Sunteți pe pagina 1din 17

ROYAL MELBOURNE INSTITUTE OF TECHNOLOGY (RMIT)

MC 257 - MASTER OF ENGINEERING (CIVIL ENGINEERING)

OENG 1117 - RISK AND PROJECT MANAGEMENT

ASSESSMENT 1
(INDIVIDUAL ASSESSMENT)

CLEON THYPARAMBIL MANUEL

STUDENT NUMBER : 3678324

SUBMITTED ON 1st SEP 2017


1) INTRODUCTION
“It must be considered that there is nothing more difficult to carry out nor more
doubtful of success nor more dangerous to handle than to initiate a new order of
things.” (Niccolo Machiavelli). And we human beings were always keen onto innovating and
improvising everything on our sight, to enhance the efficiency and performance of the
system, all with just one ultimate desire, make our life a little more easier and effortless.
Well, obviously it never ended up well every time, introduction of new things and methods
to an existing one will have some risk factor involved. Depending on the scale and
magnitude of the project, the risk involved varies. Apparently, it is impossible to eliminate
this component, but with effective identification, analysis, evaluation and treatment, it
could be controlled and monitored to a great extent. Here comes the relevance of an
effective risk management strategy. It involves various methodologies which can be
implemented to determine the source and probability of an uncertain event, to analyse the
impact it can bring about both quantitatively and qualitatively, and how to effectively treat,
monitor and control that respective risk component.

2) RISK MANAGEMENT
Huge engineering projects are usually associated with high probability of
unanticipated outcomes due to the high stake games played by the stakeholders within the
internal context due to the amount of resources and substantial limitations in management,
and some external influence. Such billion dollar projects characterized by the irreversible
commitments to the system, which after being built will either be a great asset to the nation
or an unforgettable disaster. There are several instances in which, some of the projects
ended up having little use as per the original intended purpose. Hence a detailed analysis in
every possible outcome evaluating every impact it can bring in, must be done. It has to be
kept under consideration that , it may take some time for sufficient revenue generation
from such projects taking into account the large capital money invested , especially
government undertaken projects for the public welfare. Substantial front end expenses may
have to be undertaken. For every project, the main objectives include Cost, Time and
Quality. To meet all these, effective risk management is necessary. To complete within the
estimated budget before the completion date without compromising on the performance
and utility of the building is the ultimate goal. For a successful project, it has to be shaped
with risk resolution. Even though, it's often indeterminate and endogenous and hence it's a
real issue to manage risk. Most of the ideas and principles used in risk analysis and
management practice we have seen since 1970s and 80s has developed considerably. New
and more sophisticated techniques are developed and used in almost every societal sectors
today. Advances are made in many basic issues in this domain recently and the scope of this
report is to carry out a risk assessment of Melbourne Metro Tunnel project, based on these
advanced concepts and practices in risk assessment and project management.
Fig.1 Risk Management Process

Melbourne Metro tunnel


A contemplative response to the exponential expansion of the Melbourne city.
Within the next decade the average weekday patronage is expected to near double that of
today's. To accommodate this mob, an effective public transformational innovation was
found to be highly necessary. The twin nine kilometre tunnels connecting south east
suburbs to the western city limits with 5 new underground stations is supposedly the
biggest public transport infrastructural development witnessed by the city after the
construction of city loop which was completed 30years ago.
The Sunshine - Dandenong line is anticipated to be accommodate a huge mass of
patronage flow through the city. By bypassing it without interfering with the existing city
loop will deliver an effective public transport system not only to the prescribed lane, but
also to the other lanes. The high capacity metro is estimated to accommodate a whooping
39000 passengers each 2 hour peak period each morning and afternoon from the operation
date. New underground stations included are at Arden, Parkville, CBD North, CBD South and
Domain
Fig.2 Melbourne Metro Tunnel

The Melbourne Metro tunnel connects the Cranbourne / Pakenham and Sunbury
lines, the metropolitan lines which inter connects the city's largest growth corridors to north
west and south east. It will increase number of services in theses corridor and thereby
enables subsequent expansion of these networks and suburbs. It also enhances the capacity
of inner core network for 5 other lines namely Frankston, Upfield, Craigieburn, Sandringham
and Werribee lines as it releases the inner core capacity to be shared amongst these lines.

3) RISK IDENTIFICATION
Identification of the risk is obviously the first step to be implemented in risk
assessment. Many organization follow many strategies for risk identification process and is
uncommon to specifically stick to one single method for this. With the advancement in
research and development in this domain with respect to the importance of an effective
strategy for risk assessment, many new methods have been introduced to the industry
especially in the recent decades for managing the risk by either avoiding it, transferring it or
adopting alternate methods to it. Even though, most organization still rely on conventional
and common methods of risk identification like Brainstorming, Questionnaire survey, based
on previous experience, physical and visual inspections, Interviews, group discussions etc. It
has to be noted that, these conventional methods could be effective in identifying some
obvious and probable events that can occur and must not be avoided. But it doesn't imply,
that these methods are suitable enough to identify all the risk factors associated with the
project.
As this is the primary stage of risk assessment , utmost care must be given not to
miss any potential risks, because, unless its identified at this stage, that particular factor
may not be considered in the subsequent assessment stages and can be a major issue in the
future. Hence its very critical to undertake a well structured detailed and systematic
identification procedure to be followed especially in a huge scale project with a substantial
working life span. Every single risk which can be identified with respect to the
implementation, management, maintenance, future development must be studied carefully
whether or not that specific risk comes under the control of the organization. The
methodology accepted must be able to substantially justify what, where, why, when and
how something could happen and not just a vague idea about some of them. It should also
be understood that some of the risks and their impact depends on how it combine and
interact with the existing or proposed system of administration.
For large scale engineering projects, the major risks confronted would be associated
with 3 main areas, Completion risks, Institutional risks and Market-related risks. The timely
commencement and completion of construction works could be difficult and unmanageable.
Only with efficient technical and operational methodologies, this objective could be
achieved. Market-related risks must be considered one of the most important as the
primary objective of the project is for the service and utility for the customer. Institutional
risks, like checking with the regulations, standards prevalent and to ensure social
acceptability and reputation. Hence risks must be identified in all these fields separately and
to be assessed. Many risks are observed to emerge over time. Projects which were found
good enough at a certain period of time may suddenly become ungovernable. A forecasted
study of risk assessment is hence necessary. In short, the risk identification may seems
simple, but is the most important and critical part of assessment criteria. For a large scale
project like Melbourne Metro tunnel, I would recommend not to stick with one single
criteria of risk identification, but to undertake some different risk identification methods like
Brain storming, Interview with the public and stake holders, experience based on previous
exposure of working under similar projects and other methods like SWOT and history, failur
analysis etc. and the following risks were identified
The Melbourne Metro tunnel project is estimated to cost $10.9bn considering the
several peer review and calculation. Although, there exist a huge probability that there
might be some uncertainty in the estimation process. This cost has been estimated based on
the forecasted material, labour and other service costs for the period of construction which
can be variable from what has been anticipated. This cost, along with the probable
contingency may not be the final expenditure spent on the project as its calculated based on
the best case scenario. In the event of an unanticipated issue, say an increase in material
cost, there might be additional costs involved which can alter this amount which could be
identified as one of the major project risk.
The anticipated time frame for construction completion is 5 years. This time span is
calculated as per the timely progress and management of all the procedures involved. This is
also highly probable that may vary depending upon the different elements involved.
Different statutory approvals are yet to be confirmed, if under some circumstances,
it is delayed, the whole project completion period also will be varied. The Land and property
acquisition has not been completed. It has been learned that additional funding have to be
requested for this and may take some more time. Due to the constrained working
environment right in the middle of the city, many limitations are to be met which can
substantially affect the construction period.
One of the other major risk factor involve is the expected efficiency and performance
from the project which is at stake. It is proposed that the high capacity twin tunnel metro
project will greatly enhance the public transport system of the city. It is described that the
city loop congestion could be reduced with the introduction of this project. How much
positive impact it could bring about is yet another matter of discussion. Is it really worth the
huge amount spent on a project rather than improvising the existing system of rail network.
Whether it could be a good alternative to accommodate double the number of current
passengers in the rail networks .
The Construction techniques and methodologies planned may be inappropriate as
there may be variations from the anticipated site conditions. A good example would be a
difference in ground conditions. It is not uncommon that the geotechnical analysis may not
be 100% precise and accurate and is often encountered with variations. Also, the early
works carried out are not up to the expected standard and wasn't completed on the
specified time frame. The machinery and other assets used can be worse than prescribed
and limited availability of resources across the key stake holders and contractors etc. will
enhance the risk element.
Maintenance and other operations could be challenging taking into account the
construction carried out right in the heart of the city near to many buildings and
infrastructure. There is a huge chance that it can have an adverse impact on these
neighbouring structures. The construction activities also limit the public from utilizing the
different services and community facilities in and around the construction site and restrict
swift access to different locations around. The air and sound pollution caused by the
construction will be yet another issue to be faced by the public which will greatly impact the
acceptance by people.
No matter how much experiments and analysis are carried out, the ground always
remain unpredictable. Tunnelling projects thus raise huge risk to the different stake holders
involved especially the public. The ground water table, heavy machinery and transport
activities, Darkness, limited oxygen supply, limited space, high construction noise,
temperature , Dealing with explosives and high voltage equipments etc make tunnelling
projects dangerous and risky. The buildings and people around and above the tunnelling
sites could be affected by these factors. It may leads to safety hazard threats to both the
workers and public involved in and around the workspace. Ensuring the safety and
protection of them has to be the first and foremost importance during the execution of
project.
4) RISK ANALYSIS
The primary objective of undergoing risk analysis of the observed and identified risks
is to measure its impact. There is two major factors governing this criteria. The likelihood or
the probability of occurrence of the project and the consequence or severity of that
particular risk. However, any construction project will involve many variables, and is often
difficult to accurately determine the dependence and correlations and its required to follow
subjective analytical methods to assess the impact of risk and uncertainty. For a large scale
project like Melbourne Metro tunnel, I would recommend not to stick with one single
criteria of risk analysis, instead undergo some of the common and popular as well as
advanced methods. I consider two of the following qualitative analysis and two other
quantitative analysis for the project.

Qualitative Risk analysis


This method follows the analysis of intangible factors involved, following are eg:
Risk register
It normally consists of identified hazards in a tabular format list, often divided into a
number of risk categories like the following (Hintze 2011). It will be developed referring to
the extensive work undertaken in previous studies and supplemented to consider the
different associated risk with similar huge engineering projects.
Working environment - Injuries to workers on site.
Third party - Injuries to people other than workers on site.
Project property - Damage to project property.
Third part property - Damage to third party property.
Environment - Damage to natural resources.
Time - Delay of activities with specified time.
Cost - Budget overrun.
Trust/good will - Occurrences reducing stakeholders trust.
The risk register will be expanded with project progress and can include more information
about rating and probability to help in risk evaluation.

Risk Matrix
After determining the likelihood ranking and severity ranking the risk impact can be
verified. After the likelihood factor and severity impact has be independently y ranked, we
can relate to this risk map shown below. One major feature is that it shows risk of high
probability but low severity and low probability but high severity is similar. Based on the
Impact rating (Trivial, Minor, Moderate, Major and Extreme) and Probability (Rare, Unlikely,
Moderate, Likely and very likely) the Risk impact could be identified from the following table.
Try to follow any mitigation process to eliminate/ reduce/ transfer/control the risks with
high impact.
Fig.3 Typical Risk Matrix

High High risks that are most likely to arise and have potentially serious
consequences and require immediate attention
Medium Medium risks are likely to arise but not necessarily and can have some
potentially serious consequences and must be taken care of.
Low Minor risks exhibit only low consequences and are unlikely to occur that
may be managed by routine procedures

Fig.4 Key to Risk Matrix

Quantitative Risk analysis


The quantitative risk analysis method, different from qualitative methods as it aims
to quantify cost, time and performance impacts of risks. It determine the size of cost and
schedule contingency reserves that may be needed. Techniques like sensitivity analysis,
Decision tree analysis, Expected monetary value analysis, Fault tree analysis, Event tree
analysis and Monte Carlo simulation are examples.
Event tree analysis
It's a forward, bottom up, logical modelling technique used for assessing the
probable chance of a single initiating event by exploring the responses from different
associated events. Here, let's consider a failure event of tunnel collapse during the
construction. Now we have to identify the consequent events followed by impact of
initiating event, say like ground failure plane confronted, shotcrete lining crack etc. Now, by
analysing the probability of each event as shown below in figure, we can identify the
probability of the main event to occur. Its a very useful technique which can be used
especially in case of a hazard or a failure event.

Fig.5 Example of an Event tree analysis for an event in tunnel construction

Monte Carlo simulation


It gives a fairly accurate and precise quantitative output based on the input variables.
Its uses classic calculations and close-form formula to determine the possible outcomes and
their probabilities. It gives us more realistic results in comparison to other methods used in
the industry. It can use thousands and thousands of random iteration samples using
computer power and hence gives a information rich outcome. Suppose we wanted to find
the total cost estimation of the project. We can define different input distributions like
Excavation, Ground strengthening, Shotcreting and lining, Electrical, Finishing etc. and
determine the probable total cost estimation.
Fig.6 Monte Carlo simulation using @RISK software

5) RISK EVALUATION
The evaluation of the risk is followed after analysing and understanding the risk
factors involved with the project so as to decide what has to be done about it. In this part
we have to make observations on the analysed risk so as to reach conclusions on whether
that risk needs treatment, should it to be prioritized and find out preferred options suitable
for the respect risk treatment. It is to be done through establishment of qualitative and
quantitative relationship between the benefits and associated risks. It has to clearly identify
the level of risks that can be acceptable, level of investment that can be necessary, existing
mitigation methods and its effectiveness. As we know, it's impossible to eliminate the total
risk involved with a project, hence based on the risk evaluation, risk acceptance criteria has
to be followed upon. The following risks are prioritized, undergone acceptance criteria and
classification, evaluated for existing measures to identify if further mitigation is found to be
relevant.
Budget overrun was identified as one of the most critical risk and can be given the
most priority. The amount of resources and services spent on a project will have a
substantial effect in determining the success of a project. Based on risk matrix the impact
was found out to be high as it has major impact and is likely to happen. Using Monte Carlo
simulation we can find the most probable budget. Although, the cost estimation for the
Metro tunnel project was carried out by Department and the Cost Adviser. The estimate has
undergone extensive review and refinement to ensure mitigation of the risk factor. (Refer
Fig.7 ).Evaluating the strategy implemented and measuring its effectiveness we can classify
this risk under "ADEQUATE" and opportunities for further mitigation is observed. Hence this
risk has to be considered for treatment process.
Time Delay is yet another critical risk to be considered with maximum priority. The
project is expected to be completed within 5 years. Any further delay to this can severely
impact on the system. There can be several factors involved which can lead to this cause. On
analysis on risk matrix, the impact was found to be high and necessary actions has to be
made at most urgent. Using Event tree analysis, we can list out the numerous factors which
can influence the construction time period and using the probability of occurrence of each
components, we could determine the probability of this event. Some of the main factors
which could substantially delay the time required for project completion was the delay that
can cause due to Planning and statutory approvals. To reduce the impact this could cause, a
comprehensive EES can be prepared informing minister for planning's assessment. In
addition a Planning and statutory approval program can be developed. One of the other
reason that can cause time delay is in land acquisition. For avoiding this risk, the land
requirements were identified at an early stage itself and was continued to be successful in
achieving appropriate milestones so far. Based on evaluation of existing criteria, this risk can
be have undergone 'STRONG' (Fig.7) methods to avoid the probable happening of the same.
Even though considering the scope of some improvements, it may be considered for further
Risk treatment procedures.

STRATEGY USED RESULT DESCRIPTION


Risk mitigation activities are properly
Effective output structured, designed and operating as
intended.

Controls and/or management activities are


Limited opportunity for
operating but some improvements could
Improvement
be done.

Some activities for controlling the situation


Considerable
are in place, although opportunities for
improvement opportunity
further mitigation is observed.

Substantial improvement Limited methodologies are used within the


opportunity system, Level of risk is not much reduced.

There is only some or no effective


Critical improvement
measures implemented, Immediate and
opportunity
necessary improvement recommended.

Fig.7 Risk Evaluation Criteria - Existing strategy implemented for mitigation


The expected effectiveness and performance efficiency of the project is the other
major risk factor under consideration. The Metro tunnel has the primary objective of
reducing the huge rush into the city loops and bifurcate the patronage flow into additional
network system. It is a very complex and challenging research to analyse and determine the
population growth into specific regions. There are several factors which constitutes into it
and is highly variable. The metro tunnel project connecting the south eastern and western
suburbs of the city is designed to mitigate the impact of exponential growth rate in number
of people using the train network between these suburbs. How much it could be anticipated
and how effective it can be to the existing city loop system is yet to be researched and
identified. It is highly probable that the system could reduce the patronage flow to the city
loop, but to which extent, and whether is suitable enough to accommodate the mob flow
into and out the city centre is yet to be researched. Using the Risk matrix analysis it is found
to have extreme impact, although the likelihood of such a risk is unlikely or moderate.
Based on the very limited strategies and methodologies to identify and mitigate this risk we
can classify it under 'NEEDS IMPROVEMENT' (Fig.7) and requires some risk mitigation
research and techniques to be implemented.
The limitations with the prediction of work environment especially the ground
stability. Even with our advanced and new experimental analysis on ground, it is usually
unpredictable what we can expect. This put forth a huge risk factor. But it is not always
likely to meet with such adverse conditions, but cannot be avoided too. Based on the rare
occurrence of such an event the impact of this is found to be moderate. In fact, there's
nothing much we can do about it other than use the most advanced methods identified by
geo technical engineers to analyse the ground condition. Hence we can conclude further
treatment for this risk category may not be required.
The Impact of construction in the heart of city to the neighbouring buildings, services
and the public welfare. The location of main 2 stations at both end of Swanston street in
the CBD, the North and South CBD stations will be a major constrain to the construction
procedures as well as a huge problem to neighbouring area. The piling works carried out at
the time being causes huge sound pollution, air pollution and cause inconvenience to the
people using service around the construction site. Inaccessibility to some of the cultural as
well as community centre was a major concern aroused recently. This brings about the
immediate requirement of additional improvements to the existing strategies implemented.
Even though barricades and warning notifications cover the entire region of construction
additional preventive measures to control noise pollution using noise absorbing
technologies, reducing air pollution etc could be considered and thus can be classified under
'NEEDS IMPROVEMENT' (FIg.7) and require immediate attention.
Risk factors associated with underground tunnelling projects are to be considered of
utmost importance especially in this case as its right under a metropolitan city. The
preventive measures associated with the safety of public as well as he workers involved with
the project is necessary. There are several common hazards and risks associated with
tunnelling works as of collapse, convergence, portal protection, inadequate ground support,
sinking, ground freezing, air quality and ventilation, dusts, heat stress, fire and explosion,
chemicals, visibility and lighting, electrical safety, falls from height, object falling, vibrations,
radiations etc. sufficient measures as per the standards recommended by the Australian
code must be complied with any cost. As the construction company involved with project
has been found reliable and with reasonable expertise in this field, chances of such a
mishappening is greatly reduced. Although the impact is severe, considering the
unlikelihood its impact is found to be low and sufficient measures are already been
implemented for compulsory as per the Australian standards. Strategy implemented is
found to be 'EFFECTIVE' (Fig.7) Hence further treatment of this risk factor may not have to
be carried out.

6) RISK TREATMENT
The process of risk treatment involves identifying the range of options for treating
the risk, how to evaluate them, and thereby preparing risk treatment pans and successfully
implementing them. The objective is analyse the available options so as to identify the best
possible measure to the risk considered. It's a process of selection and implementation of
the optimal and effective measures so as to modify the risk component. There are several
options for risk treatment, choosing the right one depends on how significant the risk is, the
cost of treatment commensurate with the potential advantage it can bring about to the
existing system. The following are the treatment options and associated implementation
plan which can be considered.

Risk acceptance
In several occasions, the only possible way to deal with the risk is to simply accept it.
Although, care must be taken into account with considerable impact and likelihood of its
occurrence. It is always recommended to adopt this method at circumstances where the risk
exhibits only a limited or small threat to the system and is highly unlikely to happen. But in
some cases, with the constrain in probable treatment methods we have to accept it, say as
in case of tunnel construction, the unpredicted ground behaviour. Irrespective of advanced
techniques and methodologies, it cannot be predicted and the only means of treatment is to
accept it. It means if it was to occur , the cost associated must be have to be met by the
sponsor. Although, Only risks of minimal rating are generally accepted. If in any case the risk
under considered is found to be avoidable, it has to be always preferred over the
acceptance of the risk
Risk avoidance
This is the most recommended and common risk treatment method as we annihilate
any chance of the occurrence of the risk under consideration. Although, its highly
recommended we may not always find efficient methods to totally avoid a risk. It is usually
practiced if the risk is observed to be of high impact and likely to happen. It can be
sometimes associated with the cancellation of an activity or even a set of activities.
Sometimes it is possible to modify the situations so as to avoid the risk. An example with
Metro tunnel project would be to avoid blasting methods for tunnelling and using TBM
machines to avoid probable risk which can cause due to explosives. As we had modified the
construction method, we had totally avoided the consequence of such a risk.
Risk Mitigation
If total avoidance of an identified risk is found to be impossible, we may have to
proceed with risk mitigation methods. By implementing this treatment methodology, we are
substantially reducing the potential impact which can the risk may exhibit. Measures have
to be taken to make sure that the risk mitigation is done to the maximum extent possible
with available resources so as to diminish the probable impact of such an event. This
method is the most common practice of risk treatment as its found to be more proven
technique. Using different standards and codes by the council and national regulatory
bodies have the primary objective of implementing this strategy. Using the minimum
recommended grade of construction material in tunnel construction as per the Australian
standards considering the adverse service environment expected underground, so as to
ensure the structural safety and strength of the infrastructure is a good example of this kind
of risk treatment method.
Risk Transferring
This is a powerful method of risk treatment in an organizational point of view. Even
though it may not ensure that the risk has been successfully managed. It is the mere
transfer of responsibility in full or in part from the particular project organization. The
liability or loss may not have to be met by the original project sponsor or contractor is the
main advantage of using this method. It will generally occur through contracts, bonds,
retention etc. for example your insurance contract is perhaps the most commonly used risk
transfer form used. Here a 3rd party accepts the risks of payment of a premium for covering
the damage, loss or the legal and personnel liabilities which can happen. Other examples
include lease agreements, waivers, disclaimers, tickets etc. The most common risk
transferring method under practice is the contracting method which is followed by almost
every construction projects in the industry. Here the primary contractor bifurcate its
responsibility and risk element involved to sub contractors on legal contract. There are
several types of contracts under practice like Lump Sum contract in which the primary
contractor agrees to pay a total sum of a fixed amount for the execution of a part of project.
Every risk involve with the completion of this part, now is transferred to this secondary
contractor. The secondary contractor will give a detailed scope of each and every work and
an amount is quoted for.
There is also a cost plus contract in which all costs are met with an additional profit
pay for the sub contractor. Here the risk involved is slightly lower than the lump sum
contract. Unit rate contract is fixed for the unit rate of different construction procedures.
Here there is no risk for the sub contractor if in case an additional work has to be met with,
as it may also be covered by the primary contractor.

7) MONITOR AND CONTROL RISK


Depending on the scale and scope of an engineering project, efficient monitoring
and controlling methodologies are to be planned and implemented. The risk identified
during a particular span of time may not be prevalent and may be subjected to several
variable components especially for a billion dollar project like Melbourne tunnel with a
proposed life span of a couple of centuries. So, it is necessary to have simultaneous risk
monitoring and review along with the project development. It is always advised to establish
a monitoring and review team for this process as it requires detailed study of past, present
and future elements involved with the project. It is the responsibility of the management
team to establish and control a system for ensuring the effectiveness of the risk treatment
plan. It may not be enough to identify, analyse, evaluate and treat the probable risk factors
during the construction stage but also on completion and during the service period of the
engineering project. Hence its important to have a risk management plan incorporating
different methodologies, responsibilities, risks, impact, tolerance of stake holders and
tracking. It is not a one way process but a cyclic one in which improvisations are to be done
at times required.

Fig.8 Risk Monitoring


8) CONCLUSION
Risk management is an integral part of any projects especially an engineering project,
and it should be seen and treated as such. Risk management should be fully incorporated
into the operational and management processes at every level of the organisation and
should be driven from the top to down. By the assessment done on risk management of
Melbourne Metro Tunnel, we could identify many important and relevant factors involved
with procedure. The primary objective of any project includes the Cost, time and quality of
the construction with environmental sustainability. Having a proper risk management
strategy ensures the successful achievement of these components. A comprehensive
assessment was carried out to the project identifying these goals and some of the risk
elements involved where successfully identified. The magnitude, impact and probability of
these factors were studied for the identification process. The observed risks are then
analysed and verified to ascertain the impact of occurrence of such a project. We could also
learn that there are quantitative and qualitative measures implemented to analyse a risk
factor and is recommended to carry out some of these techniques, for determining the
probable impact of the risk element. Risk register and Risk matrix analysis methods were
carried out on different identified risks and its impact has been verified. Risk register is a
common and recommended method for any construction project which enable us to have a
record of all the relevant information. Risk matrix analysis identify the likelihood and
severity of a risk to identify its impact and is found to be effective in analysing almost every
type of events. Some quantitative analysis methods were also carried out to give substantial
result outputs numerically to recognize its level of impact. The methods carried out under
this project were event tree analysis and Monte Carlo simulation using @Risk software. By
event tree analysis, we work out backward from an event by identifying different causes of
the events. By verifying the probability of occurrence of these independent elements, we
could identify the total probability of the main event. Monte Carlo analysis a advanced
methodology implemented to identify the most reliable numerical output in comparison to
other methods as it makes use of thousands of iterations randomly generated with the help
of computer power. Thus a detailed qualitative and quantitative analysis was carried out,
base on which we could evaluate the risk elements. The evaluation process of risk element
has to identify the potential risk level and prioritize the factors based on it. The elements
which are identified of highly probable and severe has to be prioritized and immediate
treatment methods are to be determined. For this process, we also must consider the
existing measures taken and its effectiveness. Likewise, every risk factors identified were
evaluated and the requirement of undergoing a treatment method is justified. Some of the
major treatment methods and plans were then studied which comprises the acceptance,
mitigation, avoidance and the transference to a sub level. The importance of simultaneous
risk monitoring and review were also studied to ensure that the project is maintained with
the best possible efficiency throughout its prescribed life span.
By doing this assessment report, we were able to inculcate the importance of a
structured risk management strategy and its benefits to the project. With the increasing
complexity and the subsequent risk factor involved with the modern world engineering
projects, the need of a powerful risk management plan is ascertained. It may also have to be
noted that, there was an exponential rate of advancement in research and invention of
techniques involved with this domain and is identified as highly relevant. Hence its
recommended for the owner, contractors and stake holders involved with a project to
understand and realize the importance of it and thereby manage and control potential risks
effectively and thus ensuring the successful completion of a quality engineering project.

9) REFERENCE

Authority, M.M.R., 2016. Melbourne Metro Business Case. Melbourne Metro Rail Authority.

Avestedt, L., 2012. Comparison of Risk Assessments for Underground Construction Projects A study
about distinctions and common features and suggestions for improvements.

Miller, R. and Lessard, D., 2001. Understanding and managing risks in large engineering
projects. International Journal of Project Management, 19(8), pp.437-443.

Faber, M.H., 2008. Risk Assessment in Engineering–Principles, System Representation Risk


Criteria. JCSS Joint Committee of Structural Safety.

Skjong, R., Vanem, E. and Endresen, Ø., 2005. Risk evaluation criteria. SAFEDOR report D, 4(2).

Zou, P.X., Zhang, G. and Wang, J., 2007. Understanding the key risks in construction projects in
China. International Journal of Project Management, 25(6), pp.601-614.

S-ar putea să vă placă și