Documente Academic
Documente Profesional
Documente Cultură
Team 5
One of the methods of lean manufacturing focused on waste reduction is setup reduction, a
process of reducing changeover time. A changeover time is the process of converting a line or machine
from running one product to another (i.e. from the last good piece of the previous run to the first good
piece of the next run) and will involve tool changes, usually carried out by an operator, to meet the
fabrication specifications of the product to be produced. Many manufacturing companies have become
champions in setup reduction by completing automating the changeover process and planning production
schedules accordingly to minimize the number of changeovers required. The intent of this laboratory
assignment is to understand the inefficiency introduced when waste is incurred by unnecessary tooling
changeovers and operator movement. Analyzing how waste can be reduced which can reduce lead time
and improve productivity.
A single team member will conduct a time study analysis on the other team members that conduct
several specific jobs such as parts assembly, walking to the station, operating 3 metal checkers machines,
etc. The jobs will be closely noted as it will be the main objective of this lab to improve the operation by
reducing the Non-Value Adding time. With close observation, inefficiencies can be clearly exposed and it
can be focused on to improve the whole process.
Lab Objectives
The main objective for this lab is to analyze a multiple operation process and determine
innovative solutions to reduce waste and implement lean manufacturing. This main objective can be
achieved by doing several steps below:
● Identify different phases of the setup, and determine which phase is a value adding (VA) or non-
value adding (NVA)
● Focus to improve the NVA phases
● Apply lean methodologies to understand the eight types wastes of lean
Data
Discussion
The team worked on 3 machines, which was the machine 1 that runs program 5656, machine 2
that runs program 5757 and machine 3 which is a 3-axis turning center that runs CNC program. Machine
1 and 2 are identical, however, the program 5656 and 5757 are slightly different. Program 5656 will finish
the end-mill and carving processes for each checkers before moving on to another one, while program
5757 will finish the end-mill carving processes for all four checkers before moving to the carving
processes for all 4 checkers again. The team gathered the data and analyzed the time difference with each
machine. Using the data gathered, the team are able to come up with potential improvements for each
machine setup.
Table 2. Original time for machine with 5656 programs
Operation Operation Machine Value Time
No. Status Added (Minutes:Second)
Total Number of 7 6
operations
Number of NVA 6 5
operations
Number of VA operations 1 1
Total Number of 7 6
operations
Number of NVA 6 5
operations
Number of VA operations 1 1
Summary of improvement NVA and downtime has been reduced, total of setup
time is higher than machine program 5656
Figure 4 - Machine 575 NVA Adjustments
Total Number of 2 1
operations
Number of NVA 1 0
operations
Number of VA operations 1 1
Summary of improvement By reducing walking distance, the team reduced the number
of NVA. The team also reduced the total time and the
downtime of the machine, making it more effective.
Machine program 5656 has a faster processing time than machine program 5757, by default
machine program 5656 is preferable for a faster setup time. Machine program 5656 is faster because of
the minimal tool change that saves processing time. The overall process were able to be improved by
reducing movement time from workplace to machine, optimized/improve tool assembly processes, and
improve the machine setup process. The CNC machine can also be optimized by making the workplace
next to the machine. Optimizing the workstation will reduce the general setup time in any scenario.
Conclusion/Key learnings
In manufacturing processes, companies can generate more product, reduce cost, and make more
profits simultaneously if they can reduce the waste associated with it. There are some ways that can be
done in order to reduce the waste in manufacturing processes, such as eliminate the non-value adding
activities (in this case, the setup for each drill head) and improve the value adding processes, and
implement SMED (Single Minute Exchange of Dies). Aside from reducing manufacturing processes
waste, companies also need to maximize their profit and throughput. To achieve this, companies can do
business evaluation that will lead them to make a calculated business decision, comparing other
alternative options, and also cost analysis to make an improvement for future references.