Sunteți pe pagina 1din 7

Division 2. Paragraph 4.

18 of Section VIII, Division 2 has rules


Assuring Tube-to-Tubesheet Joint for permissible materials, design, and construction of shell-and-
Tightness and Strength tube heat exchangers built to this division.

Tube Joint Welds. Both Section VIII Divisions 1 and 2 of the


Stanley Yokell Code define full-strength welds as those in which the weld design
MGT Inc. strength is equal to or greater than the axial tube strength. They
F201 The Academy, define partial-strength welds as those in which the design strength
is based on the mechanical and thermal axial loads (in either
970 Aurora Avenue, direction) that are determined in accordance with referred to para-
Boulder, CO 80302-7299 graphs and appendices. They define seal welds as welds used to
e-mail: syokell@mgt-inc.com supplement expanded joints to ensure leak tightness with weld
sizes not determined based on axial tube loading. Both sections
say of full-strength and partial-strength welds, “Such welds do not
This paper describes preparing mockup tubesheet specimens for require qualification by shear load testing,” and “full-strength and
visual examination using a digital microscope to determine that partial-strength welds also provide additional tube joint leak
tube-to-tubesheet joint welds are of the specified size and that tightness.” It is noteworthy that the design procedures of both
expanded joints are satisfactory for the intended purpose. It dis- divisions are the same; however division 2 allows higher allow-
cusses nondestructive examinations (NDE) of the tubesheets and able stresses than does division 1.
tube joints intended to assure achieving sufficient tightness and Individuals concerned with tubular exchangers should be aware
strength to satisfy the uses to which the exchangers will be put. that full-strength and partial-strength tube joint welds may meet
This paper refers to the ASME Boiler and Pressure Vessel all of either division’s requirements but not seal the tubes to the
Code (Code) paragraphs that apply to tube joint welds and tubesheets if there is a gap in the weld. Similarly, gaps in seal
expanded joints including shear load testing when the Code welds prevent sealing.
requires it [1]. The discussion also addresses the need for manu-
facturers to have qualified tube joining procedures and personnel Code Requirements for Welded Joints
qualified to use the qualified procedures. The work concludes with
a summary of ways to assure tube joint tightness and strength. Tube joint weld requirements for tube joints of exchangers built
[DOI: 10.1115/1.4006123] to Section VIII Division 1 are in Paragraph UW-20 and subpara-
graphs UW-20.1–20.7 of the current edition of the Code. Rules
Keywords: ASME code, control hole, control tube, digital for tube joint welds of exchangers built to Division 2 are in Para-
microscope, gas-bubble testing, hybrid expanding, hydroexpanding, graph 4.18.10. To ensure leak tightness, the author’s criterion is
mock-up, nondestructive testing, percent wall reduction, roller that the thickness of the weld through the root shall be at least as
expanding, tube joint, tube expansion, tube weld, ultrasonic testing, great as the thickness of the tube wall.
liquid penetrant testing Welded joint tightness depends upon the welds being continu-
ous, without cracks or gaps. Full-strength and partial-strength tube
Introduction joint welds must meet the Code sizes. Because there is no simple
way to determine whether the welds meet the Code requirements,
Tight, strong tube joints are essential for long life and satisfac- it is prudent to validate the procedures by preparing specimens
tory operation of shell-and-tube heat exchangers. To assure tight- (tubesheet mockups) and examining them under magnification.
ness and strength requires manufacturers to have and to follow For this purpose, the specimens must be sectioned and polished.
procedures for tubesheet drilling, tube hole preparation, tube joint The purpose of examining the welds is to determine that the weld
welding, and tube expanding. In this connection, Table RCB-7.21 sizes meet the Code requirements and are not flawed with cracks
and 7.21M and Paragraphs RB 7.24 and RC-7.24 of the TEMA or porosity.
Standards have requirements for tubesheet drilling and prepara-
tion with annular grooves; the HEI Standard for Power Plant Heat
Exchangers Paragraph 5.72 has standards for drilling and annular Weld Procedures, Procedure, and Personnel Qualifications.
grooves; the HEI Standards for Closed Feedwater Heaters Para- It is the manufacturer’s responsibility to prepare and qualify weld-
graph 3.8.3 and Table V have requirements for tubesheet drilling ing procedure specifications (WPSs), maintain procedure qualifi-
but are silent on requirements for annular grooves [2–4]. cation records (PQRs) for welded tube joints, and to qualify and
The vast majority of shell-and-tube heat exchangers in North maintain records of the workers’ qualifications in the use of the
America and many other locations are designed and constructed qualified procedures (WPQs). The Code’s Section IX has sug-
in accordance with the rules of Part UHX of Section VIII Division gested forms for these purposes. The tubesheet and tube materials
1 of the Code. For designs that Part UHX does not cover, Para- used in preparing mockup specimens must very closely match the
graph U-2(g) applies. The text of Paragraph U-2(g) is as follows. materials of production exchangers. The report of examination of
This Division of Section VIII does not contain rules to cover all the mockups should include the mill test reports for the mockup
details of design and construction. Where complete details are not tubesheet and tubes.
given, it is intended that the Manufacturer, subject to the accep- Specimen thicknesses of mockup tubesheets must be reasonably
tance of the Inspector shall provide details of design and construc- close to the thickness of the production tubesheet except in cases
tion which will be as safe as those provided by the rules of this where tubesheets are very thick. Many specimens that the author
Division. Manufacturers often use finite element analysis to sat- has examined have been as thick as 280-mm (approximately
isfy U-2(g). 11-in.). Where tubesheets are clad with weld metal, weld metal on
Depending upon the service conditions to which the exchanger mockups must be applied using the production weld procedure,
will be exposed and its design conditions are sometimes advanta- and liquid penetrant (LP) and UT examined in the same manner
geous to design and construct exchangers to Section VIII as that of the production tubesheet.
Any laboratory examinations should identify the specimens
with the manufacturer’s job number and cite the mill test report
Contributed by the Pressure Vessel and Piping Division of ASME for publication identification for the materials of the mockup along with the man-
in the JOURNAL OF PRESSURE VESSEL TECHNOLOGY. Manuscript received June 27, 2011;
final manuscript received October 25, 2011; published online October 18, 2012. ufacturer’s procedure identification and the name of the welder. It
Assoc. Editor: William J. Koves. is desirable to also include the PQR number and the welder(s)’

Journal of Pressure Vessel Technology Copyright V


C 2012 by ASME DECEMBER 2012, Vol. 134 / 064502-1

Downloaded From: http://pressurevesseltech.asmedigitalcollection.asme.org/ on 10/10/2013 Terms of Use: http://asme.org/terms


qualification for using the procedure in the report of the shops that meet the PVD, there are no certifications of personnel
examination. in the use of the procedures.
The strength and tightness of expanded joints, and the efficien-
Code Requirements for Expanded Joints cies listed in Tables A-1 and 4.C.2 assume that there will be con-
tinuous intimate contact between the tubes and holes and that
When Code tubesheet thickness calculations take advantage of
where the holes are grooved with annular grooves, tube metal will
the stiffening effect of the length of tube expanded into the tube-
substantially fill the grooves.
sheet, tubes in expanded joints must have continuous, intimate,
hydraulically tight contact with the tube hole surface. When tube
holes are prepared with annular grooves, tube metal must pene- Measurements and Settings. Procedures for production tube
trate and make intimate contact with the bottom of the grooves. expanding should include measuring a representative number of
In the Code’s Division 1, nonmandatory Appendix A provides tube holes and measuring a representative number of tubes to be
a basis for establishing allowable loads for tube joints. It is impor- expanded into the measured tube holes. These should be desig-
tant to be aware of Paragraph A-1(b) in Appendix A which states, nated control holes. The measuring tools for making these meas-
The rules in this appendix are not intended to apply to U-tube con- urements must be of recent calibration. The holes and tubes
struction. In its Division 2, normative Annex 4.C of the current should be measured for the depth of expansion at 45 deg intervals
edition provides a basis for establishing allowable loads for tube around the circumference and at 25-mm (1-in.) intervals along
joints of exchangers built to that division. Paragraph 4.C.1.2 in the depth. Percent tube wall reduction measurements of expan-
Annex 4.C has an identical paragraph as in Appendix A of Divi- sions in the control holes are used to set hydrostatic expansion
sion 1. It states, The rules in this appendix are not intended to pressures (or if explosive expanding is used, explosive content)
apply to U-tube construction. The word normative in the title of and torque settings for roller expanding. After trial expansions
Annex 4.C indicates that it is expected that design and construc- achieve appropriate settings for the desired percent wall reduction,
tion will follow the rules of the annex. the manufacturer should verify by measurement the percent wall
reduction every 50 expansions for tube end counts of 500 or
Tube Joint Efficiencies. Tables A-1 of Section VIII Division greater. When the tube end count is less than 500, the manufac-
1 and 4.C.1 of Division 2 list tube joint efficiencies. These effi- turer may adjust the intervals accordingly.
ciencies are not based on any published experimental or analytical
work but were established by Code Committee members with Examining Tube Expansion in Mockups. The purposes of
much experience with tube joints. With few changes and addi- examining tube expansions in mockups are (1) to determine that
tions, the listed efficiencies have been successfully used for expansion begins at an appropriate distance from the root of the
decades. front face welds, (2) to see whether there is continuous interfacial
contact, and (3) to make sure there is penetration of tube metal
Tube Expansion Procedures and Personnel Qualifications. into the grooves.
The ASME Code does not have requirements to certify tube
expanding procedures and to certify the qualifications of the per- Shear Load Testing
sonnel authorized to use the certified procedures. TEMA and HEI When the manufacturer builds a heat exchanger using joint effi-
Standards are also silent about tube expanding procedures. ciencies listed in Tables A-1 of Section VIII Division 1 and 4.C.2
In order for the ASME Code certified manufacturers’ heat of Section VIII Division 2 that requires shear load testing, the fix-
exchangers to be acceptable for export to members of the Euro- ture used for testing must conform to Figure A-3 for construction
pean Community, in addition to meeting the Code requirements, to Division 1 and 4.C.2 for construction to division 2.
they must meet the requirements of the European Pressure Vessel It is noteworthy that although the division 1 Appendix A and
Directive (PVD [5]). The PVD requires heat exchanger manufac- Division 2 Annex C do not apply to U-tube construction, it is a
turers to have certifications of expanding procedures and qualifi- common practice for specifications for U-tube closed feedwater
cations of workers who use the procedures. The PVD heaters to require shear load testing specimens for intermediate
requirements parallel their requirements for welding procedures and high pressure heaters. The reason for including this require-
and workers who use them. ment is the assumption that shear load tested joints that equal tube
In the Code’s Division 1, nonmandatory Appendix HH estab- strength will meet the tightness requirements of the heater. This is
lishes requirements for tube joint expanding procedure specifica- a fallacious assumption because it is possible to have a tube joint
tions. The text and accompanying forms parallel the text and as strong as the tube that has a discontinuity in the weld or if
forms for WPSs, PQRs, and WPQs of Section IX of the Code. Ap- welded and expanded, a leak path through the expanded tube
pendix HH has definitions for various types of tube expanding and length and a discontinuity in the weld.
the equipment used in doing it. Paragraph HH-4 has requirements Where the Code requires shear load testing, manufacturers
for tube expanding procedure specifications (TEPS); paragraph should test an appropriate number of tube joints. Be aware that
HH-5 has requirements for tube expanding procedure qualifica- push-out shear load tube testing welded and expanded joints
tions; paragraph HH-6 has requirements for tube expanding per- causes some loss of the interfacial pressure between the tube and
formance qualification; paragraph HH-7 subdivides tube hole surface because of the Poisson effect. Yokell illustrated this
expanding variables to be described in the procedures into essen- phenomenon in a paper on hybrid expanding that showed failures
tial and nonessential variables, paralleling the system used for in the weld before the tubes yielded [6].
WPSs. Form QEXP-1 provides a form for manufacturers to record
their TEPS. It is accompanied by Table QEXP-1 that has instruc-
tions for filling out the TEPS form. Tightness Testing Specimens
Division 2 does not have an appendix similar to that of Appen- The paper “Pressure Testing Feedwater Heaters and Power
dix HH. However for design and construction to either division, it Plant Auxiliary Heat Exchangers” pointed out that the purpose of
is prudent for specifying engineers to require manufacturers to hydrostatic testing pressure vessels is to stress the structure to
have and qualify procedures for tube expanding using the forms show that it is capable of resisting the loads due to pressure [7]. It
suggested in Section VIII Division 1 Appendix HH. Most reputa- states that, although the Code does not permit leaks during hydro-
ble North American heat exchanger shops have such written pro- static testing, such testing does not disclose minute leaks through
cedures and workers qualified in their use. But except for shops tube joints when the back face of the tubesheet is not visible. It
that have met the PVD requirements, the procedures are not certi- demonstrates by mathematical analysis that graduations on the
fied by an Authorized Inspection Agency. Similarly, except for test gages customarily used to measure hydrostatic test pressure

064502-2 / Vol. 134, DECEMBER 2012 Transactions of the ASME

Downloaded From: http://pressurevesseltech.asmedigitalcollection.asme.org/ on 10/10/2013 Terms of Use: http://asme.org/terms


Fig. 1 Ultrasonic testing feedwater heater tubesheet after Fig. 3 Gas leak bubble testing feedwater heater tube-to-tube-
weldwire cladding and machining sheet joints

Fig. 4 Typical layout of mockup tubesheet specimen for feed-


Fig. 2 Liquid penetrant examining a feedwater heater tube- water heater with two tube thicknesses
sheet cladding after machining

and declines in hydrostatic test pressure are too coarse to indicate


minute leaks. This is especially of concern when the tubeside
pressure is higher than that of the shellside.
Consequently, purchasers should specify and manufacturers
should use other nondestructive means to assure tube joint tight-
ness. These are ultrasonic testing tubesheets after weld metal clad-
ding and machining (Fig. 1), LP examining the tubesheet after
weld cladding and again after tube joining by welding (Fig. 2),
followed by gas-bubble testing (Fig. 3), and, where tightness is of
extreme importance, helium leak sniffer testing with the helium
air mixture in the shell and the tube joints sniffed. Such nondes-
tructive test must conform with the requirements of Section V of
the Code. The workers administering the tests should be qualified
to level 2 or level 3.

A Typical Preparation of a Mockup for Examination


Under the Digital Microscope
Figure 4 is a typical layout of a set of specimens cut from a
mockup that a feedwater heater manufacturer prepared. The num- Fig. 5 Photograph of specimen A 0.035 wall tubes
bers indicate the tubes selected for examination under the digital
microscope. In the specimen shown in Figs. 5–8, the tubes were
first full-strength welded, then hybrid expanded after welding. began approximately 12-mm (approximately 1/2-in.) beyond the
The manufacturer performed the welding using a qualified weld root. Because Appendix A of Division 1 and Annex 4.C of
WPS for autogenous gas tungsten arc welding (GTAW). Expanding Division 2 of the Code do not apply to U-tube feedwater heaters,

Journal of Pressure Vessel Technology DECEMBER 2012, Vol. 134 / 064502-3

Downloaded From: http://pressurevesseltech.asmedigitalcollection.asme.org/ on 10/10/2013 Terms of Use: http://asme.org/terms


Fig. 6 Photograph of specimen B 0.035 wall tubes Fig. 8 Photograph of specimen B 0.049 wall tubes

tubes the roll gage setup was Airetool #1214 with a torque setting
of 2–4.
After welding the tubes to the mockup tubesheet and subse-
quent expanding, the manufacturer filled the tubes with a plastic
medium that neither shrunk nor expanded upon hardening. The
manufacturer sawed the specimen on the axial centerlines of the
tubes and polished the halves to close to a mirror finish. The rea-
son for sawing along the tube axes was to minimize the possibility
of loosening the tubes.
Tables 1 and 2 tabulate the hole measurements and expansions
of five tubes each of 5/8 in. OD  0.035-in. (16-mm  0.089)
and 5/8-in. OD  0.049-in. (16-mm  1.24-mm) tubes for a
5-7/8-in. (150-mm) thick mockup tubesheet specimen.

Examination of Specimens Using the Digital Microscope


The author examined the specimens shown in Figs. 5–8 using
the digital microscope shown in Fig. 9. He marked the specimens
as Specimens A and B, 0.035 with the tubes numbered 6–10, and
specimens A and B 0.049 with the tubes numbered 1–5. Tube
walls are identified on the microphotographs as L for left side and
Fig. 7 Photograph of specimen A 0.049 wall tubes R for right side and with the tube number. Figure 10 illustrates the
microphotograph of the welds taken at the ligament between tubes
numbers 6 and 7 and shows the weld measurement and the mea-
surement of the unexpanded gap behind the weld root. Upon com-
there was no requirement for the manufacture to prepare speci- plete examination of the welds of the specimens a small number
mens for shear load testing and the manufacturer did not prepare had leak paths through the welds smaller than specified.
such specimens. Figure 11 illustrates the microscopic examination of the expan-
The first stage of the hybrid expansion was by hydroexpanding sions in the region of the first annular groove. It shows the tube/
intended to produce approximately 3% wall reduction. The hydro- hole interference at the intersection of the tubes with the groove
expanding was performed in the inner rows with tube IDs in edges and the penetration and bottoming out of the metal
0.520-in. (13.2-mm) range using a HydroPro, Inc. mandrel p/n deformed into the grooves. Figure 12 shows the contact of the
7130-74023-1300 with 41,800–42,100 psi (288,200–290,269 tube OD and hole ID at the land. Figure 12 shows the land
kPa) expanding pressure. The remaining rows with tube IDs in between the grooves with the tube in intimate contact with the
0.548-in. (13.9-mm) range were expanded using a HydroPro, tube hole. Figure 13 shows the second groove with tube metal bot-
Inc. mandrel p/n 7130-74023-1375 at a pressure of 40,000–41,000 toming out in the groove. The examination of the expanded length
psi (275,790–282,685 kPa) expanding pressure. The HydroPro of tubes beyond the grooves was at 2-in. (51-mm intervals).
system used was a p/n 6100-10020-60702 unit with 0–60 ksi pres- Figure 14 shows intimate contact of the tube OD with the hole ID
sure capability and a transducer p/n 84754 that had recently been at 2 in. Figure 15 indicates that there were no discontinuities over
calibrated. the entire expanded length. Complete examination of all the
The second stage of the hybrid expanding was by roller expand- expanded tubes in the specimens indicated that all tubes bottomed
ing intended to produce a final total percent wall reduction of out in the grooves and corner discontinuities were insignificant in
6–8%. Airetool manufactured the #1214 gun and tool for 6-in. all grooves examined.
(152-mm) reach with 2-in. (52-mm) roll depth. The tool is All but two expanded lengths showed intimate hole/tube con-
fitted with a thrust collar. The roll gage setup for 0.049-in. tact. Figure 16 shows one microphotograph where there are dis-
(1.24-mm) minimum wall tubes was Airetool number 2330 with continuities. The conditions shown in Fig. 16 prevailed through
torque setting 2–6. For 0.035-in. (0.89-mm) minimum wall the expanded length which led to its rejection. The author’s

064502-4 / Vol. 134, DECEMBER 2012 Transactions of the ASME

Downloaded From: http://pressurevesseltech.asmedigitalcollection.asme.org/ on 10/10/2013 Terms of Use: http://asme.org/terms


Table 1 Tubesheet Mockup Specimen First Stage Hydroexpanding/Second Stage Roller Expanding: 0.035 Minimum Wall Tubes
Two Ring Grooves 1/4in wide 3 1/64in Deep, Trapezoidal

Tubesheet thickness 5–7/8in Job No. deleted

Percent wall reduction 3% initial statge, 8% final. Expansion depth 5-3/4in

Measurements and calculations prior to tube expansion for 0.035 MW tubes

Holes for calculations

Tube row/hole No. per figure 1 1 2 3 4 5

Hole ID (a) 0.632 0.632 0.632 0.632 0.632


Tube OD (b) 0.624 0.624 0.624 0.624 0.624
Tube clearance (a and b) (c) 0.008 0.008 0.008 0.008 0.008
Tube ID (d) 0.549 0.549 0.549 0.549 0.549
Tube ID þ clearance (e) 0.557 0.557 0.557 0.557 0.557
2  wall thickness (b–d) (f) 0.075 0.076 0.076 0.076 0.076
Wall reduction factor 0.08/0.03 0.08/0.03 0.08/0.03 0.08/0.03 0.08/0.03
% Wall reduction/100 Rw
Wall reduction (Rw  f) (g) 0.006/0.002 0.006/0.002 0.006/0.002 0.006/0.002 0.006/0.002
Calculated expanded ID (h) 0.563/0.559 0.562/0.558 0.562/0.558 0.563/0.559 0.563/0.559

Table 2 Tubesheet Mockup Specimen First Stage Hydroexpanding/Second Stage Roller Expanding: 0.049 Minimum Wall Tubes
Two Ring Grooves 1/4in wide 3 1/64in Deeep, Trapenzoidal

Tubesheet thickness 5–7/8in Job No. deleted

Percent wall reduction 3% initial stage, 8% final. Expansion depth 5-3/4in

Measurements and calculations prior to tube expansion for 0.035 MW tubes

Holes for calculations

Tube row/hole No. per figure 1 1 2 3 4 5

Hole ID (a) 0.633 0.633 0.633 0.633 0.633


Tube OD (b) 0.626 0.626 0.626 0.626 0.626
Tube clearance (a–b) (c) 0.007 0.007 0.008 0.008 0.007
Tube ID (d) 0.520 0.520 0.520 0.520 0.520
Tube ID þ clearance (e) 0.527 0.527 0.528 0.528 0.527
2  wall thickness (b–d) (f) 0.106 0.106 0.105 0.105 0.106
Wall reduction factor 0.08/0.03 0.08/0.03 0.08/0.03 0.08/0.03 0.08/0.03
% Wall reduction/100 (Rw)
Wall reduction (Rw  f) (g) 0.008/0.003 0.008/0.003 0.008/0.003 0.008/0.003 0.008/0.003
Calculated expanded ID (h) 0.536/0.531 0.535/0.530 0.536/0.531 0.536/0.531 0.536/0.531

Fig. 10 Tube-to-tubesheet welds at 6L and 7R Leak paths


Fig. 9 VHX digital microscope used to examine the specimens 0.0364 in. and 0.0364 in. Unexpanded gaps behind weld roots
shown in Figs. 10–16 0.387 in. and 0.375 in.

Journal of Pressure Vessel Technology DECEMBER 2012, Vol. 134 / 064502-5

Downloaded From: http://pressurevesseltech.asmedigitalcollection.asme.org/ on 10/10/2013 Terms of Use: http://asme.org/terms


Fig. 11 7R and 6l Groove 1. Discontinuities are insignificant. Fig. 14 Tube 6L and 7R at 2 in. No discontinuities.
Grooves are trapezoidal.

Fig. 12 7R and 6L Land between grooves. No discontinuities.


Fig. 15 Tube 6L and 7R at 5 in. No discontinuities over the
expanded length.

Fig. 13 6R and 7L Groove 2. Insignificant discontinuities.


Grooves are trapezoidal. Fig. 16 Tube 7R and 8L at 2 in. Tube 8L is not in intimate con-
tact with the tubesheet and the expansion is unacceptable.

criterion for acceptance of discontinuities in contact between the


tube and hole surfaces in tubesheets 50-mm (approximately 2-in.) Summary and Conclusions
or thicker is that a minimum of 90% of the expanded length shall Assuring the attainment of satisfactory leak tightness and
be in intimate continuous contact. For thinner tubesheets, the strength of tube-to-tubesheet connections requires nondestructive
author’s criterion is 100% intimate contact. testing tubesheets and tube joint welds during and after

064502-6 / Vol. 134, DECEMBER 2012 Transactions of the ASME

Downloaded From: http://pressurevesseltech.asmedigitalcollection.asme.org/ on 10/10/2013 Terms of Use: http://asme.org/terms


construction. Although the Code-required hydrostatic testing veri- mens along with helium leak sniffer testing assures that tube-to-
fies that the exchanger strength is adequate, it does not disclose tubesheet connections will be tight and strong enough for the serv-
minute leaks through the tubesheet when the tubeside pressure is ice of the exchanger.
higher than that of the shellside. Other means of leak testing must
be used if leakage of the tubeside stream into the shell is not
tolerable.
References
[1] The ASME Boiler and Pressure Vessel Code, The American Society of Mechani-
Examining sectioned and polished mockup tubesheet speci- cal Engineers, New York. The current edition of the Code is the 2011 edition.
mens at magnifications of 24X using the VAX digital micro- The Code is published at two-year intervals.
scope can reveal weld quality, weld size conformity to [2] Standard for Power Plant Heat Exchangers, 4th ed., 2004, The Heat Exchange
specification and Code requirements. Illustrations showed how Institute, Cleveland, OH.
[3] Standards of the Tubular Exchanger Manufacturers Association, 9th ed., 2007,
such examination reveals tube/hole surface contact and lack The Tubular Exchanger Manufacturers Association, Tarrytown, NY.
thereof and penetration of deformed tube metal into annular [4] Standards for Closed Feedwater Heaters, 8th ed., 2008, The Heat Exchange
grooves. The VAX microscope allows much higher magnifica- Institute, Cleveland, OH.
tions to examine the specimen when there is suspicion of a [5] Directive 97/23/EC of the European Parliament.
[6] Yokell, S., 2007, “Hybrid Expansion Revisited,” ASME J. Pressure Vessel Tech-
potential indication. nol., 129, pp. 482–487.
The combination of applying appropriate nondestructive testing [7] Yokell, S., 2011, “Pressure Testing Feedwater Heaters and Power Plant Auxil-
methods and microscopic examination of sectioned mockup speci- iary Heat Exchangers,” ASME J. Pressure Vessel Technol., 133, 054502.

Journal of Pressure Vessel Technology DECEMBER 2012, Vol. 134 / 064502-7

Downloaded From: http://pressurevesseltech.asmedigitalcollection.asme.org/ on 10/10/2013 Terms of Use: http://asme.org/terms

S-ar putea să vă placă și