Project Execution Plan for Runway Construction David H Moloney

18th July 2016


Details how a Runway will be constructed, and how the construction will be monitored and controlled.
Brief Description

The purpose of this presentation is to give an understanding of the Methods,


Plant and Sequence to construct a Runway .

This presentation can be used to engage Stakeholders and to get the Site
Teams commitment to the programme. Also can be used for Induction
Training and as a way to capture and share knowledge.

Project Execution Plan (PEP) details how a project will be executed, monitored
and controlled.

High in Educational Value and easily understood. Recommended for


Continuing Professional Development (CPD)

This Video Presentation is innovative and has many beneficial uses.

http://www.slideshare.net/DavidHMoloney/runway-construction-project-execution-plan
Table of Contents
Runway Construction
Runway Construction Sequence & Methods
Roads & Pavings
Earthworks
Spreading & Compaction Clay fill
Earthworks
Spreading & Compaction Clay fill
Earthworks
Spreading & Compaction CABC ( Crushed aggregate base course )
Earthworks
Spreading & Compaction CABC
Runway Asphalt Pavement
Roads & Pavings

Brief Description

Sequence, plant and methods to construct a runway


Prime Coat Site Trials
Roads & Pavings

Bituminous Prime Coat shall


consist of supplying and applying
bituminous material to a previously
prepared and approved base
course in accordance with the
Specification to ensure a bond
between this surface and the
overlying course.
Runway Asphalt Pavement
Roads & Pavings
Runway Asphalt Pavement
Roads & Pavings
Runway Asphalt Pavement
Roads & Pavings
Runway Asphalt Pavement
Roads & Pavings
Runway Asphalt Pavement - Tests
Roads & Pavings
Runway Pavement - Marking
Roads & Pavings
Runway Pavement – Cleaning surface with rotating water jets
Roads & Pavings
Runway Pavement – Test for Skid Resistance
Roads & Pavings
Runway Pavement – Test for skid resistance
Roads & Pavings
Runway Pavement – Test for Smoothness
Roads & Pavings
Runway Pavement – Test for Texture
Roads & Pavings
Airfield Ground Lights Ducts & Chambers
Miscellaneous
Airfield Ground Lights Ducts & Chambers
Miscellaneous
Airfield Ground Lights Excavate Trench in CABC
Miscellaneous
Airfield Ground Lights – Concrete Ducts
Miscellaneous
Airfield Ground Lights – Surface Inset Lights
Miscellaneous
Airfield Ground Lights
Miscellaneous

Jig to Level Pot


Airfield Ground Lights - Core drill for Inset Light
Miscellaneous
Airfield Ground Lights Fit Pot with Jig
Miscellaneous
Airfield Ground Lights
Miscellaneous
ILS Localiser Antenna & Approach Lights Provides lateral radio guidance to an aircraft
approaching and landing on a runway
Miscellaneous
Approach Lights
Miscellaneous
Miscellaneous
Approach Lights Used by the pilot to align the aircraft visually with the runway centreline.
Provides radio vertical guidance to an aircraft approaching and
ILS Glide Path Antenna landing on a runway
Miscellaneous
DVOR Ground Station Omni Directional Radio Range (VOR) is a radio navigation system for aircraft, so
aircraft with to determine their position and stay on course.
Miscellaneous
Airfield Lights - Substation
Miscellaneous
Airfield Lights – Taxiway Guidance Signs
Miscellaneous
Concrete Slipform Paving
Roads & Pavings

Brief Description

Slipform Airport Concrete paving.

Texturing
& Curing

Spreader
Slipform Concrete Paver
Concrete Slipform Paving – Texturing Machine
Roads & Pavings
Concrete Slipform Paving - Slipform Machine
Roads & Pavings
Concrete Slipform Paving – Placer / Spreader Machine
Roads & Pavings
Concrete Slipform Paving
Roads & Pavings
Concrete Slipform Paving
Roads & Pavings
Concrete Slipform Paving
Roads & Pavings
Concrete Slipform Paving
Roads & Pavings
Concrete Slipform Paving – Drilling holes for dowels
Roads & Pavings
Concrete Slipform Paving – Drilling holes for dowels
Roads & Pavings
Runway Concrete Pavement
Roads & Pavings
Runway Concrete Pavement - Tests
Roads & Pavings
Road Milling / Planing Machine
Roads & Pavings
Cable Laying
Pipework

Brief Description

132 kVa Cable laying .


Cable Laying
Pipework
Cable Laying
Pipework
Cable Laying
Pipework
Cable Laying
ⓒ David H Moloney
Miscellaneous

Cable Drum Stand Cable pulled on rollers


Cable Winch

Cable Drum Unloading Cable on rollers Cable Testing prior to Backfilling


Horizontal Directional Drilling
Pipework

Brief Description

Horizontal Directional Drilling under a taxiway.


Process
1. A pilot hole id drilled to the designed profile
2. A reamer is pulled back through the hole to enlarge it
3. A pipe string is pulled into the hole.
Horizontal Directional Drilling
Pipework
Fencing
Miscellaneous

Brief Description

Fencing.
Sequence of construction;
1. Clear and grade the ground.
2. Fix corner and straining posts.
3. Fix intermediate posts.
4. Fix line wire, chain-link and razor wire.
5. Construct concrete ground beam
Miscellaneous
Fencing
Miscellaneous
Fencing
Miscellaneous
Fencing
Miscellaneous
Fencing
Airplane Wingtip Clearance
Miscellaneous

Brief Description

Regulation distances shown


for wingtip clearance.
Airplane Wingtip Clearance
Miscellaneous
Taxiway Reconstruction Airside
Miscellaneous

Brief Description

Regulations regarding working adjacent to


a live runway.
Taxiway Reconstruction Airside
Miscellaneous
Taxiway Reconstruction Airside
Miscellaneous
Article on Muscat Airport Runway Link http://www.ccc.me/pdf/bulletins/bulletin103.pdf
Runway Construction Pavement Details & Mixes

Runway Asphalt Runway Ends Concrete


Concrete
Reinforced Wall Construction Sequence
Concrete

Brief Description

The sequence to construct a reinforced concrete wall is as


follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.

Cycle Time
Pour per Day

ⓒ David H Moloney
Reinforced Wall Construction Sequence
Concrete

ⓒ David H Moloney
Culvert Construction
Concrete

Brief Description

Sequence to construct culvert


with head walls.
Culvert Construction
Concrete
Oil Interceptor
Miscellaneous
Oil Interceptor
Concrete
Earthworks
Excavation for Underground Pump station

Brief Description

Faces of excavation Stepped &


Well-point Dewatering used.
Contractors Temporary Facilities
General Items
Dewatering

Brief Description

Construction dewatering is the removal or drainage of


groundwater and or surface / rain water usually by
pumping to keep the works dry.

ⓒ David H Moloney
General Items
Dewatering

ⓒ David H Moloney
General Items
Temporary Fence type 1

Brief Description

Examples of temporary security


fences that are higher than the
usual

ⓒ David H Moloney
General Items
Temporary Fence type 1

ⓒ David H Moloney
General Items
Temporary Fence type 2

Brief Description

Temporary fence on precast beam for airport.

ⓒ David H Moloney
General Items
Temporary Fence type 2

ⓒ David H Moloney
General Items
Site Hoarding examples

ⓒ David H Moloney
General Items
Wheel Wash Drive-through

ⓒ David H Moloney
General Items
Wheel Wash Drive-through
General Items Temporary Electricity Supply & Tower Lights

ⓒ David H Moloney
General Items Welfare Facilities

Toilets – Washing

Canteen, Drying Room, Toilet & Generator

ⓒ David H Moloney
Safety & Environmental
Emergency Phone Numbers & Response
Dashboard is a single page, graphical representation of
HSE Monitoring & Reporting - Dashboard current HSE Issues and historical trends
Site Safety Posters examples
Safety Precautions
Existing Underground Utilities
Earthworks

Brief Description

Before digging
establish the location
and route of
underground utilities.

Locator to find Utilities


Spray Paint to mark pavement ⓒ David H Moloney
Existing Underground Utilities & Overhead Cables - Safety Measures
Earthworks

ⓒ David H Moloney
Health, Safety & Environment
Trench - Safety Measures
Trench - Safety Measures
Health, Safety & Environment

ⓒ David H Moloney
Air, Noise, Water & Soil Pollution
Environmentally Friendly Site
General Items
Water Pollution Prevention
Segregation of Waste
Health, Safety & Environment

Segregation of waste for proper disposal and


recycling. Less waste goes to landfill and
hazardous waste is treated to make it safe.

Colour Code for Skips & Bins


Progress Monitoring & Administration
Dashboard is a single page, graphical representation of current
Progress Monthly, Monitoring & Reporting - Dashboard progress and historical trends
Histogram Charts for Resources & Outputs

Brief Description

Histograms shows resources etc. for each month of a project.

Concrete per Location


Quantity for each month of the Project
Manpower per Discipline

Man-hours for each month of the Project


ⓒ David H Moloney
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Daily Work Record

Brief Description

Daily Work Records showing the


allocation of resources, materials and
work activities carried out daily.
Organogram

Brief Description

Shown are the line and


lateral relationships
between the various team
members and their relative
position in the site
organisation.
Staff Directory

Brief Description

List of staff and their


contact details
Quality Assurance
Dashboard is a single page, graphical representation of
Quality Assurance Dashboard current statistics and historical trends
Production by David H Moloney

My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ

S-ar putea să vă placă și