Sunteți pe pagina 1din 17

Southeast Asian gas outlook to 2045: Prospects of gas network expansion

to increase security of supply


Yuliana *
Faculty of Technology, Policy and Management - Delft, University of Technology, the Netherlands
2015

Abstract

Indonesia, Malaysia, and Brunei are countries in Southeast Asia that have been known as LNG exporters since the early periods of LNG
trade. After being major LNG exporters for the last four decades, the countries are confronted with depleting gas resources. The whole region
is facing a similar trend of increasing domestic gas consumption and a decline in domestic gas production that leads to a problem of security
of gas supply. Currently, there are two master plans of gas infrastructure in Southeast Asia: Trans-ASEAN gas pipeline (TAGP) and ASEAN
LNG facilities. This research is aimed to evaluate the ability of the current proposed plans to meet natural gas demand in the region until
2045. A gas network model of existing gas pipelines and LNG infrastructures in the region has been developed to evaluate the plans. The
results show that the current plans are hardly sufficient to meet natural gas demand especially in Indonesia, Thailand, and Singapore, and
therefore, need to be revised. Based on the BAU scenario, the three countries will need to add more regasification capacities and new TAGP
connection will only come from East Natuna to Java. In the Reference scenario, Singapore could defer the regasification expansion until
2040, and there could be additional TAGP connections, i.e. from East Natuna to West Natuna – Singapore or East Natuna to Erawan.

Keywords: Southeast Asia, natural gas, security of supply, gas pipeline, LNG, network expansion

1. Introduction islands. In this case, LNG shipping is used to deliver natural


gas from domestic gas fields that are far from domestic
Countries in Southeast Asia through a regional demand centers. The LNG regasification facilities, then, are
cooperation called ASEAN (Association of South East Asia solely used to regasify LNG from domestic production
Nations) have established cooperation in various sectors supplies to meet domestic demands. However, in gas
including energy. In 1975, the Organization of Petroleum producing countries, such as Indonesia and Malaysia, LNG
Exporting Countries (OPEC) convinced ASEAN to create a import activities also exist, probably to anticipate declining
petroleum council (also known as ASEAN Council on gas supplies from domestic production or to meet their
Petroleum - ASCOPE) that manages dedicated programs growing gas demands. Both countries have secured a long-
towards promoting and coordinating energy research, and term LNG import agreement, where Indonesia decided to
addressing energy-related problems [1]. One of the plans buy LNG from the U.S-based company, Cheniere, which
put forward by the ASCOPE is Trans-ASEAN Gas Pipeline will be started in 2018 [3], and Malaysia from the
(TAGP) to connect gas infrastructures within Southeast Norwegian company, Statoil [4].
Asia. The first cross-border gas pipeline in the ASEAN Figure 2 shows the map of existing, under construction,
region was commissioned in 1991 to export gas from and planned LNG liquefaction and regasification facilities
Malaysia to Singapore [2]. Since then, several cross-border in Southeast Asia. Singapore and Thailand, the net gas
gas pipelines have been constructed to support the regional exporters in the region have built regasification facilities to
gas trades by connecting countries with more gas reserves anticipate declining imported pipelined gas supplies from
to countries that are short of gas reserves. New TAGP Indonesia and Malaysia in the case of Singapore, and from
connections are proposed to be built to increase the Myanmar in the case of Thailand. In this research, the focus
interconnection capacity within ASEAN. The main source will be on the seven ASEAN member states, excluding the
of the TAGP supply will come from East Natuna, Indonesia. Philippines, Laos, and Cambodia, due to no (or little) gas
Figure 1 shows the master plan of the TAGP project. trading activities in those three countries. A more detailed
Indonesia, Malaysia, and Brunei are major LNG picture and technical specifications of the existing and
exporters featuring several gas liquefaction facilities. LNG proposed gas pipelines and LNG infrastructures in the
regasification facilities can be found throughout the region, region can be found in Appendix A.
even in the gas producing countries, such as Indonesia and
Malaysia. This is mainly due to their geography of scattered

*
Corresponding author
E-mail: yuliana.liu@gmail.com; yuliana@student.tudelft.nl
2

Fig. 1. Map of Trans-ASEAN Gas Pipeline [5]

Fig. 2. LNG infrastructures in Southeast Asia [6]


3

Currently, the gas producing countries are facing exporting countries, e.g. Algeria, Egypt, and Libya.
depleting gas resources. This leads to the research question Production costs include investment costs and operating
whether the current proposed plans of gas pipelines and costs which differ for each producing area. The results of
LNG infrastructures will be able to meet natural gas demand the model are forecasted investments in production and
and increase security of gas supply in the region until 2045. transport capacities.
A model-based approach will be used to answer this GASTALE model is calibrated at higher aggregation
research question. A gas network model consists of the level than EUGAS by grouping the European countries into
existing gas pipelines and LNG infrastructures in the region two groups, called EU15 and CEEC10 [9]. The model is
will be built. The utilization and additional capacity based on a recursive-dynamic game theoretic principle and
requirement of each gas infrastructure in each country are includes market participants such as producers, network
then being measured. The results will be compared with the operators, storage operators, and consumers from various
proposed infrastructure options to see whether the proposed sectors. The model produces a single wholesale price of gas
options are sufficient to meet the additional capacity as a result of its market clearing. As inputs, the model
requirements. considers production capacity and marginal production
To the extent of the author’s knowledge, gas costs at each region and also capacity, investment costs, and
infrastructure models have never been built for Southeast transportation costs for both pipeline and LNG
Asia. Therefore, a review of gas network models built for infrastructures. The model also includes capacities,
Europe and global world will be presented in section 2 in investment costs and operational costs of storage facilities
order to understand the basic foundation or principle used in in both consumer regions. The results of the model are
the existing models, important assumptions, inputs, and wholesale gas prices from the market clearing until 2030,
outputs of the models. The structure of the gas network security of supply level based on share of EU15 production
model built for Southeast Asia can be found in section 3. from the EU E15 consumption, and new investments needed
The results of the model are presented in section 4, for storage (in EU15 and CEEC10), pipelines (connecting
distinguished based on two scenarios, Business-as Usual exporting regions to importing regions), liquefaction
(BAU) and reference scenario. The main difference (exporting regions), and regasification facilities (in EU15
between these two scenarios is on the assumptions of and CEEC10) from 2005 to 2030.
growth in the Indonesian gas production and consumption. TIGER (Transport Infrastructure for Gas with Enhanced
This is because the East Natuna gas field, which is the Resolution) is a linear dispatch model to optimize natural
determinant of the continuity of the TAGP is located in gas supply to all European countries. It provides enhanced
Indonesia. Therefore, any decisions made by the Indonesian resolution because the model consists of elements from the
government will significantly affect the development of the European Database of Gas Infrastructure (EDGIS) such as
Southeast Asian gas network. In section 5, an evaluation of more than 500 nodes and more than 650 pipeline sections
the TAGP and LNG infrastructure master plans will be with their individual characteristics, e.g. diameter, pressure,
presented, together with a discussion regarding capacity, length, and owner. The model also includes gas
independency of each Southeast Asian country to meet its production in Europe and its neighboring countries (which
domestic gas demand based on its domestic gas supply, and are aggregated to 17 production regions), non-European
tradeoffs between security of gas supply and profit production from four regions which enter the system
maximization. Conclusions and further recommendations through LNG import terminals, more than 147 gas storage
can be found in section 6. facilities, at least 24 LNG terminals, 53 demand regions and
58 demand profiles distinguished by country and sector. The
results of the model are utilization of the capacities of each
2. A review of gas network models infrastructure, i.e. pipelines, storage, and LNG facilities.
The WGTM model uses a principle of spatial and inter-
Several gas infrastructure or gas network models have temporal equilibrium of the world market for natural gas
been built either at the European level, e.g. EUGAS [7], (also called a dynamic spatial general equilibrium model).
GASTALE [8, 9], TIGER [10], or at a larger scale (global), The use of the model is to calculate patterns of production,
e.g. World Gas Trade Model (WGTM) from the Baker transportation routes, and prices to equate both demands and
Institute [11]. supplies with a main objective to maximize the present
EUGAS model is based on a long-term, dynamic, and value of producer rents, assumed that the markets are
inter-regional optimization model with an aim to optimize competitive. The model uses similar inputs as the previous
the natural gas supplies at minimum costs. The model is models, however, including a larger scope, i.e. globally.
used to analyze the future European natural gas supply. The Based on the level of aggregation, the GASTALE model
model provides forecasts until 2030 (from 2005). The main is the highest because it groups the European countries into
parameters in the model are European gas demand, supply two main groups. The WGTM model, although includes
costs, and gas reserves. The model includes natural gas most countries in the world, uses a lower aggregation by
infrastructures such as gas pipelines, liquefaction plants, identifying each gas infrastructure in each country. The
and regasification terminals. In EUGAS model, natural gas TIGER model has the lowest aggregation level with its 500
demand and availability of resources are given exogenously. nodes, 650 pipeline sections, and more than 147 gas
The model does not only include European gas producers, storages in Europe.
e.g. the Netherlands, Norway, UK, but also non-European
4

The earlier discussed models mostly share same kinds of countries. Inputs of the model consist of proven gas reserves
data needed, for example, gas reserves, gas production in each country that are based on the EIA database and IEA
volume, gas demand or consumption volume, capacity of report [6], production and consumption volumes based on
each gas infrastructure, including the investment projections by the IEA [6], excluding Indonesia. Indonesian
(construction) and the operating costs. Some models also production and consumption are based on the national
explicitly state which data are exogenously defined and outlook document from the BPPT [12]. Long-term LNG
what assumptions are used in the model. This information is sales agreements are based on GIIGNL report [4]. The
very useful to build the gas infrastructure model in the minimum capacities of LNG exported from the liquefaction
Southeast Asian region. Some models have gas prices as the plants are based on the historical gas trades data from BP
output of the model. However, this is less applicable in this [13], while the maximum capacities for both liquefaction
research because most trades are based on long-term plants and LNG terminals are based on a report published
contracts and there is no gas hub or trading points that could by the IEA and ERIA [6]. The minimum capacities of the
generate new gas prices. Therefore, instead of as an output, cross border gas pipelines are based on the historical gas
the gas price will be included as a key parameter in the trades data from BP [13] while the maximum capacities and
model, and be referred to Japan-cif index because Japan and the long term pipelined gas contracts are gathered from the
other countries in Northeast Asian are the main destinations project specific websites (e.g. [14], [15]).
for LNG exports from Southeast Asia. Figure 3 shows the conceptualization of the model,
indicating the relations among the input variables.
Mathematical formulation of the model can be seen in
3. GANESA model Appendix B.

GANESA model represents the existing GAs NEtwork LNG import


sources
Regasification
Cost
Proved
Reserves

in Southeast Asia, mainly its cross-border gas pipelines and Dummy Marginal
Production
LNG infrastructures, i.e. liquefaction plants and LNG shipping
Cost
Regasified
Capacity
Cost Dummy
Capacity
volume Production
regasification terminals. The function of the model is to find Volume Gas Pipeline
Operational

the optimal allocation of natural gas that goes through Imported


LNG Price
Cross-Border
pipelined gas
Cost

liquefaction facilities (for export), regasification facilities Domestic


Demand
(E/I)
(for import), and cross border gas pipelines (export/import) Pipelined
Domestic Liquefaction Gas Price
in each country. The model has also be able to capture Gas Price Cost
Liquefied
additional capacity requirement of each gas infrastructure. volume

This can be seen as a network flow problem and can be REVENUES Dummy Exported
Capacity LNG Price
solved with linear programming. COSTS
Exported
LNG
The GANESA model adopts higher level of aggregation
by adding up all capacities from the liquefaction plants and
regasification terminals located in each country. For the Fig. 3. Conceptual Model
cross-border gas pipelines, the capacities of gas pipelines
connecting the same countries are combined. This is done
to reduce the number of decision variables in the model
which otherwise will be unnecessary since the higher level 3.2 Development of the model
perspective (country-based) is already sufficient to provide
the results expected from the model. 3.2.1 Unit cost and gas price assumptions
Several cost assumptions including wellhead cost,
liquefaction cost, regasification cost, pipeline transmission
3.1 Conceptualization cost, and LNG shipping cost need to be made. In practice,
each gas infrastructure will have its own operating cost.
The time frame of the model is 2014 to 2045 (32 years). However, the data is confidential since it is about the
The model will be developed as a linear dispatch company performance and might disturb its
programing as in the TIGER model because the objective competitiveness. Therefore, it will be assumed that each
function and constraints of the model are linear, and the type of gas facilities in each country share the same unit cost
model also has no discrete decision variables. The objective assumptions. The unit cost assumptions used in this model
function of the model is to maximize cash-flow balance can be found in [16].
(maximize profit or minimize loss) in all included countries In this model, the gas price will be assumed to be
in the model as follows: exogenously known in advance, as a result of oil-linked
projection price. However, in practice, each gas sales
32 7 agreement (GSA) has its own pricing formula, although oil-
linked pricing mechanism is the most common in the Asian
𝑀𝑎𝑥𝑖𝑚𝑖𝑧𝑒: ∑ ∑ 𝑁𝐶𝐵𝑖 (1) GSA [17, 18]. In this model, it is assumed that there is a
𝑡=1 𝑖=1
single gas price based on Japan cif price, which will be used
NCB is the abbreviation of net cash-flow balance, t as the import and export price for LNG and pipelined gas.
indicates number of years and i indicates number of Japan cif price includes insurance and freight costs.
5

Therefore, in the model, it is assumed that the exporters bear  The parameters of the GANESA model, e.g.
the cost of LNG shipping. BP provides a historical record of production level, domestic consumption growth,
Japan cif price [13]. However, extrapolation of Japan cif and extension of gas pipeline long-term contracts
price until 2045 is not available. To predict the future Japan are changed and the model could still run as
cif price, correlation of the historical data of the Japan cif expected.
price with Brent-oil index [19] will be observed. See [16]
for more detail of the regression analysis. Data validity refers to the accuracy of the data (real and
computer generated) and the data’s adequacy to build the
3.2.2 Scenarios model and conduct experiments to solve the problem [20].
Two scenarios will be run in the model, the BAU This requirement has been fulfilled because information
scenario and the Reference scenario. In the BAU scenario, about the model inputs and assumptions are based on the
gas production in Indonesia is assumed to decline after 2017 previous network models (see section 2) and the required
with a rate of 4.14% from 2018 to 2023 and 3.80% from data have been collected from various national (e.g. BPPT,
2023 to 2045 while the domestic gas consumption is SKK Migas, Pertamina, PGN) and international agencies,
assumed to grow at 2.20% per annum [12]. In this scenario, such as EIA, IEA, and BP Statistics.
Indonesia will not extend any long term gas export
contracts.
In the Reference scenario, the Indonesian gas production 4. Results
will grow constantly at 0.50% per annum. This is supported
by the historical trend of Indonesian gas production [13]. The results of the model could be looked from the two
The domestic consumption in this Reference scenario is scenarios. In each scenario, domestic gas production and
assumed to grow at 2.70% per annum according to the consumption, together with the utilization of the gas
BPPT estimates [12]. In the Reference scenario, it is pipelines and LNG infrastructures will be presented.
possible for Indonesia to export its gas and this could affect
the future plans of gas network expansion in its neighboring
countries, especially Singapore and Thailand because 4.1 Business-as-Usual Scenario
Indonesia could be their potential supplier.
4.1.1 Domestic gas production and consumption
Figure 4 shows the gas production and domestic
3.3 Verification and Validation consumption in six Southeast Asian countries. Singapore is
not included because it does not have any gas reserves and
First the model was built as a spreadsheet model using thus, there is no gas production activities in the country.
Ms. Excel in a single year and three years period.
Afterwards, with the same inputs and assumptions, the
model was built in MATLAB 2014b. The results then were
compared to see if the conceptual model has been correctly
translated into the computerized model. When the results of
the objective function and decision variables are same for
both the excel spreadsheet and Matlab script, the number of
years in MATLAB and other data inputs were increased
from 1 year, 3 years, to 32 years which is the time frame of
the model.
Operational validity is fulfilled when the output behavior
of the model has a satisfactory range of accuracy to serve
the intended purpose and applicability of the model [20]. As
the model is able to produce the results that were expected
by the author, it could be said that the model serves its
purpose. Comparing simulated and real data, sensitivity
analysis based on design of experiment and regression
analysis are techniques that could be used to validate the Fig. 4. Domestic gas production and consumption in BAU Scenario
model [21]. These techniques could be used to assess the
operational validity. Following steps are done to check the Based on this scenario, gas production from Malaysia
operational validity of the model. will surpass Indonesia’s production after 2020, given that
 The gas price is validated by comparing the result Malaysia could exploit all its potential gas reserves while
of the regression analysis with the actual data. The Indonesia does nothing to increase its production level.
differences then being measured as error Thailand who has been a net gas importer will continue to
measurement. It resulted in 1.20 of standard error. import gas either via pipelines from Myanmar or LNG from
With 95% confidence interval the gas price will various suppliers.
fall in -/+ 2.40 of the reference gas price.
6

The production from Thailand’s gas fields is expected to production gets disrupted. Within the time frame of the
keep declining and finally be totally depleted after 2022 if model, Brunei does not need to build any regasification
the country fails to find new gas fields. Most producing terminal because its domestic gas production is still
countries show both a positive (at earlier periods) and sufficient to meet its domestic gas demand. Brunei also does
negative growth trend (at later periods). The declining not have any regasification terminal because its geography
growth trend is expected to happen within the time frame of is less scattered, unlike in the case of Indonesia and
the model, except for Vietnam. Vietnam shows a positive Malaysia.
growth trend within the time frame due to later development
of its gas fields. However, Vietnam will have to manage its Table 1
LNG infrastructures utilization based on BAU Scenario
production growth faster than the domestic consumption
Country & Capacity utilization at EOY (bcm)–BAU Scenario
growth otherwise the country will have to rely on import to LNG 2015 2025 2035 2045
supply the unmet demand from domestic supply. infrastructures
Indonesia
4.1.2 Cross-border gas pipelines Liquefaction 25.41 9.66 1 0
Regasification 0 5.33 20.70 20.70
As indicated in figure 5, pipelined gas contract from (+5.45) (+31.30)
Indonesia to Malaysia will expire in 2021 and to Singapore Malaysia
in 2023. Pipelined gas from Malaysia to Singapore will last Liquefaction 34.36 31.89 31.09 11.67
a bit longer, up to 2025. Afterwards, the scenario assumes Regasification 0.14 0.14 0.14 0
Brunei
that Singapore decides not to extend the pipeline contracts Liquefaction 8.45 8.68 8.90 2.97
and will rely on LNG import. Thailand
Regasification 6.35 6.90 6.90 6.90
(+42.29) (+55.78) (+65.65)
Myanmar
Liquefaction - - (+1.67) -
Regasification (+ 1.17) - - -
Vietnam
Liquefaction - (+0.14) (+0.53) (+1.01)
Regasification (+0.17) - - -
Singapore
Regasification 4.2 10.78 11.80 11.80
(+0.3) (+1.44) (+2.82)

Both Thailand and Singapore do not have any


liquefaction plants because both countries are net gas
Fig. 5. Cross-border gas pipelines in BAU Scenario
importers. If domestic gas consumption in Thailand keeps
Pipelined gas from Myanmar to Thailand will decline growing by 1.0%, Thailand will have to significantly
increase its regasification capacity. This is also due to
gradually because in practice, there are three pipeline
declining supply from Myanmar’s pipelined gas. Therefore,
connections from Myanmar to Thailand which have
Thailand really needs to strive to find new gas fields,
different dates of expiration. The last pipelined gas is from
otherwise the country will have to rely heavily on imported
Myanmar to China which has just started in operation at the
end of 2014 and the contract will last for 30 years. The LNG.
figure shows the pipeline could operate at its maximum The latest contract agreement between Indonesia and
Singapore requires Singapore to pay USD 17 per mmbtu for
capacity from 2030 to 2035, and will decline afterwards.
the pipelined gas. Singaporean analysts find that they could
get LNG import from the USA with a cheaper price than the
4.1.3 LNG infrastructures
current pipelined gas price. This has led Singapore to build
Based on the existing pattern of domestic gas production
in Indonesia, Indonesia will have to increase its a regasification terminal in Jurong in order to have more gas
supply alternatives and more bargaining power.
regasification terminal capacities, especially to manage the
Based on the results of the BAU Scenario, after the
imported LNG. This is caused by the declining gas
pipelined gas contracts from Indonesia expire, Singapore
production and growing domestic gas demand. Indonesia
will have to start increasing its regasification capacity after
will need to increase its regasification capacity after 2030.
2025, given the domestic gas consumption keeps growing
However, this should be done earlier considering the
utilization of the regasification terminals that also handle the by 1.0%. The country will face a harder challenge to become
Asian gas hub if it only relies on imported LNG. Adding
domestic LNG supply has not been included.
more capacity to its regasification terminal is not a simple
Table 1 shows the volume of natural gas processed at the
matter for Singapore because it has a very limited land
liquefaction and regasification facilities in the Southeast
availability. Therefore, getting pipelined gas supplies from
Asian countries. The number in bracket indicates additional
capacity requirement of each LNG facility. In the Malaysian its neighboring countries could be an alternative. Another
case, Malaysia does not need to increase its regasification option to increase its regasification capacity is building
floating storage and regasification facilities. However, it
capacity. The amount of imported LNG in Malaysia is quite
might be more costly compared to existing pipelined gas
small, mainly comes from its long-term contract with Statoil
supplies from Indonesia or Malaysia.
to be used as a back-up supply when its domestic gas
7

In the case of Myanmar, the need for LNG facilities are 4.2.3 LNG infrastructures
relatively small and only for a short duration (+/- 5 years). Since the change is only at the Indonesian gas production
Therefore, it could be neglected. The government of and domestic consumption, the results of other countries
Myanmar could eliminate the needs by adjusting their LNG infrastructures’ capacity utilization remain the same.
domestic gas production and consumption. While in the In the Reference scenario, the capacity of the Indonesian
case of Vietnam, it needs to import gas especially for the liquefaction facilities is more utilized compared to the BAU
first seven years or until the domestic gas production could scenario. While, for the regasification capacity, in the
meet the required amount of gas for domestic consumption. Reference scenario, the imported LNG is only based on the
Afterwards, there is an opportunity for Vietnam to export its long-term contract with Cheniere that will be started from
excess of gas production if it could meet the expected 2018 to 2037. From 2044 onwards, Indonesia will need to
growth of consumption. import LNG because the domestic gas production will not
be able to meet the domestic gas demand anymore. The
utilization of LNG regasification terminal under the
4.2 Reference Scenario Reference scenario, especially for import, is much lower
compared to the BAU scenario, and no additional capacities
4.2.1 Domestic gas production and consumption are needed.
In this scenario, there is no change in the profile of
domestic gas production and consumption except for Table 2
LNG infrastructures utilization based on REF Scenario
Indonesia. Figure 6 shows the change of gas production and Country & LNG Capacity utilization at EOY (bcm)–REF Scenario
consumption in Indonesia. infrastructures 2015 2025 2035 2045
Indonesia
Liquefaction 25.24 25.02 13 0
Regasification 0 1.12 0 2.84
Singapore
Regasification 4.2 8.78 11.24 11.80
(+2.82)

Table 2 summarizes the utilization of LNG facilities in


Indonesia and Singapore. Since Indonesian gas production
will constantly grow, Indonesia will be able to keep
supplying pipelined gas to Singapore. This scenario
assumes that the pipelined gas contract between these two
countries will be extended. As the result, the capacity
Fig. 6. Comparison of gas production and consumption in Indonesia needed for regasification terminal in Singapore will
decrease. Figure 8 shows the comparison of the
With a constant growth of 0.05% after 2017 as in the regasification capacities used in Singapore according to the
Reference scenario, Indonesia will be able to meet its BAU and Reference Scenario.
domestic gas demand, at least until 2044. This will make the
country needs to reduce its gas export sales agreement or
even not export gas anymore after the existing long-term
contracts expired. This could be avoided if the country could
successfully manage its potential gas fields, e.g. in East
Natuna or Arafura Sea.

4.2.2 Cross-border gas pipelines


The Reference scenario assumes that both Indonesia and
Singapore agree to extend their pipelined gas contract as
long as the reserves are available. Figure 7 shows the gas
traded through the cross-border gas pipelines in the region. Fig. 8. Comparison of LNG regasification capacity in Singapore

The figure indicates that in the Reference Scenario,


Singapore will need a later time to expand its regasification
capacity, at least until 2040 (compared with 2025 in the
BAU scenario). In this scenario, there are also some
allowances for the Singaporean regasification capacity
which will bring more flexibility for Singapore to handle
more LNG import and re-distribute the LNG to other
countries who need it. This will support the goal of
Singapore to become an Asian gas hub, unlike in the BAU
scenario where the regasification capacity is not even
sufficient to fulfil its domestic consumption.
Fig. 7. Cross-border gas pipelines in Reference Scenario
8

5. Discussion company, PT. PLN, to supply 1.5 million ton per annum
(mtpa) LNG from 2015 to 2033.
In this section discussion related to the ability of the In the case of Abadi gas field in the Arafura Sea, the
TAGP and LNG infrastructure master plans to meet the proposed plan is to develop the field with a floating
additional capacity requirements, the independency of each liquefaction facility (FLNG). However, both Inpex and
ASEAN member state to meet its domestic gas demand, and Shell (the contractor and shareholder of Abadi gas field) are
trade-offs between security of gas supply and profit also looking for alternative options besides building FLNG
maximization will be presented. with 2.5 mtpa capacity. At first, the reserves in the block
was estimated to be 283.3 billion cubic meter (bcm), and
now, the proven and probable (2P) reserves is expected to
5.1 TAGP and LNG infrastructures master plans be 524.1 bcm [25]. This then leads Inpex and Shell to
consider alternative options, e.g. onshore LNG plant with a
5.1.1 TAGP master plan larger capacity of 5 mtpa that could be expanded to 10 mtpa.
There are four proposed gas pipelines in the TAGP: to The final investment decision has not been made, but it is
Java (Indonesia), Erawan (Thailand), Kerteh (Malaysia), more likely that the contractor will choose the alternative
and Vietnam [5]. However, considering the high content of option that offers larger capacity with smaller capital
CO2 in the gas from East Natuna that reaches 71% [14], it is expenditures. Besides these two liquefaction projects, there
less likely that the reserves will be able to supply the four is also a possibility to develop East Natuna gas field using
gas pipelines. In the BAU scenario, Indonesia will face an onshore LNG plant. However, further feasibility study
declining gas production. In this case, gas supply from East needs to be conducted, especially to assess the economic
Natuna will be crucial to meet Indonesian domestic demand viability of the option.
and reduce dependency on import. However, this also In terms of regasification capacity, in the BAU scenario,
indicates that the other three possible connections of gas Indonesia will need to add several regasification terminals,
pipelines will be less likely to be built. mainly to accommodate the needs for import. The required
In the Reference scenario, on the other hand, gas supply amount indicated by the model has not included the capacity
from East Natuna to demand centers in Indonesia (e.g. Java) used to regasify LNG from domestic supply.
is not very crucial because gas production from other gas The plans of both Malaysia and Vietnam to build
fields will grow constantly and be able to meet domestic gas regasification terminals will be sufficient to secure gas
demand until 2044. In this case, the Indonesian government supply in the coming years. If Vietnam could successfully
could still build a gas pipeline to Java with smaller capacity develop its gas fields, it could consider to build a
than in the BAU scenario, and also build other gas pipeline liquefaction facility. Thailand and Singapore will need to
connections. The most likely to be executed is the gas add more capacities to their regasification terminals due to
pipeline from East Natuna to Erawan because currently expiration of their pipelined gas contracts. The current plans
PTTEP, the Thai state-owned gas company is in the East will not be sufficient to replace the pipelined gas supplies.
Natuna consortium, together with Pertamina, ExxonMobil, In the case of Singapore, due to the limitation of land
and Total. PTTEP replaced Petronas (Malaysian state- availability, it could consider to build floating regasification
owned gas company) that stepped out of the consortium in facilities. In Both BAU and Reference scenario, Singapore
2012 [22]. Therefore, the gas pipeline connection to will have to increase its regasification capacity. The
Malaysia is less likely to happen. Since Vietnam has also difference is only at the time when the additional capacity
found several gas fields and signed long-term agreements of should be put in place, i.e. 2025 in the BAU scenario and
cooperation (similar with Production Sharing Contract) 2040 in the Reference scenario. While for Thailand, the
with several multi-national gas companies, e.g. Gazprom additional capacity could be slightly lower if it could secure
[23], the Vietnamese government seems to prioritize long term pipelined gas contract from East Natuna. Another
developing its own gas fields than importing pipelined gas option is to replace the use of natural gas with alternative
from East Natuna. fuels. For example, Thailand could use renewable energy or
nuclear energy to replace natural gas as the fuel for its
5.1.2 LNG infrastructures master plan electricity generation.
According to the master plan of LNG infrastructures
development in the coming years [6], Indonesia has two
liquefaction projects and no regasification project because 5.2 Independency
the proposed regasification projects have all been
constructed in 2014. In both BAU and Reference scenario, The independency level of each country could be
the liquefaction projects will be executed. measured as a ratio of its domestic gas production to its
Currently, BP Berau, the operator of Tangguh field has domestic gas consumption [26]. This could be an indicator
received environmental and social impact assessment of security of gas supply in one particular country based on
approval (AMDAL) from the Indonesian government and the ability of its domestic gas production to meet its
announced its FEED contract to two ‘domestic’ consortiums domestic gas demand. According to the previous result of
(as required in the contract). As published in BP press the gas production and domestic consumption, excluding
release [24], BP and the Tangguh Partners signed a sales and the gas trades either via pipelines or LNG shipping, the
purchase agreement with Indonesian state owned electricity
9

independency level of each country along the time frame of upstream development in several projects around the world,
the model is shown in figure 9. e.g. Canada, Australia, and across the Africa continent,
Based on the figure, Thailand has the second lowest notably in South Africa, Sudan and Egypt [18]. This
independency level after Singapore that has no gas reserves indicates the strategic moves of Petronas-Malaysia in order
and will totally rely on import in 2023. With no new gas to remain competitive in the international LNG market.
field development as in the BAU scenario, Indonesia will Meanwhile, the Indonesian gas company, Pertamina, has
start to lose its independency in 2027. On the other hand, only secured a long term contract to buy LNG from the US
according to the Reference scenario, Indonesia could still and not actively involved in international upstream gas
maintain its independency until 2043. Vietnam has the projects. This might be due to several potential gas fields in
closest match between domestic gas supply and demand. Indonesia that have not been developed or Pertamina will
However, following a concern of security of gas supply, it probably be assigned to manage the existing gas fields (after
will be better if Vietnam could develop its gas fields faster the expiration of the existing PSCs). There could be a shift
so that the independency level could increase above 1.0. to a more aggressive strategy in the future because in 2013-
2014, Pertamina has acquired several oil field assets in
Algeria, Iraq, and Malaysia [27]. Other Asian countries,
especially the long-term buyers of Southeast Asian LNG,
i.e. Japan, Korea, and China, have put investments in the
US, Canada, Russia, Australia, and East Africa [18] to
anticipate declining gas supply from Southeast Asia.

5.3 Security of supply or profit maximization (from the


Indonesian perspective)

The main goal of the contractors or the gas companies is


to gain profit as much as possible. For the Indonesian
Fig. 9. Independency level in Southeast Asian countries government as the host or owner of the gas fields, social
welfare through utilization of natural gas for domestic needs
Both Malaysia and Brunei show a declining trend of is also important, and thus the government will have to
independency level due to a higher growth of their domestic secure a long-term supply of natural gas. On the other hand,
consumption compared to their gas production. However, especially for the Indonesian government, natural gas
during the time frame of the model, their independency together with oil contribute approximately one-fifth of the
levels are still above the standard line of 1.0. Myanmar nation’s income in 2014. This has happened for a long time
shows a positive trend of growth until 2035 and decline since oil and gas were first commercialized for export. As
afterwards. In practice, the independency level of Myanmar the time goes, the domestic needs for oil and gas are
is much lower because it has several pipelined gas export increasing and for the last decades the government has been
contracts to Thailand and China. burdened by the oil subsidies heavily.
The independency level provides an insight with respect Several studies indicate that substituting oil with gas and
to country’s security of supply. Countries that have allocating more gas for domestic needs (e.g. for chemical
independency level above 1.0 are able to meet their and fertilizer industries, to build new gas-fired power
domestic natural gas demands without imports. Any import plants) will offset the loss from gas export revenues and
activities will make the buyer countries rely on supplier even bring more benefits for the economic growth of the
countries and any disputes or tensions, not only between the country [28, 29]. The growth of domestic gas consumption
two countries, but also in the region where the countries as in the BAU or Reference scenario depends on the
located (e.g. conflicts between the EU and Russia), could availability of distribution networks that could stimulate the
hamper the natural gas supplies and might have a domino demand. For the last 10 years, the domestic gas
effect to other sectors that rely on natural gas, e.g. chemical consumption growth of Indonesia is the lowest among the
industry, electricity generations. other six ASEAN member states. Therefore, the
Countries that have independency level below 1.0 need government should focus on developing its downstream gas
to find a way to increase their security of supply, e.g. infrastructure.
through a long-term contract or investing in upstream PGN, the Indonesian state-owned gas network
development in other countries. Considering pipelined gas (transmission and distribution) company actively refutes the
supplies from Indonesia will expire in 2023, Singapore government’s intention to liberalize the national gas market.
through Singapore’s Pavilion has put investments in PGN’s main argument is that it needs an assurance of both
upstream gas fields development in Tanzania and Papua gas supplies and gas demands to invest on gas
New Guinea [18]. According to a report from the IEA infrastructures [30], e.g. constructing both transmission and
regarding the investment of Asian companies, Thai state- distribution pipelines to ‘create and nurture’ the markets.
owned companies, PTTEP invests in upstream gas field Allowing more players at the downstream and requirement
development in Mozambique. Malaysia, with an for third party access and unbundling will undermine PGN’s
independency level above 1.0 also actively invests in
10

business strategy which according to one senior official has 6. Conclusions


been proven to create a new demand center in West Java.
However, as have extensively been argued by the This article has presented a model of gas network
supporters of market liberalization, liberalization is the only infrastructures in Southeast Asia. The use of the model is to
way to bring more competition to the market, and evaluate the ability of the TAGP and LNG infrastructures
consequently, competition could bring the gas to the society master plans to meet natural gas demand in Southeast Asia
with a minimum cost and also secure or bring gas supplies until 2045. Two scenarios have been analyzed to
from other parts of the world. It is important to keep in mind accommodate the uncertainty in the Indonesian domestic
that the benefits from a more competitive market can only gas production and consumption. Overall, the two scenarios
be gained in a mature market, i.e. infrastructures have been indicate insufficiency of the current plans to achieve
well developed, the investments to build the infrastructures security of gas supply, especially in Indonesia, Singapore,
have depreciated and returns start to increase as the existing and Thailand.
infrastructures can be utilized at low marginal cost [31].  According to the BAU scenario, Indonesian gas
Therefore, in the case of the Indonesian government, when production will decline after 2017. Consequently,
the gas infrastructures are still lacking, it will be more new regasification capacity (excluded capacity used
important to create a conducive business climate (bring to handle domestic LNG supply) is needed to handle
confidence) for the national companies such as Pertamina imported LNG and needs to be put in place before
and PGN to build the gas infrastructures. In other words, the 2033. This has not been accommodated in the current
government should not liberalize the gas market until the LNG infrastructure expansion plan. In terms of the
starting condition (i.e. mature market) for gas market TAGP, the East Natuna gas field should be used
liberalization is achieved. mainly for domestic needs. Therefore, gas pipelines
A caveat of this plan is the financial capability of the connections from East Natuna to other countries will
Indonesian gas companies to build the gas infrastructures. not be favorable for Indonesia to build.
The government might want to accelerate the plans to  Both Singapore and Thailand will also have to
enhance the gas distribution network in Indonesia and the increase their regasification capacities, especially
state-owned gas companies might have limited financial after the pipelined gas supplies from Indonesia and
resources to fund and finish all of the projects within the Myanmar stop due to the expiration of the contracts.
time constraint. This contains a political issue because one These needs have not been captured in the current
period of the government regime in Indonesia lasts for five LNG infrastructure expansion plan.
years and the current government might want to attract  In the Reference scenario, as the domestic gas
public sympathy in order to be elected again. Liberalization production of Indonesia will have a positive growth,
of the gas market might attract more multi-national Indonesia does not need additional regasification
companies or foreign investors to invest in Indonesia. They capacities to handle imported LNG.
are also more capable in terms of financial and human  In the Reference scenario, it will be possible for
resources to make the plans into action within the time Indonesia to export gas to Singapore via existing gas
constraint. Another caveat is the political and economic pipelines, e.g. South Sumatra-Singapore and West
pressure either from the regional organizations (e.g. Natuna-Singapore, or extend the connection from
ASEAN, ADB) or international organizations such as G-20, East Natuna to West Natuna-Singapore gas pipeline.
IMF, or World Bank that might be more favorable if  Indonesia could also export gas to Thailand by
Indonesia liberalizes its gas market. This then will depend constructing gas pipeline from East Natuna to
on the negotiation capabilities of the Indonesian Erawan as in the TAGP plan. Other proposed gas
representatives to get the best or better deals for the country. pipeline connections, i.e. to Malaysia and Vietnam
The problem of Indonesian gas market is not only at the are less likely to be executed due to the limited
downstream side, but also upstream. Ideally, if both amount of gas reserves available after the CO2
Pertamina and PGN have confidence to develop the gas removal. Another option is to export the East Natuna
fields by themselves, the government could choose not to gas in a form of LNG. This could be executed by
extend the existing PSC and award rights to develop the new building an onshore LNG plant in Natuna Island.
gas fields to one of the state-owned companies. This will Further research needs to be conducted especially to
make the government achieving the goals of security of gas know the feasibility of the plan.
supplies and also profit maximization as the government  In the Reference scenario, the additional
could freely determine the gas allocation for domestic and regasification capacity requirement especially for
export. However, Pertamina and PGN seem to lack of Singapore will be less, and the time when the
expertise to develop the offshore and stranded fields, e.g. additional capacity need to be put in place also could
East Natuna and Abadi. This makes the government be deferred to 2040 (compared to 2025 in the BAU
becomes dependent on the multi-national gas companies to scenario). However, this expansion plan has not been
develop those fields. Hence, the structure of the PSC, included in the current Southeast Asian LNG master
especially profit sharing and contract duration will become plan. Another option, i.e. floating regasification and
the main subjects of negotiations between the government storage might also be possible for Singapore,
as the owner or host and the multi-national gas companies considering its limited land availability.
as the contractors.
11

Following policy recommendations are addressed to the Reference


Indonesian government:
[1] B. K. Sovacool, "Energy policy and cooperation in Southeast Asia:
 The Indonesian government should put off the plan The history, challenges, and implications of the trans-ASEAN gas
to liberalize the national gas market because the gas pipeline (TAGP) network," Energy Policy, vol. 37, pp. 2356–2367,
market in Indonesia has not been mature yet. The 2009.
downstream gas infrastructures are still lacking and [2] P. Roberts and A. Cull, "Building the Trans-ASEAN gas pipeline,"
Asia Pacific Review, vol. July, pp. 15-20, 2003.
thus, requirements for unbundling will only [3] Reuters. (2014, 8 January 2015). Indonesia signs second LNG
slowdown the downstream infrastructure import deal with Cheniere Energy. Available:
development. This will potentially hinder the http://www.reuters.com/article/2014/07/02/indonesia-pertamina-
government’s plan to enlarge the domestic gas lng-idUSL4N0PD0XT20140702
[4] GIIGNL, "The LNG Industry in 2013," GIIGNL - International
market. As the result, the domestic consumption Group of Liquefied Natural Gas Importers2014.
growth might be far less than the predictions. [5] ACE, "Development of ASEAN Energy Sector: Power Network
However, if the Indonesian government is forced to Interconnection, Natural Gas Infrastructure, and Promotion of
liberalize (i.e. external political or economic Renewable Energy and Energy Efficiency," Asean Center for
Energy (ACE)2013.
pressure), the main priority should be developing the [6] IEA and ERIA, "South East Asia Energy Outlook," 2013.
downstream gas infrastructures first, followed by [7] J. Perner and A. Seeliger, "Prospects of gas supplies to the European
institutions reform or de-regulation. market until 2030—results from the simulation model EUGAS,"
 The government should carefully manage its PSC Utilities Policy, vol. 12, pp. 291-302, 2004.
[8] M. G. Boots, F. A. M. Rijkers, and B. F. Hobbs, "GASTALE: An
structure (trade-offs between security of supply and oligopolistic model of production and trade in the European gas
profit maximization) especially at difficult project market " ECN - Energy Research Centre of the Netherlands2003.
locations where the state-owned company, i.e. [9] W. Lise and B. F. Hobbs, "Future evolution of the liberalised
Pertamina, does not have the ability to develop the European gas market: Simulation results with a dynamic model,"
Energy, vol. 33, pp. 989–1004, 2008.
fields (e.g. East Natuna gas field). A consortium [10] S. Lochner, "From Russia with Gas An analysis of the Nord Stream
could support Pertamina to gain technology learning pipeline’s impact on the European Gas Transmission System with
from other multi-national gas companies in the the Tiger-Model " Institute of Energy Economics at the University
consortium. In this case, Pertamina should not be of Cologne2007.
[11] P. Hartley and K. B. Medlock, "The Baker Institute World Gas
passive, and could take a role as a co-operator to Trade Model," joint study between James A. Baker III Institute for
develop the difficult fields in order to gain Public Policy and Center for Environmental Science and Policy-
experiences and learning. Stanford University2005.
There are several limitations of the model, especially [12] BPPT, "Indonesia Energy Outlook 2014," BPPT, Jakarta,
Indonesia2014.
regarding the unit costs and gas price assumptions. When [13] BP, "Statistical Review of World Energy 2014," 2014.
the information is available, the unit costs could be assigned [14] Offshore-Technology. 2 December 2014). Natuna Gas Field,
differently based on each gas infrastructure location. The Indonesia. Available: http://www.offshore-
gas prices could also be based on the actual price setting technology.com/projects/natuna/
[15] Offshore-Technology. 2 December 2014). Zawtika Project, Gulf of
formula in each gas sales agreement. Martaban, Myanmar. Available: http://www.offshore-
Further improvement could be made by disaggregating technology.com/projects/zawtika-gulf-martaban-myanmar-burma/
the model, i.e. infrastructure-based instead of country-based [16] Y. Yuliana, "Gas Infrastructure in Indonesia: Modelling options
as the current model. By disaggregating the model, the from domestic supply and export," Master Thesis, Delft University
of Technology, the Netherlands, 2015.
results could indicate additional capacity requirement of [17] J. T. Jensen, "Asian Natural Gas Markets, Supply Infrastructure, and
each facility at each location to see whether: expansion is Pricing Issues," presented at the Pacific Energy Summit, Jakarta,
possible, a new facility needs to be built, functional 2011.
switching (e.g. Arun liquefaction plant was converted or [18] IEA, "The Asian Quest for LNG in a Globalising Market,"
International Energy Agency (IEA)2014.
switched to a regasification facility due to depletion of gas [19] EIA, "International Energy Outlook 2014: World Petroleum and
reserves near the plant) or even abandoning the facility. Other Liquid Fuels With Projections to 2040," U.S. Energy
Geological data of the gas fields could be included in the Information Administration, Washington, DC2014.
model to better estimate the production trend and the rest [20] R. G. Sargent, "Verification and validation of simulation models,"
Journal of Simulation, vol. 7, pp. 12-24, 2013.
amount of reserves available. Gas storages could also be [21] J. P. C. Kleijnen, "Verification and validation of simulation models
included in the model when more data is available. There is " European Journal of Operational Research, vol. 82, pp. 145-162,
also an opportunity to include potential LNG buyers or 1995.
suppliers into the model. This could be applied together with [22] 2b1stconsulting. (2012, 5 January 2015). PTTEP to replace Petronas
in Indonesia East Natuna Project. Available:
the infrastructure-based model, taking into account the http://www.2b1stconsulting.com/pttep-to-replace-petronas-in-
distance from the supply sites to the buyers’ locations. indonesia-east-natuna-project/
Furthermore, the research could be extended by [23] Gazprom. (2013, 2 December 2013). Gazprom launches gas
evaluating each infrastructure option of the TAGP and LNG production in Vietnam. Available:
http://www.gazprom.com/press/news/2013/october/article173419/
master plans to see the feasibility of the project, taking into [24] BP. (2014, BP Announces Onshore Front End Engineering and
account the PSC structure (including cost recovery scheme, Design Contracts for Tangguh Expansion Project. Available:
profit sharing, and tax obligation), volatility of oil-linked http://www.bp.com/en/global/corporate/press/press-releases/bp-
gas prices and capital expenditures to build the announces-onshore-front-end-engineering-and-design-contracts-
.html
infrastructures.
12

[25] S. Hamlen. (2014, 22 February 2015). Southeast Asia Focuses On [28] LKI, "Gas Utilization in Indonesia," LKI2013.
FLNG Factor. Available: http://www.epmag.com/southeast-asia- [29] A. Q. Tjandranegara, "Gas Bumi Sebagai Substitusi Bahan Bakar
focuses-flng-factor-759921#p=full Minyak: Optimasi Investasi Infrastruktur dan Analisis Dampaknya
[26] W. Lise, B. F. Hobbs, and F. van Oostvoorn, "Natural gas corridors Terhadap Perekonomian Nasional," Dissertation, Chemical
between the EU and its main suppliers: Simulation results with the Engineering, University of Indonesia, Depok, West Java, Indonesia,
dynamic GASTALE model," Energy Policy, vol. 36, pp. 1890– 2012.
1906, 2008. [30] Kompas. (2015, 16 April 2015). PGN Merasa Dianaktirikan oleh
[27] Kompas. (2015, 17 May 2015). Pertamina Resmi Buka Kantor di Pemerintah.
Malaysia. Available: [31] IEA, "Developing a Natural Gas Trading Hub in Asia," International
http://bisniskeuangan.kompas.com/read/2015/05/17/161500726/Se Energy Agency2013.
nin.Pertamina.Resmi.Buka.Kantor.di.Malaysia?utm_source=WP&
utm_medium=box&utm_campaign=Kknwp
Appendix A

Table A1. Existing LNG Liquefaction Facilities in Southeast Asia [6]


Capacity
Country Project (Location) Status Start
mmtpa Bcm/y
Brunei Brunei LNG 7.2 9.8Operating 1972
Bontang (East Kalimantan) 21.6 29.4
Operating 1978
Arun* (Aceh) 4.8 6.4Operating 1978
Tangguh LNG (Papua) 7.6 10.3
Operating 2009
Indonesia
Donggi-Senoro 2.0 2.7Construction 2014
(Central Sulawesi)
Sengkang (South Sulawesi) 2.0 2.7 Construction 2014
MLNG I, II, III (Bintulu) 24.2 32.9 Operating 1983
Malaysia ~ expansion 3.6 4.9 Construction 2015
Kanowit FLNG (Sarawak) 1.2 1.6 Construction 2015
*The Arun LNG terminal is being converted from a liquefaction unit to a regasification unit

Table A2. Existing LNG Regasification Facilities in Southeast Asia [6]


Capacity
Country Project (Location) Status Start
mmtpa Bcm/y
West Java FSRU 3.7 5.2 Operating 2012
Lampung FSRU 2.0 2.8 Construction 2014
Indonesia Arun (Aceh) 1.5 2.1 Construction 2014
Banten FSRU 3.0 4.1 Construction 2014
Central Java FSRU 3.0 4.1 Construction 2014
Malaysia Lekas (Malacca) 3.8 5.2 Operating 2013
Jurong Island 3.5 4.7 Operating 2013
Singapore
~ expansion 5.3 7.1 Construction 2014
Thailand Ma Ta Phut 5.0 6.9 Operating 2011
Table A3. Existing Cross-Border Pipelines in Southeast Asia
(Data from various sources)

In
No. operation From To Length (km) Other Information
since
1. 1991 Malaysia Singapore 5 24 inch; 155MMCFD (max. 250MMCFD), a part of Peninsular gas
(Segamat - Peninsular) pipelines project; 20 years (until 2011)
2. 1999 Myanmar Thailand 410 36inch; 200MMCFD (max. 500MMCFD) (since 2010, additional pipeline
(Yadana) to Yangon, Myanmar with a capacity of 150MMCFD); reserves 5.3 tcf; 30
years (until 2025)
3. 2000 Myanmar Thailand 277 24 inch; 260 MMCFD (max. 300MMCFD); reserves 3.2 tcf; 30 years
(Yetagun) (until 2027)
4. 2001 Indonesia Singapore 654 28 inch; 325MMCFD; 22 years (until 2023)
(West Natuna) (Jurong)
5. 2001 Indonesia Malaysia 96 22 inch; 250 MMCFD (max.300 MMCFD); 20 years; (until 2021)
(West Natuna) (Duyong)
6. 2002 CAA* Malaysia 170 24inch; 270 MMCFD
7. 2003 Indonesia Singapore 468 28 inch; 350 mmscfd; 20 years (until 2023)
(South Sumatra)
8. 2007 CAA* Vietnam 330 18inch, 120 MMcfd
9. 2005 JDA** Thailand 390MMCFD, 35 years ( 5 years exploration, 5 years retention, 5 years
development, 20 years production)
55km-28inch + 277km-34inch, max 1,020mmscfd
10. 2006/2007 Malaysia Singapore 4 115 MMCFD, 18 years (until 2025)
11. 2009 JDA** Malaysia 96.5 36 inch onshore, max. 750MMSCFD
12. 2013 M9 Thailand 300 230km offshore and 70km onshore; 28 inch; max.300MMSCFD; reserves
1.8-2.5tcf
Table A4. Planned LNG Liquefaction and Regasification Facilities [6]
Capacity
Country Project (Location) Status Start
mmtpa Bcm/y
Liquefaction Facilities
Indonesia ~ expansion LNG Tangguh 3.8 5.2 Planned 2018
Abadi FLNG (Arafura Sea) 2.5 3.4 Planned 2016
Malaysia Rotan FLNG (Sabah) 1.5 2.0 Planned 2016
Regasification Facilities
Malaysia Lahad Datu (Sabah) 0.8 1.1 Planned 2016
Pengerang (Johor) 3.8 5.2 Planned 2017
Thailand ~ expansion Ma Ta Phut 5.0 6.9 Planned 2017
Vietnam Thi Vai 1.0 1.4 Planned 2016
Bin Thuan 3.0 4.1 Planned 2018

Table A5. Planned Cross-Border Pipelines [5]


No. From To Length (km)
1. East Natuna (Indonesia) JDA-Erawan (Thailand) 1500
2. East Natuna (Indonesia) Kerteh (Malaysia) 600
3. East Natuna (Indonesia) Jawa (Indonesia) 1400
4. East Natuna (Indonesia) Vietnam 900
Appendix B

The objective function in this model is to maximize cash-flow balance or revenue in all included
countries in the model.
32 7

𝑀𝑎𝑥𝑖𝑚𝑖𝑧𝑒: ∑ ∑ 𝑁𝐶𝐵𝑖
𝑡=1 𝑖=1

𝑁𝐶𝐵𝑖,𝑡 = 𝐶𝐵𝑖,𝑡 + 𝑝𝑖𝑝𝑒𝑙𝑖𝑛𝑒 𝑡𝑟𝑎𝑛𝑠𝑎𝑐𝑡𝑖𝑜𝑛𝑚,𝑡 ;


Where:
NCB means net cash-flow balance; CB means cash-flow balance; i = index of countries;
m = index of cross-border pipelines; t = years
CBi = domestic revenue – production cost + lng_export_revenue – (lng_liquefaction_cost +
LNG_shipping_cost + LNG_import_cost + LNG_regasification_cost)

 domestic_revenue i = domestic_gas_price * domestic_consumption i


 production_cost i = wellhead_price * production_volume i
 lng_export_revenue i = single_gas_price * (lng_export i + lng_export_dummy i )
 total_liquefaction_cost i = liquefaction_cost * lng_export i + (liquefaction_cost + k) *
lng_export dummy i
 lng_import_cost i = single_gas_price * (lng_import i + lng_import_dummy i )
 total_regasification_cost i = regasification_cost * lng_import i + (regasification_cost + k) *
lng_import_dummy i
 total_shipping_cost i = shipping_cost * (lng_import i + lng_import_dummy i )
Assumed to be paid by producer or exporting countries because the gas price refers to Japan-
CIF index

Pipeline transaction
Exporting country will gain revenues as follows:
single_gas_price * ( pipeline_volume m + pipeline_volume_dummy m ) - transmission_cost *
pipeline_volume m – (transmission_cost + k) * pipeline_volume_dummy m

Importing country will pay costs as follows:


single_gas_price * ( pipeline_volume m + pipeline_volume_dummy m )

Decision variables:
 Volume gas transmitted via pipeline (5 variables)
P12, P17, P27, P54, P58 (next will be called pipeline m, where m is from 1 to 5)
Index: P12  pipeline from 1 to 2
Country index: 1 = Indonesia; 2 = Malaysia; 3 = Brunei; 4 = Thailand; 5 = Myanmar;
6 = Vietnam; 7 = Singapore; 8 = China
 Volume LNG exported (7 variables)
 Volume LNG imported (7 variables)
 Dummy variable (or capacity needed) for existing transmission pipeline (5 variables)
 Dummy variable (or capacity needed) for export through liquefaction facilities (7 variables)
 Dummy variable (or capacity needed) for import through regasification facilities (7 variables)
The constraints are (for all i, m, t) :
 balancing_volume = 0,
where balancing_volume = production_volume + lng_import + lng_import_dummy – (
domestic_consumption + lng_export + lng_export_dummy ) +/- pipeline_volume and
pipeline_volume_dummy
 lng_export > = min_export_capacity (based on historical & existing long-term contract)
 lng_export < = max_export_capacity (based on existing liquefaction capacity)
 lng_import < = max_import_capacity (based on existing regasification capacity)
 pipeline_volume > = min_pipeline_capacity (based on historical & existing long-term contract)
 pipeline_volume < = max_pipeline_capacity (based on existing pipeline capacity)
 proved_reserves > = 0

Set:

 i = ncountries (i = 1,…,7)
 t = nperiods (t = 1,…,32)
 m = pipeline route (m = 1,…,5)

Table B1. Data Library of GANESA Model


Exogenous variables Size [row, column] Unit in the model
single_gas_price [nperiods, 1] USD/bcm
liquefaction_cost [nperiods, 1] USD/bcm
regasification_cost [nperiods, 1] USD/bcm
shipping_cost [nperiods, 1] USD/bcm
transmission_cost [nperiods, 1] USD/bcm
domestic_gas_price [ncountries, nperiods] USD/bcm
wellhead_price [ncountries, nperiods] USD/bcm
production_volume [ncountries, nperiods] bcm
domestic_consumption [ncountries, nperiods] bcm
Constraints (lower and upper bounds)
min_export_capacity [ncountries, nperiods] bcm
max_export_capacity [ncountries, nperiods] bcm
max_import_capacity [ncountries, nperiods] bcm
min_pipeline_capacity [npipelines, nperiods] bcm
max_pipeline_capacity [npipelines, nperiods] bcm
Decision variables (for each i, t, and m)
lng_export [1, nperiods] bcm
lng_export_dummy [1, nperiods] bcm
lng_import [1, nperiods] bcm
lng_import_dummy [1, nperiods] bcm
pipeline_volume [1, nperiods] bcm
pipeline_volume_dummy [1, nperiods] bcm

S-ar putea să vă placă și