Fixed Time Related


Amount
Item Description Unit Cost Cost
UAE Dhs UAE Dhs UAE Dhs

GENERAL REQUIREMENTS FOR THE


WHOLE OF THE WORKS

Generally

Where any item, clause or sub-clause of the


General Requirements has not been priced, it will
be deemed that the value of such item, clause or
sub-clause is included in the rates for measured
items elsewhere in the Bills of Quantities.

The rates and prices in these Bills of Quantities


are fixed for the duration of the Contract and shall
not be subject to any adjustment in respect of rise
or fall in the cost of labour, materials, plant,
equipment, transport or any other matters
affecting the cost of execution of the Contract.

References hereunder to the Schedule of Project


Requirements are intended solely to direct the
Contractor to the specific requirements of the
Schedule of Project Requirements in respect of a
particular item and do not in any way limit the
scope of such item to the requirements of the
Schedule of Project Requirements.

The Contractor is deemed to have included for


complying in all respects with the applicable
terms, conditions and provisions of the
Specification and the other documents forming the
Contract in his prices for General Requirements.

Conditions of Contract

The Contractor shall price hereunder any


obligations contained in the Conditions of Contract
which are not allowed for elsewhere and which the
Contractor wishes to price separately

Clause
No.

A 1 Definitions and Interpretation Item Included

EHV 28, 31 32 BQ 1/2


BILL NO. 1
GENERAL REQUIREMENTS FOR
THE WHOLE OF THE WORKS

Fixed Time Related


Amount
Item Description Unit Cost Cost
UAE Dhs UAE Dhs UAE Dhs

To Collection UAE Dhs -

Conditions of Contract (Cont'd)

Clause
No.

A 2 Engineer and Engineer's Representative Item

B 3 Assignment and Subletting Item

C 4 Contract Documents Item


Included
D 5 Drawings and Specifications Item

E 6 Obligations of the Contractor Item

F 6A Free Issue Items Item

G 7 Bonds Item 1,031,001.17

H 8 Advance Payment Item

J 9 The Site Item

K 10 Contractor's Employees Item

L 11 Plant, Workmanship and Contractor's


aaaiiiaEquipment Item

M 12 Title, Risk, Care, Indemnities and


aaaiiiaInsurance Item

N 13 Applicable Laws Item Included

P 14 Patent and Other Protected Rights Item

Q 15 Secrecy Item

R 16 Traffic and Loads Item

S 17 Commencement and Progress Item

T 18 Suspension of Works Item

EHV 28, 31 32 BQ 1/3


BILL NO. 1
GENERAL REQUIREMENTS FOR
THE WHOLE OF THE WORKS

Fixed Time Related


Amount
Item Description Unit Cost Cost
UAE Dhs UAE Dhs UAE Dhs
U 19 Time for Completion and Liquidated
aaaiiiaDamages Item

To Collection UAE Dhs 1,031,001.17

Conditions of Contract (Cont'd)

Clause
No.

A 19A Tests on Completion Item

B 20 Taking Over Item

C 21 Defects Item

D 22 Variations Item

E 22A Provisional Sums Item

F 23 Claims Item

G 24 Nominated Subcontractors Item

H 25 Measurement Item

J 25A Extended Warranties from


aaaiiiaSubcontractors Item
Included
K 26 Interim and Final Certificates Item

L 27 Payment Item

M 28 Fixed Price Item

N 29 Frustration and Force Majeure Item

P 30 Default of Contractor Item

Q 31 Termination for Convenience and


aaaiia Default of Employer Item

R 32 Jurisdiction Item

S 33 Notices Item

EHV 28, 31 32 BQ 1/4


BILL NO. 1
GENERAL REQUIREMENTS FOR
THE WHOLE OF THE WORKS

Fixed Time Related


Amount
Item Description Unit Cost Cost
UAE Dhs UAE Dhs UAE Dhs

T 34 Dubai Municipality Permits and


aaaiiiaCertificates Item

To Collection UAE Dhs -

Restrictions

A Access for and Possession or use of the Site (See


SOPR Clause 3.1, 6.1 and 6.5) Item 19,092.61

B Limitations of working space (See SOPR Clause


6.5) Item 38,185.23

C Maintenance of existing services on, under or


over the Site (See SOPR Clause 6.15) Item Included

D Execution of the Works in the required specific


order, sections or phases Item Included

Contractor's Administrative Arrangements

E Site administration (See SOPR Clause 8.1 and 9) Item Included

F Supervision Item 12,601,125.45

G Security (See SOPR Clause 6.9) Item 152,740.91

H Safety, health and welfare of workpeople (See


SOPR Clause 3.3.5, 3.3.6, 3.3.8 and 6.10) Item 13,302,543.04

J Transport of workpeople (See SOPR Clause


3.3.13) Item 2,291,113.72

Constructional Plant

K Small plant and tools Item 229,111.37

L Scaffolding (See SOPR Clause 6.13) Item 381,852.29

M Cranes and lifting plant (See SOPR Clause


3.3.12) Item 12,410,199.30

EHV 28, 31 32 BQ 1/5


BILL NO. 1
GENERAL REQUIREMENTS FOR
THE WHOLE OF THE WORKS

Fixed Time Related


Amount
Item Description Unit Cost Cost
UAE Dhs UAE Dhs UAE Dhs
N Transport (See SOPR Clause 5.2) Item Included

P Other plant not listed above but necessary for the


completion of the Works Item Included

To Collection UAE Dhs 41,425,963.92

Constructional Plant (Cont'd)

A Third Party Inspection Item Included

B Off Site Storage Item Included

Employer's and Consultants' Facilities

C Site photographs (See SOPR Clause 9.6) Item 15,274.09

D Employers and Consultants Accommodation (See


SOPR Clause 3.3.9) Item 267,296.60

Contractor's Facilities

E Offices, laboratories, compounds, stores, messing


facilities and living accommodation (See SOPR
Clause 3.3.5, 3.3.7 and 3.3.8) Item 381,852.29

F Temporary fencing, hoardings, screens and


guardrails (See SOPR Clause 6.5) Item Included

G Temporary roads, hardstandings and crossings


(See SOPR Clause 6.4) Item Included

H Water for the Works (See SOPR Clause 3.3.2) Item 954,630.72

J Lighting and power for the Works (See SOPR


Clause 3.3.1) Item 1,374,668.23

K Temporary telephones, telex and facsimile (See


SOPR Clause 3.3.4) Item 229,111.37

Temporary Works

EHV 28, 31 32 BQ 1/6


BILL NO. 1
GENERAL REQUIREMENTS FOR
THE WHOLE OF THE WORKS

Fixed Time Related


Amount
Item Description Unit Cost Cost
UAE Dhs UAE Dhs UAE Dhs

L Traffic diversion (See SOPR Clause 6.2) Item Included

M Access roads (See SOPR Clause 6.4) Item Included

N Bridges Item Included

P Pumping Item Included

Q De-watering (See SOPR Clause 6.14) Item Included

To Collection UAE Dhs 3,222,833.30

Sundry Items

A Testing of materials (See SOPR Clause 4) Item 190,926.14

B Testing of the Works Item Included

C Provision of As-Built Drawings (See SOPR Clause


7.3) Item 38,185.23

D Protecting the Works from inclement weather


(See SOPR Clause 6.5) Item Included

E Project notice board (See SOPR Clause 6.6) Item 38,185.23

F Removing rubbish, protective casings and


coverings and cleaning the Works at completion
(See SOPR Clause 6.7) Item 305,481.83

G Traffic regulations (See SOPR Clause 6.2) Item Included

H Maintenance of public and private roads (See


SOPR Clause 6.3) Item Included

J Drying the Works Item Included

K Control of noise and pollution (See SOPR Clause


6.12) Item Included

L Statutory obligations Item Included

EHV 28, 31 32 BQ 1/7


BILL NO. 1
GENERAL REQUIREMENTS FOR
THE WHOLE OF THE WORKS

Fixed Time Related


Amount
Item Description Unit Cost Cost
UAE Dhs UAE Dhs UAE Dhs
M Design of the Works to the extent provided for in
the Contract Item Included

N Warranties Item Included

P Co-ordination of the Works Item Included

R All mock ups, prototypes and samples required by


the Specification, the Drawings and the Schedule
of Project Requirements (See SOPR Clause 10) Item 381,852.29

To Collection UAE Dhs 954,630.72

COLLECTION

Page No. 1/1 -

Page No. 1/2 1,031,001.17

Page No. 1/3 -

Page No. 1/4 41,425,963.92

Page No. 1/5 3,222,833.30

Page No. 1/6 954,630.72

EHV 28, 31 32 BQ 1/8


BILL NO. 1
GENERAL REQUIREMENTS FOR
THE WHOLE OF THE WORKS

Fixed Time Related


Amount
Item Description Unit Cost Cost
UAE Dhs UAE Dhs UAE Dhs

TOTAL FOR BILL NO. 1 - GENERAL REQUIREMENTS


FOR THE WHOLE OF THE WORKS TO MAIN SUMMARY UAE Dhs 46,634,429.11