Sunteți pe pagina 1din 5

SUI SOUTHERN GAS COMPANY LIMITED, KARACHI TERMINAL

ARRANGEMENT TO TAKE 2ND TERMINAL RLNG GAS AT CTS BIN-QASIM

JOB DESCRIPTION

Procedure to take gas from 2nd LNG Terminal which covers the pressurizing and commissioning
of 42” dia pipeline from MVA Pakland to MVA SMS Kotri, MVA Massu to MVA Lundo and
the other contingency arrangements at different places to ensure and meet the best engineering
practice we follow, as per following procedure to transport the RLNG gas from CTS Bin-Qasim
and to deliver SNGPL at exit point Sawan.

 Commencement of Job is subjected to availability of Gas for pressurizing the system.

1. PERSONNEL
Executives.
i) Site Incharge : Mr. Naushad Hizb-CE (Ops) HQ3/
: Mr. Khalil Khawaja-DCE (Ops) I/C Section-IV
: Mr. Najeeb Shafique –SE (MPLI)
: Mr. Mumtaz Memon- CE (Ops) HQ2
with team of Operation & Instrument Engineers
ii) Operational Incharge : Mr. Saeed Alam- CE (MPLI)

2. Subordinate Staff.
i) MRM : 03
ii) Helpers : 08
3. RESPONSIBILITIES.

3.1 MR. KHALIL KHAWAJA-DCE (Ops) I/C Section-IV


MR NAJEEB SHAFIQUE SE-(MPLI)
Area of responsibility: CTS Bin-Qasim to MVA RS-4
MR. NAUSHAD HIZB-CE (OPS) I/C HQ3
MR. ATIF KHAN DCE-(OPS) HQ3
MR. SHAKEEL AHMED-SE(Ops) HQ3
Area of responsibility: MVA RS-4 to MVA Massu
MR. MUMTAZ HUSSAIN MEMON- CE(Ops) I/C HQ2
MR. MUNEER PITAFI –ENGINEER (Ops) HQ2
Area of responsibility: MVA RS3 to MVA Lundo
 They will be responsible for all activities and shall be In-charge of entire activity
of valve operation required for pressurizing and commissioning in their respective
sections. Will be directly responsible for safe execution of entire operation in
accordance with the laid down procedures.
 Will be responsible to depute Engineers and staff at locations for valve operation
during the entire job.
 Will be responsible to coordinate with the team members for valve operation at
site in close liaison with Operation Incharge / Gas Control.
 PTW will be issued by In-charge Section-IV and HQ-3 for work to start at their
respective sections.
 Arrange proper lubrication of all valves of above segment.
 Arrange firefighting equipment, explosive meter and other facilities at work site,
duly checked for proper working.
3.2 MR. SAEED ALAM - CE (MPL-I)
 Will coordinate with team at site to carry out the subject job.
 Will give clearance at all stages for work to start from gas control KT after
communicating with work site and ensuring status of pipeline network
according to gas supply and demand condition.
 Will ensure valve operation according to the laid down procedure.
 Will arrange instrument Mechanic with requisite tools at Site.
 Will arrange explosive meter at site during operation.
 Will depute MPLI personnel for valve operation before starting the job.
 Will arrange for pressurizing & commissioning the system.
4. SAFETY MEASURES:
Following safety arrangements must be available at the work site and PTW issuing
authority and HSE department shall be responsible to ensure the same.
a. Arrange portable Fire Extinguishers in sufficient numbers at Site
b. Personal Safety Equipment, such as helmets, hand gloves, goggles etc. should be
make available at Site.
c. First Aid Box to be ready at Site.
d. Gas Explosive meter in working condition to be available at site.
e. Ensure issuance of P.T.W prior to start the job.
f. Safety gadget must be wear at all times during operations at Main Valve
assemblies:
• Safety helmet
• Safety boots
• Safety glasses
• Safety gloves
• Ear defenders / Muff
g. Safety Precautions should be observed /followed by field teams during the
operation:
a. Ensure that PTW is filled and signed by Section In-charge and Site in-charge prior
to start work.
b. Ensure that Safety sign boards are erected at the work site.
c. Ensure that once the work is completed all tools and equipment have been kept at
the proper place.
d. Never smoke at work site.
e. Mobile cell should be off during blowing & purging of the Gas.
f. No naked lights are allowed near to site during blow down and purging activities.
g. All vehicle will remain switched off during blow down and purging activities.
h. Ensure all relevant safety equipment is operational.
i. All members of team must receive brief safety instructions prior to start work at
launcher & receiver sites.
j. Ensure that personnel not involved in operation do not enter within barriers during
operations at valve assemblies.
k. Firefighting measures should be taken at sites prior to start opening blow-off
valves. CO2 fire extinguisher must be kept available at all sites. Firefighting teams
should be trained how to extinguish fire and how to protect themselves.
l. First aid kits must be available at work sites.
m. No idle person should stand near to the purging site.
n. In case of gas / condensate leakage urgent measures should be taken to assist
MPL-I personnel to eliminate the leakage as quickly as possible.
o. After completion of operation work site to be cleared properly.

SEQUENCE OF OPERATION
(Drawings are attached for reference)

 Ensure that the mobile communication between different work site and Gas Control room
KT is working properly.

CTS BIN QASIM SECTION-IV (refer Annexure-I)


 Hold Pre-Job meeting and assign duties to all officers & Staff participating in the
Operation. A Toolbox Talk (safety meeting) is to be arranged that focuses on safety
topics related to the job, such as workplace hazards and safe work practices. Explain
safety precautions to be taken during the operation to all team members.
 Segregate work area & erect safety signage at site.
 Arrange portable fire extinguishers, personal protective equipment (PPEs) & First Aid
Box (To be arranged by concerned section in-charge).
 Before starting activity ensures that the gas injection from FOTCO gas terminal is
within 100 MMCFD during the entire activity.
 Seek permission from Gas Control KT to start job. At the commencement of RLNG gas
injection from second terminal vent valve at upstream of 30” dia valve “A” to be opened
for purging and it is to ensure that clean gas is coming out of the vent.
 When 100% clean gas is coming out of the vent close the vent and gradually open 30” dia
ball valve “A” at CTS Bin-Qasim to allow RLNG injection from FOTCO re-gasification
system into SSGCL 42” dia RLNG-II pipeline.
MVA PAKLAND SECTION-IV (refer Annexure-II)
 Ensure that all the 42” dia main valves at MVA RS-5, Thatta & RS-4 are open.
 In close coordination with Gas Control KT open 42” dia ball valve “B”, “C” and “D” at
MVA Pakland and allow gas by opening meter skid by-pass pipeline valves to
pressurize the 42” dia RLNG-II Pipeline from MVA Pakland to MVA SMS Kotri.
(Keeping in view gas supply and demand condition of the system).
MVA SMS KOTRI HQ-3 SECTION (refer Annexure-III)
 When the pressure of 42” dia RLNG-II pipeline and 24” dia SNG-KYC pipeline
equalizes then first close 24” dia main valve “E” and open 42” dia interconnection valve
and 24” dia interconnection valve at MVA SMS Kotri as shown in detail A-A of drawing
SMS Kotri.
 Make sure that interconnection valve between 16” dia ILBP pipeline and 18” Badin
pipeline is closed. Open interconnection valve “R” of 24” dia SNG-KYC pipeline and
18” dia Badin Pipeline at MVA SMS Kotri.
 Open interconnection valve “p”, interconnecting 20” dia Kadanwari pipeline and 24” dia
SNG-KYC pipeline located at upstream of 24” dia main pipeline valve, which allow
indigenous gas flow towards Karachi through 20” & 24” dia pipelines.
MVA SIND UNIVERSITY HQ-3 SECTION (refer Annexure-IV)
 It is to ensure that interconnection valves of 30” dia pipeline with 20” dia Kadanwari
pipeline 16” dia ILBP pipeline at MVA Sind University are closed.
 Open 02 nos. 12” dia valves of interconnection of 30” dia pipeline and 18” dia Badine
Gas pipeline at MVA Sindh University. (make sure that interconnection valves with 20”
dia Kadanwari pipeline and 16” dia ILBP pipeline are closed). This will allow RLNG-II
Gas from 24” dia SNG-KYC pipeline and Badin Gas pipeline through 30” dia ILBP by-
pass pipeline to HQ-3.
HEADQUARTER HQ-3 (refer Annexure-V)
 Close 24” dia newly installed compressor suction isolation valve “H”. When the pressure
equalizes across valve “I”,
 Open 24” dia Massu-HQ3 pipeline interconnection valve “I” then “J” gradually (make
sure that 20” dia Kadanwari pipeline interconnection valve is closed). This will allow to
flow RLNG gas towards MVA Massu.
MVA MASSU BHURGARI & MVA LUNDO HQ-3 SECTION (refer Annexure-VI)
 Open 42” dia valve “m” fully.
 Before opening 24” dia interconnection valve “K” at MVA Massu the interconnection to
RLNG-II pipeline, the 42” dia RLNG-II pipeline section between MVA Massu and MVA
Lundo will first pressurized by opening 16” dia sacrificial valve at MVA Lundu
gradually (keeping in view that the supply to HQ2 compressor station should not
drop below the required pressure limit).
 When pressure of 42” dia RLNG-II pipeline equalizes across the 42” dia valve then open
42” dia main valve at MVA Lundo.
 Open 24” dia interconnection valve “K” gradually at MVA Massu to allow RLNG Gas
flow through 42” dia pipeline from MVA Massu to Compressor Station HQ-2.

UTILIZING 20” DIA KADANWARI PIPELINE FOR RLNG-II GAS.


SEQUENCE OF OPERATION
(Drawings are attached for reference)

HEADQUARTER HQ-3 (refer Annexure-V)


 Close 20” dia Kadanwari main pipeline valve “a” and ensure that pig receiver neck
valve “b” is closed, then open Kadanwari pipeline Interconnection valve “L” to allow
RLNG-II to 20” dia Kadanwari pipeline.
MVA MASSU BHURGARI (Kosar Gas diversion) (refer Annexure-VI)
 Open 12" dia Kosar Gas diversion pipeline valves "c" & “d” and close valves “f” &
“e”, which allow Kosar Field Gas flow towards HQ2. Simultaneously open 20" dia
RLNG-II interconnection valves “g” & “h”, which allow RLNG-II gas from 20” dia
Kadanwari pipeline to 42” dia RNLG-II pipeline.
MVA SMS KOTRI HQ-3 SECTION (refer Annexure-III)

OVERALL IN-CHARGE.

Mr. Syed Mahmood Jeelani DGM (GD) will be over-all In- charge of entire operation.

Date: 17-11-2017

S-ar putea să vă placă și