Item.
Description Qty. Unit Rate Amount in Rs.
No.

1.0 EXCAVATION

Excavation for foundation in all kinds of soil, dry or wet, hard or soft,
including all operation, complete with breaking clods, levelling,
dressing, dewatering, shoring & compacting. Include backfilling of
suitable excavated earth also with clean sand where required i/c
breaking clods, dressing, watering and consolidating by ramming in
layers not exceeding 8" depth to obtain compaction as per instruction
and specification of the Consultant and approval of Client (Site
Engineer)

1.1 For Pipe Supports Foundation 45.0 m3


1.2 For Pig Receiver Pad 6.5 m3
1.3 For Seperator V-101 Foundation 19.0 m3
1.4 For Seperator V-102 Foundation 19.0 m3

2.0 BACKFILLING

Backfilling from selected excavated materials (witin state limits or from


stockpile as designated place by engineer) lay in layers not exceeding
to 150mm, including loading, unloading, spreading and compaction as
per required in specifications, filling to embankments /general any
type structural and areas developing filling with suitable excavated
material / stockpile , debris etc. Works complete in all respect, as per
drawings specifications and as directed by the Engineer.; Earthfilling
spreading and compaction to achieve 95% of maximum dry
density(proctor's value)

2.1 For Pipe Supports Foundations 23.0 m3

3.0 DISPOSAL OF EXCESS EXCAVATED MATERIAL

Disposal including lifting, transportation & shifting of excess


excavated material outside the premises or as per instruction and
specification of the Consultant and approval of Client (Site Engineer)

3.1 For Pipe Supports Foundation 19.0 m3


3.2 For Pig Receiver Pad 4.0 m3
3.3 For Seperator V-101 Foundation 17.5 m3
3.4 For Seperator V-102 Foundation 17.5 m3

4.0 NON-SHRINKAGE GROUT

Supply & laying of 25 mm thk. non-shrinkage grout, having minimum


compressive strength of 40 N/mm2 in accordance with the Company
specification, standard drawings and etc.
4.1 For Pipe Supports Foundation 5.0 m2

5.0 PLAIN CEMENT CONCRETE


DOC. No. : 2738-CIV-BOQ-001
OIL AND GAS DEVELOPMENT COMPANY LTD. PREP. BY : BA
TIE-IN OF BITRISM & GUNDANWARI REV. : 0
AT AT SINJHORO PLANT DATE : 20-DEC-2017
BILL OF QUANTITIES
FOR CIVIL WORKS
Item.
Description Qty. Unit Rate Amount in Rs.
No.

Providing and laying Plain cement concrete of specified strength


using approved quality 3/4" max. size graded crushed aggregate &
fine aggregate including approved Steel formwork & its removal, all
operations of vibrating, levelling, compacting and curing etc. complete
as per specification & instruction of the Consultant.
Note:
1. Sulphate Resistant cement should be used for all works.
2. Mix design for each type of sample will be
provided by the Contractor

5.1 CC 1:4:8 (1 cement 4 sand and 8 coarse aggregate).

5.1.1 For Pipe Supports Foundation 3.5 m3


5.1.2 For Pig Receiver Pad 1.6 m3
5.1.3 For Seperator V-101 Foundation 4.1 m3
5.1.4 For Seperator V-102 Foundation 4.1 m3

6.0 REINFORCED CEMENT CONCRETE

Providing and laying Reinforced cement concrete shall be developed


28 days cylindrical strength of 3000psi specified, using approved
quality 3/4" max. size graded crushed aggregate & fine aggregate
including approved form work & its removal, all operations of
vibrating, levelling, compacting and curing etc complete but excluding
the cost of steel as per specification & instruction of the Consultant.
Note:
1. Sulphate Resistant cement should be used for all sub-strucure
works.
2. Mix design for each type of sample will be
provided by the Contractor

6.1 For Pipe Supports Foundation 20.0 m3


6.2 For Pig Receiver Pad 4.4 m3
6.3 For Seperator V-101 Foundation 18.0 m3
6.4 For Seperator V-102 Foundation 18.0 m3

7.0 STEEL REINFORCEMENT

Providing and laying hot rolled grade 460 steel reinforcement bars
complying with BS-4449) including the cost of straightening, cutting,
bending, binding, wastage and such overlaps as are not shown in
drawings, placing in position on cement concrete 1:2:4 precast spacer
block or M.S chairs, tying with binding wire (GI wire of 18 guage),
including cost of chairs and wires etc. in all kinds of RCC works.

60 Ksi Deformed Steel Rebars

7.1 For Pipe Supports Foundation 4.2 Tons


7.2 For Pig Receiver Pad 1.0 Tons
7.3 For Seperator V-101 Foundation 1.5 Tons
7.4 For Seperator V-102 Foundation 1.5 Tons
DOC. No. : 2738-CIV-BOQ-001
OIL AND GAS DEVELOPMENT COMPANY LTD. PREP. BY : BA
TIE-IN OF BITRISM & GUNDANWARI REV. : 0
AT AT SINJHORO PLANT DATE : 20-DEC-2017
BILL OF QUANTITIES
FOR CIVIL WORKS
Item.
Description Qty. Unit Rate Amount in Rs.
No.

8.0 STEEL EMBEDDED PARTS

Providing, fabricating and fixing of steel embedded parts in concrete


such as M.S plates/ Lugs/ grating/Split-end tangs/ Lifting Hooks/
Holding down/Anchor bolts/ H.D. bolts type C and Nuts etc. Complete
as per drawings, specifications and approval of Client.

Anchor Bolts/Lugs/MS Plates/Grating

8.1 For Pipe Supports foundation 0.8 Tons

9.0 STEEL STRUCTURE

Supply of material, fabrication, painting, erection, surface preparation


of steel structure for Platforms and Crossovers etc. Complete as per
drawings, specifications and approval of Client.

9.1 Steel Structure for Pipe Supports 1.50 Tons

NOTE:
The Quantities taken in this BOQ are estimated, only for bidding purpose. Contractor is responsible to estimate the quantities as per site
1
requirements, drawings & tender documents.

2 Contractor is responsible to add any missing / required item as per scope of works, drawings, specifications & Tender Documents.

3 Contractor is responsible to estimate the quantities before going to purchase the supply items.
DOC. No. : EC0484-01-BOQ-E-000901
Eni Pakistan Limited PREP. BY : BA
INSTALLATION OF SUCTION SCRUBBER REV. : B
NEAR BADHRA-09 RIG CAMP DATE : 09-FEB-2015
BILL OF QUANTITIES
CIVIL WORKS
Item.
Description Qty. Unit Rate Amount in Rs.
No.
1.0 DISMANTLING OF EXISTING STRUCTURE

Dismantling work of P.C.C, R.C.C and Steel Structures with


Embedded Parts (if any) and etc, including stacking of steel bars and
Rate only m3
disposal of unserviceable material lead as per direction of Engineer in
charge.

2.0 EXCAVATION

Excavation for foundation in all kinds of soil, dry or wet, hard or soft,
including all operation, complete with breaking clods, levelling,
dressing, dewatering, shoring & compacting. Include backfilling of
suitable excavated earth also with clean sand where required i/c
breaking clods, dressing, watering and consolidating by ramming in
35.0 m3
layers not exceeding 8" depth to obtain 95% modified AASHTO
density including lifting, shifting or disposing of surplus earth outside
the premises or as per instruction and specification of the Consultant
and approval of Client (Site Engineer).Contractor will carryout
compaction test as per specification with out any extra cost.

3.0 NON-SHRINKAGE GROUT

Supply & laying of 25 mm thk. non-shrinkage grout, having minimum


compressive strength of 40 N/mm2 in accordance with the Company
specification, standard drawings and etc.

3.1 Non-Shrinkage Grout (25mm Thk.) 9.2 m2

4.0 PLAIN CEMENT CONCRETE

Providing and laying Plain cement concrete of specified strength


using approved quality 3/4" max. size graded crushed aggregate &
fine aggregate including approved Steel formwork & its removal, all
operations of vibrating, levelling, compacting and curing etc. complete
as per specification & instruction of the Consultant.
Note:
1. SR cement should be used for all works.
2. Mix design for each type of sample will be
provided by the Contractor

4.1 CC 1:4:8 (1 cement 4 sand and 8 coarse aggregate). 7.7 m3

5.0 REINFORCED CEMENT CONCRETE

Providing and laying Reinforced cement concrete shall be developed


28 days cylindrical strength of 3750psi specified, using approved
quality 3/4" max. size graded crushed aggregate & fine aggregate
including approved form work & its removal, all operations of
vibrating, levelling, compacting and curing etc complete but excluding
the cost of steel as per specification & instruction of the Consultant.
Note:
1. SR cement should be used for all sub-strucure
works.
2. Mix design for each type of sample will be
provided by the Contractor

5.1 RCC 1:2:4 (1 cement 2 sand and 4 coarse aggregate). 43.0 m3


DOC. No. : EC0484-01-BOQ-E-000901
Eni Pakistan Limited PREP. BY : BA
INSTALLATION OF SUCTION SCRUBBER REV. : B
NEAR BADHRA-09 RIG CAMP DATE : 09-FEB-2015
BILL OF QUANTITIES
CIVIL WORKS
Item.
Description Qty. Unit Rate Amount in Rs.
No.
6.0 STEEL REINFORCEMENT

Providing and laying hot rolled grade 460 steel reinforcement bars
complying with BS-4449 including the cost of straightening, cutting,
bending, binding, wastage and such overlaps as are not shown in
drawings, placing in position on cement concrete 1:2:4 precast spacer
block or M.S chairs, tying with binding wire (GI wire of 18 guage),
including cost of chairs and wires etc. in all kinds of RCC works.

6.1 Deformed Steel 6.0 Tons

7.0 STEEL EMBEDDED PARTS

Providing, fabricating and fixing of steel embedded parts in concrete


such as M.S plates/ Lugs/ grating/Split-end tangs/ Lifting Hooks/
Holding down/Anchor bolts/ H.D. bolts type C and Nuts etc. Complete
as per drawings, specifications and approval of Client.

7.1 Anchor Bolts/Lugs/MS Plates/Grating 0.5 Tons

8.0 STEEL STRUCTURE

Supply of material, fabrication, painting, erection, surface preparation


of steel structure for Platforms and Crossovers etc. Complete as per
drawings, specifications and approval of Client.

8.1 Steel Structure for Pipe Supports 1.60 Tons

8.2 Steel Structure for Vent support structure 3.20 Tons