Sunteți pe pagina 1din 5

back to basics

Execution plan – what’s that?


Tony Reid* presents the second of a series of ten articles on various project controls topics, which
aim to describe the vital requirement to implement sound project controls processes on major
projects

I
magine the scene. You have just
bought an aged property and you
are going to refurbish it
completely. You know what you
want and you know how much you
can afford to spend in order to make it
happen. You also know that you
cannot do it all yourself and you will
need support from several different
skills areas – all of whom will have to
work together in a coordinated way.
You will also need to procure a
significant amount of equipment and
materials on the way.
Most importantly of all, you want to
be sure that, after the work is
completed, you have achieved every-
thing you aimed for, and you are
satisfied with the result.
How on earth are you going to
ensure that everyone involved knows
what is required, when it has to be
completed, and how they all need to
work together to complete it in Figure 1
accordance with your requirements?
You are going to do this by preparing Why? when? by whom? For example, Phase 1 is when the
a ‘project execution plan’. The project Major projects are comprised of ITB is introduced by the sales function
execution plan (PEP) is the vehicle by highly complex mixtures of tasks to be to senior management, who will make
which the project director or project executed, quality standards to be met, a ‘bid/no bid’ decision. This decision
manager communicates his or her budgets to be managed, interfaces could be based on one or more of the
requirements to everyone who is going between functions to be controlled, following considerations:
to play a part in the successful risks to be assessed, equipment and
achievement of the project objectives. materials to be acquired, designs to be G Is the project within the field of
Ideally, in the client/contractor developed, contracts to be awarded, expertise of the business?
relationship, the client should prepare and so on… G Is the range of competition too
his own PEP, indicating to his own The project director has to find a great, thus minimising probability
team such factors as the concept way to communicate his intentions – at of award?
behind the project, the business case least at such a level that his team has G Is the work essential, in relation to
for going ahead, an explanation of the sufficient guidance to develop their the current order book?
principles of the project economics, approach to their own roles and G What is the level of risk? Is now the
and a description of the intended responsibilities. time to decline to bid at all?
method of contracting the work. The reason he should do this is to G What are the expected margins
This article, however, is intended to recognise that, from the point of from that market – or that specific
support the contracting side of project receipt of an inquiry document client?
execution and so we will address the (Invitation to bid – ‘ITB’), a number of
PEP which the contractor’s project people in the organisation will be Should the decision be made to prepare
management should prepare, for the progressively mobilised to prepare the and submit a bid, then Phase 2 is initiated
use of his project team. bid. (See Figure 1.) and the next part of the team is mobilised:

PROJECT CONTROL PROFESSIONAL September 2006 17


G The Bid Manager, to develop the the bid stage. It is worth remembering business case, and what can we do
structure of the bid, to define the that, whatever goes in the bid will, to support him in realizing it?
schedule for its preparation, and to following award, become a contractual G How do we avoid conflict?
assign names to specific sections of the commitment – and so it is worth the
document to start preparing their input. effort to get it right. Health, Safety and the Environment
G The Project Director/Manager, When should it be prepared then? As G Which safety legislation is
(who is sometimes also the Bid the above shows, there is an optimum relevant?
Manager) to address the technical parts point at which enough information is G Is the client making any particular
of the bid, and to play the appropriate available to a small community to HSE demands which are unusual to
role, along with the commercial/legal allow a fair understanding of the us?
people, in developing the approach to project, but beyond which so many G Does the client have any legal
the required method of contracting. He others are mobilised that a failure to requirement to observe local HSE
is also the person who should prepare inform would cause confusion. regulations?
the execution plan. The point at which the execution G When can we describe the project
G The Commercial/Legal Manager(s), plan is released should be at the safety strategy to the team?
to start the process of reviewing the beginning of phase 3, preferable at a G Are we going to impose our normal
proposed contract conditions, to assess full bid team kick-off meeting, where standards on the site, and to what
risk and to consider how to align his the project director can present his extent can we enforce them?
own company objectives with those of plan and explain the rationale to G Are there any specific, local,
the client. everyone involved. environmental issues?
G The Document Control Manager, G To what extent do we need to
to take charge of ensuring that the What does the execution plan address the environment local to the
correct parts of the ITB are distributed contain? site?
to those named by the bid manager In order to understand what should be
who have to make a contribution to the covered in an execution plan, it may be Engineering
bid, and to ensure that all subsequent worth considering the kinds of G What is the status of design?
documentation generated during the questions which arise from the team G Is there an equipment list?
bid period is managed and controlled when a major bid effort is launched. G Is there any specialized, long-
efficiently. (See Figure 2.) delivery equipment?
G How much of the equipment is
The next step, Phase 3 of mobilisation, Estimating designed by the suppliers?
would normally include the following G What class of estimate is required – G Where are all the available
function heads, who would then budget or definitive? drawings?
mobilise the appropriate members of G How is the project to be awarded – G What are our expected
their disciplines to contribute to the bid lump sum /fixed price, or deliverables?
requirements: reimbursable or cost plus, etc? G Is the concept agreed?
G Where is equipment and material to G Whose process licence is involved?
G Estimating be sourced – locally to site? Within G What, if any, are the safety issues to
G Engineering European Union? Worldwide? be addressed in the design?
G Procurement G Is there an equipment list? G Do we have to do any design during
G Construction G Where are all the available the bid period for the estimate?
G Commissioning drawings?
G Planning G Is there a prescribed work Procurement
G Cost control breakdown structure (WBS) or G What is the procurement strategy –
G Document control cost breakdown structure (CBS)? local or worldwide?
G Health, Safety and the Environment G Does the client expect a particular G Are there any markets ruled out by
G Quality management. breakdown or structure of the the client for political reasons?
estimate? G Is there a client-preferred supplier
By this stage, a significant number G Are we required to use the client listing?
of staff are involved and starting to code of accounts, or our own? G Is there an equipment list?
work to what is highly likely to be a G Does the bid schedule allow G Is there any specialized, long-
tight schedule to deliver the bid. adequate time for estimate reviews delivery equipment?
It is simply good sense, then, to and estimate risk analysis? G What type of contract will we have?
provide them with guidance on how G How much involvement does the
the business (in the shape of the project Commercial client want/need in the purchasing
director) wants to execute the work so G How can we align our objectives cycle?
that they may all base their contri- with those of the client, in order to
butions on the same premise – that is optimize our chances of winning, Construction
all ‘singing from the same song-sheet’. and establishing a rapport with the G What is the exact location of the
Of course, the benefits of describing client? site?
the plan for the project go far beyond G Do we understand the client G Which safety regulations are

18 PROJECT CONTROL PROFESSIONAL September 2006


Figure 2

applicable? breakdown structure (WBS) or can breakdown structure (CBS) within


G Can we use international we develop our own? which we must work?
subcontractors or is there a G Is there a prescribed cost G To what extent are we going to
prescribed local labour content? breakdown structure (CBS) within engage the planning and the cost
G What are the assignment conditions which we must work? control?
we can offer staff? G To what extent are we going to G How are we going to manage the
G What is the nature of any heavy engage the planning and the cost transition from the estimate to the
lifts? control? control budgets?
G Do we have to provide and manage G What are the procurement and G Who are the nominated budget
a construction camp? subcontract strategies? holders?
G Is there an equipment list? G What are the cost reporting formats
Commissioning G Where are all the available and requirements to satisfy the
G Is commissioning within our scope? drawings? client?
G Which safety regulations are G What are the client reporting G What is the strategy for cost
applicable? requirements? trending and forecasting?
G What is the client’s involvement? G How is the project to be awarded –
G Do we have to train the client lump sum/fixed price, or Document control
operators? reimbursable or cost plus, etc? G Do we have to use the client
G At what stage does the client want G How is the estimate being document numbering system or can
to start operator training? structured and what is the cost we use our own – or is it both?
breakdown structure (CBS)? G Can we use our own document
Planning management systems and
G What is the expected award date Cost control processes?
and what is the target completion G Is there a prescribed work G Is there a need to engage with the
date? breakdown structure (WBS)? client asset register?
G Is there a prescribed work G Is there a prescribed cost G What is the extent of client

PROJECT CONTROL PROFESSIONAL September 2006 19


involvement in the procuring worldwide) covered in the estimate, and has a
comment/review/approval cycle? G to address any legal or commercial strategy for engaging with the cost
G Does the client have a prescribed issues which may require a strategy control process throughout the
document distribution matrix for amendment which will affect the execution of the project. The third
their own organisation? team’s action plan article will address the planning
G to communicate any change to the function in some detail.
Quality management delivery date of the bid or, indeed,
G Can we apply our own quality of the project itself. Subcontract plan: the contracts
management system to the project, function uses the information in the
or is the client insisting that we use To whom should it be made execution plan to develop the approach
his system (which could have major available? to subcontracting – local contractors
cost implications)? The execution plan should quite only, or international, or joint
G Do we have to make any major simply be available to everyone on the ventures? They must decide which is
changes to our QMS for this project. The word ‘available’ is used in the most appropriate form of contract
project, or only the normal level of the context that it is preferable that it to be used, start considering possible
customization? be issued to discipline heads so they pre-qualification and tendering
can make it available to their staff – by processes, and how risk is to be
It can be seen from the above that there means of personal presentation and managed.
are several common areas of explanation of its content and
information which are of interest to rationale. Engineering will take guidance on the
different disciplines. It is easy to One way or another, however, standards and specifications to be
understand, therefore, that if no EVERYONE on the project team used, the extent of the list of
information is provided to them, each should know about its content. deliverables, the unique and total
will make assumptions which may not numbers of equipment involved, any
be compatible with each other, and To which other project tools does long delivery or particularly complex
which would lead to inconsistencies in it relate? equipment involved, and whether any
the response to the bid. The execution plan does not stand in further work has to be done on process
It is sensible, therefore, for the isolation on a project. It should be the or specification development.
project director to take the lead and focal point of reference for guidance
inform his team on the key topics for many other project management Construction plan: the success of
which make a difference between a tools. These are described below. construction depends on everything
consistent and an inconsistent or, which precedes it, and so the
worse still, non-compliant, bid. Health, safety and the environment adherence of others to the execution
It is also sensible to realize that an are of paramount importance to the plan has a major impact on the way
inconsistent bid document may still people involved and to the reputation construction progresses. Meeting the
lead to a winning tender but may later of the business. The protection of the programme, making the progress and
result in complex and expensive issues environment is EVERYONE’S assigning the correct resources at the
when practices and strategies across concern and all related issues must be right time, are all key factors which
the project team start to diverge, addressed carefully. The execution emanate from the threads of the
because assumptions were made in the plan should make a clear and formal execution plan.
absence of clear direction. statement of project intent on all HSE
matters. Quality management: from the
How often should it be updated? description in the execution plan of
Every project is subject to change, and Project programme: the planning what is to be done, the Quality
change even occurs during the bid engineer is one of the most important Management system develops the
preparation period. It is obviously ‘users’. It is his job to translate the approach to how the quality of the
important that changes should be defined scope of work into the outcome will meet the requirements of
communicated to the team, and the integrated plan (for engineering, the client.
execution plan should be the preferred procurement, construction and
medium to achieve this. commissioning) for the whole team to Commissioning plan: this has to take
The frequency cannot be defined but use to organize their work. He needs to account of the point in the construction
the potential reasons for re-issuing the know the scope, the material phase when the plant is ready for pre-
plan certainly can. These are as quantities, the details of the equipment commissioning and then commi-
follows: to be installed, where it is all to be ssioning (which comes from the
procured (he has to build in allowances programme – see above) and what are
G to communicate any change to the for designing, approvals, purchasing, the requirements about operator and
bid specification from the client manufacturing, deliveries, shipping, training manuals – and when they have
G to explain any internal changes of customs clearances, etc. (some or all of to be ready to train local operating staff.
approach to the bid (for example – a which may be relevant).
change from the decision to procure He also has to ensure that he has Cost control: the structure of the
only in the European Union to planned for all the cost elements budgets, which are derived from the

20 PROJECT CONTROL PROFESSIONAL September 2006


estimate, may be linked to a client- which provide a basis for taking the # Ensure that the right people have
required cost breakdown structure, to execution plan seriously, and for using it, and that they know why
allow the client to engage project costs it as a significant tool for achieving It should be issued to all the discipline
with his own financial control system. better levels of benefits to the business. leaders involved in the project, and
Also, the control of costs may be they should then share its contents
delegated to named project budget # Be clear about what an execution with EVERY member of their own
holders and these must be identified plan is teams. It is essential that ALL
and involved in the definition of the The project execution plan (PEP) is the participants are working to the same
project cost control procedures. vehicle by which the project director or set of rules, and the execution plan
The execution plan should provide project manager communicates his defines these rules.
valuable information on all of this. requirements to everyone who is going
to play a part in the successful What next?
Progress measurement: the measure- achievement of the project objectives. The next article will address planning.
ment of progress of engineering, It will consider why planning is so
procurement and construction has to # Understand why and when should fundamental to the control of a project
be considered carefully, and the it be prepared, and by whom in order to allow a focus on the key
objectives and requirements of the It is prepared in order to communicate activities, and why planning of the
client and the contract, as defined in the project intentions – to allow the project activities must be engaged with
the execution plan, must be recognized team sufficient guidance to develop the control of their costs. It will also
in ensuring that the needs of the their approach to their own roles and discuss the need for full integration
project are met. The measurement of responsibilities. It should be prepared across the project, the development of
the planned progress and the costs of when the ‘core’ team understands the manpower plan, and the
achieving it, together combine to form enough about the project to set requirement to measure progress.
one of the most important aspects of strategy but before too many of the
project control – the integration of cost team are mobilised and doing their
and time. own thing, and must be prepared by
the project manager.
Reporting: the client usually has clear
requirements about reporting, so that # Understand what it contains
he can align the progress and current It contains sufficient information
costs of the project with his own about how the project director wants to * Eur Ing C.R.A. (Tony) Reid,
business reporting structure. It is vital run the project to allow each of the BSc, CEng, MIET, FACostE, MIOD
to define these in the execution plan so team disciplines to develop their own Tony Reid is a chartered (electrical)
that the whole project team aligns with approach within a defined structure. engineer, and a Fellow and Past President
the same objectives. The objective is to facilitate the of the Association of Cost Engineers. He
development of an integrated detailed started his career in electricity supply, in
Legal and commercial: it is the task plan which supports the overall commissioning, operations and main-
of the legal and commercial function strategy. tenance.
to protect the business interests of the He has nearly 30 years’ experience in
contractor but also to align with those # Update it as required project controls, initially in electricity
of the client. The execution plan It should be updated whenever a supply, then in international oil and gas
should provide sufficient information significant change takes place which contracting, and more recently in a project
about the project for them to be able to may have an impact on any of the management consultancy until he retired
carry out their work effectively. participating disciplines, and which from full-time employment earlier this year.
may affect the way the project is being He now operates as an independent
Take-away messages executed, perhaps introducing further project controls consultant, and can be
Finally, here are some key messages risk to its successful completion. contacted at email: crareid@aol.com.

PROJECT CONTROL PROFESSIONAL September 2006 21

S-ar putea să vă placă și