ID Task Name Duration Start Finish December 2017 January 2018 February 2018 March 2018 April 2018

Duration Start Finish December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2
1 SHENO TOWN CRUSH PROGRAM 108 days Mon 22-01-18 Wed 20-06-18
2 Bill No 03: Pipes & fittings 108 days Mon 22-01-18 Wed 20-06-18
3 1) Supply and installation of pipes and fittings for transmission main 1 day Tue 13-02-18 Tue 13-02-18
4 1.1)Transmission main 35 days Mon 26-02-18 Fri 13-04-18
5 Supply and installation of DCI pipes and fittings. 15 days Mon 26-02-18 Fri 16-03-18
6 Supply and installation of fittings for the remaining activities 15 days Mon 26-02-18 Fri 16-03-18
7 Supply of materials and installation in valve chamber 32 days Thu 01-03-18 Fri 13-04-18
8 Construction of concrete valve chamber 32 days Thu 01-03-18 Fri 13-04-18
9 Gully crossings 32 days Thu 01-03-18 Fri 13-04-18
10 Construction of C-20 reinforced concrete support columns 32 days Thu 01-03-18 Fri 13-04-18
11 Trust and anchor blocks 32 days Thu 01-03-18 Fri 13-04-18
12 C20 concrete trust blocks 32 days Thu 01-03-18 Fri 13-04-18
13 Pressure test and desinfection 32 days Thu 01-03-18 Fri 13-04-18
14 Pressure test and desinfection of pipelines 32 days Thu 01-03-18 Fri 13-04-18
15 1.2) New main from BH1-N to DC-R3 69 days Mon 29-01-18 Thu 03-05-18
16 Supply and installation of DCI pipes and fittings. 40 days Mon 19-02-18 Fri 13-04-18
17 Supply and installation of fittings. 40 days Mon 19-02-18 Fri 13-04-18
18 Supply of materials and installation in valve chamber 32 days Mon 19-03-18 Tue 01-05-18
19 Construction of concrete valve chamber 32 days Mon 19-03-18 Tue 01-05-18
20 Gully crossings 17 days Mon 09-04-18 Tue 01-05-18
21 Construction of C-20 reinforced concrete support columns 17 days Mon 09-04-18 Tue 01-05-18
22 Trust and anchor blocks 49 days Mon 26-02-18 Thu 03-05-18
23 C20 concrete trust blocks 32 days Mon 26-02-18 Thu 03-05-18
24 Pressure test and desinfection 60 days Mon 29-01-18 Fri 20-04-18
25 Pressure test and desinfection of pipelines 60 days Mon 29-01-18 Fri 20-04-18
26 construction of valve chamber with concrete manhole cover 55 days Mon 12-02-18 Fri 27-04-18
27 Construction of C-15 reinforced concrete valve chamber 55 days Mon 12-02-18 Fri 27-04-18
28 Supply and installation of pipes and fittings for distribution 55 days Mon 26-03-18 Fri 08-06-18
29 New Village Water Supply Line 60 days Tue 13-02-18 Mon 07-05-18
30 50m3 Reservoir 60 days Mon 26-02-18 Fri 18-05-18
31 10m3 Reservoir 40 days Mon 02-04-18 Fri 25-05-18
32 Water Points 30 days Mon 30-04-18 Fri 08-06-18
33 3) Sevice connections Water points & water Kiosks. 66 days Mon 29-01-18 Mon 30-04-18
34 Instalation of HDPE pipes for service connections 30 days Tue 20-03-18 Mon 30-04-18
35 Water Kiosks 30 days Mon 29-01-18 Fri 09-03-18
36 Miscellaneous works 30 days Mon 29-01-18 Fri 09-03-18
37 Water points 39 days Mon 29-01-18 Thu 22-03-18
38 Construction of valve chamber 10 days Mon 29-01-18 Fri 09-02-18
39 Installation of water meters 7 days Mon 12-02-18 Tue 20-02-18

Task Inactive Summary External Tasks Path Predecessor Normal Task

Split Manual Task External Milestone Path Driving Predecessor Normal Task

Milestone Duration-only Deadline Path Driven Successor Milestone Task


Project: Sheno Crush Program
Summary Manual Summary Rollup Path Predecessor Milestone Task Path Driven Successor Summary Task
Date: Tue 20-02-18
Project Summary Manual Summary Path Driving Predecessor Milestone Task Path Driven Successor Normal Task

Inactive Task Start-only Path Predecessor Summary Task Progress

Inactive Milestone Finish-only Path Driving Predecessor Summary Task Manual Progress

Page 1
ID Task Name Duration Start Finish December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2
40 Fence and gate 15 days Wed 21-02-18 Tue 13-03-18
41 Drainage system and water disposal 7 days Wed 14-03-18 Thu 22-03-18
42 4) Supply of pipes, fittings, tools and equipment for post 8 days Mon 11-06-18 Wed 20-06-18
43 Tools and equipments 8 days Mon 11-06-18 Wed 20-06-18
44 Bill 05: Power line 95 days Mon 29-01-18 Fri 08-06-18
45 Leasing with EEPCO 30 days Mon 29-01-18 Fri 09-03-18
46 Connection of Power line with BH 65 days Mon 12-03-18 Fri 08-06-18
47 Bill No 06: 0 days Mon 12-03-18 Mon 12-03-18
48 Construction of Generator houses 10 days Thu 15-02-18 Wed 28-02-18
49 Loading & unloading Ramp 10 days Thu 15-02-18 Wed 28-02-18
50 Miscellaneous 10 days Thu 15-02-18 Wed 28-02-18
51 Construction of two Chlorination buildings 10 days Mon 26-02-18 Fri 09-03-18
52 Miscellaneous 10 days Mon 26-02-18 Fri 09-03-18
53 Guard houses 10 days Mon 26-02-18 Fri 09-03-18
54 Miscellaneous 10 days Mon 26-02-18 Fri 09-03-18
55 Construction of Operator's Dwelling 10 days Mon 26-02-18 Fri 09-03-18
56 Miscellaneous 10 days Mon 26-02-18 Fri 09-03-18
57 Construction of Water Supply Service Office 10 days Mon 26-02-18 Fri 09-03-18
58 Painting 10 days Mon 26-02-18 Fri 09-03-18
59 Hydraulics 10 days Mon 26-02-18 Fri 09-03-18
60 Site work 10 days Mon 26-02-18 Fri 09-03-18
61 Fences and gates operational compounds 30 days Fri 02-02-18 Thu 15-03-18
62 Fence and gates 30 days Fri 02-02-18 Thu 15-03-18
63 Bill No 07: Reservoirs 30 days Mon 29-01-18 Fri 09-03-18
64 Construction of one 150m3 RC elevated tank for Feto SV 66 days Mon 29-01-18 Mon 30-04-18
65 Supply and installation of pipes, valves & fittings 30 days Mon 29-01-18 Fri 09-03-18
66 valve chambers 30 days Mon 26-02-18 Fri 06-04-18
67 Site work 36 days Mon 12-03-18 Mon 30-04-18
68 Construction of two 200 m3 RC ground reservoirs 66 days Mon 29-01-18 Mon 30-04-18
69 Supply and installation of pipes, valves & fittings 30 days Mon 29-01-18 Fri 09-03-18
70 valve chambers 30 days Mon 26-02-18 Fri 06-04-18
71 Site work 36 days Mon 12-03-18 Mon 30-04-18
72 Component 3 30 days Mon 29-01-18 Fri 09-03-18
73 Construction of Sanitation Facilities in Sheno 30 days Mon 29-01-18 Fri 09-03-18
74 BILL No. 1: Construction of Public Toilet and Shower 30 days Mon 29-01-18 Fri 09-03-18
75 Hydraulics and sanitary fixtures 30 days Mon 29-01-18 Fri 09-03-18
76 Site work 30 days Mon 29-01-18 Fri 09-03-18
77 Bill No.02:Construction Septic Tank and Soak away pits for public Toilets 30 days Mon 29-01-18 Fri 09-03-18

Task Inactive Summary External Tasks Path Predecessor Normal Task

Split Manual Task External Milestone Path Driving Predecessor Normal Task

Milestone Duration-only Deadline Path Driven Successor Milestone Task


Project: Sheno Crush Program
Summary Manual Summary Rollup Path Predecessor Milestone Task Path Driven Successor Summary Task
Date: Tue 20-02-18
Project Summary Manual Summary Path Driving Predecessor Milestone Task Path Driven Successor Normal Task

Inactive Task Start-only Path Predecessor Summary Task Progress

Inactive Milestone Finish-only Path Driving Predecessor Summary Task Manual Progress

Page 2
ID Task Name Duration Start Finish December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2
78 Miscellaneous 30 days Mon 29-01-18 Fri 09-03-18
79 Bill No.03:Construction of flush school toilet for girls 30 days Mon 29-01-18 Fri 09-03-18
80 Hydraulics and sanitary fixtures 30 days Mon 29-01-18 Fri 09-03-18
81 Site work 30 days Mon 29-01-18 Fri 09-03-18
82 Bill No.4:Construction Septic Tank and Soak away pits for School Toilets 30 days Mon 29-01-18 Fri 09-03-18

83 Miscellaneous 30 days Mon 29-01-18 Fri 09-03-18


84 Bill No 5: BOQ for Sanitary Land fill site and Leachet Pond 89 days Tue 13-02-18 Fri 15-06-18
85 Bill No.6: Sludge Drying Bed 89 days Tue 13-02-18 Fri 15-06-18
86 Comp 1-WS to HAMUSGABEYA & ADADI TOWN 30 days Mon 29-01-18 Fri 09-03-18
87 Supply and installation of pipes and fittings 95 days Mon 29-01-18 Fri 08-06-18
88 Installation of HDPE Pipes 30 days Mon 29-01-18 Fri 09-03-18
89 Supply of Fittings for HDPE pipes 20 days Mon 05-02-18 Fri 02-03-18
90 Installation of Fittings for HDPE pipes 30 days Mon 05-03-18 Fri 13-04-18
91 Trust & anchor blocks and crossings 30 days Mon 16-04-18 Fri 25-05-18
92 Road crossings 15 days Mon 19-03-18 Fri 06-04-18
93 Valve chambers 30 days Mon 19-03-18 Fri 27-04-18
94 PRESSURE TESTING AND DISINFECTION 30 days Mon 30-04-18 Fri 08-06-18
95 Service connections 55 days Mon 19-02-18 Fri 04-05-18
96 Service Connections 30 days Mon 26-03-18 Fri 04-05-18
97 Water points 30 days Mon 19-02-18 Fri 30-03-18
98 Power lines from EEPCO tranformers and from of the generators 70 days Mon 29-01-18 Fri 04-05-18
99 Power line from EEPCO transformer 70 days Mon 29-01-18 Fri 04-05-18
100 Bill No. 6 70 days Mon 22-01-18 Fri 27-04-18
101 Construction of Generator houses 53 days Mon 22-01-18 Wed 04-04-18
102 Doors, Windows and ventilation frames 45 days Thu 01-02-18 Wed 04-04-18
103 Electrical Installation 45 days Mon 22-01-18 Fri 23-03-18
104 Miscellaneous 45 days Mon 22-01-18 Fri 23-03-18
105 Construction of one Chlorination buildings 30 days Mon 19-03-18 Fri 27-04-18
106 Miscellaneous 30 days Mon 19-03-18 Fri 27-04-18
107 Guard houses (2) 30 days Mon 19-03-18 Fri 27-04-18
108 Miscellaneous 30 days Mon 19-03-18 Fri 27-04-18
109 Fences and gates operational compounds 30 days Mon 19-03-18 Fri 27-04-18
110 Fence and gates 30 days Mon 19-03-18 Fri 27-04-18

Task Inactive Summary External Tasks Path Predecessor Normal Task

Split Manual Task External Milestone Path Driving Predecessor Normal Task

Milestone Duration-only Deadline Path Driven Successor Milestone Task


Project: Sheno Crush Program
Summary Manual Summary Rollup Path Predecessor Milestone Task Path Driven Successor Summary Task
Date: Tue 20-02-18
Project Summary Manual Summary Path Driving Predecessor Milestone Task Path Driven Successor Normal Task

Inactive Task Start-only Path Predecessor Summary Task Progress

Inactive Milestone Finish-only Path Driving Predecessor Summary Task Manual Progress