Documente Academic
Documente Profesional
Documente Cultură
Vladimír Daniška
3) Calculation procedure
Limited extent of input data. The facility inventory data are grouped. The extent of
decommissioning categories is reduced (10 – 30).
Extent of unit factors is limited to the extent of decommissioning categories and the extent
of professions considered for personnel
PSL structure can be used as the check list. The decommissioning activities are
recommended to be organised according the PSL standardized list. The cost elements are
calculated at the level lowest identified activity
Manpower and labour cost unit factors calculation approach is used for labour cost
Calculation procedures
Calculation parameters
Hands on activities, period
(unit factors, constants, …) dependent activities, collateral cost
Procedure for preparation calculation structure for simplified decommissioning costing, cont.:
6) Allocation of inventory input data and calculation data for inventory dependent activities
Allocation of inventory data to individual calculation items
Allocation of unit factors to individual calculation items
Procedure for preparation calculation structure for simplified decommissioning costing, cont.:
7) Constraints for inventory dependent activities, non productive working time components
Identification of working constraints for individual activities
Allocation of relevant increase factors for individual activities
Allocation of coefficients for non productive working time components
Calculation sequence
Input variable,
calculation of
calculation item [man.hours/var]
[man.hours]
cost for
Decommissioning
category of the
inventory calculation item
Working constrain
factor 1
Total manpower extended Increase factors for
Working constrain for working constraints individual working
factor 2 [man.hours] constraints
[%]
Working constrain
factor N
Composition of the working
group
Calculation of duration [N1, N2, …Nn]
of the activity
Sequence of calculation
Procedure for
calculation of Overal labour rates per
labour cost Total labour cost
profession
[CUR/hour]
[CUR] Manpower per
profession
[hours]
The same
procedure is used
for calculation of
overheads
expenses based
on manpower
components and
Total labour cost
per calculation
overheads cost item – sum
ratios for per all
professions
professions
CUR - currency
5) Calculation of investment cost and expenses for period dependent activities and for collateral
cost items
Fixed cost items are introduced into the calculation structure as fixed values
Period specific items are calculated based on duration and period specific cost factor
6) Calculation of contingency
Contingency is calculated as single item per calculation item based on sum of labour
cost, investment cost and expenses and the percentage of contingency defined for the
calculation item
7) Formatting of data
The calculated cost are presented according the structure of the chapter 12 of the PSL
structure
Calculation sequence
Value of input variable
Procedure for [var] mass, area, …
investment cost
investment cost unit factors
[CUR] [CUR/var]
The same
procedure is
applied for
calculation of
expenses
Investment Period
dependent on specific
Sum of all items of Calculated
duration investment
investment duration of the
Fixes value Fixed activity
investment value of
investment
CUR - currency
var - input variable
Procedure for
Sequence of calculation
calculation of
contingency
Contingency ratio
specific for
calculation item [%]
Sum of labour cost,
Total contingency per calculation item investment and expenses
CUR - currency