Method Of Statement For START A CONVERSATION

Installation of wires and cables – Like Share 265 people like this.

Wiring SUBSCRIBE
You will Receive Each New Method Statement In Your Email as Soon as It Is
Below  is  the  list
Published.
Fiber Cable of  equipment  /
Tools  required
Enter your email address:

Testers for  installation


of  wires  and Subscribe
cables,  which Delivered by FeedBurner
Range of quality equipment cab be used for
from a leading specialist different "We recommend these Project Management Templates for delivering
supplier projects  after your projects successfully."
doing  the
customization
as  per  the
project
requirements.

Cutting Tools
Hydraulic Crimping Tools
Manual Crimping Tools
Scaffolding Step Ladder
Cable Drum Trolleys
Cable Spindle s & Jacks
Cable Rollers
Measuring Equipment
Megger
Pulling Wires, Rope, Lubricant (Soap­based, Wax Based)
Hand Gloves, Fall protection and Other necessary PPE’s.

Installation Of Wires & Cables

All  materials  intended  for  cables  &  wires  shall  be  submitted  for
approval  of  the  consultant  as  per  the  standard  procedure  using
the Notification of permanent material received at site. POPULAR METHODSTATEMENTS
Material  samples  shall  be  submitted  as  required  by  the Download Method Statement for Installation of
consulting engineer for approval. Lightning Protection System
June 6th, 2015
 INSPECTION AND GUIDANCE
Download Method Statement for Installation of Lightning Protection System
The  Supervisor  will  complete  the  inspection  checklist  and  follow Including Earth Pits  Dow [...]
the Inspection & Test Plan detailed in this procedure. The intent
Download Method Statement for Testing &
http://www.methodstatementhq.com/method­of­statement­for­installation­of­wires­and­cables­wiring.html 1/6
6/7/2015 Method Of Statement For Installation of wires and cables
of this procedure is to establish a high level of assurance that the Download Method Statement for Testing &
end product meets the specification requirements. Commissioning of Variable Air Volumes VAV
The  QA/QC  Inspectors  should  verify  the  approved  procedures System
are  followed  and  the  inspections  and  testing  records  are June 5th, 2015

completed. Download Method Statement for Testing & Commissioning of Variable Air
Volumes VAV System  Downl [...]
TRAINING & QUALIFICATIONS OF PERSONNEL

All operatives will attend safety induction along with the relevant Download Method Statement for Installation Of
document  copies  i.e.  valid  visa  company  ID  copy,  and  copy  of Underground Electrical Duct Banks and Sleeves
previous  experience  and  training  in  the  same  job  which  proves June 5th, 2015
his competency. Download method statement for Installation Of Underground Electrical Duct
Supervisor  should  closely  monitor  the  activity,  if  he  finds  any Banks and Sleeves  Downlo [...]
operative is lagging on safe work competency, he will be sent for
re­induction and even retraining if deemed necessary. Download Method Statement for Installation Of
Examine the areas to execute the work and the conditions under Cable Raceways Trays Ladders & Trunking
which the work will be performed. Identify conditions detrimental June 4th, 2015

or  unsafe  for  the  proper  and  timely  completion  of  the  Work.  Do Installation Of Raceways (Cable Tray, Cable Ladder And Cable Trunking) For
not  proceed  until  unsatisfactory  or  unsafe  conditions  have  been Electrical Services  Dow [...]
corrected.

INSPECTION & STORAGE OF MATERIALS Download Method Statement For Testing &
Commissioning of Audio Visual System AVS
Submit  Notification  of  Permanent  Material  Received  on  Site  i.e. June 4th, 2015
Material Inspection Request upon receipt of materials delivery to
Download Method Statement For Testing & Commissioning of  Audio
site.  Attach  Delivery  Receipt,  Material  Submittal  Approval  and Visual System AVS  Download pa [...]
other  documents  to  show  complete  compliance  with
specifications and QA/QC Plan. Download Method Statement For Testing &
Any  material  found  not  as  of  approved  material  or  with  surface Commissioning of Access Control System ACS
damage which is not rectifiable will be set aside. These materials June 3rd, 2015
will  be  labelled  and  returned  to  supplier  warehouse  and  a  Non­
Download Method Statement For Testing & Commissioning of  Access
conformance  Report  will  be  issued  to  the  supplier  by  QAlQC Control System ACS  Download  [...]
superior.
Store  materials  in  protected  dry  location  off­ground  in Download Method Statement For Installation of
accordance  with  manufacturer’s  instructions  and  to  protect  from Access Control System ACS
mechanical  damage  or  weather  effects  etc.  Extreme  care  shall June 3rd, 2015
be taken while handling the subject materials.
Download Method Statement For Installation of  Access Control System ACS
Lay  down  area  at  site  to  be  coordinated  with  MAIN  Download package contain [...]
CONTRACTOR and arrangements to be made for unloading and
/ or mobilization of materials.
Ladders  /  Scaffoldings  to  be  secured  firmly  over  the  working
platform  and  inspected  by  competent  personnel  and  tagging
system (green/red) are implemented, prior to start of work.
Prior  to  commencement  of  work,  the  Engineers  &
Supervisor/Foreman  will  inspect  all  materials  delivered  to  work
place  are  checked  for  with  their  shipment  check  list  and  ensure
they  are  the  relevant  piece  for  the  site  and  materials  are  not
damaged, without excessive scratches or visible corrosion.
Only  required  materials  to  be  shifted  to  site  and  stored
temporarily  and  ensure  extra  materials  are  not  dumped  to  site
and congest the working area.
Once  work  is  completed  extra  materials  and  tools  to  be  return
back to stores, work area to be kept clean.

http://www.methodstatementhq.com/method­of­statement­for­installation­of­wires­and­cables­wiring.html 2/6
6/7/2015 Method Of Statement For Installation of wires and cables
Pre Installations

Ensure all drawings are approved and available to the installation
team.
Prior  to  the  installation  of  cables  in  any  area,  cable  ladders  or
any  containment  system  must  be  inspected  and  approved.
Ensure that the factory test reports for continuity of the cables is
provided and reviewed to ensure the fault free installation.
Check  that  ladders/trays  are  free  from  any  sharp  edges  and
have sufficient space for installing the cables.
Ensure that ladders/trays are provided with purpose made bends
to accommodate the minimum bending radius of the cable. This
is to ensure that cable is not given undue stress.
PVC  sleeves  shall  be  installed  for  all  cables  passing  through
brick, block or concrete or similar structures in case there is need
for future withdrawal.
Non  ferrous  spacer  clips  for  multiple  runs  and  single  fixing  non­
ferrous  clips  for  single  runs  will  be  provided  for  cables  fixed
directly to the structure.
Collect  and  keep  ready  at  site  materials  such  as  cable  pulling
sleeves, tools, rollers  and tackles etc.

Preparations:

Cables  and  wires  shall  be  installed  in  accordance  with  the
approved  shop  drawings  and  properly  coordinated  with  MAIN
CONTRACTOR  site  engineer/construction  manager  for  exact
locations and levels.
Proper marking / selection of location on site to be done prior to
commencement of installation works.
Complete  a  mock­up  installation  before  main  works  and  get  its
approval.

INSTALLATION PROCEDURE I WORK SEQUENCE

Wires Pulling

i.    Make sure that all conduits and boxes in both ends are free from
damages and blockages etc and installation is approved.

ii.    Blockage shall be checked by inserting the draw wire and checking
that it reaches to the other end without any disturbance.

iii.    Once the conduit is not blocked the wires shall be pulled using the
draw wires while ensuring no damage occurs while pulling.

iv.    Pulling compound or lubricant shall be used for pulling the wires
where required.

v.    Use soap­based pulling compound for short runs i.e. less than 20
meters for semi conductive insulated wires.

vi.        Use  wax  based  pulling  compound  for  the  runs  greater  than  20
meters for semi conductive insulated wires.

vii.    While pulling the wires care should be taken to not insert the pull
tension greater than the manufacturer allowed limits.

Cable Pulling & Termination

1.  Transport and place the cable drums as per drum schedule and
at  the  locations  where  space  is  available  for  working.  The  cable
drum shall be placed on a jack & spindle arrangement to ensure
free rotation of the drum.

http://www.methodstatementhq.com/method­of­statement­for­installation­of­wires­and­cables­wiring.html 3/6
6/7/2015 Method Of Statement For Installation of wires and cables
ix.      Erect scaffolding where required as per the site requirements.

x.      Cable rollers shall be placed under the cable during pulling over
longer  distances  and  standoff  rollers  for  acute  bends,  to  ensure  that
the  cable  is  pulled  with  minimum  effort  and  the  cable  outer  jacket  is
free of scouring lines.

xi.            The  cable  shall  be  pulled  by  using  pulling  means  such  as  fish
tape,  rope  and  basket  weave  wire/cable  grips  so  as  not  to  damage
cable or its containment system. Care will be taken to ensure that the
maximum pulling tension of all the cables is not exceeded at any time.

xii.      Cable should be free of any static load i.e. to be places side by
side parallel on the cable tray or ladders. Any kind of dead weight on
the cable shall be avoided.

1.  At  all  times  the  cable  schedule  &  section  drawings  for  the
relevant  area  will  be  referred  to  ensure  proper  location  of  cable
on  the  required  ladder  and  to  ensure  compliance  with  project
specifications.
2.  A pulling compound / lubricant shall be used where necessary as
per site conditions i.e. in slabs and underground conduits etc, the
lubricant should not deteriorate the cable insulation.

xv.      The cables shall be secured to the containment system using
approved  cable  ties  for  horizontal  runs  and  cable  cleats  for  vertical
runs.

1.  All  control  cables  will  be  installed  at  a  minimum  distance  of
100mm  from  power  cables  unless  otherwise  agreed  with
consultant as per site conditions.
2.  Earth (green/yellow) cables shall also be pulled along the power
cables.
3.  At  all  time  of  pulling,  mark  both  power  and  earth  cables  for
pairing  them  on  both  sides  of  connection  i.e.  at  sending  and
receiving ends.
4.  Before  termination  complete  length  and  route  of  the  cable  shall
be  inspected  by  QA/QC  engineer  ,  after  which  a  RFIA  shall  be
raised for consultant approval. Cable shall be caped and sealed
on both ends after installation until termination is done.

xx.            Termination  shall  be  done  by  using  the  approved  termination
materials  that  include  glands,  lugs  and  other  accessories  part  of
termination  kit,  by  using  proper  crimping  tools.  Matching  colour  gland
sheaths shall be provided.

1.  All  termination  shall  be  provided  with  tight  fitting  covering
sleeves.

Insulation Resistance Test

Set the Meggar meter to 1000 volts DC for cables and 500 volts
DC for wires.
Take  reading  between  phase,  phase  and  neutral,  phase  and
earth neutral and earth.
Note  that  resistance  reading  must  not  exceed  2  mega­ohms
(MΩ)
Check and record the resistance readings as per specification on
the approved insulation resistance test forms.

Cables Identifications

Install  the  tags  /  labels  as  per  project  specifications  and  as  per
approved material submittals.
Cables  shall  be  identified  at  feeders  i.e.  the  sending  and
receiving ends (outgoing cables in SMDB’s and final DB’s) about
50mm below the gland.

http://www.methodstatementhq.com/method­of­statement­for­installation­of­wires­and­cables­wiring.html 4/6
6/7/2015 Method Of Statement For Installation of wires and cables
Identification labels shall be provided at all positions where cable
changes  direction  and  each  side  of  the  wall  or  floor  slab  and
where cables are in multiple runs.
Cores of cables connecting control gear, thermostats, valves etc
will also be identified and shall be fitted with identification sleeves
bearing  the  same  marking  as  the  terminals  of  the  apparatus  to
which these are connected.
For  cables  at  feeders,  identification  will  be  done  as  per
specification and approved materials.

Attachments:

ITP
Checklist
Risk Assessment

"We recommend these Project Management Templates for
delivering your projects successfully."

JOIN US NOW:You will Receive Each New Method Statement In
Your Email as Soon as It Is Published.

Enter your email address:

Subscribe
Delivered by FeedBurner

LIKE US ON FACEBOOK
Find us on Facebook

Methodstatementhq
Like

265 people like Methodstatementhq.

Share this:

 Facebook  Reddit  StumbleUpon  Google  Tumblr

http://www.methodstatementhq.com/method­of­statement­for­installation­of­wires­and­cables­wiring.html 5/6
6/7/2015 Method Of Statement For Installation of wires and cables

More Method Statements:
1.  Installation Of Access Control System Method Of Statement
This method statement provides steps for the installation of access control security
system in order for operatives to understand the work to be executed, how it is to be
executed while making...

2.  Method Of Statement For Installation of GI Conduits &
Accessories For Electrical Works Method Of Statement For Installation
of GI Conduits & Accessories For Electrical Works is given below for the reference
of our visitors if you want to use this method statement...

3.  Transformer testing & commissioning method statement
Below is a standard method statement which can be used as learning purpose and
to prepare further professional method statement for testing and commissioning of
transformers. Required tools for transformer...

4.  Installation Of Central Battery Emergency Lighting System 1.
Purpose This document describes the methodology for the installation of
emergency Lighting central battery System in Project, and to ensure that all
concerned persons are familiar with the sequence...

5.  METHOD STATEMENT FOR PVC WIRING & TERMINATION
This work method statement explains and covers the wiring through conduits and
its termination to the equipment / boards etc. Required Tools Pulling Rope
Lubricant Markers Masking Tape Quality &...

6.  What Is A Method Of Statement? What is a method statement? this is
a question many people come across while they are working in the field of a
process, manufacturing or construction. A method statement as...

7.  Method Statement For Installation Of Central Battery System
The following procedure will be followed for installation of Central Battery system
and can be customized as per the specific needs for different projects. Equipment
& Tools required Tool Box Pulling...

8.  Method Statement for Conduit Installation Including
Accessories PVC & GI Below is a comprehensive method statement for
conduit installation which can be used for purpose of any project and it can be
approved easily by consultants because it covers all aspects of...

9.  Installation Of MV LV Switchgear & Panels – Method
Statement This method statement for installation of medium and low voltage
switchgear and panels boards on site is prepared to define the method used to
ensure that all MV/LV switch gear and...

10.  Method Statement For Installation & Testing of SMATV
System Below are the steps or method statement for installation & testing of
SMATV System in a project. 1.0   Purpose 2.0   Scope 3.0   References 4.0  
Definitions 5.0   Responsibilities 6.0   Equipment 7.0  ...

Tags: Installation of wires and cables, Method Of Statement, Wiring Method
Statement

◀ Method Statement For Installation & Testing of
SMATV System
Installation of Marble and Granite Tiles on floor, stairs,
walls and counters ▶

© MethodstatementHQ.Com 2012­2015. All Rights Reserved. All Content Are Copyright Protected.

http://www.methodstatementhq.com/method­of­statement­for­installation­of­wires­and­cables­wiring.html 6/6

S-ar putea să vă placă și