01 OBRAS PRELIMINARES 151.00 01.01 TRASLADO DE MATERIALES día 1.00 151.00 151.00 02 MANO DE OBRA 2,540.00 02.01 FABRICACION DE EXTENSÓMETRO día 10.00 254.00 2,540.00 03 MATERIALES 1,173.00 03.01 TUBO METÁLICO DE 1 1/2" . und 5.00 25.00 125.00 03.02 PLATINA DE 1 1/2" und 5.00 14.00 70.00 03.03 PESA 4kg. und 5.00 10.00 50.00 03.04 ESTACAS DE ACERO 1" und 5.00 8.00 40.00 03.05 INSUMOS PARA SOLDADURA. glb 1.00 495.00 495.00 03.06 ALIMENTACIÓN día 10.00 39.30 393.00 Costo Directo 3,864.00 GATOS GENERALES 5% 193.20 UTILIDADES 7% 270.48 _____________ PRESUPUESTO TOTAL 4,327.68 .
SON : CUATRO MIL TRESCIENTOS VEINTISIETE Y 68/100 DOLARES AMERICANOS