WEEKLY PROGRESS REPORT (CIVIL)


From :09/10/2016 To: 15/10/2016
Report No. 2
Project Title: Al Arida 132/33kv S/S
4400006058 Contractor: COGELEX GE
Weather: 37˚C Subcontractor: Al Shibel
Contract Sign: TCC: FAC:
Civil Completion (%) Plan: Actual:

Readiness & Equipment Erection Schedule


Location
Equipment
Ready for Equipment Delivered
NO. Equipment Location If Yes, Date If Yes, Date Erected at Site If Yes, Date Remarks
Erection at Site (Yes/No)
(Yes/No)
(Yes/No)
1 Basement No No No
2 132 kV GIS Room No No No
3 33/13.8 kV Switchgear Room No No No
4 Control Room No No No
5 Battery Room No No No
6 Power Transfo. Fnd. & Firewalls No No No
7 Auxilary Transfo. Fnd. & Firewalls No No No
8 Capacitor Bank Fnd. & Strc. No No No
9 Gantry Fnd. & Strc. No No No
10 Bus Bar, SA,CSE,PI Fnd.& Strc. No No No
11 Cable Trench & Ductbanks No No No

CIVIL & STRUCTURAL ACTIVITIES


Percentage %
NO. WORK DESCRIPTION Last This Compl Findings/Recommendations
week week eted
CIVIL ACTIVITIES FOR THIS WEEK
1 Concreting of isolated foundation at Control Room area 45% 55% 100% Done no findings and recommendation
2 Pouring of concrete screed prior for Water proofing membrane protection 35% 65% 100% Done no findings and recommendation
3 Reinforcement Placing and Binding of Tie-beam at control room area. 0% 45% 45% Inprogress
4 Reinforcement Placing and Binding of Raft foundation at Switch gear area and GIS Control Room 0% 25% 45% Inprogress
5 Cutting and Bar Bending of Rebar's at fabrication area prior for steel fixing 0% 25% 25% Inprogress
6 House Keeping is in progress 0% 0% 0% Inprogress
7
CIVIL ACTIVITIES PLANNED FOR NEXT WEEK
1 Concrete pouring for grade beam at control room area
2 Reinforcement Placing and Binding of Raft foundation at Switch gear area and GIS Control Room
3 Concrete pouring of Raft foundation at Switch gear area and GIS Control Room
4 Installation of grounding at control room area
5 House Keeping is in progress
MANPOWER & EQUIPMENT STATUS (DIRECT & INDIRECT)
Contractor Sat Sun Mon Tue Wed Thu Subcontractor Sat Sun Mon Tue Wed Thu
Project /Site Manager 1 1 1 1 1 1 Site manager 1 1 1 1 1 1
Project Engineer 0 0 0 0 0 0 Site Civil Engineer 1 1 1 1 1 1
Site Civil Engineer 0 0 0 0 0 0 Site Supervisor 1 1 1 1 1 1
QA/QC Civil Engineer 1 1 1 1 1 1 Surveyor 0 0 0 0 0 0 ###
QA/QC Electrical Engineer 0 0 0 0 0 0 Steel Fixer 12 12 12 12 12 12
Site Electrical Engineer 0 0 0 0 0 0 Carpenter 8 8 8 8 8 8
Mechanical/design Engineer 0 0 0 0 0 0 Labour 10 10 10 10 10 10 ###
Protection Engineer 0 0 0 0 0 0 Mason 4 4 4 4 4 4
Testing Engineer 0 0 0 0 0 0 Water proofing people 0 0 0 0 0 0
Safety Officer 0 0 0 0 0 0 Office Boy 1 1 1 1 1 1
Project Secretary 0 0 0 0 0 0 Driver/Equipment operator 2 2 2 2 2 2
Electrician/technician 0 0 0 0 0 0 Store keeper 1 1 1 1 1 1
Helper 0 0 0 0 0 0 Plumber 0 0 0 0 0 0

Page 1 of 2
Foreman 0 0 0 0 0 0 Electrician 2 2 2 2 2 2
Welder 0 0 0 0 0 0 Safety Officer 1 1 1 1 1 1
Site security 4 4 4 4 4 4 Civil foreman 1 1 1 1 1 1
Office boy 1 1 1 1 1 1 Welder 1 1 1 1 1 1
Store keeper 1 1 1 1 1 1 Document Controller 1 1 1 1 1 1 ###
Driver/Equipment operator
Total 8 8 8 8 8 8 Total 47 47 47 47 47 47

National Grid SA
Southern Projects Department
Civil & Electromechanical Projects Division South
Tel. 017-2319158, Fax: 017-2271020

Equipment Present In Use Equipment Present In Use


Road roller 0 0 Plate Compactor 1 0
Fuel Carrier 0 0 Steel cutting & bending machine 3 3
Excavator 0 0 Jumping compactor 0 0
Water Tanker 0 0 Trucks 1 1
Fork Lifter 0 0 Bob cat 0 0
Vibrator 3 0 Payloader 0 0
Hilty machine 0 0 TOTAL 5 4
SAFETY & SECURITY
QA/QC (RFI's/RMI's) 10
SITE INSTRUCTIONS 1