ENTIDAD : MUNICIPALIDAD DISTRITAL SANTA ROSA

PROYECTO : "FORTALECIMIENTO DE CAPACIDADES DE HIGIENE Y SANEAMIENTO BASICO EN LA IES CESAR VALLEJO-KUNURANA ALTO-SANTA ROSA"
REGION : PUNO
PROVINCIA : MELGAR
DISTRITO : SANTA ROSA
COSTO AL : DIC - 2009

Item Descripción Und.


CONSTRUCCION SERVICIO HIEGIENICO
01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m glb
02 OBRAS PRELIMINARES
02.01 LIMPIEZA DE TERRENO MANUAL m2
02.02 TRAZO NIVELACION Y REPLANTEO m2
03 MOVIMIENTO DE TIERRAS
03.01 EXCAVACION DE ZANJAS PARA ZAPATAS m3
03.02 EXCAVACION DE ZANJAS PARA CIMIENTOS m3
03.03 CORTE Y NIVELACION INTERIOR APISONADO MANUAL m2
03.04 RELLENO COMPACTADO MANUAL MATERIAL PROPIO m3
03.05 RELLENO COMPACTADO MANUAL- CON MATERIAL DE PRESTAMO m3
03.06 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3
04 OBRAS CONCRETO SIMPLE
04.01 SOLADOS PARA ZAPATAS 4" MEZCLA 1:2 CEMENTO HORMIGON m2
04.02 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA m3
04.03 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS m2
04.04 SOBRECIMIENTOS MEZCLA 1:8 CEMENTO HORMIGON +25%PM m3
05 OBRAS CONCRETO ARMADO
05.01 ZAPATAS
05.01.01 ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS kg
05.01.02 CONCRETO fc=210kg/cm2 EN ZAPATAS m3
05.02 COLUMNAS
05.02.01 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg
05.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2
05.02.03 CONCRETO f'c=210 kg/cm2 PARA COLUMNAS m3
05.03 VIGAS
05.03.01 ACERO ESTRUCTURAL TRABAJADO PARA VIGAS kg
05.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2
05.03.03 CONCRETO f'c=210 kg/cm2 PARA VIGAS m3
05.04 LOSAS ALIGERADAS
05.04.01 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS ALIGERADAS kg
05.04.02 ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADAS m2
05.04.03 LADRILLO HUECO DE ARCILLA 15X30X30 CM PARA TECHO ALIGERADO u
05.04.04 CONCRETO f'c=210 kg/cm2 PARA LOSAS ALIGERADAS m3
06 MUROS Y TABIQUES DE ALBAÑILERIA
06.01 MURO DE LADRILLO MECANIZADO 24X13X9 de cabeza m2
06.02 MURO DE LADRILLO MECANIZADO 24X13X9 de soga m2
07 REVOQUES ENLUCIDOS Y MOLDURAS
07.01 TARRAJEO INTERIOR MEZCLA C/A 1:5 m2
07.02 TARRAJEO EXTERIOR MEZCLA C/A 1:5 m2
07.03 TARRAJEO EN COLUMNAS MEZCLA C/A 1:5 SUPERFICIE m2
07.04 TARRAJEO EN VIGAS MEZCLA C/A 1:5 SUPERFICIE m2
07.05 VESTIDURA DE DERRAMES EN PUERTAS, VENTANAS Y VANOS m
08 CIELO RASOS
08.01 CIELO RASOS CON MEZCLA DE CEMENTO-ARENA 1:5 m2
09 VEREDAS DE CONCRETO
09.01 EXCAVACION PARA VEREDAS HASTA H=0.05M m2
09.02 VEREDA: EMPEDRADO m2
09.03 VEREDA: ENCOFRADO Y DESENCOFRADO m2
09.04 VEREDA: CONCRETO f´c=140kg/cm2 m2
09.05 VEREDA: JUNTA ASFALTICA m2
10 PISOS Y PAVIMENTOS
10.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2
10.02 PISO DE CERAMICO ANTIDEZLISANTE DE 40X40 COLOR DE 1RA m2
11 ZOCALOS
11.01 ZOCALO DE CERAMICO DE 20X30 cm DE 1RA m2
12 CARPINTERIA DE MADERA
12.01 PUERTAS APANELADA DE MADERA AGUANO m2
13 CARPINTERIA METALICA
13.01 VENTANA DE FIERRO PERFIL DE 1" X 1/8" FIJA +REF "T" DE 1" m2
13.02 PUERTA METALICA CONTRAPLACADA PARA BAÑOS INTERIORES m2
14 CERRAJERIA
14.01 BISAGRA ALUMINIZADA CAPUCHINA DE 3" X 3" pza
14.02 CERRADURA PARA PUERTA PRINCIPAL pza
15 VIDRIOS, CRISTALES Y SIMILARES
15.01 VIDRIO SIMPLE PROVISION Y COLOCACION EN VENTANAS DE FIERRO p2
15.02 ESPEJO p2
16 PINTURA
16.01 PINTURA EN CIELO RASOS AL LATEX m2
16.02 PINTADO DE MURO INTERIOR AL LATEX m2
16.03 PINTADO DE MURO EXTERIOR AL LATEX m2
16.04 PINTADO DE COLUMNAS AL LATEX m2
16.05 PINTADO DE VIGAS AL LATEX m2
16.06 PINTADO DE DERRAMES AL LATEX m2
17 INSTALACIONES ELECTRICAS
17.01 SALIDA PARA CENTROS DE LUZ pto
17.02 SALIDA PARA INTERRUPTORES BIPOLARES SIMPLES CON PVC pto
17.03 TABLEROS DISTRIBUCION u
17.04 FLUORESCENTECIRCULAR 32 W INCLUYE EQUIPO Y PANTALLA pza
18 APARATOS Y ACCESORIOS SANITARIOS
18.01 INODORO TURCO PARA BAÑOS pza
18.02 INODORO TANQUE BAJO BLANCO pza
18.03 LAVATORIOS DE PEDESTAL BLANCO pza
18.04 COLOCACION DE ACCESORIOS SANITARIOS pza
19 INSTALACIONES SANITARIAS
19.01 SISTEMA DE DESAGUE
19.01.01 SALIDA DE PVC PARA DESAGUE DE 2" pto
19.01.02 SALIDA DE PVC PARA DESAGUE DE 4" pto
19.01.03 SALIDA DE VENTILACION PVC SAL DE 2" pto
19.01.04 REGISTRO DE BRONCE 2" PROVISION Y COLOCACION u
19.01.05 SUMIDEROS DE 2" pza
19.01.06 CAJA DE REGISTRO DE DESAGUE 10" X 20" TAPA FºFº pza
19.02 SISTEMA DE AGUA FRIA
19.02.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" pto
19.02.02 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m
19.02.03 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" pza
19.02.04 CAJA DE REGISTRO DE AGUA 10" X 20" TAPA FºFº pza
20 PRUEBAS DE CONTROL DE CALIDAD
20.01 PRUEBA DE CONTROL DE CALIDAD DEL CONCRETO ( PRUEBA ALA COMPRESION u
21 FLETE
21.01 TRASPORTE DE VARIOS glb
22 PLACA RECORDATORIA
22.01 PLACA RECORDATORIA u

CONSTRUCCION TANQUE SEPTICO


01 OBRAS PRELIMINARES
01.01 LIMPIEZA DE TERRENO MANUAL m2
01.02 TRAZO NIVELACION Y REPLANTEO m2
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACION DE ZANJAS PARA ESTRUCTURAS m3
02.02 CORTE Y NIVELACION INTERIOR APISONADO MANUAL m2
02.03 RELLENO COMPACTADO MANUAL- CON MATERIAL DE PRESTAMO m3
02.04 ELIMINACION MATERIAL EXCEDENTE EN CARRETILLA (50 m) m3
02.05 RELLENO PARA POZO PERCOLADOR m3
03 OBRAS CONCRETO SIMPLE
03.01 SOLADOS DE 4" DE ESPESOR m2
03.02 MANPOSTERIA DE PIEDRA CON CONCRETO m2
04 OBRAS CONCRETO ARMADO
04.01 LOSAS MACISAS
04.01.01 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS MACIZAS kg
04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS m2
04.01.03 CONCRETO f'c=175 kg/cm2 PARA LOSAS MACIZAS m3
04.02 PLACAS
04.02.01 ACERO ESTRUCTURAL TRABAJADO PARA PLACAS kg
04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PLACAS m2
04.02.03 CONCRETO f'c=175 kg/cm2 PARA PLACAS m3
05 CARPINTERIA METALICA
05.01 TAPA METALICA u
06 INSTALACIONES SANITARIAS
06.01 SISTEMA DE DESAGUE
06.01.01 TUB. DE PVC DE 4" A TANQUE SEPTICO m
06.01.02 CAJA DE REGISTRO DE DESAGUE 10" X 20" TAPA FºFº pza
07 PRUEBAS DE CONTROL DE CALIDAD
07.01 PRUEBA DE CALIDAD SISTEMA DE DESAGUE glb
07.02 PRUEBA DE CONTROL DE CALIDAD DEL CONCRETO ( PRUEBA ALA COMPRESION u

COSTO DIRECTO
GASTOS GENERALES
GASTOS DE SUPERVISION
GASTOS DE LIQUIDACION
SUB TOTAL
PRESUPUESTO TOTAL
Metrado Precio (S/.) Parcial (S/.)

400.00
1.00 400.00 400.00
103.32
63.00 0.21 13.23
63.00 1.43 90.09
894.17
10.80 6.87 74.20
8.92 6.87 61.28
32.33 1.49 48.17
3.02 7.14 21.56
32.33 19.98 645.95
20.88 2.06 43.01
2,040.70
9.00 13.42 120.78
10.56 114.31 1,207.11
23.92 19.84 474.57
2.28 104.49 238.24
8,708.71
1,432.35
104.10 3.29 342.49
4.50 242.19 1,089.86
1,883.27
208.09 3.29 684.62
30.60 23.64 723.38
1.91 248.83 475.27
2,372.48
362.10 3.29 1,191.31
27.20 24.82 675.10
2.15 235.38 506.07
3,020.61
294.56 3.34 983.83
37.06 27.92 1,034.72
296.63 1.00 296.63
3.12 226.10 705.43
3,278.75
32.83 41.34 1,357.19
51.78 37.11 1,921.56
1,941.05
139.05 9.01 1,252.84
42.03 9.01 378.69
13.65 9.62 131.31
11.61 9.98 115.87
20.85 2.99 62.34
485.80
31.71 15.32 485.80
713.37
14.35 0.69 9.90
14.35 8.69 124.70
5.74 18.80 107.91
14.35 31.01 444.99
4.67 5.54 25.87
1,885.46
32.23 13.94 449.29
32.23 44.56 1,436.17
2,675.00
61.95 43.18 2,675.00
1,246.46
9.62 129.57 1,246.46
1,975.36
5.74 78.65 451.45
8.19 186.07 1,523.91
229.24
12.00 4.69 56.28
4.00 43.24 172.96
199.07
5.74 24.92 143.04
0.74 75.72 56.03
1,164.92
31.71 4.51 143.01
139.05 4.69 652.14
42.03 5.07 213.09
13.65 5.27 71.94
11.61 5.27 61.18
4.47 5.27 23.56
620.30
6.00 32.53 195.18
4.00 32.45 129.80
1.00 120.60 120.60
6.00 29.12 174.72
2,384.70
7.00 136.48 955.36
2.00 146.48 292.96
7.00 137.86 965.02
16.00 10.71 171.36
1,786.60
732.40
9.00 15.61 140.49
9.00 16.06 144.54
1.00 25.64 25.64
9.00 25.31 227.79
6.00 21.72 130.32
1.00 63.62 63.62
1,054.20
18.00 48.06 865.08
24.00 3.47 83.28
1.00 19.15 19.15
1.00 86.69 86.69
20.00
1.00 20.00 20.00
1,000.00
1.00 1,000.00 1,000.00
350.00
1.00 350.00 350.00

25.28
15.41 0.21 3.24
15.41 1.43 22.04
436.68
37.20 6.87 255.56
15.41 1.49 22.96
1.68 19.98 33.57
43.87 2.06 90.37
2.95 11.60 34.22
740.57
8.40 13.77 115.67
23.97 26.07 624.90
3,684.72
1,679.60
140.04 3.34 467.73
17.10 21.63 369.87
3.88 217.01 842.00
2,005.12
203.23 3.34 678.79
24.36 21.63 526.91
3.65 219.02 799.42
207.12
2.00 103.56 207.12
391.76
391.76
34.00 7.78 264.52
2.00 63.62 127.24
40.00
1.00 20.00 20.00
1.00 20.00 20.00

39,629.18
17.872739229 7,082.82
5.1426751702 2,038.00
3.1542413949 1,250.00
50,000.00
50,000.00
ENTIDAD : MUNICIPALIDAD DISTRITAL DE PEDRO VILCA APAZA
PROYECTO : CREACION DE COMPLEJO DEPORTIVO EN LA COMUNIDAD DE MAYAPUNCU DEL DISTRITO DE PEDRO VILCA APAZA-SAN ANTONIO DE PUTINA-PUNO
REGION : PUNO
PROVINCIA : SAN ANTONIO DE PUTINA
DISTRITO : PEDRO VILCA APAZA
COSTO AL : OCTUBRE DEL 2013

CRONOGRAMA DE DESEMBOLSOS
PRESUPUESTO
COSTO
PARTIDA DESCRIPCIÓN PARCIAL
UNIDAD METRADO UNITARIO
(2) (1) x (2)

01 CERCO PERIMETRICO 0.00 0.00 0.00 49,036.49

01.01 OBRAS PRELIMINARES 0.00 0.00 0.00 315.79

01.01.01 LIMPIEZA DE TERRENO MANUAL m2 120.30 0.33 39.70

01.01.02 TRAZO Y REPLANTEO m2 180.45 1.53 276.09

01.02 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 1,002.61

01.02.01 EXCAVACION DE ZANJAS PARA ZAPATAS m3 4.98 32.96 164.14

01.02.02 EXCAVACION DE ZANJAS PARA CIMIENTOS CORRIDOS m3 12.72 21.97 279.46

01.02.03 RELLENO CON MATERIAL DE PROPIO MANUAL m3 9.62 43.43 417.80

01.02.04 CARGUIO Y ELIMINACION DE MATERIAL EXEDENTE m3 16.25 8.69 141.21

01.03 OBRAS DE CONCRETO SIMPLE 0.00 0.00 0.00 8,720.13

01.03.01 SOLADO PARA ZAPATAS DE 3" MEZCLA 1:12 CEMENTO-HORMIGON m2 2.00 18.29 36.58

01.03.02 CONCRETO F'C=175 KG/CM2 EN CIMIENTOS ANCLAJE DE PARANTES DE CERCO m3 2.98 246.90 735.76

01.03.03 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA m3 21.50 153.58 3,301.97

01.03.04 SOBRECIMIENTOS MEZCLA 1:8 CEMENTO-HORMIGON 25% PM m3 7.78 187.36 1,457.66

01.03.05 ENCOFRADO Y DESENCOFRADO NORMAL m2 103.68 30.75 3,188.16

01.04 OBRAS DE CONCRETO ARMADO 0.00 0.00 0.00 1,754.61

01.04.01 ZAPATAS 0.00 0.00 0.00 286.98

01.04.01.01 ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS kg 18.90 4.70 88.83

01.04.01.02 CONCRETO F'C=210 KG/CM2. PARA ZAPATAS m3 0.80 247.69 198.15

01.04.02 COLUMNAS 0.00 0.00 0.00 1,025.02

01.04.02.01 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 64.50 4.77 307.67

01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 11.00 45.38 499.18

01.04.02.03 CONCRETO F'C=210 KG/CM2. PARA COLUMNAS m3 0.69 316.19 218.17

01.04.03 VIGAS 0.00 0.00 0.00 442.61

01.04.03.01 ACERO ESTRUCTURAL TRABAJADO PARA VIGAS kg 45.50 4.77 217.04

01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 4.20 26.94 113.15

01.04.03.03 CONCRETO F'C=210 KG/CM2. PARA VIGAS m3 0.46 244.40 112.42

01.05 REVOQUES ENLUCIDOS Y MOLDURAS 0.00 0.00 0.00 2,337.18

01.05.01 TARRAJEO DE SUPERFICIE DE COLUMNAS Y VIGAS CON CEMENTO ARENA m2 118.88 19.66 2,337.18
ENTIDAD : MUNICIPALIDAD DISTRITAL DE PEDRO VILCA APAZA
PROYECTO : CREACION DE COMPLEJO DEPORTIVO EN LA COMUNIDAD DE MAYAPUNCU DEL DISTRITO DE PEDRO VILCA APAZA-SAN ANTONIO DE PUTINA-PUNO
REGION : PUNO
PROVINCIA : SAN ANTONIO DE PUTINA
DISTRITO : PEDRO VILCA APAZA
COSTO AL : OCTUBRE DEL 2013

CRONOGRAMA DE DESEMBOLSOS
PRESUPUESTO
COSTO
PARTIDA DESCRIPCIÓN PARCIAL
UNIDAD METRADO UNITARIO
(2) (1) x (2)
01.06 CARPINTERIA METALICA 0.00 0.00 0.00 33,361.91

01.06.01 MALLA OLIMPICA METALICA INCLUIDO ACABADOS TIPO I und 35.00 888.05 31,081.75

01.06.02 PUERTA METALICA SEGUN DISEÑO PARA ACCESO PRINCIPAL und 1.00 2,280.16 2,280.16

01.07 CERRAJERIA 0.00 0.00 0.00 171.20

01.07.01 CERRADURA PARA PUERTA PRINCIPAL PESADA und 2.00 85.60 171.20

01.08 PINTURA 0.00 0.00 0.00 1,373.06

01.08.01 PINTURA EN SUPERFICIE DE COLUMNAS Y VIGAS INTERIOR Y EXTERIOR CON LATEX LAVABLE 02 MANOS m2 118.88 11.55 1,373.06

02 CANCHA SINTETICO 0.00 0.00 0.00 113,753.00

02.01 OBRAS PRELIMINARES 0.00 0.00 0.00 255.75

02.01.01 LIMPIEZA DE TERRENO MANUAL m2 775.00 0.33 255.75

02.02 TRAZO NIVELACION Y REPLANTEO 0.00 0.00 0.00 682.00

02.02.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 775.00 0.88 682.00

02.03 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 16,466.51

02.03.01 CORTE DE MATERIAL SUELTO RENDIMIENTO=460 M3/DIA m3 480.00 3.06 1,468.80

02.03.02 RELLENO CON MATERIAL DE PRESTAMO CON MAQUINARIA m3 60.00 18.77 1,126.20

02.03.03 RELLENO CON MATERIAL SELECCIONADO GRAVA m3 159.00 31.19 4,959.21

02.03.04 RELLENO CON MATERIAL HORMIGON m3 60.00 33.02 1,981.20

02.03.05 RELLENO CON MATERIAL ARENA GRUESA m3 60.00 34.19 2,051.40

02.03.06 RELLENO CON MATERIAL SELECCIONADO Y HORMIGON m3 30.00 55.74 1,672.20

02.03.07 ELIMINACION DE MATERIAL EXCEDENTE (CARGUIO Y TRANSPORTE) m3 600.00 3.77 2,262.00

02.03.08 NIVELACION INTERIOR Y COMPACTADO m2 775.00 1.22 945.50

02.04 PISOS Y PAVIMENTOS 0.00 0.00 0.00 76,578.00

02.04.01 CANCHA DE CESPED SINTETICO m2 600.00 127.63 76,578.00

02.05 VEREDAS 0.00 0.00 0.00 4,558.62

02.05.01 VEREDA DE CONCRETO F'C= 140 KG/CM2. ACAB. FROTACH. BRUÑADO m2 104.00 31.87 3,314.48

02.05.02 VEREDA:ENCOFRADO Y DESENCOFRADO m2 26.05 30.32 789.84

02.05.03 JUNTAS DE DILATACION CON ASFALTO E=1" m 35.00 12.98 454.30

02.06 INSTALACIONES SANITARIAS 0.00 0.00 0.00 7,869.68

02.06.01 SISTEMA DE DRENAJE 0.00 0.00 0.00 7,869.68

02.06.01.01 TUBERIA PVC DIAM. 4" C-7.5 m 120.00 22.73 2,727.60


ENTIDAD : MUNICIPALIDAD DISTRITAL DE PEDRO VILCA APAZA
PROYECTO : CREACION DE COMPLEJO DEPORTIVO EN LA COMUNIDAD DE MAYAPUNCU DEL DISTRITO DE PEDRO VILCA APAZA-SAN ANTONIO DE PUTINA-PUNO
REGION : PUNO
PROVINCIA : SAN ANTONIO DE PUTINA
DISTRITO : PEDRO VILCA APAZA
COSTO AL : OCTUBRE DEL 2013

CRONOGRAMA DE DESEMBOLSOS
PRESUPUESTO
COSTO
PARTIDA DESCRIPCIÓN PARCIAL
UNIDAD METRADO UNITARIO
(2) (1) x (2)
02.06.01.02 TUBERIA PVC DIAM. 2" C-7.5 m 64.00 10.67 682.88

02.06.01.03 TUBERIA PVC DIAM. 3" C-7.5 CRIBADO m 320.00 11.51 3,683.20

02.06.01.04 CAJA DE REGISTRO DE 24" X 24" und 8.00 97.00 776.00

02.08 PINTURA Y VARIOS 0.00 0.00 0.00 1,017.05

02.08.01 PINTURA ESMALTE EN EN CANCHA DE GRAS SINTETICO m 171.26 3.39 580.57

02.08.02 ARCO DE Fº Fº DE 3" und 2.00 218.24 436.48

02.08 GRADERIOS DE CONCRETO 0.00 0.00 0.00 6,325.39

02.08.01 OBRAS PRELIMINARES 0.00 0.00 0.00 72.60

02.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 60.00 0.33 19.80

02.08.01.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 60.00 0.88 52.80

02.08.02 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 1,922.58

02.08.02.01 EXCAVACION DE ZANJAS PARA GRADERIO m3 18.00 21.97 395.46

02.08.02.02 EMPEDRADO PARA GRADERIO m3 43.20 35.35 1,527.12

02.08.03 OBRAS DE CONCRETO SIMPLE 0.00 0.00 0.00 2,921.77

02.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 52.20 20.90 1,090.98

02.08.03.02 CONCRETO 1:10 +30% P.G. PARA GRADERIO m3 13.00 140.83 1,830.79

02.08.04 REVOQUES ENLUCIDOS Y MOLDURAS 0.00 0.00 0.00 736.23

02.08.04.01 TARRAJEO DE SUPERF DE GRADERIO CON MEZCLA DE CEMENTO ARENA m2 58.20 12.65 736.23

02.08.05 PINTURA 0.00 0.00 0.00 672.21

02.08.05.01 PINTADO DE GRADERIO CON PINTURA ESMALTE m2 58.20 11.55 672.21

03 OBRAS COMPLEMENTARIAS 0.00 0.00 0.00 4,319.50

03.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40M X 3.60M. glb 1.00 3,500.00 3,500.00

03.01.02 FLETE TERRESTRE TOTAL und 1.00 819.50 819.50

0.00 0.00 0.00 0.00 0.00 0.00

0.00 COSTO DIRECTO 0.00 0.00 0.00 167,108.99

0.00 GASTOS GENERALES 0.00 0.00 0.00 13,368.72

0.00 GASTOS SUPERVISION 0.00 0.00 0.00 5,013.27

0.00 GASTOS DE LIQUIDACION 0.00 0.00 0.00 1,336.87

0.00 GASTOS DE PREINVERSION 0.00 0.00 0.00 3,007.96

0.00 COSTO GG+GS+GL+GP 0.00 0.00 0.00 22,726.82


ENTIDAD : MUNICIPALIDAD DISTRITAL DE PEDRO VILCA APAZA
PROYECTO : CREACION DE COMPLEJO DEPORTIVO EN LA COMUNIDAD DE MAYAPUNCU DEL DISTRITO DE PEDRO VILCA APAZA-SAN ANTONIO DE PUTINA-PUNO
REGION : PUNO
PROVINCIA : SAN ANTONIO DE PUTINA
DISTRITO : PEDRO VILCA APAZA
COSTO AL : OCTUBRE DEL 2013

CRONOGRAMA DE DESEMBOLSOS
PRESUPUESTO
COSTO
PARTIDA DESCRIPCIÓN PARCIAL
UNIDAD METRADO UNITARIO
(2) (1) x (2)
0.00 COSTO TOTAL DE OBRA 0.00 0.00 0.00 189,835.81
0.00 PORCENTAJE DE AVANCE MENSUAL 0.00 0.00 0.00 0.00
0.00 PORCENTAJE DE AVANCE ACUMULADO 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
NOGRAMA DE DESEMBOLSOS

MES 1 MES 2
PARCIAL PARCIAL
S/. S/.

0.00 0.00

0.00 0.00

39.70 0.00

276.09 0.00

0.00 0.00

164.14 0.00

279.46 0.00

417.80 0.00

141.21 0.00

0.00 0.00

36.58 0.00

735.76 0.00

3,301.97 0.00

1,457.66 0.00

3,188.16 0.00

0.00 0.00

0.00 0.00

88.83 0.00

198.15 0.00

0.00 0.00

307.67 0.00

499.18 0.00

218.17 0.00

0.00 0.00

217.04 0.00

113.15 0.00

112.42 0.00

0.00 0.00

2,337.18 0.00
NOGRAMA DE DESEMBOLSOS

MES 1 MES 2
PARCIAL PARCIAL
S/. S/.
0.00 0.00

31,081.75 0.00

0.00 2,280.16

0.00 0.00

0.00 171.20

0.00 0.00

0.00 1,373.06

0.00 0.00

0.00 0.00

255.75 0.00

0.00 0.00

682.00 0.00

0.00 0.00

1,468.80 0.00

1,126.20 0.00

4,959.21 0.00

1,981.20 0.00

2,051.40 0.00

1,672.20 0.00

2,262.00 0.00

945.50 0.00

0.00 0.00

0.00 76,578.00

0.00 0.00

3,314.48 0.00

789.84 0.00

454.30 0.00

0.00 0.00

0.00 0.00

2,727.60 0.00
NOGRAMA DE DESEMBOLSOS

MES 1 MES 2
PARCIAL PARCIAL
S/. S/.
682.88 0.00

3,683.20 0.00

776.00 0.00

0.00 0.00

0.00 580.57

0.00 436.48

0.00 0.00

0.00 0.00

0.00 19.80

0.00 52.80

0.00 0.00

0.00 395.46

0.00 1,527.12

0.00 0.00

0.00 1,090.98

0.00 1,830.79

0.00 0.00

0.00 736.23

0.00 0.00

0.00 672.21

0.00 0.00

3,500.00 0.00

819.50 0.00

0.00 0.00

79,364.13 87,744.86

6,349.13 7,019.59

2,380.92 2,632.35

0.00 0.00

3,007.96 0.00

0.00 0.00
NOGRAMA DE DESEMBOLSOS

MES 1 MES 2
PARCIAL PARCIAL
S/. S/.
0.00 0.00
0.47 0.53
0.47 1.00
0.00 0.00
0.00 0.00
ENTIDAD : MUNICIPALIDAD DISTRITAL DE PEDRO VILCA APAZA
PROYECTO : CREACION DE COMPLEJO DEPORTIVO EN LA COMUNIDAD DE MAYAPUNCU DEL DISTRITO DE PEDRO VILCA APAZA-SAN ANTONIO DE PUTINA-PUNO
REGION : PUNO
PROVINCIA : SAN ANTONIO DE PUTINA
DISTRITO : PEDRO VILCA APAZA
COSTO AL : OCTUBRE DEL 2013

CALENDARIO DE AVANCE DE OBRA VALORIZADO


PRESUPUESTO
MES 1 MES 2
COSTO
PARTIDA DESCRIPCIÓN UNITARIO
PARCIAL
UNIDAD METRADO PARCIAL PARCIAL
METRADO % METRADO % METRADO
(2) (1) x (2) S/. S/.

01 CERCO PERIMETRICO 49,036.49

01.01 OBRAS PRELIMINARES 315.79

01.01.01 LIMPIEZA DE TERRENO MANUAL m2 120.30 0.33 39.70 120.30 39.70 100.00% 0.00 0.00 120.30

01.01.02 TRAZO Y REPLANTEO m2 180.45 1.53 276.09 180.45 276.09 100.00% 0.00 0.00 180.45

01.02 MOVIMIENTO DE TIERRAS 1,002.61 0.00 0.00 0.00

01.02.01 EXCAVACION DE ZANJAS PARA ZAPATAS m3 4.98 32.96 164.14 4.98 164.14 100.00% 0.00 0.00 4.98

01.02.02 EXCAVACION DE ZANJAS PARA CIMIENTOS CORRIDOS m3 12.72 21.97 279.46 12.72 279.46 100.00% 0.00 0.00 12.72

01.02.03 RELLENO CON MATERIAL DE PROPIO MANUAL m3 9.62 43.43 417.80 9.62 417.80 100.00% 0.00 0.00 9.62

01.02.04 CARGUIO Y ELIMINACION DE MATERIAL EXEDENTE m3 16.25 8.69 141.21 16.25 141.21 100.00% 0.00 0.00 16.25

01.03 OBRAS DE CONCRETO SIMPLE 8,720.13 0.00 0.00 0.00

01.03.01 SOLADO PARA ZAPATAS DE 3" MEZCLA 1:12 CEMENTO-HORMIGON m2 2.00 18.29 36.58 2.00 36.58 100.00% 0.00 0.00 2.00

01.03.02 CONCRETO F'C=175 KG/CM2 EN CIMIENTOS ANCLAJE DE PARANTES DE CERCO m3 2.98 246.90 735.76 2.98 735.76 100.00% 0.00 0.00 2.98

01.03.03 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA m3 21.50 153.58 3,301.97 21.50 3,301.97 100.00% 0.00 0.00 21.50

01.03.04 SOBRECIMIENTOS MEZCLA 1:8 CEMENTO-HORMIGON 25% PM m3 7.78 187.36 1,457.66 7.78 1,457.66 100.00% 0.00 0.00 7.78

01.03.05 ENCOFRADO Y DESENCOFRADO NORMAL m2 103.68 30.75 3,188.16 103.68 3,188.16 100.00% 103.68

01.04 OBRAS DE CONCRETO ARMADO 1,754.61 0.00 0.00 0.00 0.00 0.00

01.04.01 ZAPATAS 286.98 0.00 0.00 0.00 0.00 0.00

01.04.01.01 ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS kg 18.90 4.70 88.83 18.90 88.83 100.00% 18.90

01.04.01.02 CONCRETO F'C=210 KG/CM2. PARA ZAPATAS m3 0.80 247.69 198.15 0.80 198.15 100.00% 0.00 0.00 0.80

01.04.02 COLUMNAS 1,025.02 0.00 0.00 0.00 0.00 0.00

01.04.02.01 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS kg 64.50 4.77 307.67 64.50 307.67 100.00% 64.50

01.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 11.00 45.38 499.18 11.00 499.18 100.00% 0.00 0.00 11.00

01.04.02.03 CONCRETO F'C=210 KG/CM2. PARA COLUMNAS m3 0.69 316.19 218.17 0.69 218.17 100.00% 0.00 0.00 0.69

01.04.03 VIGAS 442.61 0.00 0.00 0.00 0.00 0.00

01.04.03.01 ACERO ESTRUCTURAL TRABAJADO PARA VIGAS kg 45.50 4.77 217.04 45.50 217.04 100.00% 45.50

01.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 4.20 26.94 113.15 4.20 113.15 100.00% 0.00 0.00 4.20

01.04.03.03 CONCRETO F'C=210 KG/CM2. PARA VIGAS m3 0.46 244.40 112.42 0.46 112.42 100.00% 0.00 0.00 0.46

01.05 REVOQUES ENLUCIDOS Y MOLDURAS 2,337.18 0.00 0.00 0.00 0.00 0.00

01.05.01 TARRAJEO DE SUPERFICIE DE COLUMNAS Y VIGAS CON CEMENTO ARENA m2 118.88 19.66 2,337.18 118.88 2,337.18 100.00% 0.00 0.00 118.88

01.06 CARPINTERIA METALICA 33,361.91 0.00 0.00 0.00 0.00 0.00

01.06.01 MALLA OLIMPICA METALICA INCLUIDO ACABADOS TIPO I und 35.00 888.05 31,081.75 35.00 31,081.75 100.00% 0.00 0.00 35.00

01.06.02 PUERTA METALICA SEGUN DISEÑO PARA ACCESO PRINCIPAL und 1.00 2,280.16 2,280.16 0.00 0.00 1.00 2,280.16 100.00% 1.00

01.07 CERRAJERIA 171.20 0.00 0.00 0.00

01.07.01 CERRADURA PARA PUERTA PRINCIPAL PESADA und 2.00 85.60 171.20 0.00 0.00 2.00 171.20 100.00% 2.00

01.08 PINTURA 1,373.06 0.00 0.00 0.00 0.00 0.00


ENTIDAD : MUNICIPALIDAD DISTRITAL DE PEDRO VILCA APAZA
PROYECTO : CREACION DE COMPLEJO DEPORTIVO EN LA COMUNIDAD DE MAYAPUNCU DEL DISTRITO DE PEDRO VILCA APAZA-SAN ANTONIO DE PUTINA-PUNO
REGION : PUNO
PROVINCIA : SAN ANTONIO DE PUTINA
DISTRITO : PEDRO VILCA APAZA
COSTO AL : OCTUBRE DEL 2013

CALENDARIO DE AVANCE DE OBRA VALORIZADO


PRESUPUESTO
MES 1 MES 2
COSTO
PARTIDA DESCRIPCIÓN UNITARIO
PARCIAL
UNIDAD METRADO PARCIAL PARCIAL
METRADO % METRADO % METRADO
(2) (1) x (2) S/. S/.

01.08.01 PINTURA EN SUPERFICIE DE COLUMNAS Y VIGAS INTERIOR Y EXTERIOR CON LATEX LAVABLE 02 MANOS m2 118.88 11.55 1,373.06 0.00 0.00 118.88 1,373.06 100.00% 118.88

02 CANCHA SINTETICO 113,753.00 0.00 0.00 0.00

02.01 OBRAS PRELIMINARES 255.75 0.00 0.00 0.00 0.00 0.00

02.01.01 LIMPIEZA DE TERRENO MANUAL m2 775.00 0.33 255.75 775.00 255.75 100.00% 0.00 0.00 775.00

02.02 TRAZO NIVELACION Y REPLANTEO 682.00 0.00 0.00 0.00 0.00 0.00

02.02.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 775.00 0.88 682.00 775.00 682.00 100.00% 0.00 0.00 775.00

02.03 MOVIMIENTO DE TIERRAS 16,466.51 0.00 0.00 0.00

02.03.01 CORTE DE MATERIAL SUELTO RENDIMIENTO=460 M3/DIA m3 480.00 3.06 1,468.80 480.00 1,468.80 100.00% 0.00 0.00 480.00

02.03.02 RELLENO CON MATERIAL DE PRESTAMO CON MAQUINARIA m3 60.00 18.77 1,126.20 60.00 1,126.20 100.00% 0.00 0.00 60.00

02.03.03 RELLENO CON MATERIAL SELECCIONADO GRAVA m3 159.00 31.19 4,959.21 159.00 4,959.21 100.00% 0.00 0.00 159.00

02.03.04 RELLENO CON MATERIAL HORMIGON m3 60.00 33.02 1,981.20 60.00 1,981.20 100.00% 0.00 0.00 60.00

02.03.05 RELLENO CON MATERIAL ARENA GRUESA m3 60.00 34.19 2,051.40 60.00 2,051.40 100.00% 0.00 0.00 60.00

02.03.06 RELLENO CON MATERIAL SELECCIONADO Y HORMIGON m3 30.00 55.74 1,672.20 30.00 1,672.20 100.00% 0.00 0.00 30.00

02.03.07 ELIMINACION DE MATERIAL EXCEDENTE (CARGUIO Y TRANSPORTE) m3 600.00 3.77 2,262.00 600.00 2,262.00 100.00% 0.00 0.00 600.00

02.03.08 NIVELACION INTERIOR Y COMPACTADO m2 775.00 1.22 945.50 775.00 945.50 100.00% 0.00 0.00 775.00

02.04 PISOS Y PAVIMENTOS 76,578.00 0.00 0.00 0.00

02.04.01 CANCHA DE CESPED SINTETICO m2 600.00 127.63 76,578.00 0.00 0.00 600.00 76,578.00 100.00% 600.00

02.05 VEREDAS 4,558.62 0.00 0.00 0.00

02.05.01 VEREDA DE CONCRETO F'C= 140 KG/CM2. ACAB. FROTACH. BRUÑADO m2 104.00 31.87 3,314.48 104.00 3,314.48 100.00% 0.00 0.00 104.00

02.05.02 VEREDA:ENCOFRADO Y DESENCOFRADO m2 26.05 30.32 789.84 26.05 789.84 100.00% 0.00 0.00 26.05

02.05.03 JUNTAS DE DILATACION CON ASFALTO E=1" m 35.00 12.98 454.30 35.00 454.30 100.00% 0.00 0.00 35.00

02.06 INSTALACIONES SANITARIAS 7,869.68 0.00 0.00 0.00 0.00 0.00

02.06.01 SISTEMA DE DRENAJE 7,869.68 0.00 0.00 0.00 0.00 0.00

02.06.01.01 TUBERIA PVC DIAM. 4" C-7.5 m 120.00 22.73 2,727.60 120.00 2,727.60 100.00% 0.00 0.00 120.00

02.06.01.02 TUBERIA PVC DIAM. 2" C-7.5 m 64.00 10.67 682.88 64.00 682.88 100.00% 0.00 0.00 64.00

02.06.01.03 TUBERIA PVC DIAM. 3" C-7.5 CRIBADO m 320.00 11.51 3,683.20 320.00 3,683.20 100.00% 0.00 0.00 320.00

02.06.01.04 CAJA DE REGISTRO DE 24" X 24" und 8.00 97.00 776.00 8.00 776.00 100.00% 0.00 0.00 8.00

02.08 PINTURA Y VARIOS 1,017.05 0.00 0.00 0.00 0.00 0.00

02.08.01 PINTURA ESMALTE EN EN CANCHA DE GRAS SINTETICO m 171.26 3.39 580.57 171.26 580.57 100.00% 171.26

02.08.02 ARCO DE Fº Fº DE 3" und 2.00 218.24 436.48 0.00 0.00 2.00 436.48 100.00% 2.00

02.08 GRADERIOS DE CONCRETO 6,325.39 0.00 0.00

02.08.01 OBRAS PRELIMINARES 72.60 0.00 0.00

02.08.01.01 LIMPIEZA DE TERRENO MANUAL m2 60.00 0.33 19.80 60.00 19.80 100.00% 60.00

02.08.01.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 60.00 0.88 52.80 60.00 52.80 100.00% 60.00

02.08.02 MOVIMIENTO DE TIERRAS 1,922.58 0.00 0.00


ENTIDAD : MUNICIPALIDAD DISTRITAL DE PEDRO VILCA APAZA
PROYECTO : CREACION DE COMPLEJO DEPORTIVO EN LA COMUNIDAD DE MAYAPUNCU DEL DISTRITO DE PEDRO VILCA APAZA-SAN ANTONIO DE PUTINA-PUNO
REGION : PUNO
PROVINCIA : SAN ANTONIO DE PUTINA
DISTRITO : PEDRO VILCA APAZA
COSTO AL : OCTUBRE DEL 2013

CALENDARIO DE AVANCE DE OBRA VALORIZADO


PRESUPUESTO
MES 1 MES 2
COSTO
PARTIDA DESCRIPCIÓN UNITARIO
PARCIAL
UNIDAD METRADO PARCIAL PARCIAL
METRADO % METRADO % METRADO
(2) (1) x (2) S/. S/.

02.08.02.01 EXCAVACION DE ZANJAS PARA GRADERIO m3 18.00 21.97 395.46 18.00 395.46 100.00% 18.00

02.08.02.02 EMPEDRADO PARA GRADERIO m3 43.20 35.35 1,527.12 43.20 1,527.12 100.00% 43.20

02.08.03 OBRAS DE CONCRETO SIMPLE 2,921.77 0.00 0.00

02.08.03.01 ENCOFRADO Y DESENCOFRADO NORMAL m2 52.20 20.90 1,090.98 52.20 1,090.98 100.00% 52.20

02.08.03.02 CONCRETO 1:10 +30% P.G. PARA GRADERIO m3 13.00 140.83 1,830.79 13.00 1,830.79 100.00% 13.00

02.08.04 REVOQUES ENLUCIDOS Y MOLDURAS 736.23 0.00 0.00

02.08.04.01 TARRAJEO DE SUPERF DE GRADERIO CON MEZCLA DE CEMENTO ARENA m2 58.20 12.65 736.23 58.20 736.23 100.00% 58.20

02.08.05 PINTURA 672.21 0.00 0.00

02.08.05.01 PINTADO DE GRADERIO CON PINTURA ESMALTE m2 58.20 11.55 672.21 58.20 672.21 100.00% 58.20

03 OBRAS COMPLEMENTARIAS 4,319.50 0.00 0.00 0.00 0.00 0.00

03.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40M X 3.60M. glb 1.00 3,500.00 3,500.00 1.00 3,500.00 100.00% 0.00 0.00 1.00

03.01.02 FLETE TERRESTRE TOTAL und 1.00 819.50 819.50 1.00 819.50 100.00% 0.00 0.00 1.00

COSTO DIRECTO S/. 167,108.99 S/. 79,364.13 S/. 87,744.86

GASTOS GENERALES S/. 13,368.72 S/. 6,349.13 S/. 7,019.59

GASTOS SUPERVISION S/. 5,013.27 S/. 2,380.92 S/. 2,632.35

GASTOS DE LIQUIDACION S/. 1,336.87

GASTOS DE PREINVERSION S/. 3,007.96 S/. 3,007.96

COSTO GG+GS+GL+GP S/. 22,726.82 S/. 0.00

COSTO TOTAL DE OBRA S/. 189,835.81 S/. 0.00

PORCENTAJE DE AVANCE MENSUAL 47.49% 52.51%

PORCENTAJE DE AVANCE ACUMULADO 47.49% 100.00%


CE DE OBRA VALORIZADO
SUMATORIA
PARCIAL
%
S/.

39.70 100.00%

276.09 100.00%

0.00 0.00%

164.14 100.00%

279.46 100.00%

417.80 100.00%

141.21 100.00%

0.00 0.00%

36.58 100.00%

735.76 100.00%

3,301.97 100.00%

1,457.66 100.00%

3,188.16 100.00%

0.00 0.00%

0.00 0.00%

88.83 100.00%

198.15 100.00%

0.00 0.00%

307.67 100.00%

499.18 100.00%

218.17 100.00%

0.00 0.00%

217.04 100.00%

113.15 100.00%

112.42 100.00%

0.00 0.00%

2,337.18 100.00%

0.00 0.00%

31,081.75 100.00%

2,280.16 100.00%

0.00 0.00%

171.20 100.00%

0.00 0.00%
CE DE OBRA VALORIZADO
SUMATORIA
PARCIAL
%
S/.

1,373.06 100.00%

0.00 0.00%

0.00 0.00%

255.75 100.00%

0.00 0.00%

682.00 100.00%

0.00 0.00%

1,468.80 100.00%

1,126.20 100.00%

4,959.21 100.00%

1,981.20 100.00%

2,051.40 100.00%

1,672.20 100.00%

2,262.00 100.00%

945.50 100.00%

0.00 0.00%

76,578.00 100.00%

0.00 0.00%

3,314.48 100.00%

789.84 100.00%

454.30 100.00%

0.00 0.00%

0.00 0.00%

2,727.60 100.00%

682.88 100.00%

3,683.20 100.00%

776.00 100.00%

0.00 0.00%

580.57 100.00%

436.48 100.00%

0.00 0.00%

0.00 0.00%

19.80 100.00%

52.80 100.00%

0.00 0.00%
CE DE OBRA VALORIZADO
SUMATORIA
PARCIAL
%
S/.

395.46 100.00%

1,527.12 100.00%

0.00 0.00%

1,090.98 100.00%

1,830.79 100.00%

0.00 0.00%

736.23 100.00%

0.00 0.00%

672.21 100.00%

0.00 0.00%

3,500.00 100.00%

819.50 100.00%

S/. 167,108.99

S/. 13,368.72

S/. 5,013.27

S/. 1,336.87

S/. 3,007.96

S/. 0.00

100.00%

100.00%
ENTIDAD : MUNICIPALIDAD DISTRITAL DE PEDRO VILCA APAZA
PROYECTO : CREACION DE COMPLEJO DEPORTIVO EN LA COMUNIDAD DE MAYAPUNCU DEL DISTRITO DE PEDRO VILCA APAZA-SAN ANTON
REGION : PUNO
PROVINCIA : SAN ANTONIO DE PUTINA
DISTRITO : PEDRO VILCA APAZA
COSTO AL : OCTUBRE DEL 2013
O DE PEDRO VILCA APAZA-SAN ANTONIO DE PUTINA-PUNO

S-ar putea să vă placă și