Documente Academic
Documente Profesional
Documente Cultură
Not only is global energy consumption steadily growing, electricity close to the source of the coal and transmit it to
but energy is increasingly being drawn from resources the consumers. As many renewable energy sources such
located far from the place of usage. The topic of as hydropower, wind and sun, are location-dependent in
transporting energy over long distances is growing in their production, there is often no alternative to long-
importance. distance transmission.
Oil is often shipped in super-tankers and gas in pipelines. The transmission of electrical energy is thus set to play an
Coal for electricity production uses rail transportation, a important and growing role. In this article, ABB Review
solution that can require the costly reinforcement of looks at a recent development in the area of bulk power
tracks. It may be more economical to generate the transmission.
Power in MW
4000
mission. Both AC and DC generation sources.
generators produce electrici- 3000
4 Using 800 kV HVDC, power transfer of up 5 Extensive equipment testing is required before commercial 800kV HVDC can be offered
to 18000 MW is possible on a single right of commercially. These pictures show the transformer a , the transformer bushing b and the valve
way. hall bushing (title photo, page 22) being tested in Ludvika, Sweden.
a b
Double bipole
6000-18000 MW
Bipole
3000-9000 MW
Footnote
2)
1200kV AC was commercially operated on a line connecting Russia and Kazakhstan from 1989 to 1996. The line was taken out of operation due to the collapse of the
Soviet Union.
ence between the sending and receiv- bushings, thyristor valves, arresters, passed successfully. Also the seismic
ing end is of no importance if the voltage dividers, DC filter capacitors withstand has been verified by calcu-
only connection is DC. In fact, the and support insulators. lations. The design and manufacture
connected networks can even be of the 800 kV wall bushing is complet-
asynchronous as DC has no phase Technical achievements ed, and the bushing is installed in the
angles and does not depend on the Development has been going on at 800 kV test circuit, including:
frequency. ABB for several years and all equip- DC withstand 1250 kV
ment that must be exposed to 800 kV AC withstand 910 kV
Faults on DC lines or in converters has been designed, manufactured and
will give rise to increased frequency tested. Some examples are discussed
at the generating end and decreasing below:
Deregulation of power
frequency at the receiving end – un- generation has lead to
less there is sufficient overload capa- Transformer prototype increased trade with more
bility in the remaining pole, and par- A simplified transformer prototype has
allel DC lines are available to handle been manufactured, including all the electric power transmitted
the power difference. If the fault is insulation details for an 800 kV con- over longer distances.
permanent, a scheme to trip the gen- verter transformer 5a . The initial test-
erators should be implemented in ing of the transformer prototype in-
This poses more stringent
order to maintain frequency stability cluded: requirements on the
in the sending network. This is nor- DC withstand 1250 kV transmission system.
mally only a problem if parallel syn- AC withstand 900 kV
chronous AC lines exist; especially if The tests were successfully passed. Long term test circuit
their power rating is much lower than As a final demonstration of its feasibil-
that of the DC lines – such lines can Transformer bushing ity, a long term test station has been
trip when the phase angles increase A prototype of the transformer bush- built and put into operation. Here, all
too much. ing for the highest 6-pulse group has equipment is tested at 855 kV for at
been produced 5b . The bushing has least half a year 6 .
Configurations passed all type and routine tests, in-
For 800 kV HVDC, several converter cluding: Station design
configurations are possible 3 . Possible DC withstand 1450 kV When designing 800 kV HVDC with a
line configurations are shown in 4 . AC withstand 1050 kV power of 6000 MW, it is important to
design the station so that a failure of a
Technical challenges Wall bushings single critical component results in a
The highest voltage of HVDC today is The wall bushing is based on the loss of only a fraction of the power. 7
600 kV. The Itaipu project was com- well-proven design for the recent in- 8 shows a station with four power
missioned more than 20 years ago and stallations at 500 kV. Besides the elec- blocks. This can be configured in one
is operating two bipoles of ± 600 kV trical requirements, the 18 m length of of the following manners:
and transmitting 6300 MW over a dis- the wall bushing (title picture page Two poles each consisting of two
tance of 800 km. 800 kV HVDC re- 22) has been a mechanical challenge. series connected groups
quires development of transformers, However, all electrical and mechanical Two poles each consisting of two
transformer bushings, valve hall wall type and routine tests have been parallel groups.
6 Voltage withstand endurance testing on the 800 kV test circuit at Factbox 1 The ability of a combined AC and DC transmission to maintain
STRI, Ludvika stability despite the loss of DC links: scenario 1 11a with
strong AC link
RI capacitor
By-pass breaker
Voltage divider
Number of parallel 500 kV lines
1 2 3 4 5 6 7 8 9 10
1 yes yes yes yes yes yes yes yes yes yes
2 yes yes yes yes yes yes yes yes yes yes
Number
3 no yes yes yes yes yes yes yes yes yes
of lost
4 no no no no yes yes yes yes yes yes
Disconnector DC groups
5 no no no no no no no yes yes yes
6 no no no no no no no no no no
Composite support insulators
7 no no no no no no no no no no
8 no no no no no no no no no no
Successful testing tion facilities are located at many 2,000 km are in the order of five per-
Based on all development work made places along the route. cent. The third major advantage is that
the conclusion is that 800 kV is now fewer lines are needed with less right
available for commercial transmis- One disadvantage of AC is its cost. of way requirement. As mentioned
sions. The system described above is quite above, transmission of 12,000 MW can
expensive as, in reality, a full electric be achieved with two lines using
Comparison of AC and DC infrastructure has to be built along the 800 kV HVDC. Transmitting the same
route. power with 800 kV AC would require
Cost eight lines.
10 provides a cost comparison be- Another disadvantage is the require-
tween transmitting 12,000 MW over a ment of land and right of way. As AC The main disadvantage of HVDC is
distance of 2,000 km with AC and DC. transmission cannot fully utilize the that power is transmitted from one
800 kV HVDC gives the lowest overall thermal capacity of each line when point to the other and that it is quite
cost and the optimum is at the lowest the line is very long, a line in parallel costly to build tapping stations (al-
losses in the line. will have to be installed. though it is possible and has been
done).
Advantages and disadvantages Advantages and disadvantages of DC
of AC One major advantage of HVDC is its
The major advantage of AC is the flex- low cost for transmission of very high
The major advantage of
ibility with which loads and genera- power over very long distances. AC is the flexibility with
tion along the route can be connect- which loads and genera-
ed. This is especially important if the A second great advantage is that the
transmission route passes through a losses are quite low. The total losses tion along the route can
highly populated area and if genera- in the transmission of power over be connected. This is
especially important if the
transmission route passes
through a highly populat-
ed area and if generation
facilities are located at
many places along the
route.
Combined AC and DC transmission
As mentioned above, the main disad-
vantage with HVDC is the high cost of
the tapping of power along the line.
However, a combination of low cost
bulk power HVDC transmission in
parallel with a lower voltage AC net-
work could in many cases become the
optimal solution in providing both
low cost and high flexibility and the
7 An HVDC converter station with four power blocks – the configuration is chosen to minimize the 8 An HVDC converter station with two poles
effects of individual component failures each consisting of two series connected
groups
ability to supply customer along the ing half of the customers along the
10 The cost of stations, lines and losses as a
route. route. In this case there are no stabili-
function of the line losses
ty problems as the systems are asyn-
Power 12.000 MW There are however some technical chronous.
Line lenght 2000 km problems with the combined AC and
800 kV AC 8 lines 500 kV DC 4 lines
1000 kV AC 5 lines
DC solution. Disturbances in the DC Alternative 3
800 kV DC 2 lines
8000
transmission will in many cases trip Option 11c is the same as 11b but uses
the AC connection as the phase angles an HVDC back to back connection to
becomes too large. This problem can increase the flexibility of power sup-
7000
be solved in various ways as is shown ply without needing to synchronize
in 11 . the two systems. Preferably this back
million $