Documente Academic
Documente Profesional
Documente Cultură
,QGHSHQGHQWO\RSHUDWHGPDLQHQJLQHERZDQGVWHUQWKUXVWHUDQGVWHHULQJJHDU
FRQWUROV[5ROOV5R\FH-R\VWLFN
7KHVHSDUWLFXODUVVKRXOGEHWDNHQDVLQGLFDWLYHDQGGRQRWFRQVWLWXWHDZDUUDQW\)RUDGGLWLRQDOLQIRUPDWLRQSOHDVHFRQWDFW*XOI0DUN8./WGDWFKDUWHULQJXN#JXOIPDUNFRPRUDWZZZ*XOI0DUNFRP
M.V. HIGHLAND NAVIGATOR
UT745 - 9,600 BHP PLATFORM SUPPLY/ROV SUPPORT VESSEL
Yard no.134
MAIN PARTICULARS
L.O.A.....................APPROX. 84.0 m
L.P.P....................................76.2 m
BREADTH MLD......................18.8 m
DEPTH MAIN DK....................7.6 m
DESIGN DRAFT.......................6.35 m
MAX DRAFT..........APPROX. 6.20 m
CLASS
DnV +1A1-SF-E0-DYNPOS AUTR-DK(+)-HL(2,8)-CLEAN UT 745
DEMOUNTABLE CRASHRAIL
PROFILE
UP
DN.
AIR CASING
MEDICINE
EX.
75 80 85 90 95 100 105 % 110
DN. INSTR.
85 90 95 100 105 110 ROOM
WHEELHOUSE UP
BASE OIL
BASE OIL
CASING
UP
F.O. F.O.
DN. C-DECK
BRIDGE DECK
MIDSHIP FR.65
2M AIR CASING
2nd. eng.
2M 1M
2M
OFFICE
UP
75 80 85 90 95 100 105 110 115 120 125
DN.
DAY ROOM UP
2M 1M
DN 1M
AIR
CASING
B-DECK
2M
OFFICE
2M 2M
2M
2M AIR CASING
2M
STORES
EX.
2M LOCKER
UP EX.
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 852M 90 95 100 105 110 115 120 125
DN.
MESS STORE
UP
EX.
STORE
DN 2M AIR
CASING DAY ROOM
-25°C +4°C
PROV. PROV. DRY GALLEY
PROV.
SIDEGATE
A-DECK
EMERG. GEN
SURVEY OFF.
PAINT STORE
2M 2M
AC
LAUNDRY 2M
OX WASHROOM
RECEPTION 2M
INSTR.
UP ROOM
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85
WORKSHOP
90 95 100 105 110 115 120 125
TO ENG.ROOM 2M
HOSPITAL 2M
2M
ROV SURVEY
OFFICE
CO2
SIDEGATE
MAIN DECK
F.O. F.O. F.O. BASE OIL
F.O. F.O.
SERV.
F.W.
BRINE/MUD MUD MUD MUD
DN.
BRINE
HPR F.W.
W.B./D.W.
F.W. STAB TK.
BRINE
STAB TK. STAB TK. W.B./D.W. CEMENT CEMENT CEMENT CEMENT
STEERING W.B./D.W. W.B./D.W./SLOP
GEAR TANK TANK TANK TANK W.B.
ROOM
THRU. WORKSHOP CONTROL ROOM
Aker Brattvaag
HATCH
5 ROOM
EX.
0 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125
UP
CEMENT CEMENT CEMENT CEMENT
UP
TANK TANK TANK TANK DN.
F.W. BRINE
W.B./D.W.
HPR
F.W.
BRINE/MUD MUD MUD MUD
Søviknes Verft AS
Tel: +47 70 21 08 00 Fax: +47 70 21 08 01
6280 Søvik, Norway
F.O.
BRINE/W.B. BRINE/MUD MUD MUD MUD F.O. F.W.
BRINE
F.W. W.B./D.W.
SVAS NO.
HPR
134-101-00
F.W.
UP
W.B.
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125
REV.
F.W.
UP
F
HPR
W.B./D.W.
F.W.
BRINE/MUD MUD MUD MUD
F.O. BRINE/W.B. BRINE
F.O. F.W. F.W.
F.O. F.O.
C/D
VOID
SERV. SETTL. DRAIN
TANK
F.O. F.O. F.O. BASE OIL TANK TOP
7KHVHSDUWLFXODUVVKRXOGEHWDNHQDVLQGLFDWLYHDQGGRQRWFRQVWLWXWHDZDUUDQW\)RUDGGLWLRQDOLQIRUPDWLRQSOHDVHFRQWDFW*XOI0DUN8./WGDWFKDUWHULQJXN#JXOIPDUNFRPRUDWZZZ*XOI0DUNFRP
M.V. HIGHLAND NAVIGATOR
UT745 - 9,600 BHP PLATFORM SUPPLY/ROV SUPPORT VESSEL
TANK CAPACITIES
7KHVHSDUWLFXODUVVKRXOGEHWDNHQDVLQGLFDWLYHDQGGRQRWFRQVWLWXWHDZDUUDQW\)RUDGGLWLRQDOLQIRUPDWLRQSOHDVHFRQWDFW*XOI0DUN8./WGDWFKDUWHULQJXN#JXOIPDUNFRPRUDWZZZ*XOI0DUNFRP
Vessel specification
ST259 Arctic – Offshore Construction Vessel – Oceanic
CONSTRUCTION/CLASSIFICATION FEATURES
Built by Keppel Singmarine Pte Ltd Completely new ship design, fallpipe system and rock installation
system.
Year of construction 2011
Rock installation capacity abt. 2,000 t/h.
Classification Bureau Veritas
Installation depth 1,500 m through fallpipe with inner diameter of
abt. 700 mm.
MAIN DATA
Diesel electric propulsion system comprising three main diesel
Dynamic positioning system DP-2
generator sets and one auxiliary diesel generator set.
Positioning system DGPS, HIPAP, Fanbeam
Accommodation on fore ship, complement 60 persons.
Length overall 158.60 m
Engine room in aft ship.
Breadth 36 m
Rock installation system and moonpool in mid ship.
Moulded depth 13.50 m
Innovative fall pipe ROV with integrated survey ROV.
Design draught 9.40 m
Optional: Side Chute for rock installation close to structures and in
Cargo carrying capacity 24,000 t shallow waters.
Cargo hold capacity 15,500 m³ Optional: Deflector, mountable on Fallpipe ROV for accurate rock
installation. Typically used on soft soils and narrow rock berms for
Sailing speed loaded 13.5 kn
longer stretches.
Total installed power 15,192 kW (3x4,500kW +
Optional: Jet Flow Tool, mountable on Fallpipe ROV for flattening
1x1,200kW + 1x492kW)
and trenching purposes.’ For more details reference is made to
Main engines 3 x 4,500 kW the Jet Flow Tool leaflet.
(3x main generator sets)
Optional: Solid Ballast Unit, mountable on aft deck for solid
Main propellers 2 x 4,500 kW ballasting of gravity based structures.
(2x azimuth thrusters)
SIDE VIEW
T +31 78 69 69 000
F +31 78 69 69 555
royal@boskalis.com
www.boskalis.com
Rockpiper:
Description Manufacturer Model/Type
Vessel - Propulsion
Engines
Main generators (3x) Wärtsilä W9L32 common rail
Auxiliary generator (1x) Wärtsilä W6L20 C3
Emergency generator (1x) Caterpillar 3412 C DITA
Thrusters
Main propellers (2x) Rolls-Royce Azimuth thrusters UUC405
Retractable thrusters (2x) Rolls-Royce Azimuth thrusters UL2001FP
Bow thruster (1x) Rolls-Royce Azimuth thrusters TT2400 DPN FP
Vessel - Dynamic Positioning System
DGPS (2x) C&C technologies C-NAV 3050’s GNSS
Diff. Corrections (2x) C&C technologies Proprietary satellite corrections
DGPS (1x) Trimble Trimble SPS851 GNSS
Diff. Corrections (1x) Fugro SeaStar Proprietary satellite corrections
MBX-4 (3x) Hemisphere GPS IALA beacon receivers
Gyro Compass (2x) Tokio Keiki TG-8000
Gyro Compass Fiber optic (1x) Ixsea Octans Mk4
Heading, Attitude and Positioning Sensor (1x) Kongsberg Seatex Seapath 330
FanBeam (1X) MDL Laser Radar 4.2
Motion sensor (4x) Seatex MRU5
USBL HiPAP (1X option for 2) Simrad Kongsberg HiPAP 501
CTD (1x) Seabird SeaCat SBE19 plus
Video overlay and recording system Visualsoft VisualDVR
HiPAP Transponder with Acoustic release and Flotation
Simrad Kongsberg cNode Maxi 34-180R
collar (1X)
HiPAP Transponder with Acoustic release and Flotation
Simrad Kongsberg MPT339/DTR
collar (1X)
Rock Installation Unit
Stone Dumping Unit (SDU) Huisman A10-44000
SDU - Motion Reference Unit (MRU) Seatex 5&H
Glass Reinforced Polyester (GRP) - inner diameter 700
Fall Pipe Boskalis
mm
Nordnes
Decades of experience
This document is the property of Van Oord Group. This document or any part thereof is CONFIDENTIAL and may not be made
known, copied, multiplied, or used in any other way without the permission of Van Oord Group.
Table of contents
Content
1 DP Flexible Fall Pipe Vessel Nordnes ............................................................................................. 4
1.1 Vessel Data ............................................................................................................................. 4
1.2 Propulsion................................................................................................................................ 5
1.3 Dynamic Positioning System ................................................................................................... 5
1.4 Accomodation .......................................................................................................................... 6
1.5 Communication facilities.......................................................................................................... 6
1.6 Vessel Certification .................................................................................................................. 6
2 Fall Pipe ROV Stornes ..................................................................................................................... 7
2.1 General .................................................................................................................................... 7
2.2 Dimensions .............................................................................................................................. 7
2.3 Propulsion................................................................................................................................ 7
3 Rock Installation Equipment on board Nordnes............................................................................... 8
3.1 Flexible Fall Pipe System ........................................................................................................ 8
3.2 Vessel Self-Unloading Equipment........................................................................................... 8
3.3 The BMH self-unloading system ............................................................................................. 8
3.4 Handling Tower Stornes .......................................................................................................... 8
3.4.1 General ................................................................................................................................ 8
3.4.2 FPROV hoisting/umbilical winch.......................................................................................... 9
3.4.3 Umbilical/hoisting wire ......................................................................................................... 9
3.4.4 ROV catcher frame............................................................................................................ 10
3.4.5 Umbilical guidance frame .................................................................................................. 10
L.B.P. : 161.15 m
Beam : 24.5 m
DP class II
1.2 Propulsion
Main: MAK 8M43 5900 kW
@ 1800 rpm
Dynamic positioning:
@ 1800 rpm
Diesel generators (4x) Caterpillar 3516 B DITA max 1900 kW (2549 bhp) @1800
− And hard wired signals to the power plant, rudder and thrusters.
1.4 Accomodation
Total accommodation 50 bunks divided in:
− 22 x 1 person cabin (incl. 2 x 1 person client cabin)
− 15 x 2 person cabin (incl. 2 x 2 person client cabin)
− Each cabin has a toilet and shower facility.
− Further the accommodation contains:
− x client offices
− x offices Van Oord
− Mess room
− Day & recreation room
− Gym
− Meeting room
2.1 General
The FPROV is, as the lowest section of the fallpipe, used to control the direction of the production
flow. Before and after rock installation operations, survey operations are executed with survey
equipment mounted on the FPROV.
The FPROV consists of a carbon steel space frame with a vertical tunnel through the centre to
accommodate the fallpipe.
Two survey arms can be deployed to a horizontal position with a reach of 2.5 m. Each arm is able to
support 250 kg of mounted (survey) equipment. The arms are operated by hydraulic rotary actuators.
A fail-safe retraction mechanism stows and latches the arms if hydraulics fails or allows the arms to
fold under the FPROV under total system failure. This is to ensure that the FPROV can always be
recovered through the moonpool.
2.2 Dimensions
Diameter: 3.80 m
2.3 Propulsion
Installed power: 300 kW, distributed to four 75 kW nominal motor shaft power thrusters drive
units.
Transmission system: Electro-hydraulic. Each thruster has its own 75 kW (nominal) electro-hydraulic
power pack. The FPROV can operate with only three of the four packs in
service.
Electric motors: Impaq 75 kW, 4-pole 50/60 Hz (60Hz for full performance). Hydraulic pumps:
Variable delivery swash plate pump.
Thrusters: Curvetech HT750BA – 920 mm overall diameter with four bladed propeller
and bent axis hydraulic motor. 15 kN static thrust available per thrusters.
The vessel self-unloading equipment consists of three conveyors. The hold conveyor is situated at the
bottom of the vessel, just above the tank top and under the holds. The length of the hold conveyor is
110 m and it has a width of 2.20 m. The speed of the hold conveyor can be varied between 0.5 m/s
and 2.2 m/s.
Next in line is the so called C-conveyor. This is a system of 2 conveyor belts placed vertical in the loop
tower. These conveyors run at a constant speed of 2.2 m/s. The last conveyor of the ships self
unloading equipment is the boom conveyor housed inside the hinged discharge boom hanging above
the four forward hatches. The length of the boom conveyor is 85 m and it has a width of 1.60 m. The
boom conveyor runs at a constant speed of 3.2 m/s.
The cargo flows by force of gravity onto the hold conveyor situated below the bottom gates. The hold
conveyor brings all installation material forward to the C-conveyor system. The material is then
pressed between the two conveyors and lifted 22.5 m up to the boom conveyor. The boom conveyor
transports the material to the hopper on deck.
From here the material is transported via the deck transport system to the flexible fallpipe.
The handling tower and the dosage hopper are placed on deck, situated on the starboard side
between holds no. 4 and 6.
The handling tower is situated in the center of the vessel. In this way the moonpool under the tower is
not blocking the starboard- and portside hold conveyors in the bottom part of the vessel. The hopper is
situated at the starboard side of the vessel, right under the exit opening of the boom conveyor. During
offshore operations the boom conveyor stays the starboard position. Inside the tower a number of
platforms are situated for storing and handling of the FPROV, the flexible fall pipe and the bucket
winch.
− Three single drum winches are installed in the tower for the purpose of hoisting and lowering the
FPROV. The three steel armoured umbilical wires (winches, over three positioning sheaves in the
top of the tower to the FPROV. The three umbilicals are identical, two of them are used for power
supply to and controls of the FPROV and for data transmission. The third umbilical is used as a
spare.
To guide the flexible fallpipe from the bucket storage container to the bottom of the sea following
equipment is installed in the tower:
− Outer adjustable bucket guidance frame;
− Outer fixed bucket guidance frame;
− Bucket winch;
− Inner fixed bucket guidance frame;
− Inner retractable bucket guidance frame.
To enable launch and recovery of the FPROV through the moonpool during marginal weather, a
Umbilical Moonpool Frame is installed. This UMF is hoisted and lowered by means of four UMF
chains, connected in the four corners of the frame. The UMF chains are so called endless chains and
enable the UMF to be pulled up and pulled down. Each UMF chain is controlled by its own catcher
frame winch.
During launch and recovery of the FPROV and flexible fallpipe and while the FPROV is in the water
the horizontal movements of the three umbilicals are limited to a minimum by means of the UMF.
During sailing and loading the FPROV will be stored on the two moonpool top doors on deck level in
the tower. Once the FPROV is lifted from the top doors, the doors can be skidded sideways and so
opening the moonpool and enabling the FPROV and flexible fallpipe to be lowered through the
moonpool. With the FPROV and flexible fallpipe launched and the top doors closed the circular
opening in the top doors allows the flexible fallpipe to pass through during installation operations. For
general purposes a marine crane is mounted in the top of the tower.
Mechanical characteristics:
During launch and recovery of the FPROV through the moonpool the ROV catcher frame winches are
coupled to the ROV hoisting winch thus enabling “one joystick control” for both ROV catcher frame
winches and ROV hoisting winch.
Make: Effer
7,700 kg @ 23.10 m
The crane winch is a 10 T direct pull winch in double reefed execution (20T pull capacity). The winch
is installed on the boom with 100 m of wire rope with a diameter of 24mm. The hoisting speed on the
second layer of the wire rope at the recommended oil flow (160 lit/min) is 10 m/min (double reefed).
Between the bucket storage container and the outer adjustable bucket guidance frame a bucket
connection table is installed. The bucket connection table is used as a work deck to connect the
different bucket sections of the flexible fallpipe.
Through the guidance frame the buckets are guided towards the tower and the bucket winch and
back. The guidance frame contains a bucket chain twist detection to detect twists in the bucket chains
before it can cause damage to the bucket winch.
Speed: 10 m/min
The foundation of the bucket storage container rests on 1 kingpin and 2 skidbeams: one kingpin
between hold 1 and the loophouse, one between hold 2 and hold 3 and one between hold 4 and the
tower. The bucket storage container can be turned around the kingpin over the skidbeams from port to
center and back by means of hydraulic cylinders. The container will be rotated before launch of the
flexible fallpipe only to bring the desired compartment in line with the outer adjustable bucket guidance
frame and bucket connection table (this is only required if the actual flexible fallpipe length has to be
more than 300 m). To enable loading over starboard in certain quarries where the loading conveyor is
not high enough, the bucket storage container can be rotated to portside completely.
To stack the buckets during recovery of the flexible fallpipe two stack winches, including the stack
winch power packs, are mounted on the forward side of the container: one for stacking on starboard
side of the container and one for stacking on port side. Each stack winch drives an “endless” stack
chain around a counter wheel on the aft of the storage container. During recovery of the flexible
fallpipe the bucket chains can be connected to the stack chains and the buckets can be pulled into the
bucket storage container compartment.
The bucket storage container controls can be operated local on the container itself or from a remote
portable control.
3.7.1 Bunker
Capacity: 37.5 m3
Type: JV 132-28
Width: 2,000 mm
Length: 7,000 mm
Drive power: 22 kW
Width: 1,400 mm
Length: 9,000 mm
Drive power 22 kW
Width: 1,400 mm
Length: 7,000 mm
Drive power: 22 kW
By integrating the mV-signal from the load cells and the pulse signal from the speed recorder de
weight integrator processor unit generates a product flow in tons per hour. Furthermore the processor
unit is able to display the conveyor load in kg/m, the conveyor speed in m/s and a production day total
and overall total.
5 Survey Equipment
DP Reference Systems
Description Equipment
Position Trimble SPS855 D-GNSS (incl Fugro Marinestar corrections)
C-Nav 3050 D-GNSS (single reference corrections)
Seatex Seapath 330 D-GNSS (Seastar DGNSS corrections receiver)
KM HiPAP 501 USBL
KM Radius 1000
Heading Seatex Seapath 330 GNSS heading device
IxBlue HydrINS Fibre Optic Gyro
Ship’s heading device
Motion Seatex MRU-5
IxBlue HydrINS
DP KM K-POS
4
Survey – SRI Operations
Description Equipment
Primary positioning system FUGRO StarPack D-GNSS (XP/HP/BestPos multi-ref solutions)
Secondary positioning system Seatex Seapath 330 D-GNSS (Seastar DGNSS corrections receiver)
Tertiary positioning system C-Nav 3050 D-GNSS (single reference corrections)
Primary heading system Seatex Seapath 330 GNSS heading system
Secondary heading system IxBlue HydrINS Fibre Optic Gyro
Primary motion sensor Seatex MRU-5
Secondary motion sensor IxBlue HydrINS
Primary SSBL system KM HiPAP501 USBL
Current profiler Teledyne-RDI Workhorse Long Ranger (75kHz)
MBES (hull mounted) R2Sonic 2024
Data acquisition software QINSy
Data charting & designing VOSS.NET
5
Survey – SRI Operations
Description Equipment
SSBL Positioning Various KM cNode miniS SSBL transponders & Responders
INS IxBlue ROVINS
Heading IxBlue ROVINS
Motion IxBlue ROVINS
Depth sensor Tritech SK704 bathymetric system
Velocity sensor Teledyne-RDI Workshorse Navigator DVL (1200kHz)
Water column parameter sensor Valeport miniSVS & miniSVP
Scanning sonar Tritech Gemini 720is Imaging sonar
Multibeam system R2Sonic 2024 high resolution multibeam system
Video camera system Bowtech Explorer Extreme & SubC DVR-O
6
Vessel specification
Dynamically positioned pipelay vessel Solitaire