Documente Academic
Documente Profesional
Documente Cultură
RISK LEVEL
CONSEQUENCE
LIKELIHOOD
RISK
Sr No
ACTIVITY SIGNIFICANT HAZRAD/RISK EXISITNG CONTROL MEASURES FURTHER CONTROL MEASURES REMARKS
LEVEL
Shoring should be in place if depth of trench warrants it along with extended poling
boards & ladders for safe access/egress. Operative should ensure that shoring etc has
been done to his/her satisfaction before descending into trench & gain access only by A written inspection record by a
Crushing, persional injury, death 2 3 6 suitable access equipment. Excavations must not be adjacent to buildings and heavy competent person should be kept
plant kept away from edges. Stop blocks should be placed behind wheels of vehicles of the excavation.
tipping into excavation. Do not store materials, waste materials or plant adjacent to
excavation.
At all stages of the excavation, a competent person must supervise the work and the
workers given clear instructions on working safely in the excavation. If plant is being
Impact with plant and A written inspection record by a
Soil excavation used above the trench then no operatives should be in the trench when the machine is competent
underground services.persional 3 3 9 in use. Area must be scanned for underground services & permit to excavate issued person should be kept
injery, death of the excavation.
before work commences. Hand digging only in the vicinity of underground services. Area
of dig shall be secured by 2M heras fencing.
CONSEQUENCE
LIKELIHOOD
Sr No RISK
ACTIVITY SIGNIFICANT HAZRAD/RISK EXISITNG CONTROL MEASURES FURTHER CONTROL MEASURES REMARKS
LEVEL
Fall prevention barriers shall be erected around excavation. Stop blocks installed at a A written inspection record by a
Falls from height & falling
objects,persional injery, death 2 3 6 safe distance from excavation preventing vehicles from falling into excavation. PPE – competent person should be kept
Hard hats & Safety shoes to be worn. of the excavation
Insufficient working space to 2 2 4 Contractor to consider carefull phased approach and plan the work
undertake demolitions
Lack of team working and own Both contractor and Subcontrctors to engender team spirit and co-operation with Progress reports will be updated
5 Co-ordination 2 3 6
Agendas being pursued shared responsibilities and ownership. DGES Steering Group to keep accountability and monitered daily
Injury, Death due to the wild Personal Protection Equipment (PPE) – Safety shoes to be worn duing site activities, A safety meeting will be held once
7 Wild animals 2 4 8
animal attacks Maintaining first aid kits a week to educate workers