Sunteți pe pagina 1din 1

`

residential house
date:10/08/2017 material
rates in
NO. description of work unit quantity $ amounts in $
1 hardwood Nos 80 28 2240
2 roof. Sheet Nos 120 6 720
3 cement bags 350 7 2450
4 steel bars nos 80 8 640
5 water fosto 150 1.5 225
6 stones load 20 50 1000
7 sand load 20 35 700
8 bricks no. 5000 0.5 2500
9 gravel load 10 60 600
10 white washing (lime) bags 40 6 240
11 paint bags 600
12 Windows (alumium) No. 6 200 1200
13 glass paint 200
14 doors (wooden Nos 10 170 1700
15 steel door Nos 2 100 200
16 floor tiles no 200 6 1200
17 compaction 300
18 water tank 300
19 gate Nos 1 600 600
20 ceiling (chip board) nos 115 6.5 747.5
21 back filling (sand) 1600
22 Plumbing Installation 300
23 Electrical Installation 400
24 Sewage Pepping 300
25 Toilet . Accessories 20962.5
26 nails 400
27 varendah RCC 6000
28 facia board and others 3000
29 face stone 5000
30 35362.5
contengance and
checking 2637.5
ground total 38000
labour
216 65 14040

prepared and submitted by:hoy-bila construction.co net ground total($): 52040 $

S-ar putea să vă placă și