Sl.

Transmittal No. Date


No

14 A8GA-CC006-AFC-TN-0014 6-Jun-17

18 A8GA-CC006-AFC-TN-0018 9-Jun-17

19 A8GA-CC006-AFC-TN-0019 9-Jun-17

43 A8GA-CC006-AFC-TN-0043 14-Jul-17
53 A8GA-CC006-AFC-TN-0053 25-Jul-17

66 A8GA-CC006-AFC-TN-0066 16-Aug-17
BAUXITE EXPORT PROJE
PORT DEVELOPMENT AN
Inward register for tran

Subject / Reference Action required/Status

SPC to approve. (SP has


provided reponse asking for
MTC of rebar revised MTC & adhesion
certificate)

Civil Work Procedure- R0 SPC to approve

ITP for Car Dumper Vault - SPC to approve


R0

ITP for Pile Works ITP for Pile Works


MTC-Inspection Cetificate of
SPC to approve
rebar

MTC Rebar 8 MM to 32 MM SPC to approve


TE EXPORT PROJECT, GUINEA - CC - 006
EVELOPMENT AND INFRASTRUCTURE
d register for transmittal from Afcons

Attachment Pending Current


Action by
(Yes / No) since Status

Yes Mr. Sanjoy 100 Open

Yes Mr. Sanjoy 97 Open

Yes Mr. Sanjoy 97 Open

Yes Mr. Sanjoy 62 Open


Yes Mr. Sanjoy 51 Open

Yes Mr. Sanjoy 29 Open


Remarks SPCPL Comments

TC's are not matched


communicated through
E-mail dt. 29th Aug &
18th Aug.

Approved under Cat-B.


Approved and submitted to Rev-0 submitted to
client in IFC for information
PMC

Approved under Cat-B.


Approved and submitted to Rev-0 submitted to
client in IFC for information PMC

Under Client approval - IBTS Approved under Cat-B.


Rev-1 submitted to
no. 498 PMC are attached
TC's are not matched
communicated through
E-mail dt. 29th Aug &
18th Aug.

TC's are not matched


communicated through
E-mail dt. 29th Aug &
18th Aug.
SPCPL Remarks

Attached

Attached

Attached Doc No.-


A8GA-006-FLR-QA-
PL-5003_R1_WS
with Rev1 for
Construction.