collection system and
inlets exists on Willoughby Avenue which would an electronic submersible pumping system with
be connected to new storm drain pipe from high level alarms to discharge any storm water
this project. This system is not deep (5’ below accumulated in the parking garage to the gravity
finish street grade) but we assume there will storm system.
be enough elevation drop to allow storm water
from the proposed staff parking area and service Required Development Permits
area to be collected in storm drain structures The following is a list of potential development
and piped underground in 12” CPP pipe to the permits that may be required for this project:
Willoughby Avenue system. Foundation and
• CBJ Conditional Use Permit
roof drains would also be routed to this side of
the site where feasible. Loading dock walls are • CBJ Grading and Drainage Permit
assumed to be elevated above grade, therefore • CBJ Building Permit
no separate system is required for drainage.
• CBJ Utility Connection Permit
Storm drainage collected on the eastern half of
the site where the underground parking access • Utility service coordination for telephone,
road, entry plaza, bus drop-off zone and art/ electric and Cable TV.
sculpture areas have been identified, will drain It is assumed the site is classified as “uplands”
into the existing storm drain system on Whittier and that it would not fall under the jurisdiction
Street. An existing 18” CPP storm drain pipe with of the U.S. Army Corps of Engineers (COE).
storm drain structures is located on the east side
of Whittier Street. The existing museum storm
drain is currently connected to this system.
General • Functional performance: How well will the It is anticipated that more than one material
structural systems perform during normal will eventually be selected for a given structural
The structural design will be developed accord-
use? (For example, is there perceptible vibra- system (e.g. multiple framing systems for the
ing to the applicable building codes and design
tion of the floor plate underfoot?) building floor plates), based on the answers to
standards. These codes and standards include,
the above questions.
but are not limited to the following: • Functional compatibility: Are the structural
systems compatible with the other design
• 2009 International Building Code (IBC)
disciplines’ functional needs (e.g. fire rat-
Foundations and Garage Floor Slab
• ASCE 7-08 Minimum Design Loads for Build- ings, routing of mechanical systems)? The foundation design will be developed accord-
ings and Other Structures ing to the recommendations of the geotechnical
• Constructability: Do the structural systems engineer, based on the site-specific soils condi-
• AISC 341 Seismic Provisions for Steel Build- work with the construction sequencing? Are tions. It is known that the general soil make-up
ings they consistent with locally available labor? consists of man-made granular fill over native
The building will be designed as an Occupancy • Cost effectiveness: Are we achieving “bang tidal beach soils. The granular fill is subject to
Category II structure (standard occupancy), per for the buck” and staying within the project regular tidal saltwater inundation.
ASCE 7 Table 1-1. As a result, importance factors budget? The foundations are anticipated to consist
for snow, wind and seismic loads are all 1.0. This
• Cleanliness: In areas where the building con- of driven steel piles, most likely H sections.
level of design is intended to ensure life safety
tents are sensitive to contamination, can the Depending on the structural loads, piles may be
during a design-level event.
structural systems be selected to minimize placed in groups or standalone. For example, at
potential contamination? (For example, in heavily loaded interior columns, pile groups may
Structural Systems Selection be required to support the loads, whereas along
the storage/vault areas, are there structural
In general, many factors will be considered systems that do not need spray-applied a uniformly loaded basement wall, single piles
when selecting the materials and systems for fireproofing that may degrade over time?) may be spaced at regular intervals.
the building’s structure. Some of the questions
that will be answered during design include the • Aesthetics: In areas where structure will be Piles will be capped with cast-in-place concrete
following: exposed to view, are the materials compat- pile caps at concentrated load locations, and
ible with the architectural form? In areas cast-in-place concrete grade beams at uniform
• Life safety: How well will the structural where the structure is NOT exposed to view, load locations.
systems perform during catastrophic wind, are the structural members (e.g. seismic
seismic and snow events? The parking garage floor slab is anticipated to be
braces) able to be concealed? a cast-in-place, mildly reinforced (i.e. non-post-
34
ECI/HYER :: THA ARCHITECTURE
Column Framing Lateral Force Resisting System The vertical resisting elements (braced frames
and shear walls) will vary according to the loca-
The column construction will vary depending The building will be subjected to lateral forces
tion in the building, as follows:
on the functional needs of the surrounding due to wind and seismic events, and the struc-
spaces, and the architectural aesthetic needs, as ture will be designed to resist these forces and 1. Library/lobby roof: The architecturally
follows: resolve them into the ground. exposed roof structure will be braced on all
sides by diagonal steel rod tension bracing,
1. Lower level parking/mechanical areas: In Lateral wind forces are the result of pressure and
deployed in X configurations. Braces may be
these areas, columns are anticipated to be suction on the building’s vertical surfaces. Wind
constructed with clevises and turnbuckles,
structural steel (W shapes). Where fire rating loads are transferred to the horizontal roof and
or other similar mechanisms for making the
is required, columns may be wrapped and/or floor diaphragms by the building’s exterior wall
connections.
fireproofed. Where vehicle impact resistance assemblies.
is a concern, columns may be protected by a 2. Conventional low-slope roofs: Roof dia-
Seismic forces are inertial forces, generated
waist-high concrete encasement. phragms will be connected to buckling-
when the ground accelerates beneath the
restrained braced frames (BRBF’s), which
2. First and second floor “clean” areas: In the building. Inertial forces will concentrate at the
consist of wide-flange beams and columns
Secure Storage and any other sensitive roof and second floor levels, where the seismic
and manufactured diagonal BRB bracing
areas, columns will be concrete (precast or mass is greatest. Foundations and ground floor
members (Star Seismic “Powercat” braces
cast-in-place). This will eliminate the need slabs are in phase with the ground, and do not
or equivalent www.starseismic.net). Braces
for fireproofing and/or column wraps, which contribute seismic forces to the above-ground
are generally oriented in single-diagonal or
could break down over time and contami- structure.
chevron (inverted V) configurations. Diago-
nate the room contents.
The roof or floor deck at each level acts as a hori- nal bracing members will be configured
3. First floor, second floor, and roof areas with zontal diaphragm to transfer lateral loads to the to avoid conflicts with the floor plan and
exposed structure: Where the columns are vertical resisting elements (steel braced frames window/door openings. BRB members and
exposed to view, they will be precast con- and concrete shear walls). The diaphragms are their end connections (gusset plates and
crete. Columns may be cast into expressive connected to collector beams (drag struts), welds) are engineered by the brace manu-
forms according to the architectural design. which accumulate and deliver the lateral loads facturer, using the geometry and loading
Embedded steel hardware will accept the to the vertical resisting elements. Collector ele- criteria supplied by the Engineer of Record.
connections of the surrounding floor and ments are designed for special load combina- Bracing connections are field welded to gus-
roof framing members. tions and detailing provisions as required by the set plates (approximately 120” total of 5/16”
building codes. In general, the collectors consist fillet weld is assumed for each connection).
4. First and second floor perimeter columns
of steel beams, with slip-critical bolted or welded
and columns at braced frame bays: In these 3. Garage, basement mechanical room and first
end connections.
areas, columns will be structural steel (HSS level Secure Storage walls: Where concrete
or W shapes).
36
ECI/HYER :: THA ARCHITECTURE
Mechanical.
Narrative
38
ECI/HYER :: THA ARCHITECTURE
cooling units. Packaged air-conditioning units will have the ability to be shut-off during when be a constant volume system with variable
will include a wall or floor mounted evaporator the building is unoccupied to save energy. speed fan motor to allow the fine adjustment
section and a separate remote condenser unit. of air change rates per hour within zone. This
Cooling equipment suspended from the ceiling AHU-2 System system will incorporate precise humidity control
will be avoided to prevent interference with AHU-2 (42,000 CFM) will serve the museum (primary) and temperature control (secondary).
cable routing. An indirect floor drain will be pro- lobby and exhibit areas. This system will be a Outside air intake will be kept to the absolute
vided for condensate drainage. constant volume multi-zone system with variable minimum level necessary to provide positive
speed fan control to allow the adjustment of air zone pressurization and gas dilution (if neces-
Ventilation Systems changeover rates within the zone. This system sary. The need for redundant supply fans and
The primary building ventilation systems will will be capable of high precision humidity and “ready for use” spare parts will be determined
include six (6) separate and independent central temperature control. At this point the museum/ as part of the project risk assessment.
air handling units (AHU’s). Each unit may include exhibit area is a single large open volume. The Special indoor environments required for media
some or all of the following sections: mixing box, system will have the capability to control this storage will be provided using air tight vaults
pre-filter (MERV 7), final filter (MERV 14), desic- area as a single zone and the flexibility to con- “cocooned” with the archive area. These spe-
cant dehumidifier, gas phase filtration, supply trol it as several independent zones depending cialty vaults will incorporate dedicated cooling
fan, DX cooling coil, heating coil, humidification on how the space is being utilized. and dehumidification systems.
steam dispersion panel, silencer and discharge
plenum. Service plenums (18” to 24” wide) will AHU-3 System AHU-6 will serve the second floor secure storage
be provided between specific AHU sections (archive area) and will be identical to AHU-4.
AHU-3 (27,000 CFM) will serve the central first
to allow for proper maintenance and cleaning and second floor staff collections and processing AHU-5 System
access. Supply fans will be equipped with vari- areas. This system will be setup with VAV supply
able speed drive (VSD) controllers to allow pre- terminal units and corresponding exhaust air AHU-5 (24,000 CFM) will serve the second floor
cise supply air volume control. Basis of design valves (EAVs). The system will provide precise reading/research rooms, LAMP offices and cen-
for AHUs will be Scott Springfield, Haakon or a pressure control using an “air flow tracking” tral processing areas. This system will be setup
pre-approved equal. control strategy similar to a laboratory. with VAV supply terminal units and correspond-
ing exhaust air valves (EAVs) similar to AHU-3.
AHU-1 System Wet lab areas will include general use fume It will provide precise pressure control using an
hoods with dedicated roof mounted exhaust “air flow tracking” control strategy similar to a
AHU-1 (38,000 CFM) will serve the main entry
fans. laboratory.
and first and second floor lobbies, café, audito-
rium, administration, staff and technical service AHU-4 and 6 Systems General Exhaust Air
and general use areas. This system will be a con-
ventional variable air volume (VAV) system and AHU-4 (26,500 CFM) will serve the first floor Toilet rooms and janitor closest will have exhaust
secure storage (archive area). This system will systems sized to provide between 8 and 12 air
40
ECI/HYER :: THA ARCHITECTURE
Tempered Water System • Sanitary and storm drain piping will be cast include an indoor seasonal shut-off ball valve
iron, except drains from processing areas above the ceiling.
A dedicated tempered water system (85
will be chemical resistant up to a point of
Degrees F supply temperature (adjustable)) will Processing/Wet Lab Area Plumbing Fixtures
dilution, typically downstream of major rest-
be provided to serve the facilities combination
rooms. Below ground piping will use no-hub • Sinks and counters will be integral units
emergency shower/eyewashes (EWS). Water
fittings. No-hub fittings are also acceptable specified by the Architect.
temperature will be controlled using a dedicated
for above ground piping.
hydronically heated indirect water heater and a • Associated faucets will be institutional
single tempering valve designed for multi-emer- • Plumbing fixture groups will be provided grade.
gency shower usage. Tempered water recircula- with isolation valves to facilitate mainte-
tion will be provided utilizing an inline circulator nance. Valves two inches and smaller will be • Drain, waste and vent piping will be stan-
pump to continuously provide tempered water quarter-turn ball valves. dard DWV piping.
to each combination emergency shower/eye- • Acid resistant DWV system will be provided
wash location. Our design will assume that only General Plumbing Fixtures if required.
one EWS will be operational at any given time. • Plumbing Fixtures will be vitreous china and • Emergency shower and eyewash station
stainless steel as applicable. designs will be based on HAWS or Guard-
Compressed Air
• Wall hung toilets, urinals and lavatories will ian and supported by local tempered water
A compressed air system will be provided to systems.
be specified based on American Standard or
serve the wood shop. Remote compressed air
as approved.
outlets will be provided at other locations identi- Elevator Pits
fied by the Client (i.e. fume hoods) as the design • Public toilets and urinals will have 120VAC
progresses. Compressed air will typically be automatic infrared flush valves. Staff toilets An automatic elevator sump pump with oil sens-
piped at 80 to 90 psig, with local regulators at and urinals shall have manual flush valves. ing shut-off will be provided for each elevator pit
each point of use. All point of use regulators will sump. Pumps will indirect drain to the building
• Drinking fountains with push-bar type exterior.
be furnished with filters. faucet operators will be specified for handi-
capped operation. Fire Protection
Plumbing Piping
• Floor drains will be provided for all rest- The facility will receive its water from the munici-
• Domestic water piping will be type L copper.
rooms and mechanical rooms, as well as pal water system. Backflow protection will be
Solder will be 95-5 tin-antimony or 430 silver
janitor closets equipped with mop sinks. provided at the fire protection system connec-
solder. Lead-tin (50-50) solder will not be
accepted. • Exterior hose bibbs will be non-freeze, auto- tion point to the service water riser. If water
matic draining will be provided at a mini- pressure is inadequate, a fire pump/jockey pump
• Vent piping above ground will be DWV system will be provided.
mum of 100 FT intervals. Each hose bibb will
(drain, waste, and vent) copper or cast iron.
42
ECI/HYER :: THA ARCHITECTURE
Electrical.
Narrative
General video for auditorium, access control, CCTV and • Underwriters Laboratory, UL
burglary/intrusion detection. The following is
The design of the electrical systems to sup-
port the new Statewide Library, Archives and
our conceptual electrical design based on our Service and Distribution
current understanding of the Project.
Museum will focus on providing the appropri- Incoming Service
ate indoor environment(s) for the preservation,
viewing and security of its historical collections.
Applicable Codes and Standards A new electrical service will be provided to sup-
Applicable Codes include, but are not limited to, port the Library Archives Museum Building. The
The project design will utilize information pro- the following: new electrical service will be fed from existing
vided by the Alaska Department of Transporta- Alaska Electric Light and Power (AEL&P) facili-
tion and Public Facilities State Libraries, Archives • International Building Code (IBC) ties located near the site. A pad mounted trans-
and Museums Needs Assessment dated Septem- • International Mechanical Code (IMC) former will be provided near the building service
ber 2009. Our design team will work closely with entrance adjacent to the building wing with the
the client’s administrators, collections manag- • International Fire Code (IFC)
main electrical room.
ers, curators, conservators and security person- • National Electric Code (NEC)
nel to solicit further design input to allow us to Main Distribution
provide the appropriate electrical systems and Applicable Standards include, but are not limited
to, the following: Preliminary load calculations estimate the size
their proper level of control for this facility.
of the Main Distribution Switchboard to be
While the Library, Archives and Museum project • Illuminating Engineering Society of North approximately 2,500 Amps at 480Y/277 Volts.
is not pursuing LEED certification, the principles America, IESNA The switchboard will be located in a dedicated
for energy efficiency and environmentally sen- • National Electrical Contractors Association main electrical room. The main switchboard will
sitive design will play a key role in the decision - NECA distribute power to satellite electrical rooms
making process regarding electrical systems. located on each level. The satellite electrical
In addition, emphasis will be given to build- • National Electrical Manufacturers' Associa-
rooms will be placed strategically throughout
ing systems that can be easily maintained and tion - NEMA
the facility to minimize branch circuit homerun
operated. • National Fire Protection Association - NFPA lengths.
Electrical systems will include lighting, normal/ • EIA/TIA Telecommunications Standards The Library Archive Museum will be served at
emergency/standby power distribution and 480Y/277 volts, 3 phase, 4 wires. Dry type step
• BiCSi Telecommunications Distribution Meth-
special systems. Special systems will include fire down transformers will be provided to derive
ods Manual
alarm, telecommunications distribution, audio/ 208Y/120V power for required loads.
44
ECI/HYER :: THA ARCHITECTURE
panelboards serving specialty electronic equip- flexible and will compliment the architecture in control will be via switches located within the
ment, telecommunications equipment or other their respective spaces. Fluorescent lamps will spaces to be controlled. Switches for public
sensitive loads. be T5 or T5HO, RE841 type with a high color- spaces will be key switches or will be located in
rendering index and a 4100 degree K color tem- areas occupied by facility staff.
Lighting Systems perature. Higher color rendering index sources
In individual work areas occupant control will be
will be investigated during the design for use in
General specified to support optimum productivity and
critical work areas. Lamps will be low mercury
comfort conditions. Occupancy sensors will be
Lighting will typically be furnished in accor- type and will meet the requirements for classifi-
provided to maximize energy savings.
dance with the IES Lighting Handbook, 9th Edi- cation as non-hazardous waste when subjected
tion. Design lighting levels will be coordinated to the Toxic Characteristic Leaching Procedure Daylight activated control will be considered for
with the recommendations of the IES and the (TCLP) prescribed by the Environmental Protec- areas with daylight contributions.
requirements for preservation of the collec- tion Agency. Selected fixtures will be connected to generator/
tions. The architectural design will provide a A combination of other lamp sources will be standby power to allow limited operation during
generous amount of daylight in those spaces utilized where the function, maintenance, or power outage conditions. Refer to the system
where it is desirable. The lighting design will control scheme require their use. These lamp diagrams for a representation of these areas at
take advantage of this natural light while pro- sources will include high intensity discharge (HID) this stage of design. These areas will be further
viding a smooth transition from daytime to metal halide, solid state (LED) and incandescent. defined during the next design phase.
nighttime operations. Efforts will be made to consolidate lamp types Emergency egress lighting and exit signs will be
and reduce future maintenance costs. connected to generator/emergency power to
Lighting Concepts
provide Code required egress lighting. Under
Lighting concepts will be developed with the Lighting Control
normal circumstances the fixtures will be
architect and interior designer during the next Lighting control schemes will vary from areas switched along with the other room fixtures, but
design phase. Lighting will be conducive to the with highly specialized control to areas with during a power failure the emergency fixtures
building architecture and will enhance the visi- basic lighting control. Refer to the system dia- will fail “ON”.
tor’s experience and interest. Fixture types and grams for a representation of these areas at this
geometric layout patterns will compliment room stage of design. Exterior Lighting
shapes, functions and operational goals.
General lighting control in public areas will be With the recent improvements in the develop-
The most prevalent light source will be high accomplished with manual and automatic con- ment of solid state light sources, it is anticipated
efficiency fluorescent lighting which will be trol. Automatic control will be actuated by Build- that the exterior lighting will utilize LED (Light
employed throughout the interior spaces. A ing Automation System (BAS) output signals Emitting Diodes) as the light source. This light
variety of fixture types will be used to distribute and will control the lighting circuits via lighting source minimizes energy consumption will pro-
light in a controlled way that will be efficient, contactors located in electrical rooms. Manual viding excellent control and long life. Source
46
ECI/HYER :: THA ARCHITECTURE
Main Telecom Room: The MTR will serve as the Satellite telecom rooms or TRs should be at least • Access portals between public and secure
main hub for the communications systems for 14 feet long by 18 feet wide with at least 10 foot spaces and semi-ultra spaces (semi-ultra
the facility and will contain the following: ceilings. Exact location and quantities of TRs will secure or Level 3 access control).
be determined during design, but a minimum of
a) Telephone service entrance • Access portals between public, secure and
two satellite TRs in addition to the MTR are envi-
semi-ultra secure spaces and ultra secure
b) Modular patch panels for termination of lo- sioned to adequately serve the building square
spaces (ultra secure or Level 4 access con-
cal horizontal telecom cabling footage and required special systems head end
trol).
c) Fiber Optic distribution panels for connect- equipment.
The system will be capable of providing differ-
ing the MTR to each satellite TR for the Cable Tray: A cable tray system will be provided
ent levels of access. The system will use proxim-
purposes of providing data connectivity and for telecommunications cabling. Cable tray will
ity or contactless card readers. The exact place-
for voice communications if a Voice Over IP be provided to serve the various areas of the
ment and types will be coordinated during the
telephone system (VoIP) (owner provided) facility and provide pathway back to the MTR
design process.
d) Voice riser terminations for connecting the and TRs. Cabling will be plenum rate for use in
the cable tray in accordance with Code. A badging system will be provided to allow
MTR to each satellite TR if a VoIP telephone
production of access control cards on site. A
system (owner provided) is not intended for Conduit will be provided from the devices (tele-
badging system typically consists of a worksta-
use in the facility communication outlets, television outlets, etc.)
tion with access to the access control system
e) Data Network switches (owner provided) to the accessible ceiling space and then to the
server, a camera for taking of badge photos and
nearest cable tray.
f) Data Network equipment (owner provided) a badge printer for printing of badges. The loca-
Where devices are not capable of being served tion of the badging system will be coordinated
g) VoIP network switches (owner provided) by the cable tray system, conduit will be pro- during the design process.
h) VoIP server (owner provided) vided from the devices, direct to the nearest TR
Remote control operation of a lobby entry door
or the MTR.
To accommodate head end equipment for the or a loading dock/delivery door can be provided
access control system (see below), the Closed should the need be identified during design.
Access Control System Such remote control operation could rely on
Circuit Television System (CCTV), and other
An access control system will be provided to CCTV cameras and a small local intercom system
special systems, we recommend the Main Tele-
control access to the following areas: to verify the validity of a request to enter.
com Room (MTR) be at least 20 feet long by 18
feet wide with at least 10 foot ceilings. Should • Building entrances including overhead doors The access control system will be capable of
the need or desire arise to co-locate any of the (basic or Level 1 access control). being accessed and will be monitored from the
intended digital archival storage into the MTR, Security Office.
• Access portals between public spaces and
an increase in size of the MTR will be required.
secure spaces (secure or Level 2 access
control).
48
ECI/HYER :: THA ARCHITECTURE
Audio-visual horn/strobe units with combination Auditorium Audio/Video System
horn and flashing alarm strobe will be used.
A complete audio/video distribution system will
Comprehensive smoke and heat detection will be provided in the Auditorium to allow distribu-
be provided throughout the building. Smoke tion of multiple sources and allow flexible use of
detectors will utilize multiple detection meth- the space for presentations, teaching, movies,
odologies and time based algorithms to provide etc. The system will include high quality sound
increased detection sensitivity while minimizing system, microphones (including wireless), over-
false alarms. In addition smoke detection will be head projector(s), powered projection screen(s),
provided as noted below: A/V control system and sophisticated lighting
and controls.
a) Smoke detectors will be installed in me-
chanical return air systems in accordance Teleconference/video conference capabilities
with International Mechanical Code (IMC) will also be provided as determined during
requirements. design.
b) For control of smoke control doors.
c) For control of fire/smoke dampers.
Sprinkler Switches: Sprinkler flow and tamper
switches will be monitored to indicate flow in
any part of the system or a partial or complete
shutdown of the system at the gate valves.
Sprinkler Pre-Action Systems, Clean Agent
Systems and Fire Suppression Systems will be
monitored by the Fire Alarm System. Smoke
detection required for initiation of these systems
(e.g., cross zoned smoke detectors) will be pro-
vided and monitored by the Fire Alarm System.
Appropriate relay outputs will be provided from
the Fire Alarm System to activate these systems
upon a verified alarm.
Assumptions • Basic Allowable area – 3-stories and 15,500 sf • Book Drop – 2 Hr fire resistant rated con-
per story. struction.
Two-story building with a total building area
of approximately 114,000 sf plus 10,600 sf of • Allowable Increase – based on 200% allow- Structural Frame: type II-A buildings
mechanical space and 82 stalls of parking below able area increase per floor (IBC 506.3) plus
• 1 Hr fire protection as required per table 601
grade. Building will be constructed according to a 75% allowable area increase for frontage
and 602.
the 2009 International Building Code (IBC) and per section 506.2 = 58,125 sf allowable per
all applicable local and state code amendments. floor. Exterior Walls: type II-A buildings
The following study is based on the 2006 IBC as • No fire protection is required for type II-A
• Height increase: automatic sprinkler increase
the 2009 version has yet to be adopted. buildings which are equal to or greater than
to 4-stories and shall not exceed 85’ per IBC
Occupancy 504.2 30 feet from a property line per table 601
and 602.
• A-3 – Assembly (Library, museum, audito- • Area separation between the A-3 and S-1 oc-
rium and meeting rooms) cupancies. • 1 Hr fire protection is required for type II-A
buildings which are less than 30 feet from a
• B – Business (Offices); most likely an acces- Fire Resistance Rated Construction
property line per table 601 and 602.
sory occupancy to A-3
Incidental Use Areas
Interior Non bearing Walls: type II-A buildings
• S-1 – Moderate-hazard storage: Archives
• Boiler Room – An automatic sprinkler system
(books, files and artifacts) • No fire protection required per table 601 and
is provided, therefore a separation capable
602.
• S-2 – Low-hazard storage: Parking garage of resisting the passage of smoke is required
per section 508.2.2.1. Floor Construction type II-A buildings
Occupancy Separation: Non-separated use per
section 508.3.2. Use the most restrictive, A-3, for • Storage Rooms over 100 sf – An automatic • 1 Hr fire protection as required per table 601
construction purposes. sprinkler system is provided, therefore a and 602.
separation capable of resisting the passage Roof Construction type II-A buildings
Construction Type
of smoke is required per section 508.2.2.1.
II-A • 1 Hr fire protection as required per table 601
• Furnace Rooms w/ any piece of equipment is and 602.
Allowable Area and Height over 400,000 Btu/hour input - An automatic
sprinkler system is provided, therefore a • Fire retardant-treated wood members shall
• Based on A-3 occupancy, type II-A construc-
separation capable of resisting the passage be allowed at 20’ or more above finished
tion and fully sprinklered.
of smoke is required per section 508.2.2.1. floor (table 601, exception C).
52
ECI/HYER :: THA ARCHITECTURE
serving an occupant load of 50 or more per • Landscaping – Will meet planning and zon-
section 1008.1.9. ing requirements.
• Corridor Width – Corridors may be no less • Parking – per City of Juneau Planning
than 44 inches in width per section 1017.2. Department with anticipated extension of
Cultural District Overlay (60% reduction).
• Emergency Lights & Exit Signs – The entire
building is required to have emergency • Loading zones – 4 required
lighting and exit signs per section 1006.1
and 1011.1. Exceptions: Approved exit sign
illumination means that provide continuous
illumination independent of external power
sources for duration of not less than 90 min-
utes, in case of primary power loss, are not
required to be connected to an emergency
electrical system per section 1011.5.3.
• Address Numbers – The Fire Chief may
require address numbers plainly visible and
legible from the street.
• Key Boxes – The Fire Chief may require an
approved key box.
Zoning Requirements
Per Zoning requirements for the City and Bor-
ough of Juneau:
• Setbacks – 5’ all sides
• Height Limitations – 35 feet max. (Possible
height increase to 45 feet with CBJ credits,
or with a variance or planned rezoning of
the area).
Loading
Elev.
W Security
Wood Wd. Iso. Crate Ed. Classroom Off.
Work Stor. Storage Coll. Museum
Shop Sup. Volunteer Cafe
Staff M Lock.
M
Conf. Conf. Auditorium
W Elev.
Clean
Lobby
Shop
UP Vest.
3D
Con.
Cons.
Supply Store
Wet Lab Museum
Photo Lobby
Wet Lab Museum
Exhibit Storage
Secure
Storage Pro-
cessing 2D
Con.
KEY
M W
Collection
Collections
Ex.
Stor.
Coll.
Sup.
54
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Collections Areas
Roof
Elev.
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M M
Elev.
W
DN
Open
Supply Roof
Service
Special Desk
Processing
Projects
Video Research
Conf. Room
Reading
Secure Room
Storage
Microform
Storage
Readers
Media 1
KEY
LAMP
Media 2 Offices
Collections
Roof
Terrace
Staff
HC
Elev.
HC
HC
HC
Parking
KEY
Mechanical
Cast in Place
Concrete Slab on
Concrete Grade Beams
over Steel Piles
Precast Concrete
Columns Over
Steel Piles
Steel Columns Over
Steel Piles
Cast In Place Concrete
Wall with Pilasters
Over Steel Piles
56
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Floor Structure
Loading
Elev.
W Security
Wood Wd. Iso. Crate Ed. Classroom Off.
Work Stor. Storage Coll. Museum
Shop Sup. Volunteer Cafe
Staff M Lock.
M
Conf. Conf. Auditorium
W Elev.
Clean
Lobby
Shop
UP Vest.
3D
Con.
KEY
Cons.
Supply Store
Wet Lab Museum
Lobby Cast in Place Concrete Slab
Photo
on Concrete Grade Beams
Wet Lab Museum
Exhibit Storage
over Steel Piles
Secure
Storage Pro-
cessing 2D
Concrete Slab on
Con. Composite Steel Deck
Ex.
Stor.
Steel Columns
Buckling-Restrained
Coll.
Sup.
Braced Frame (BRBF)
Roof
Elev.
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M M
Elev.
W
DN
Open
Supply Roof
Service
Special Desk
Processing
Projects
Video Research
Conf. Room
Reading
KEY
Secure Room
Storage Concrete Slab on
Composite Steel Deck
Microform
Storage
Readers Concrete Topping Slab on
Concrete Pre-cast Planks
Pre-Cast Concrete
LAMP
Offices
Roof Steel Columns
Terrace
Buckling-Restrained
Staff Braced Frame (BRBF)
Cast In Place Concrete Wall
58
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Roof Structure
Elev.
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M M
Elev.
W
DN
Open
Supply
Processing Special
Projects
Video Research
Conf. Room KEY
Reading
Secure Room Architecturally Exposed,
Storage Curved Timber Frame Roof
Microform
Conventional
Storage Low Slope Roof
Readers
Pre-Cast Concrete
Note:
Wall and column and bracing
Roof Structure Diagram thickness are exaggerated for graphic
Loading
Elev.
W Security
Wood Wd. Iso. Crate Ed. Classroom Off.
Work Stor. Storage Coll. Museum
Shop Sup. Volunteer Cafe
Staff M Lock.
M
Conf. Conf. Auditorium
W Elev.
Clean
Lobby
Shop
UP Vest.
3D
Con.
Cons.
Supply Store
Wet Lab Museum
Photo Lobby
Wet Lab Museum
Exhibit Storage
Secure
Storage Pro-
cessing 2D
Con.
KEY
M W
Collection
Ex.
Air Handler -1, VAV
Stor. Air Handler -2, CV
Coll. Air Handler -3, VAV
Sup.
Air Handler -4, CV
Air Handler -5, VAV
Air Handler -6, CV
60
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Air Handler Zones
Roof
Elev.
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M M
Elev.
W
DN
Open
Supply Roof
Service
Special Desk
Processing
Projects
Video Research
Conf. Room
Reading
Secure Room
Storage
Microform
Storage
Readers
KEY
LAMP
Offices Air Handler -1, VAV
Roof
Terrace
Air Handler -2, CV
Air Handler -3, VAV
Staff
Air Handler -4, CV
Air Handler -5, VAV
Air Handler -6, CV
(0)
Loading
(0)
Elev.
W Security
Wood Wd. Iso. Crate Ed. Classroom Off.
Work Stor. Storage Coll. Museum (+) (+)
Shop Sup. Volunteer (0) Cafe
Staff M Lock.
(0) (0) (0) M (0)
(0) (0) (+) (+)
Conf. Conf. Auditorium
W Elev.
(+)
M W
Ultra Clean ( ++ )
Collection
(0)
( ++ )
Semi-Clean (+)
Ex.
( + ) Stor. Semi-Dirty (0)
Coll.
Ultra Dirty (-)
Sup.
(+) Neutral Pressure
Pressure Flow
62
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Building Environment
Roof
Elev.
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M (+) (+) (+) M (+)
(+) Elev. (0) (+)
(0) (0)
W
DN
Open
Supply Roof
(+) (+)
(+)
(+)
Service
Special Desk
Processing
Projects (+)
Video Research
Conf. ( ++ ) (+) Room
(+)
(+)
Reading
Secure Room
Storage
(+)
( ++ ) KEY
Microform
Storage
Readers Environmental Pressure
(+)
(0) Air Quality Level
Ultra Clean ( ++ )
LAMP
Offices Semi-Clean (+)
(+) Roof
Terrace
Semi-Dirty (0)
(0) Ultra Dirty (-)
Staff
(+) Neutral Pressure
Pressure Flow
HC
Elev.
HC
HC
HC
Parking
Mechanical
KEY
Wet Sprinklers
Parking Level
64
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Fire Protection
Loading
Elev.
W Security
Wood Wd. Iso. Crate Ed. Classroom Off.
Work Stor. Storage Coll. Museum
Shop Sup. Volunteer Cafe
Staff M Lock.
M
Conf. Conf. Auditorium
W Elev.
Clean
Lobby
Shop
UP Vest.
3D
Con.
Cons.
Supply Store
Vault Wet Lab Museum
Photo Lobby
Wet Lab Museum
Exhibit Storage
Secure
Storage Pro-
cessing 2D
Con.
KEY
M W
Collection
Pre-action Sprinklers
Ex.
Stor.
Wet Sprinklers
Coll.
Sup. Dry Pipe Sprinklers
Roof
Elev.
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M M
Elev.
W
DN
Open
Supply Roof
Service
Special Desk
Processing
Projects
Video Research
Conf. Room
Reading
Secure Room
Storage
Microform
Storage
Readers
Media 1
KEY
LAMP
Media 2 Offices
Pre-action Sprinklers
Roof
Terrace Wet Sprinklers
Staff
66
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Emergency Power
HC
Elev.
HC
HC
HC
Parking
KEY
Mechanical
Fully Operational
( HVAC, Lighting, and Power )
Limited Emergency
Power Operation
( HVAC, Reduced Lighting,
and Limited Power )
Parking Level
Loading
Elev.
W Security
Wood Wd. Iso. Crate Ed. Classroom Off.
Work Stor. Storage Coll. Museum
Shop Sup. Volunteer Cafe
Staff M Lock.
M
Conf. Conf. Auditorium
W Elev.
Clean
Lobby
Shop
UP Vest.
3D
Con.
Cons.
Supply Store
Wet Lab Museum
Photo Lobby
Wet Lab Museum
Exhibit Storage
Secure
Storage Pro-
cessing 2D
Con.
KEY
Fully Operational
M W ( HVAC, Lighting, and Power )
Collection
Ex.
Stor. Limited Emergency
Power Operation
Coll. ( HVAC, Reduced Lighting,
Sup.
and Limited Power )
68
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Emergency Power
Roof
Elev.
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M M
Elev.
W
DN
Open
Supply Roof
Service
Special Desk
Processing
Projects
Video Research
Conf. Room
Reading
Secure Room
Storage
Microform KEY
Storage
Readers
Media 1
Fully Operational
( HVAC, Lighting, and Power )
LAMP
Media 2 Offices
Roof Limited Emergency
Terrace
Power Operation
( HVAC, Reduced Lighting,
Staff
and Limited Power )
HC
Elev.
HC
HC
HC
Parking
Mechanical
KEY
BASIC LIGHTING
Parking Level
70
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Light Control
Loading
Elev.
W Security
Wood Wd. Iso. Crate Ed. Classroom Off.
Work Stor. Storage Coll. Museum
Shop Sup. Volunteer Cafe
Staff M Lock.
M
Conf. Conf. Auditorium
W Elev.
Clean
Lobby
Shop
UP Vest.
3D
Con.
Cons.
Supply Store
Wet Lab Museum
Photo Lobby
Wet Lab Museum
Exhibit Storage
Secure
Storage Pro-
cessing 2D
Con.
KEY
M W
Collection
Ex.
HIGHLY SPECIALIZED
Stor.
SPECIALIZED
Coll.
Sup. FULL CONTROL
MODERATE CONTROL
BASIC LIGHTING
Roof
Elev.
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M M
Elev.
W
DN
Open
Supply Roof
Service
Special Desk
Processing
Projects
Video Research
Conf. Room
Reading
Secure Room
Storage
Microform
Storage
Readers
Media 1
KEY
LAMP
Media 2 Offices HIGHLY SPECIALIZED
Roof
Terrace SPECIALIZED
BASIC LIGHTING
72
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Access Control
Secure Public
Loading
Elev.
W Security
Wood Wd. Iso. Crate Ed. Classroom Off.
Work Stor. Storage Coll. Museum
Shop Sup. Volunteer Cafe
Staff M Lock.
M
Conf. Conf. Auditorium
W Elev.
Clean
Lobby
Shop
UP Vest.
3D Public
Con. High Value
Objects
Cons. Public
Supply Store Surveillance
Vault Wet Lab Museum
Photo Lobby
Wet Lab Museum
Exhibit Storage
Secure
Storage Pro-
cessing 2D
Con.
KEY
M W
Collection
Public
Ex.
Stor.
Public Surveillance
Coll. Secure
Sup.
Semi-Ultra Secure
Ultra Secure
Secure Public
Roof
Elev.
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M M
Elev.
W
DN
Open
Supply Roof
Service
Special Desk
Processing
Projects
Video Research
Conf. Room
Reading
Secure Room
Storage
Microform
Storage
Readers
Media 1
KEY
LAMP
Media 2 Offices
Public
Roof
Terrace Public Surveillance
Secure
Staff
Ultra Secure
74
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Closed Circuit Surveillance
HC
Elev.
HC
HC
HC
Parking
Mechanical
KEY
No CC TV Surveillance
Exterior Surveillance
Parking Level
Loading
Elev.
W Security
Wood Wd. Iso. Crate Ed. Classroom Off.
Work Stor. Storage Coll. Museum
Shop Sup. Volunteer Cafe
Staff M Lock.
M
Conf. Conf. Auditorium
W Elev.
Clean
Lobby
Shop
UP Vest.
3D
Con.
Cons.
Supply Store
Vault Wet Lab Museum
Photo Lobby
Wet Lab Museum
Exhibit Storage
Secure
Storage Pro-
cessing 2D
Con.
KEY
M W
Collection
76
ECI/HYER :: THA ARCHITECTURE
Systems Diagrams
Closed Circuit Surveillance
Roof
Elev.
W
Micrographics Special Technical and Class-
Administration Outreach Staff
Projects Service room
Workspace M M
Elev.
W
DN
Open
Supply Roof
Service
Special Desk
Processing
Projects
Video Research
Conf. Room
Reading
Secure Room
Storage
Microform
Storage
Readers
Media 1
KEY
LAMP
Media 2 Offices
Low Density Surveillance
Roof
Terrace No CC TV Surveillance
Staff
THA Architecture
733 SW Oak Street, Suite 100
Portland, Oregon 97205
503.227.1254