32 RTL-1.8 Decorating
Features Resource Type
Labour
1.Paint Resistant to moisture Mason
transmission Contractor/Supervisor
Long life of Paint Painter
Light weight
Stain protection Contractor/Supervisor
Easy to clean Labour
Contractor/Supervisor
Sustanibility and Long Lasting Labour
Contractor/Supervisor
Labour
Project Code: COH
S.No Code of Accounts Activity Time Average Time Calculation
days Max Time Mid time
1 COH-1 Construction of House
2 COH-1.1 Planning 18 30 25
3 COH-1.1.1 Design 30 40 28
4 COH-1.1.1.1 Layout 5 7 6
5 COH-1.2 Foundation 25 27 24
6 COH-1.2.1 Excavation 5 7 6
7 COH-1.2.2 Lean Concrete
8 COH-1.2.3 Reinforcement of Bed 2 5 4
9 COH-1.2.4 Formwork of Bed 6 8 6
10 COH-1.2.5 Concreting of Bed 5 7 6
11 COH-1.3 Steel Erection 8 10 5
12 COH-1.3.1 Steel Columns 5 4 3
13 COH-1.3.2 Beams 2 4 3
14 COH-1.3 Building of wall and structure 120 150 130
15 COH-1.4 Electrical work 10 8 6
16 COH-1.4.1 Install and terminate 5 7 6
17 COH-1.4.2 HVAC Equipment 4 6 5
18 COH-1.5 Piping works 5 4 3
19 COH-1.5.1 Drains 10 8 6
20 COH-1.6 Masonary work 22 26 25
21 COH-1.6.1 Lay masoonary 10 8 6
22 COH-1.6.2 Flooring 13 9 6
23 COH-1.7 Tilling 5 7 6
24 COH-1.7.1 Tillings in toilets 4 6 5
25 COH-1.7.2 tilling in kitchen 5 8 6
26 COH-1.8 Plumbing 7 7 6
27 COH-1.9 Finishing 10 8 6
28 COH-1.9.1 Paint 5 7 6
29 COH-1.9.2 Doors 6 8 6
30 COH-1.9.3 Windows 8 7 6
31 COH-1.9.4 Polishing floor 3 6 5
erage Time Calculation Time Risk
Min. Time Pert Category S.D.