Fence crossing : we can place the 4” PVC conduit with sub duct.
Fo cable strands:
1. Blue
2. Orange
3. Green
4. Brown
5. Slate
6. White
7. Red
8. Black
9. Yellow
10. Violet
11. Pink
12. Aqua
Budget loss:
Splice loss + attenuation loss + connector loss
Concrete :
As per SAES-Q-001 : non –structure concrete does not required curing (2000psi on
structure concrete does not required curing).
Concrete encasement for all conduit system must have minimum 75mm concrete covering.
Terra Tape: Orange colour Detectable terra tape is used for telecommunication system.
One layer of terra tape must be placed above the FO cable , tape need to be placed min
300mm above the cable and min 300mm below the ground level.
EMS: Electronic Marker System. EMS was placed at each end of the duct bank bellow the
marker post , min 150mm above the duct bank
Sub Duct :
Patch Panel :
1U comm scope patch panel.
Conning patch panel.
Ground test :
Pedestal : bellow 25 ohms
Comm. Cabinet : bellow 3 ohms
Wadi Crossing: In wadi crossing cable can be directly placed at 2.5m deapth , and 2 layer of
detectable warning tape is required.
If it is 4” coduit duct bank mandrel test need to be carried out befor concreting (initial
mandrel), after concreting (Final mandrel)
For connecting PVC conduit sealant , primer, cement solution are used.
Testing of FO cable :
Grounding Test :
Grounding test need to carried out for the pedestal and the communication cabinet.
Under Ground and the outside building PVC coated RGS conduits was used for the
protection of the cable .
SAES-T-911
Where it is necessary to install metallic pipe bends at building entrances, pole risers, etc.,
and the pipe bend is extended underground with non-metallic conduits, the cable shield to
metallic pipe bond may be omitted at the underground end of the pipe bend, provided that
this is concurred to by the Saudi Aramco Communications Standards Committee Chairman.
However, if the metallic pipe bend is extended underground with metallic pipe, the cable
shield/armor must be bonded to the metallic pipe at both ends.
Subduct colour : Orange , Green , White
Notes : For higher speed and fast transmission single mode FO cable is used.