Sunteți pe pagina 1din 6

Energy efficient grids

Ultra high voltage


transmission
Alternative scenarios for long distance bulk power
transmission – 800 kV HVDC and 1000 kV HVAC
Gunnar Asplund

Not only is global energy consumption steadily growing, electricity close to the source of the coal and transmit it to
but energy is increasingly being drawn from resources the consumers. As many renewable energy sources such
located far from the place of usage. The topic of as hydropower, wind and sun, are location-dependent in
transporting energy over long distances is growing in their production, there is often no alternative to long-
importance. distance transmission.

Oil is often shipped in super-tankers and gas in pipelines. The transmission of electrical energy is thus set to play an
Coal for electricity production uses rail transportation, a important and growing role. In this article, ABB Review
solution that can require the costly reinforcement of looks at a recent development in the area of bulk power
tracks. It may be more economical to generate the transmission.

22 ABB Review 2/2007


Ultra high voltage transmission

Energy efficient grids

F rom the advent of elec-


trical transmission, AC
has established itself as lead-
1 The capability of an AC line degrades with increasing length:
This graph is for a 1000 kV line with max. 70 percent compensation
have to follow the example
set by OECD countries.
and 30 degree angle between terminals
ing technology in electrical In developing countries, AC is
networks. Its advantage lay being adopted for new grids,
Transmission capability on 1000 kV AC
in the possibility of using as indeed it was in other
6000
transformers to raise it to countries. It is, however, also
higher voltage levels, facili- 5000 used to some extent for trans-
tating economical trans- mission of power from distant

Power in MW
4000
mission. Both AC and DC generation sources.
generators produce electrici- 3000

ty at a relatively low voltage 2000 AC transmission over long


level. If this voltage were distances
1000
used for transmission over Prerequisites for a line built
long distances, high and 0 to transfer power over long
prohibitively expensive loss- 200 700 1200 1700 2200 2700 3200 distances are stability and the
es would ensue. Line length in km ability to survive faults such
as lightning strikes. The de-
AC technology is also very sign criterion that must be
flexible when connecting different Thirty years ago, the capacity of grids fulfilled is defined as N-i with i=11).
locations to form an electric grid, was largely in balance with demand. This means that the maximum power
permitting a very robust and reliable With the growth in consumption, this that can be lost without the stability
electric supply to the consumers. situation changed. Generation has in- of the AC system as such being com-
In its early days, the question of reli- creased in new places: For example, promised is equal to the power of the
ability of supply was predominant: wind power parks are normally con- largest generating unit or the line with
As generation took place relatively structed in locations where the grid is the highest capacity. If all power from
close to consumption, priority was weak. Deregulation of power genera- a distant generating plant is transmit-
not focused on transmitting large tion has also lead to increased trade ted on a single line, the AC system
power quantities over large distan- with more electric power transmitted has to withstand the loss of all this
ces. over longer distances. This poses power. If larger amounts of power are
more stringent requirements on the to be transmitted, several parallel lines
To render AC more suitable for such transmission system. must be used that are interconnected
bulk transmission, a typical measure every 300 to 400 km to increase reli-
was the adoption of series compen- ability.
sation for lines. This works quite well
The evolution of grids in
when power is transmitted from one most countries is charac- AC lines have quite high power han-
point to another, but is normally not terized by the addition of dling capability if short. The capability
used inside a meshed grid as the flow is dependent on the voltage and the
of power is more unpredictable. network layers of higher thermal rating of the conductors. Lon-
and higher voltages. ger lines have higher impedance and
The development of AC systems has this reduces the power transfer capa-
seen continuing increases in transmis- In developing countries the situation bility. The equation for transfer of
sion voltage. When power consump- is very different. It is more akin to the active power is:
tion is low, voltage can also be low. situation in OECD countries in the
Typically, doubling the voltage qua- 1950s and 1960s. However, the rate of U1·U2·sin(δ)
P=
druples the power transfer capability. development is much higher, especial- X
Consequently, the evolution of grids ly in China and India. Technology has
in most countries is characterized by advanced in the last thirty years, and Where P is the active power, U1 and
the addition of network layers of solutions adopted do not necessarily U2 the voltage at each end of the line,
higher and higher voltages.
Footnote
2 Six parallel AC lines in six sections with series and shunt compensa-
In OECD countries there 1)
The design criterion N-i defines the
tion. The line can continue to function despite the failure of individual
was an almost exponential number of elements whose failure
components
increase of electric power can be tolerated before the overall
system loses functionality. Applying
consumption until the oil
this to electricity networks, N represents
crisis at the beginning of
the number of major components in the
the 1970s. The impact of network (ie, generators, substations,
this crisis halted plans to lines etc), and i the number of these
go for higher voltages components that can fail at the same
such as 800, 1000 and even time without leading to instability in the
1200 kV. network.

ABB Review 2/2007 23


Ultra high voltage transmission

Energy efficient grids

δ the phase angle between the fault. This can be


3 Alternative converter configurations for 800 kV HVDC line
the two ends and X the line achieved with the help of
impedance. tuned reactors that minimize
Single twelve pulse Series connected Parallel twelve pulse
group per pole twelve pulse groups groups per pole the induced current.
in each pole
As the length of the line in-
creases, the impedance of the 800 kV AC is fully commer-
line increases with it. For the cial and all equipment are
transfer power to be main- available. Development is
tained, the angle δ must be ongoing for all equipment of
increased. This is possible up 1000 kV AC.
to an angle of around 30 de-
grees, after which problems 800 kV DC transmission
with dynamic stability can be
encountered. The best way to 3000-4500 MW 4500-6400 MW 6000-9000 MW System aspects
overcome this problem is to The principle of DC trans-
reduce the impedance by se- mission lies in converting
ries compensation. This can be Technical challenges AC to DC in a rectifier station, trans-
done without significant problems 1000 kV and 1200 kV AC has been mitting the power in a DC bipolar line
up to a compensation of around tested in several test-installations and and converting the power back to AC
70 percent. At higher levels of com- even short-time commercial applica- in an inverter station.
pensation the system will be less tions but is not currently used in any
robust 1 . commercial application2). There are
several challenges involved in build-
Thirty years ago, the
When a line is loaded below SIL ing such lines and new equipment capacity of grids was
(surge impedance loading) it will needing to be developed includes largely in balance with
produce reactive power; if shunt com- transformers, breakers, arresters, shunt
pensation is not added the voltage reactors, series capacitors, current and demand. With the growth
can rise excessively. If the line is voltage transformers, and connecting in consumption, this
loaded above SIL, it will consume and ground switches.
reactive power and the voltage can
situation changed.
drop too far. From a reliability point There are also special requirements in
of view, it is necessary to build an the domain of control and protection. From a system point of view, DC is a
AC transmission in sections with both At single phase earth faults, the chal- simpler technology for transmission
series and shunt compensation as well lenge is to clear the fault without over long distances. The rectifier and
as interconnection between the sec- opening the breakers of all three inverter stations can control current
tions 2 in order to assure that full phases. The problem lies with the and voltage very quickly and are
power transmission is possible at all high capacitive current generated by therefore suitable for the control of
times. the operating phases that flows into power flow. The phase angle differ-

4 Using 800 kV HVDC, power transfer of up 5 Extensive equipment testing is required before commercial 800kV HVDC can be offered
to 18000 MW is possible on a single right of commercially. These pictures show the transformer a , the transformer bushing b and the valve
way. hall bushing (title photo, page 22) being tested in Ludvika, Sweden.
a b
Double bipole
6000-18000 MW

Bipole
3000-9000 MW

Footnote
2)
1200kV AC was commercially operated on a line connecting Russia and Kazakhstan from 1989 to 1996. The line was taken out of operation due to the collapse of the
Soviet Union.

24 ABB Review 2/2007


Ultra high voltage transmission

Energy efficient grids

ence between the sending and receiv- bushings, thyristor valves, arresters, passed successfully. Also the seismic
ing end is of no importance if the voltage dividers, DC filter capacitors withstand has been verified by calcu-
only connection is DC. In fact, the and support insulators. lations. The design and manufacture
connected networks can even be of the 800 kV wall bushing is complet-
asynchronous as DC has no phase Technical achievements ed, and the bushing is installed in the
angles and does not depend on the Development has been going on at 800 kV test circuit, including:
frequency. ABB for several years and all equip- DC withstand 1250 kV
ment that must be exposed to 800 kV AC withstand 910 kV
Faults on DC lines or in converters has been designed, manufactured and
will give rise to increased frequency tested. Some examples are discussed
at the generating end and decreasing below:
Deregulation of power
frequency at the receiving end – un- generation has lead to
less there is sufficient overload capa- Transformer prototype increased trade with more
bility in the remaining pole, and par- A simplified transformer prototype has
allel DC lines are available to handle been manufactured, including all the electric power transmitted
the power difference. If the fault is insulation details for an 800 kV con- over longer distances.
permanent, a scheme to trip the gen- verter transformer 5a . The initial test-
erators should be implemented in ing of the transformer prototype in-
This poses more stringent
order to maintain frequency stability cluded: requirements on the
in the sending network. This is nor- DC withstand 1250 kV transmission system.
mally only a problem if parallel syn- AC withstand 900 kV
chronous AC lines exist; especially if The tests were successfully passed. Long term test circuit
their power rating is much lower than As a final demonstration of its feasibil-
that of the DC lines – such lines can Transformer bushing ity, a long term test station has been
trip when the phase angles increase A prototype of the transformer bush- built and put into operation. Here, all
too much. ing for the highest 6-pulse group has equipment is tested at 855 kV for at
been produced 5b . The bushing has least half a year 6 .
Configurations passed all type and routine tests, in-
For 800 kV HVDC, several converter cluding: Station design
configurations are possible 3 . Possible DC withstand 1450 kV When designing 800 kV HVDC with a
line configurations are shown in 4 . AC withstand 1050 kV power of 6000 MW, it is important to
design the station so that a failure of a
Technical challenges Wall bushings single critical component results in a
The highest voltage of HVDC today is The wall bushing is based on the loss of only a fraction of the power. 7
600 kV. The Itaipu project was com- well-proven design for the recent in- 8 shows a station with four power

missioned more than 20 years ago and stallations at 500 kV. Besides the elec- blocks. This can be configured in one
is operating two bipoles of ± 600 kV trical requirements, the 18 m length of of the following manners:
and transmitting 6300 MW over a dis- the wall bushing (title picture page Two poles each consisting of two
tance of 800 km. 800 kV HVDC re- 22) has been a mechanical challenge. series connected groups
quires development of transformers, However, all electrical and mechanical Two poles each consisting of two
transformer bushings, valve hall wall type and routine tests have been parallel groups.

6 Voltage withstand endurance testing on the 800 kV test circuit at Factbox 1 The ability of a combined AC and DC transmission to maintain
STRI, Ludvika stability despite the loss of DC links: scenario 1 11a with
strong AC link
RI capacitor
By-pass breaker
Voltage divider
Number of parallel 500 kV lines

1 2 3 4 5 6 7 8 9 10

1 yes yes yes yes yes yes yes yes yes yes

2 yes yes yes yes yes yes yes yes yes yes
Number
3 no yes yes yes yes yes yes yes yes yes
of lost
4 no no no no yes yes yes yes yes yes
Disconnector DC groups
5 no no no no no no no yes yes yes

6 no no no no no no no no no no
Composite support insulators
7 no no no no no no no no no no

8 no no no no no no no no no no

ABB Review 2/2007 25


Ultra high voltage transmission

Energy efficient grids

Successful testing tion facilities are located at many 2,000 km are in the order of five per-
Based on all development work made places along the route. cent. The third major advantage is that
the conclusion is that 800 kV is now fewer lines are needed with less right
available for commercial transmis- One disadvantage of AC is its cost. of way requirement. As mentioned
sions. The system described above is quite above, transmission of 12,000 MW can
expensive as, in reality, a full electric be achieved with two lines using
Comparison of AC and DC infrastructure has to be built along the 800 kV HVDC. Transmitting the same
route. power with 800 kV AC would require
Cost eight lines.
10 provides a cost comparison be- Another disadvantage is the require-
tween transmitting 12,000 MW over a ment of land and right of way. As AC The main disadvantage of HVDC is
distance of 2,000 km with AC and DC. transmission cannot fully utilize the that power is transmitted from one
800 kV HVDC gives the lowest overall thermal capacity of each line when point to the other and that it is quite
cost and the optimum is at the lowest the line is very long, a line in parallel costly to build tapping stations (al-
losses in the line. will have to be installed. though it is possible and has been
done).
Advantages and disadvantages Advantages and disadvantages of DC
of AC One major advantage of HVDC is its
The major advantage of AC is the flex- low cost for transmission of very high
The major advantage of
ibility with which loads and genera- power over very long distances. AC is the flexibility with
tion along the route can be connect- which loads and genera-
ed. This is especially important if the A second great advantage is that the
transmission route passes through a losses are quite low. The total losses tion along the route can
highly populated area and if genera- in the transmission of power over be connected. This is
especially important if the
transmission route passes
through a highly populat-
ed area and if generation
facilities are located at
many places along the
route.
Combined AC and DC transmission
As mentioned above, the main disad-
vantage with HVDC is the high cost of
the tapping of power along the line.
However, a combination of low cost
bulk power HVDC transmission in
parallel with a lower voltage AC net-
work could in many cases become the
optimal solution in providing both
low cost and high flexibility and the

7 An HVDC converter station with four power blocks – the configuration is chosen to minimize the 8 An HVDC converter station with two poles
effects of individual component failures each consisting of two series connected
groups

26 ABB Review 2/2007


Ultra high voltage transmission

Energy efficient grids

9 An artist’s impression of the station of 8

ability to supply customer along the ing half of the customers along the
10 The cost of stations, lines and losses as a
route. route. In this case there are no stabili-
function of the line losses
ty problems as the systems are asyn-
Power 12.000 MW There are however some technical chronous.
Line lenght 2000 km problems with the combined AC and
800 kV AC 8 lines 500 kV DC 4 lines
1000 kV AC 5 lines
DC solution. Disturbances in the DC Alternative 3
800 kV DC 2 lines
8000
transmission will in many cases trip Option 11c is the same as 11b but uses
the AC connection as the phase angles an HVDC back to back connection to
becomes too large. This problem can increase the flexibility of power sup-
7000
be solved in various ways as is shown ply without needing to synchronize
in 11 . the two systems. Preferably this back
million $

6000 to back is a Voltage Source Converter


Alternative 1 (HVDC Light), which will stabilize the
5000 Option 11a uses a fairly strong AC con- voltages and increase the power trans-
nection that can withstand most dis- fer of the AC lines.
turbances in the DC connection with-
4000
1 2 3 4 5 6 7 8 9 10 out having to disconnect. Conclusions
Percent line losses In order to transmit bulk power over
As an illustration, it is assumed that long distances (more than 500–1000 km),
the HVDC transmits 12,000 MW over 800 kV HVDC is normally the most
2,000 km in two bipoles with each four cost efficient alternative. The biggest
11 Three alternatives for combining AC and
converter groups. It is assumed that the drawback of HVDC is the high cost
DC to connect two networks. In a , a strong
HVDC can take a temporary overload of tapping power along the route.
AC link supports the DC, in b , the two AC
of 50 percent if one or more groups A combination, where the bulk power
networks are separated and in c the gap is
should trip. Further, it is assumed that is fed by HVDC and the power need-
bridged by an HVDC back to back link
there is a parallel AC net of 500 kV ed along the route is fed by AC seems
a b c lines that will have to pick up the to be the most cost effective and flexi-
power that the HVDC cannot transmit. ble solution. 1000 kV AC is more suit-
Sending network The results in are shown in Factbox 1 . able as an overlay net to existing 400
or 500 kV AC nets in densely populat-
This table shows the system will remain ed areas.
dynamically stable after the loss of sev-
HVDC eral DC groups. Each DC group has a
back power of 1500 MW. The outcome is de-
to back
pendent on the preloading of the AC-
lines. Here it is assumed they are load-
ed up to 34 percent before the fault.
Gunnar Asplund
Receiving network Alternative 2 ABB Power Technologies, Power Systems DC
Option 11b permits the two networks Ludvika, Sweden
to operate asynchronously, each feed- gunnar.asplund@se.abb.com

ABB Review 2/2007 27

S-ar putea să vă placă și