VALORIZACION MENSUAL N-01
enero-18
MUNICIPALIDAD DISTRITAL DE INKAWASI
CREACION DEL CAMINO DESDE HUARANCALQUI HASTA LOS SECTORES
CHANCABAMBA Y LIMONPUQUIO
CUSCO-LA CONVENCION-INKAWASI
AVANCES
PRESUPUESTO
ANTERIOR ACUMULADO ACTUAL
Metrado P.U P. Parcial Metrado Parcial % Metrado Parcial %
NAL Y OBRAS DE ARTE APERTURA DE SECCION DE VIA
ANCES
SALDO
ACUMULADO
Metrado Parcial % Metrado Parcial %
COSTO DIRECTO
RESUMEN
AVANCE
PRESUPUESTO AVANCE ANTERIOR
ACTUAL
COSTO DIRECTO
PRESUPUESTO
COSTO DIRECTO
GASTOS GENERALES 10.32 %
SUB PRESUPUESTO
GASTOS DE SUPERVISION 5.0 %
EXPEDIENTE TECNICO 1.01 %
LIQUIDACION DE OBRA 2.39 %
PRESUPUESTO TOTAL
AVANCE DIARIO
febrero-18
RITAL DE INKAWASI
MINO DESDE HUARANCALQUI HASTA LOS SECTORES
LIMONPUQUIO
NCION-INKAWASI
PRESUPUESTO
751.09 751.09 -
112.12 20,019.03 -
22,500.00 22,500.00 1.00
-
912.27 5,519.23 1.41 0.20 0.20 0.10 0.20 0.20
1,336.51 8,085.89 1.85 0.10 0.10 0.10 0.10 0.10
622.34 3,765.16 6.05
475.37 2,875.99 6.05
-
240.00 960.00 4.00
12.26 1,348.60 110.00
3,560.67 3,560.67 1.00
-
6.19 209,332.80 22,917.90 800.00 900.00
16.44 152,188.04 9,257.18
5.90 54,617.36 9,257.18
10.93 374,221.12 21,637.98 1300.00 1100.00
4.24 2,869.12 226.68 100.00
-
7.51 27,256.64 - 500.00 200.00 227.38 200.00 562.00
2.94 10,670.38 - 500.00 200.00 227.38 200.00 562.00
8.64 31,357.84 - 500.00 200.00 227.38 200.00 562.00
3.81 92,186.30 24,195.88
-
-
3.46 19,822.24 5,728.97
15.06 7,210.43 478.78
-
1.54 175.87 114.20
28.37 5,578.11 196.62
10.88 1,400.15 128.69
11.04 107.64 9.75
50.86 7,760.22 152.58
340.32 2,817.85 8.28
504.82 5,709.51 11.31
561.16 9,882.03 17.61
8.09 11,653.08 1,440.43
686.10 18,524.70 27.00
122.48 5,765.13 47.07
15.18 1,208.78 79.63
-
1.54 333.53 216.58
28.37 3,468.52 122.26
37.35 5,521.82 147.84
561.16 21,683.22 38.64
389.37 17,435.99 44.78
122.48 1,480.78 12.09
56.62 1,165.24 20.58
6.46 764.99 118.42
-
1.54 187.11 121.50
28.37 1,263.88 44.55
122.48 7,661.12 62.55
56.62 305.75 5.40
-
400.00 9,600.00 24.00
50.00 650.00 13.00
-
162.46 1,299.68 8.00
370.10 4,441.20 12.00
526.84 2,107.36 4.00
-
0.45 20,045.01 44,544.47
-
3.70 19,458.30 5,259.00
27.87 16,722.00 600.00
800.00 800.00 1.00
19,992.70 19,992.70 1.00
-
-
865.28 11,092.89 12.82
2.92 522.68 179.00
3.64 1,565.20 430.00
1.40 16,937.12 12,097.94
2.13 1,618.80 760.00
2,500.00 7,500.00 3.00
OBLACION BENEFICIARIA -
-
-
560.00 5,600.00 10.00
560.00 5,600.00 10.00
-
1,185.00 5,925.00 5.00
10.88 522.24 48.00
-
280.00 14,000.00 50.00
6,083.36 6,083.36 1.00
1,355,056.49
139,841.83
1,494,898.32
67,752.82
13,686.07
32,385.85
1,608,723.06
PLAZO DE EJECUCION 240 DIAS
FECHA DE INICIO DE OBRA
FECHA DE TERMINO DE OBRA
PROVINCIA LA CONVENCION
DISTRITO INKAWASI
PERIODO DE VALORIZACION 31 DE ENERO
VALORIZACION AL 31 DE ENERO
RESIDENTE
febrero
7.00 8.00 9.00 10.00 11.00 12.00 13.00 14.00 15.00
MI J V S D L M MI J