Sunteți pe pagina 1din 2

Doc No : HKH-P133-MS-C-044

HKH Project: 2B+G+1+30 Storey Residential Building INSPECTION AND TEST PLAN Rev. No. : 0
W.L.L. At Dafna District, Plot 61071244, Doha, Qatar Date. : 28.01.2017
Internal & External Block works Page : 1 of 2
Inspection / Responsible Surveillance Points Verification /
Sl. Activity / Inspection Description Reference Testing Requirement/
Testing Person(s) Sub Quality
No. Document. Acceptance Criteria HKH Lacasa
Frequency Con. Records
1.0 General
Relevant drawings, ITP’s and
Contract Spec. All the documents to have minimum status Sr. Technical / Drawings/
Method statements, and
1.1 and materials Once of code (B) No objection with comments Sr.QA-QC - H H Documents/
Technical/Material are submitted
submittal. incorporate and proceed. Engineer Submittal Logs
and approved.
Material Inspection shall have approval Stores /
Check material approvals while Contract
1.2 Every delivery status QA/QC - H H Material SIR
receive on site Specification
Code B. Engineer
- Mock up to be prepared and approved
by Supervision Consultant as per the SIR &
Block work Construction
following wall types. Checklist
1.3 Mock - up preparation and approval. method Once Manager / QA- - H H
a. A. block masonry walls for plaster
Statement QC Engineer
finish.
b. Cavity wall.
2.0 Application
- Each wall shall be set out with one
Approved layer of blocks and all the dimensions
Every Prepared SIR &
method shall be set out within acceptable
2.1 Setting out Area Site Engineer - H H Checklist
statement and tolerances.
Shop drawings - Accessories shall be installed in line
with approved shop drawings.
3.0 Installation Checks
- Usage of mortar should be the
Approved
Every Prepared approved mortar mix. Prepared mortar
3.1 Block work mortar mixing method Site Engineer - S S Checklist
Area shall be consumed within initial setting
statement
time.
- For solid and hollow blocks- Joint
Approved vertical width should be 10mm thick.
Every Prepared
3.2 Joint Width method First horizontal joint with substrate Site Engineer - S S Checklist
Area
statement shall max. 30mm and all other joints
must be 10mm thick.
Doc No : HKH-P133-MS-C-044
HKH Project: 2B+G+1+30 Storey Residential Building INSPECTION AND TEST PLAN Rev. No. : 0
W.L.L. At Dafna District, Plot 61071244, Doha, Qatar Date. : 28.01.2017
Internal & External Block works Page : 1 of 2
- All the blocks and substrates should be
wetted prior to installations, walls
Approved
Every Prepared should be constructed as true planes
3.3 Installation of Blocks method Site Engineer - S S Checklist
Area and to the lines and dimensions as
statement
indicated on the approved drawings
and tolerances.
Approved shop Every Prepared - Lintels to be constructed as per detail SIR &
3.4 Lintels Site Engineer - H H
drawing Area shown in the approved drawing. Checklist
- Stiffener columns as per detail in the
Approved shop Every Prepared shop drawing
3.5 Stiffener Columns & Beams Site Engineer - S S Checklist
drawing Area - Stiffener Beams to be as per approved
shop drawing.
Every - With continuous water spray for Site
3.6 Curing Approved MS - S S Checklist
Prepared Area min 3 days Engineer
- Clean / Protect all horizontal
Every surfaces and cavities from mortar. Site
3.7 Cleaning and Completion Approved MS - S S Checklist
Prepared Area Replace/ Repair all damaged block Engineer
works.
- The walls should be constructed for
Site
Approved the dimensions as per the approved
Dimensional checks and Handing Every Engineer/Q SIR &
Shop shop drawing and should be within - H H
3.8 over (Prior to Plastering Works) Prepared Area A-QC Checklist
drawings the allowable tolerances as per proj.
Engineer
specifications Division 4

LEGEND: H - Hold Point; W - Witness Point; S - Surveillance Inspection; R - Review Documents Only;

Prepared By Reviewed by: Approved by:


HKH Review & Approval
Sr. QA/QC Engineer Construction Manager Sr.Project Manager
Name: Mr. Pramod Balan Mr. Gareth Owen Mr. Ifthikar Ali