Duration Start Finish December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2
1 SHENO TOWN CRUSH PROGRAM 108 days Mon 22-01-18 Wed 20-06-18
2 Bill No 03: Pipes & fittings 108 days Mon 22-01-18 Wed 20-06-18
3 1) Supply and installation of pipes and fittings for transmission main 1 day Tue 13-02-18 Tue 13-02-18
4 1.1)Transmission main 35 days Mon 26-02-18 Fri 13-04-18
5 Supply and installation of DCI pipes and fittings. 15 days Mon 26-02-18 Fri 16-03-18
6 Supply and installation of fittings for the remaining activities 15 days Mon 26-02-18 Fri 16-03-18
7 Supply of materials and installation in valve chamber 32 days Thu 01-03-18 Fri 13-04-18
8 Construction of concrete valve chamber 32 days Thu 01-03-18 Fri 13-04-18
9 Gully crossings 32 days Thu 01-03-18 Fri 13-04-18
10 Construction of C-20 reinforced concrete support columns 32 days Thu 01-03-18 Fri 13-04-18
11 Trust and anchor blocks 32 days Thu 01-03-18 Fri 13-04-18
12 C20 concrete trust blocks 32 days Thu 01-03-18 Fri 13-04-18
13 Pressure test and desinfection 32 days Thu 01-03-18 Fri 13-04-18
14 Pressure test and desinfection of pipelines 32 days Thu 01-03-18 Fri 13-04-18
15 1.2) New main from BH1-N to DC-R3 69 days Mon 29-01-18 Thu 03-05-18
16 Supply and installation of DCI pipes and fittings. 40 days Mon 19-02-18 Fri 13-04-18
17 Supply and installation of fittings. 40 days Mon 19-02-18 Fri 13-04-18
18 Supply of materials and installation in valve chamber 32 days Mon 19-03-18 Tue 01-05-18
19 Construction of concrete valve chamber 32 days Mon 19-03-18 Tue 01-05-18
20 Gully crossings 17 days Mon 09-04-18 Tue 01-05-18
21 Construction of C-20 reinforced concrete support columns 17 days Mon 09-04-18 Tue 01-05-18
22 Trust and anchor blocks 49 days Mon 26-02-18 Thu 03-05-18
23 C20 concrete trust blocks 32 days Mon 26-02-18 Thu 03-05-18
24 Pressure test and desinfection 60 days Mon 29-01-18 Fri 20-04-18
25 Pressure test and desinfection of pipelines 60 days Mon 29-01-18 Fri 20-04-18
26 construction of valve chamber with concrete manhole cover 55 days Mon 12-02-18 Fri 27-04-18
27 Construction of C-15 reinforced concrete valve chamber 55 days Mon 12-02-18 Fri 27-04-18
28 Supply and installation of pipes and fittings for distribution 55 days Mon 26-03-18 Fri 08-06-18
29 New Village Water Supply Line 60 days Tue 13-02-18 Mon 07-05-18
30 50m3 Reservoir 60 days Mon 26-02-18 Fri 18-05-18
31 10m3 Reservoir 40 days Mon 02-04-18 Fri 25-05-18
32 Water Points 30 days Mon 30-04-18 Fri 08-06-18
33 3) Sevice connections Water points & water Kiosks. 66 days Mon 29-01-18 Mon 30-04-18
34 Instalation of HDPE pipes for service connections 30 days Tue 20-03-18 Mon 30-04-18
35 Water Kiosks 30 days Mon 29-01-18 Fri 09-03-18
36 Miscellaneous works 30 days Mon 29-01-18 Fri 09-03-18
37 Water points 39 days Mon 29-01-18 Thu 22-03-18
38 Construction of valve chamber 10 days Mon 29-01-18 Fri 09-02-18
39 Installation of water meters 7 days Mon 12-02-18 Tue 20-02-18
Split Manual Task External Milestone Path Driving Predecessor Normal Task
Inactive Milestone Finish-only Path Driving Predecessor Summary Task Manual Progress
Page 1
ID Task Name Duration Start Finish December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2
40 Fence and gate 15 days Wed 21-02-18 Tue 13-03-18
41 Drainage system and water disposal 7 days Wed 14-03-18 Thu 22-03-18
42 4) Supply of pipes, fittings, tools and equipment for post 8 days Mon 11-06-18 Wed 20-06-18
43 Tools and equipments 8 days Mon 11-06-18 Wed 20-06-18
44 Bill 05: Power line 95 days Mon 29-01-18 Fri 08-06-18
45 Leasing with EEPCO 30 days Mon 29-01-18 Fri 09-03-18
46 Connection of Power line with BH 65 days Mon 12-03-18 Fri 08-06-18
47 Bill No 06: 0 days Mon 12-03-18 Mon 12-03-18
48 Construction of Generator houses 10 days Thu 15-02-18 Wed 28-02-18
49 Loading & unloading Ramp 10 days Thu 15-02-18 Wed 28-02-18
50 Miscellaneous 10 days Thu 15-02-18 Wed 28-02-18
51 Construction of two Chlorination buildings 10 days Mon 26-02-18 Fri 09-03-18
52 Miscellaneous 10 days Mon 26-02-18 Fri 09-03-18
53 Guard houses 10 days Mon 26-02-18 Fri 09-03-18
54 Miscellaneous 10 days Mon 26-02-18 Fri 09-03-18
55 Construction of Operator's Dwelling 10 days Mon 26-02-18 Fri 09-03-18
56 Miscellaneous 10 days Mon 26-02-18 Fri 09-03-18
57 Construction of Water Supply Service Office 10 days Mon 26-02-18 Fri 09-03-18
58 Painting 10 days Mon 26-02-18 Fri 09-03-18
59 Hydraulics 10 days Mon 26-02-18 Fri 09-03-18
60 Site work 10 days Mon 26-02-18 Fri 09-03-18
61 Fences and gates operational compounds 30 days Fri 02-02-18 Thu 15-03-18
62 Fence and gates 30 days Fri 02-02-18 Thu 15-03-18
63 Bill No 07: Reservoirs 30 days Mon 29-01-18 Fri 09-03-18
64 Construction of one 150m3 RC elevated tank for Feto SV 66 days Mon 29-01-18 Mon 30-04-18
65 Supply and installation of pipes, valves & fittings 30 days Mon 29-01-18 Fri 09-03-18
66 valve chambers 30 days Mon 26-02-18 Fri 06-04-18
67 Site work 36 days Mon 12-03-18 Mon 30-04-18
68 Construction of two 200 m3 RC ground reservoirs 66 days Mon 29-01-18 Mon 30-04-18
69 Supply and installation of pipes, valves & fittings 30 days Mon 29-01-18 Fri 09-03-18
70 valve chambers 30 days Mon 26-02-18 Fri 06-04-18
71 Site work 36 days Mon 12-03-18 Mon 30-04-18
72 Component 3 30 days Mon 29-01-18 Fri 09-03-18
73 Construction of Sanitation Facilities in Sheno 30 days Mon 29-01-18 Fri 09-03-18
74 BILL No. 1: Construction of Public Toilet and Shower 30 days Mon 29-01-18 Fri 09-03-18
75 Hydraulics and sanitary fixtures 30 days Mon 29-01-18 Fri 09-03-18
76 Site work 30 days Mon 29-01-18 Fri 09-03-18
77 Bill No.02:Construction Septic Tank and Soak away pits for public Toilets 30 days Mon 29-01-18 Fri 09-03-18
Split Manual Task External Milestone Path Driving Predecessor Normal Task
Inactive Milestone Finish-only Path Driving Predecessor Summary Task Manual Progress
Page 2
ID Task Name Duration Start Finish December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2
78 Miscellaneous 30 days Mon 29-01-18 Fri 09-03-18
79 Bill No.03:Construction of flush school toilet for girls 30 days Mon 29-01-18 Fri 09-03-18
80 Hydraulics and sanitary fixtures 30 days Mon 29-01-18 Fri 09-03-18
81 Site work 30 days Mon 29-01-18 Fri 09-03-18
82 Bill No.4:Construction Septic Tank and Soak away pits for School Toilets 30 days Mon 29-01-18 Fri 09-03-18