Documente Academic
Documente Profesional
Documente Cultură
DTT79002 /A1,1281-P-DW-601-6,1281-P-DW-601-7,1281-P-DW-601-10/A1
Amine
Water
Line Number
8"-AM-T79143-01C08-H.SHT1
8"-AM-T79141-01C08-H.SHT3
8"-AM-T79358-01C08-H.SHT1
8"-AM-T79361-01C08-H.SHT1
-
-
-
-
-
-
-
-
-
-
-
-
INDEX FOR HYDROTEST PACKS
Included N/A
ACCEPTANCE NOTE
FORM No: PITR009-A Sheet 1 of 1
PRE-HYDRO/PNEUMATIC TEST
The above test pack test has been checked for material and NDT clearance and all relative
acceptance documents are prepared in accordance with project specifications.
Print Name
Signature
Date
HYDRO/PNEUMATIC TEST
The above strength test has been carried out in accordance with Project Specifications and
certified complete.
Print Name
Signature
Date
PIPING INSPECTION TEST RECORD PITR001-A Sheet: 1 of 1
Installation:
Project: HI39480 Isometric No.: Refer PITR002-A
BALEIA AZUL
P & ID No.: Refer PITR002-A Line No.: Refer PITR002-A System/Subsystem No.: 0
2 Check all welding & welded attachments are complete & NDT cleared. Y N n/a
5 Check that any necessary hydro/pneumatic test temporaries have been inst Y N n/a
6 Check that all relief valves, bursting discs, orifice plates, check valves, Y N n/a
control valves, strainers & specified instrumentation are removed.
7 Check that all orifice tappings have been seal welded & that unused Y N n/a
tapped holes have been plugged and seal welded.
Check that all sprinkler heads, rosettes & nozzles have been removed &
8 Y N n/a
connections plugged.
9 Confirm correct flow direction through all items Y N n/a
11 Check that all pipe supports are completely installed as per drawings. Y N n/a
13 All in-line valves to be fully open for filling & testing with the exception Y N n/a
of ball valves (to be half open during testing)
Operational Flow Medium: Amine Design Pressure : 0
Duration of test : One Hour Test Pressure : 0
Design temperature : 0 Test temperature: Ambient Test Medium: Water
Remarks:
Signature
Print name
Date
Installation:
Project: HI39480 System/Subsystem No.: 0
BALEIA AZUL
Title: FLUSHING CERTIFICATE AREA: M13A
Signature
Print name
Date
Installation:
Project: HI39480 SYS / SUB SYSTEM No.: 0
BALEIA AZUL
TITLE : HYDRO/PNEUMATICTEST RECORD AREA: M13A
EXCEPTIONS / COMMENTS
Print name
Date
5 Check that the correct bolts & gaskets are installed at all mechanical joints Y N n/a
7 Check all sprinkler heads & deluge nozzles etc installed. Y N n/a
8 Check that all relief valves have been correctly installed. Y N n/a
9 Check that all thermowells & disconnected instrumentation have been Y N n/a
reinstated.
10 Check that bursting discs, orifice plates, check valves, globe valves, Y N n/a
strainers & control valves have been installed in the correct flow
orientation.
Check valve spindle is lubricated and handwheel/lever operates over full
11 Y N n/a
range.
12 Check valve tag. no. is correct to P&ID and any required locking devices Y N n/a
is fitted.
13 Check that spectacle blinds are in the correct flow position as indicated Y N n/a
on the P&ID.
14 Check that gags on spring supports have been removed. Y N n/a
15 Check that all pump suction strainers have been correctly installed.* Y N n/a
16 Check lines have been released to painting, heat tracing or insulation Y N n/a
department
REMARKS: * Commissioning witness point
Signature
Print name
Date
PIPING PUNCH LIST
Project : BALEIA AZUL Line No. 8"-AM-T79143-01C08-H.SHT1 Test Pack No. M03-AM-TP001