Sunteți pe pagina 1din 9

Field Investigation of Collapse of a 13-Story High-Rise

Residential Building in Shanghai


W. D. Wang 1; Q. Li 2; Y. Hu 3; J. W. Shi 4; and C. W. W. Ng, F.ASCE 5

Abstract: In 2009, a 13-story residential building founded on lightly reinforced prestressed high-strength concrete (PHC) pipe piles in
Downloaded from ascelibrary.org by Colorado University at Boulder on 02/14/17. Copyright ASCE. For personal use only; all rights reserved.

Shanghai collapsed completely during the excavation of an adjacent underground garage (i.e., on the southern side). In the course of con-
struction, excavated soil had been dumped on the northern side of the building and formed a 10-m-high fill slope before the collapse. In order
to identify the principal cause of the sudden building collapse, an extensive field investigation was carried out immediately after the accident.
In addition to geotechnical exploration of soil properties, physical evidence was collected and documented including the layout of collapse
debris, damage to piles, and induced pile movements. To assist in the investigation and provide insights into the collapse, three-dimensional
finite-element analysis was carried out to simulate the process of excavation and dumping. For piles located adjacent to the dumped soil on the
northern side of the building, uppermost fractures could be seen near the interface between the reinforced and unreinforced sections, which
were located approximately 1–2 m below the original level of the pile head. Most of these failure surfaces were flat, implying that these piles
failed under tension. For piles situated on the excavation (southern) side of the collapsed building, the uppermost fracture surfaces were tilted
at an angle and the concrete was severely damaged, suggesting that these fractures occurred mainly from compression. Photographs of the
pipe interior taken with a high-resolution digital camera and results of a low-strain pile integrity test revealed that most piles examined had
generally broken into three or more sections. According to results of the numerical analysis, the largest bending moment was developed in the
piles on the excavation side of the building at a depth corresponding to the interface of the soft and firm-stiff clay layers (13.5 m below the
ground surface), under the combined effect of excavation and dumping. This suggests that the failure occurred first for piles on the excavation
side, and eventually caused the building to fall flat onto the excavation site. A lesson learned from the accident is that geotechnical engineers
and contractors should be better trained to improve their understanding of the effects of surcharge loading on PHC piles. Moreover, proper
construction procedures and site supervision schemes should be explicitly spelled out and strictly followed by all parties during construction.
DOI: 10.1061/(ASCE)CF.1943-5509.0001005. © 2017 American Society of Civil Engineers.
Author keywords: Building collapse; Field investigation; Three-dimensional finite-element analysis; Pile failure; Excavation; Dumped
soil; Bearing capacity failure.

Introduction life of one construction worker. As shown in Fig. 1, the superstruc-


ture of the collapsed building remained almost intact with a number
On the early morning of June 27, 2009, a 13-story high-rise build- of broken piles still attached to it. A large area of soil dumped on
ing (Number 7) under construction at the Lotus Riverside residen- the northern side of the building can also be seen in the photograph
tial complex suddenly collapsed in Shanghai, China, claiming the taken after the accident.
Building collapse can be broadly classified into two categories,
1
Senior Engineer (Professor-Level), Dept. of Underground Structure and partial collapse and total collapse, on the basis of the extent of the
Geotechnical Engineering, Underground Space Engineering Design and collapse (Wardhana and Hadipriono 2003). According to Wardhana
Research Institute, Arcplus Group PLC., Hankou Rd., Shanghai 200002, and Hadipriono (2003), 20% of the 225 cases of building failures
People’s Republic of China. E-mail: weidong_wang@ecadi.com examined in the United States were total collapse failures. How-
2
Senior Engineer, Dept. of Underground Structure and Geotechnical ever, well-documented case histories of building collapse (particu-
Engineering, Underground Space Engineering Design and Research larly total collapse) are rarely available in the literature for reasons
Institute, Arcplus Group PLC., Hankou Rd., Shanghai 200002, People’s either to do with the law, or people’s reputations. Cuoco et al.
Republic of China (corresponding author). E-mail: qing_li@ecadi.com
3 (1992) reported the case history of a 16-story building that
Senior Engineer, Dept. of Underground Structure and Geotechnical
Engineering, Underground Space Engineering Design and Research collapsed during construction using the lift-slab method. The super-
Institute, Arcplus Group PLC., Hankou Rd., Shanghai 200002, People’s structure of the building collapsed entirely. During field investiga-
Republic of China. E-mail: yun_hu@ecadi.com tion, the structural engineer of record located a slab jack remote
4
Lecturer, College of Civil and Transportation Engineering, Hohai from the project site, providing evidence that the most probable
Univ., Xikang Rd., Nanjing 210078, People’s Republic of China. E-mail: cause of the collapse is jack failure because of instability of steel
ceshijiangwei@163.com wedges. Another relevant work is that of Ghosh (2011), who at-
5
Chair Professor, Dept. of Civil and Environmental Engineering, tempted to uncover the actual cause of the total collapse of a 5-story
Hong Kong Univ. of Science and Technology, Clear Water Bay, Kowloon,
residential building in New Delhi, India. Ghosh (2011) concluded
Hong Kong, People’s Republic of China. E-mail: cecwwng@ust.hk
Note. This manuscript was submitted on June 14, 2016; approved on
that the collapse was likely the result of structural failure. The lit-
October 28, 2016; published online on February 11, 2017. Discussion per- erature has seldom reported case histories investigating foundation
iod open until July 11, 2017; separate discussions must be submitted for failures for high-rise buildings.
individual papers. This paper is part of the Journal of Performance of Shortly after the accident in Shanghai, the local government
Constructed Facilities, © ASCE, ISSN 0887-3828. appointed the authors to lead a team and carry out forensic

© ASCE 04017012-1 J. Perform. Constr. Facil.

J. Perform. Constr. Facil., -1--1


changes. Fig. 2 shows a typical soil profile and geotechnical prop-
erties at the site. In general, there are seven soil layers within the
upper 50 m of soil below the ground surface. The approximately
3.5-m-thick crust is composed mainly of fill and silty clay, which
are overconsolidated because of desiccation. The desiccated
crust overlies a 10-m-thick soft clay layer which is followed by a
16-m-thick firm-stiff silty clay layer. Further down lies clayey silt.
Underlying these deposits is a fine sand layer.
The water content typically increases from nearly 30% in the
crust to approximately 50% in the soft clay layer, and then de-
creases gradually to 25% just above the silt layer. The natural water
content of the soft clay is larger than its liquid limit, so the soil
Downloaded from ascelibrary.org by Colorado University at Boulder on 02/14/17. Copyright ASCE. For personal use only; all rights reserved.

exhibits soft and compressible behavior. Fig. 2 also shows the in


situ undrained shear strength (su ) profile measured in two vane
shear tests. The undrained shear strength changes slightly in the
Fig. 1. View of the site after the building collapse (image by Y. Hu) range from 20 to 30 kPa for soft (silty) clay, but increases all
the way up to 80 kPa for the silty clay layer underneath. According
to geotechnical field investigations, groundwater at this site mainly
comes from precipitation as well as the nearby Ding Pu river and
investigations and remedial work. Upon arrival at the site, the team the phreatic surface fluctuates between 0.7 and 0.9 m below the
of investigators collected and documented collapse debris in order ground surface.
to preserve as much physical evidence as possible. In order to iden-
tify the most probable cause of the collapse, the foundation piles
of the building were extensively investigated and the damage to the Description of Building and Foundation Piles
piles and induced pile movements were assessed. To assist in the
The entire Lotus Riverside complex measures approximately
investigation and offer insights into the collapse, three-dimensional
42,300 m2 in plan, and consists of 11 reinforced concrete shear
(3D) finite-element analysis was carried out to simulate the proc-
wall buildings 10–13 stories high, together with an underground
esses of excavation and soil dumping. Based on the facts collected
space which actually comprises two independent, adjacent 1-story
on-site and the interpretation of numerical results, the most prob-
garages. A plan view of the building of concern (Number 7) is
able cause of the collapse of the 13-story high-rise building is
shown in Fig. 3. The underground garage is constructed on the
proposed and discussed.
southern side of the building, which contains 13 levels of apart-
ments above the ground surface, with a total height of 37.7 m.
Project Pile foundations consisting of 118 prestressed high-strength
concrete (PHC) pipe piles supported the superstructure of the build-
ing. Fig. 4 shows the layout of the pipe piles for the building. All
Geological Conditions and Soil Properties PHC piles were steam-cured under a pressure of 1.0 MPa at 180°C
Shanghai is located at the estuary of Yangtze River Delta along to improve early strength, allowing for earlier removal time of
the coast of the East China Sea. The geology is mainly composed forms. Each pile was 33 m long, and had an outer diameter of
of alluvial and marine sediments deposited during the Quaternary 400 mm and a wall thickness of 80 mm. The piles penetrated
Period as a result of periodic warm and cold climates and sea level the clay layers and rested on fine sand as a bearing stratum.

Unit weight Water content Void ratio Vane shear strength Cone resistance
3 wn (%)
γt (kN/m ) e su (kPa) qc (MPa)
Soil profile 16 17 18 19 20 15 25 35 45 55 0.6 0.9 1.2 1.5 0 40 80 120 0 5 10 15
0 Fill
(1.8m)
Silty clay
5 Soft
(silty) clay
10 Soft clay wp wL

pile
15

20 Firm-stiff
Depth (m)

silty clay
25

30
Clayey silt
35

40 (34.8m)
Fine sand
45

50

Fig. 2. Geological conditions and soil properties (wn natural water content; wL liquid limit; and wp plastic limit)

© ASCE 04017012-2 J. Perform. Constr. Facil.

J. Perform. Constr. Facil., -1--1


deep soil mixing wall and two rows of soil nails made of steel tubes.
The soil mixing wall was 0.7 m thick and 7.2 m long giving rise to a
penetration depth of 4.4 m below the formation level. The steel tube
had an outer diameter of 48 mm and a wall thickness of 3 mm. The
upper and lower rows of soil nails were 9 and 6 m in length, re-
spectively, and were installed at a downward angle of 15 degrees
from the horizontal direction.

Construction Status at Time of Collapse

Excavation of the Underground Garage


Downloaded from ascelibrary.org by Colorado University at Boulder on 02/14/17. Copyright ASCE. For personal use only; all rights reserved.

Prior to the accident, the superstructure of building Number 7 had


already been built. During excavation of the underground garage,
the building suddenly collapsed and tipped over onto the excava-
tion on the southern side. The western part of the underground
garage, i.e., Zone I, had been excavated to the formation level
(Fig. 3). A plain concrete layer had been completed in this area,
but structural reinforced concrete slab had not been cast. Zone
Fig. 3. Plan view of the construction site II had yet to be excavated. After the collapse, the building lay
on top of the excavation, although the superstructure remained
almost intact (Fig. 1).

The capacity of a single pile was designed to be approximately Dumped Soil


1,300 kN. Ground beams were used to connect all the piles
and to transfer loads from the superstructure to the piles. The According to construction logs, the dumping process can be
ground beams had cross-sectional dimensions of 600 × 700 mm broadly divided into two stages and is schematically shown in
(width × height). The upper 2 m of the hollow PHC piles was filled Fig. 5. In December 2008, a large amount of spoil was dumped
with reinforced concrete and cast together with the ground beam to on the northern side of the building forming a 4-m-high fill slope
enable a robust connection, and is hence referred to as the rein- approximately 16 m away from the building. From June 20, 2009,
forced zone in this study. Full-scale bending tests show that this type excavation of the underground garage began on the southern side of
of pipe pile has a bending capacity of approximately 158 kN · m the building. The excavated soil was dumped on top of the previ-
under pure bending conditions. ously formed 4-m fill slope on the northern side of the building. By
June 27, the fill slope had grown to approximately 90 m in length
and 40 m in width (in plan) and stood 10 m tall. The vertical loading
Excavation
from the trapezoidal dumped soil was equivalent to a uniformly
Fig. 5 shows the relative locations of building Number 7 and the distributed loading of 94 kPa, assuming that the unit weight of
excavation for the underground garage (along cross section A-A the dumped soil was 16.5 kN=m3 . Note that the size of the fill slope
in Fig. 3). The excavation for the entire garage took up an area was measured after the collapse of the building.
of 8,000 m2 and the excavation depth was 4.6 m. The basement Because a 10-m-thick soft stratum lies beneath the stiff crust
was first excavated to 1.8 m below the ground surface using the (refer to Fig. 2), the soft clay could have lost its bearing capacity
open cut method at a slope of 1∶1.5. Below 1.8 m, the excavation because of the surcharge loading imposed by the dumped soil.
was supported by a composite soil nail wall, which consisted of a Based on the undrained assumption, the bearing capacity of the soft

Fig. 4. Layout of foundation piles before and after the collapse

© ASCE 04017012-3 J. Perform. Constr. Facil.

J. Perform. Constr. Facil., -1--1


Downloaded from ascelibrary.org by Colorado University at Boulder on 02/14/17. Copyright ASCE. For personal use only; all rights reserved.

Fig. 5. Construction status at time of collapse (along cross section A-A)

clay was estimated to be 5.14su ¼ 129 kPa, where su is undrained Results of Field Investigation
shear strength, being equal to 25 kPa. For simplicity, the weight of
the fill and silty clay layers above was also considered to be a sur- Pile Movements
charge loading, which was estimated to be approximately 63 kPa.
Under this circumstance, the total stress exerted on the soft clay Using the global positioning system (GPS) technique, the locations
stratum was approximately 157 kPa, exceeding the estimated bear- of individual pipe piles after the collapse could be determined ac-
ing capacity. Hence, the soft clay layer had likely lost its bearing curately (Fig. 4). The pile locations changed significantly after the
capacity. collapse. However, because it was very difficult to match the post-
collapse locations with the original locations, the actual movement
of each pile could not be readily determined. Fortunately, two piles
Field Investigation Program at the southeast of the building, i.e., B23 and B24, were at least
3.4 m apart from other piles, and locations of these two piles before
The field investigation program involved two stages. The inves-
and after the collapse could be identified with certainty. The two
tigative work in the first stage began shortly after the collapse.
pile heads had moved toward the excavation site by 3.9 and 3.8 m.
In this stage, exposed broken piles that were still connected to
Moreover, both had moved slightly toward the west, indicating a
foundation beams adjacent to the dumped soil on the northern side rotation of the building in falling over. Thus, it may be implied
of the building were investigated. Special attention was paid to the that the foundation piles of the building had shifted substantially
damage to the pile head. Six piles (A1–A6 as shown in Fig. 4) following the collapse.
embedded in the ground were dug out to inspect the failure
features of the pile shaft. Moreover, the fracture features of two
of these piles (A1 and A2) at large depths (2 m below the original Damage to Piles near the Dumped Soil
level of pile head) were inspected using a high-resolution digital As described previously, the superstructure of building Number 7
camera. Damage to the pile shaft can be directly identified in pho- rested on 118 PHC pipe piles. After the collapse, the building lay
tographs taken. flat on the excavation site on the southern side of the building. The
After the debris of the collapsed building was removed com- piles on the northern side of the building, i.e., those adjacent to the
pletely, the piles located adjacent to the excavation on the southern dumped soil, were pulled out and exposed. As shown in Fig. 6,
side of the building were investigated (i.e., second stage). In this these piles broke but the pile head remained connected to the foun-
stage, excavations were carried out to expose a total of 24 piles dation beam. Approximately half of the foundation piles of the
(B1–B24) and the elevation and tilt of fractures nearest to the building were exposed. The piles near the excavation side were
pile head were determined. Moreover, a high-resolution digital buried in the soil and cannot be directly seen in Fig. 6.
camera was used to observe directly the damage to the shaft of The broken piles that were still connected to the foundation
nine of the 24 piles. For some piles where underground water beam had a residual length of approximately 1–2 m. The pipe pile
kept flowing inside, the integrity of these piles was examined was connected to the bottom slab by filling the upper 2.0 m of its
using low-strain pile integrity testing method. The method uses hollow part with reinforced concrete. Therefore, the reinforced pile
a hammer to generate stress waves and an accelerometer to shaft near the connection had a very different stiffness compared to
record input and reflection waves, based on which failure is de- the unreinforced one. The decrease in stiffness with depth is likely
termined according to Chinese professional standard of JGJ the reason why most piles broke near the depth of 2.0 m. For sev-
106-2003 (MCPRC 2003). eral piles, the reinforced concrete block was even completely pulled

© ASCE 04017012-4 J. Perform. Constr. Facil.

J. Perform. Constr. Facil., -1--1


Reinforced concrete the pile to take photos along the pile shaft. Piles A1 and A2 were
block being pulled out examined using this method. In A1, another two fractures were
identified, located approximately 2.2 and 10.5 m below the upper-
most fracture. As previously described, the broken pile section that
remained attached to the foundation was approximately 2 m long.
Therefore, pile A1 failed at three locations, i.e., 2, 4.2, and 12.5 m
below the original level of the pile head. The failure 2 m below the
pile head occurred in the soft clay layer, whereas the failure 12.5 m
below the pile head took place near the interface of the soft and
firm-stiff silt clay layers. Pile A2 failed in a similar pattern to
A1. The pile broke approximately 2, 4, and 11 m below the original
level of the pile head.
Downloaded from ascelibrary.org by Colorado University at Boulder on 02/14/17. Copyright ASCE. For personal use only; all rights reserved.

Damage to Piles near the Excavation


Fig. 6. Pipe piles connected to foundation beams (adjacent to the Because piles on the excavation side were covered by building
dumped soil on the northern side of the collapsed building) (image debris, only after the debris was removed could they be investi-
by Y. Hu) gated. Upon excavation of the soil at shallow depths during inves-
tigation, it was found that the uppermost fracture in piles exhibited
a different failure pattern to those in piles near the dumped soil.
Most failure surfaces were tilted at an angle. The concrete was frac-
out. No obvious damage was observed at the connection between tured severely or even crushed and some of the steel bars within the
the pile head and foundation beams for the majority of the exposed concrete were jutting out at an angle as shown in Fig. 7. Based on
pipes. A close examination revealed that most piles near the these observations, it is suspected that the upper part of the pile had
dumped soil had failure surfaces (uppermost fractures) that almost failed under eccentric compression, where one side of the pile had
formed a right angle with the pile axis. These failure surfaces were compressed while the other side had come under tension.
probably the result of tensile failure. As a result, some of the re- In order to determine where the uppermost fracture occurred, the
inforced concrete blocks were pulled out. precise levelling technique was used to measure the elevation of the
Using a high-resolution digital camera, it was possible to ob- failure surfaces. It was found that the uppermost fracture occurred
serve directly the damage to the PHC piles that were still embedded 1–2 m below the original level of the pile head, which agrees fairly
deep in the ground. In order to obtain clear photographs, the interior well with the finding for the piles adjacent to the dumped soil. The
of the investigated piles were cleaned with pressurised water before tilt of the broken pile embedded in the ground was also measured.
the internal inspections. Muddy water inside the pile was pumped The measured tilt angle varied from 0° to 60°. Piles tilting at 10–20°
out, and the camera, together with a lighting kit, were lowered into from the vertical axis accounted for 46% of all piles investigated.

Surcharge side

Excavation side Excavation side

(a) (b)

Surcharge side Surcharge side

Excavation side Excavation side


(c) (d)

Fig. 7. Uppermost fractures in piles on the excavation (southern) side of the collapsed building (images by Y. Hu): (a) B1; (b) B12; (c) B18; (d) B19

© ASCE 04017012-5 J. Perform. Constr. Facil.

J. Perform. Constr. Facil., -1--1


Ground surface
0 Elevation of pile head Fill
2 Uppermost Silty clay
Fracture 4 fracture
6 Intermediate Bottom of Soft silty clay
fracture reinforcement
8
10 Soft clay
12
Lowest (?)
14

Depth (m)
fracture (?) (?)
16 (?)
18
20
22 Firm-stiff
24 silty clay
26
28
Downloaded from ascelibrary.org by Colorado University at Boulder on 02/14/17. Copyright ASCE. For personal use only; all rights reserved.

30
Clayey silt
32
34 B7 B13 Fine sand
(a)

Fig. 9. Locations of fractures in pipe piles on the excavation (southern)


side of the collapsed building

Fracture

the camera could not be used. The quick influx of water into the
pile was indicative of the existence of another fracture in each of
these four piles (possible failure location was shown in Fig. 9).
Comparing the photographs collected in the two stages of inves-
tigation, piles located on the excavation side of the building were
damaged more severely than those close to the dumped soil at larger
depths. The intermediate fracture surfaces of pile B1 and pile B8
were located at the depths of 4.1 and 4.2 m below the original level
of the pile head, respectively. In addition, pile B13 and pile B20
(b) broke into two at the depths of 4.4 and 5.8 m, respectively.
Several piles were blocked by soil at relatively shallow depths,
Crack thus it was not possible to insert the camera inside. Instead, the low-
strain pile integrity test, which has been widely applied for assess-
ing the structural integrity of concrete piles (Rausche and Seitz
1983; Hussein and Garlanger 1992), was performed to identify
the location of fractures at large depths. For instance, piles B23
and B24 were blocked at the depths of 6.2 and 5.3 m, respectively.
Based on the low-strain pile integrity test results, it was deduced
that pile failure took place 7 and 6 m below the original level of the
pile head for piles B23 and B24, respectively.
Based on the results of field measurements and the photographs
taken, fracture locations for 12 piles on the excavation side of the
building were determined and shown in Fig. 9, which shows that
most of the piles had broken into at least three sections. The upper-
(c) most fracture mainly occurred within 2 m below the original level
of the pile head. The intermediate fractures were found at depths
Fig. 8. Photos of the pipe interior taken with a high-resolution digital ranging from 4 to 6 m below the pile head in the soft clay layers.
camera for pipe piles on the excavation (southern) side of the collapsed The lowest fracture might occur approximately 11–14 m below the
building: (a) B1; (b) B8; (c) B20 elevation of the original pile head. This depth is close to where the
interface between the soft clay and firm-stiff silty clay layers was
located.

It was also found that piles located in the middle of the building
tilted at a smaller angle than those on either the eastern or western Three-Dimensional Finite-Element Analysis
side.
After the debris was removed, the internal damage in 12 piles Based merely on the pile failure features obtained from the field
(B1, B3, B4, B7, B8, B10, B12, B13, B20, B22, B23, and B24 as investigation, it was not possible to deduce the mechanism under-
shown in Fig. 4) was inspected using either a high-resolution cam- lying the building collapse. To assist in identifying the most prob-
era or low-strain pile integrity test (or both). As shown in Fig. 8, able cause of the collapse, three-dimensional finite-element analysis
failures and cracks could be readily identified in four piles (B1, B8, was carried out to simulate the process of excavation on one side of
B13, and B20) down to 11–14 m below the elevation of original the building and dumping on the opposite side. Special attention
pile head by using the same high-digital camera. Below 11–14 m, was paid to stress created in the pipe piles by excavation and
because the underground water kept flowing into the pile quickly, dumping.

© ASCE 04017012-6 J. Perform. Constr. Facil.

J. Perform. Constr. Facil., -1--1


excavation and dumped soil, as well as a simplified profile of the
dumped soil are shown in Fig. 10(b). In the analysis, the subsoil
was modeled by 15-node wedge solid elements. Retaining walls
were simulated using eight-node quadrilateral shell elements,
whereas the soil nails were modeled by ground anchors. For both
foundation beams and structural beams, three-node beam elements
were used. The 118 pipe piles were simulated using the embedded-
pile model, which consists of beam elements connected to the sur-
rounding soil. It has been found that the embedded-pile model is
able to reproduce the behavior of laterally loaded pile in numerical
analysis (Dao 2011). The 3D model consisted of 65,439 elements
and a total of 181,147 nodes. Movements in all directions and all
Downloaded from ascelibrary.org by Colorado University at Boulder on 02/14/17. Copyright ASCE. For personal use only; all rights reserved.

rotations were fixed at the bottom of the mesh. Roller boundaries


were adopted for the vertical faces of the mesh.

Constitutive Model and Model Parameters


(a) An elastoplastic model with a Mohr-Column failure criterion was
170 m
adopted to simulate the soil behavior and the finite-element analy-
sis was carried out based on total stress analysis (φu ¼ 0). In the
I analysis, the undrained shear strength of the clay (su ) was determined
90 m
6m Cross section I-I according to the in-situ vane shear strength. Following the recom-
mendations by Jardine et al. (1985), and Gourvenec and Randolph
39 m
10 m

Second dumping Dumped soil


1:1 (2003), the undrained elastic modulus of the clay was assumed to be
4m

1:1 First dumping


16 m 24 m 500 times su . The fine sand layer was modeled under drained con-
I Building ditions. The effective drained modulus E 0 was estimated from the
160 m

7m from the blowcount value N of standard penetration test (SPT).


The retaining walls and the pipe piles were assumed to be elastic
37 m

Excavation and their elastic moduli were 30 and 38 GPa, respectively. Table 1
summarizes all the parameters used in the finite-element analysis.
85 m
y

x
Numerical Modeling Procedures

(b) The construction sequence was simplified and modeled as follows:


(1) generation of initial stress conditions; (2) construction of foun-
Fig. 10. Three-dimensional finite-element mesh: (a) 3D isometric dation pipe piles and the building; (3) dumping of soil to a height of
view; (b) plan view 4 m (first stage) on the northern side of the building; and (4) con-
struction of retaining walls, excavation and dumping of soil to the
final height of 10 m (second stage).

Finite-Element Mesh and Boundary Conditions Interpretation of Computed Results


Fig. 10(a) shows a 3D isometric view of the finite-element mesh Fig. 11 shows the bending moment distribution of a foundation pile
adopted for the analysis. The finite-element program PLAXIS 3D with depth. The pile (Pe ) located on the excavation side of the
Foundation (PLAXIS 2008) was used. The length of the mesh in the building as shown in Fig. 4 is used for illustration. As illustrated
lateral (y) direction was 170 m. The width (x) and depth (z) were in the inset, a positive bending moment means that the pile bends
160 and 50 m, respectively. The relative locations of the building, toward the surcharge loading side, whereas a negative one means

Table 1. Soil Parameters Used in Finite-Element Analysis


Soil layer Depth (m) Γ (kN=m3 ) su a (kPa) c 0 (kPa) φ 0 (°) Eu (MPa) E 0 (MPa) f s (kPa) fp (kPa)
Dumped soil — 16.5 22 — — 11 — — —
Fill 0–1.3 17.0 20 — — 10 — — —
Silty clay 1.3–3.5 17.5 50 — — 25 — 15 —
Soft silty clay 3.5–7.5 16.8 24 — — 12 — 18 —
Soft clay 7.5–13.5 16.6 21 — — 10.5 — 20 —
Silty clay 13.5–19.2 17.7 60 — — 30 — 35 —
Silty clay 19.2–21.5 18.3 80 — — 40 — 45 —
Silty clay 21.5–29.7 18.0 52 — — 26 — 40 750
Clayey silt 29.7–32.8 19.0 130 — — 65 — 70 3,500
Fine sand 32.8–50 19.0 — 1 30 65 50 80 4,000
Note: c 0 = effective cohesion; Eu = undrained elastic modulus; E 0 = effective elastic modulus; f s = ultimate skin friction; f p = ultimate end bearing;
su = undrained shear strength; γ = unit weight; φ 0 = effective friction angle.
a
Undrained shear strength was obtained from in situ vane shear tests.

© ASCE 04017012-7 J. Perform. Constr. Facil.

J. Perform. Constr. Facil., -1--1


0 Fill shown in Fig. 12. The pure bending capacity of 158 kN · m for pipe
Positive Silty clay
piles is also shown for ease of comparison. The maximum bending
Negative Soft
5 moments in the two piles developed similarly, i.e., they kept in-
(silty) clay
creasing as construction proceeded. At any given time, bending
Excavation +
10 side
Mmax Soft clay moments in the piles near the excavation were always larger than
those near the dumped soil. This means that the bending capacity
of the piles on the excavation side of the building was exceeded,
Depth (m)

15 -
Mmax and these piles failed before those on the soil dumping side did.
Pure bending Because the embedded pile model which actually consists of elastic
20 capacity Firm-stiff beam elements was adopted, the breakage of the piles could not be
silty clay
Pure bending simulated in the analysis. This is the reason why the bending mo-
25 capacity ment kept increasing after the bending capacity was exceeded.
Downloaded from ascelibrary.org by Colorado University at Boulder on 02/14/17. Copyright ASCE. For personal use only; all rights reserved.

30 First stage dumping Likely Collapse Scenario


Clayey silt
Excavation and
second stage dumping Fine sand
In light of the observed damage to piles and induced pile move-
35 ments as well as the computed bending moments in the piles, a
-400 -300 -200 -100 0 100 200 300 400
likely collapse scenario is proposed. Owing to the surcharge load-
Bending moment (kN.M)
ing imposed by the soil dumped and adjacent excavation, the soft
Fig. 11. Typical computed bending moment distribution with depth in clay underneath the dumped soil area likely suffered a bearing
pipe piles capacity failure, giving rise to significant lateral soil movements.
These soil movements caused the pipe piles to deform. The maxi-
mum bending moment developed in the pipe piles on the excava-
tion side of the building at a depth corresponding to the interface of
the soft and firm-stiff clay layers (13.5 m below the ground sur-
Calculation phase
face). As the height of the dumped soil grew, the bending moment
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 eventually exceeded the bending capacity of the piles near the inter-
0
face. As a result, the piles near the excavation broke first, causing
the building to tilt toward the excavation. When the overturning
-100 moment exceeded the resisting moment, the tilt of the building
started to accelerate. The more slender the building is (i.e., larger
M-max (kN.m)

building aspect ratio), the more significant the overturning moment


-200 Pure bending capacity will be. As the tilting increased, the piles adjacent to the dumped
soil experienced a tension failure which caused the building to
-300
topple over.
Pile along the excavation
Pile near the dumped soil Lessons Learned
-400
Similar buildings with PHC pile foundations and an underground
Fig. 12. Comparison of maximum negative bending moments (M −
max ) garage are commonly found in Shanghai (Hong 2013), but a com-
for piles near the excavation and near the dumped soil plete collapse of an entire building has not been reported before this
accident. Generally, the effect of surcharge loading from the dump-
ing of soil close to a building is not considered in the design stage in
Shanghai. PHC piles are normally designed to withstand vertical
that the pile bends toward the excavation. Fig. 11 shows that after loading only, rather than horizontal loading. Had it been possible
soil had been dumped to a height of 4 m on the northern side of the to identify the potential for excessive lateral soil displacement of
building, the maximum bending moment of the pile reached ap- the soft clay layer under combined effects of surcharge and exca-
proximately 58 kN · m. This value is within the pure bending vation, the failure may have been prevented. Geotechnical engi-
capacity of the pile, suggesting that the pile had likely remained neers and contractors should be better trained to improve their
intact at that point in time. This is consistent with the fact that understanding of the effects of surcharge loading and the impor-
the building was not damaged in the first six months after the soil tance of proper site supervision. In addition, proper construction
dumping. procedures should be clearly and explicitly spelled out to all parties
The maximum positive bending moment in the pile developed involved in the construction of buildings supported by PHC piles.
approximately 10 m below the ground surface, where the soft clay
layer could be found. The maximum negative bending moment in
the pile occurred approximately 14.5 m below the ground surface, Conclusions and Recommendations
corresponding to the interface between the soft and firm-stiff silty
clays. In addition, the absolute value of the negative bending mo- A 13-story high-rise residential building collapsed completely dur-
ment exceeded the maximum positive bending moment. This im- ing the excavation and construction of an underground garage on
plies that the foundation piles of the building would have broken the southern side of the building in June 2009 in Shanghai. In order
first at the depth where the interface between the soft and stiff clay to identify the principal cause of the collapse, an extensive field
layers was located. investigation was carried out immediately after the accident. In ad-
In an attempt to identify the sequence of pile failure, computed dition to geotechnical exploration of subsoil properties, the inves-
maximum negative bending moments (M − max ) in the piles near the tigative work involved careful examination and collection of
excavation (Pe ) and near the dumped soil (Pd ) are compared and physical evidence of the damage to PHC pipe piles and induced

© ASCE 04017012-8 J. Perform. Constr. Facil.

J. Perform. Constr. Facil., -1--1


pile movements. A total of 30 pipe piles were examined compre- contractors should be better trained to improve their understand-
hensively. The postcollapse pile locations, damage, and tilt of ing of the effects of surcharge loading on PHC pile behavior.
exposed pile heads were studied. Moreover, damage to pile shafts Proper construction procedures and site supervision schemes
embedded in the ground were inspected using a high-resolution should be clearly and explicitly spelled out to all parties involved
digital camera and low-strain pile integrity test. To assist in the in the construction of buildings supported by PHC pipe piles.
investigation and provide insights into the collapse, three-
dimensional finite-element analysis was carried out. Based on the
results of the field investigation and the 3D numerical analysis, References
the following conclusions may be drawn:
1. For pipe piles located close to the dumped soil on the northern Cuoco, D. A., Peraza, D. B., and Scarangello, T. Z. (1992). “Investigation
side of the collapsed building, uppermost fractures mainly oc- of L’ambiance plaza building collapse.” J. Perform. Constr. Facil.,
curred near the connections of the reinforced and unreinforced 10.1061/(ASCE)0887-3828(1992)6:4(211), 211–231.
Dao, T. P. T. (2011). “Validation of plaxis embedded piles for lateral
Downloaded from ascelibrary.org by Colorado University at Boulder on 02/14/17. Copyright ASCE. For personal use only; all rights reserved.

sections. Most of these fracture surfaces were flat, implying that


the pipe piles near the dumped soil had failed under tension. loading.” M.Sc thesis, Delft Univ. of Technology, Delft, Netherlands.
Nevertheless, for piles on the excavation (southern) side of the Ghosh, C. (2011). “Investigation of a building collapse in Delhi.” Proc.,
Indian Geotechnical Conf. (IGC-2011), Indian Geotechnical Society,
building, the uppermost fracture surfaces were tilted and
Punjab, India, 1064–1067.
the concrete was severely damaged, suggesting the failure
Gourvenec, S., and Randolph, M. F. (2003). “Effect of strength
was mainly caused by compression. The observed pile failure nonhomogeneity on the shape of failure envelopes for combined load-
modes are indicative of building overturning owing to bearing ing of strip and circular foundations on clay.” Geotechnique, 53(6),
capacity failure. 575–586.
2. Most of the pipe piles investigated had broken into three sec- Hong, J. H. (2013). “Application of PHC pipe piles in large residential
tions and some into four. The uppermost fractures occurred community project in Shanghai.” Housing Sci., 4, 59–62 (in Chinese).
approximately 1–2 m below the designed elevation of the pile Hussein, M., and Garlanger, J. (1992). “Damage detection for concrete
head. The intermediate fracture surfaces were located 4–6 m piles using a simple non-destructive method.” Proc., First Int. Conf.
below the piled head. The lowest fractures probably occurred Fracture Mechanics of Concrete Structures, Northwestern Univ.,
11–14 m below the pile head, near the interface between the Breckenridge, CO, 573–576.
soft clay and firm-stiff silty clay layers. Jardine, R. J., Fourie, A. B., Maswoswe, J., and Burland, J. B. (1985).
3. Under the combined influences of a 4.6-m-deep excavation on “Field and laboratory measurements of soil stiffness.” 11th Int. Conf.
the southern side of the building and the dumping of soil to a SMFE, A.A. Balkema, Rotterdam, Netherlands, 551–514.
height of 10 m on the opposite side, the soft clay underneath the MCPRC (Ministry of Construction of the People’s Republic of China). (2003).
“Technical code for testing of building foundation piles (JGJ106-2003).”
dumped soil area suffered a bearing capacity failure, leading to
Chinese Building Publishing Company, Beijing (in Chinese).
significant lateral soil movements in this layer. Consequently, lar-
PLAXIS. (2008). “PLAXIS 3D foundation reference manual-version 2.”
ger bending moments were developed in piles on the excavation Delft, Netherlands.
side than in those on the dumping side. As a result, the piles near Rausche, F., and Seitz, J. (1983). “Integrity testing of shafts and caissons.”
the excavation broke first, causing the building to tilt toward the Proc., of Symp., 6 at 1983 ASCE Spring Convention, G. G. Goble, ed.,
excavation. With enough tilting, piles adjacent to the dumped soil ASCE, Reston, VA, 192–207.
broke as a result of tension, and the building toppled over. Wardhana, K., and Hadipriono, F. C. (2003). “Study of recent building fail-
4. Because surcharge loading is generally not considered in the ures in the United States.” J. Perform. Constr. Facil., 10.1061/(ASCE)
design of PHC piles in Shanghai, geotechnical engineers and 0887-3828(2003)17:3(151), 151–158.

© ASCE 04017012-9 J. Perform. Constr. Facil.

J. Perform. Constr. Facil., -1--1

S-ar putea să vă placă și