Dear Sir,
Polgahawela, Pothuhera and Alawwa Integrated Water Supply Project
Contract No: SP-NWP/POLGAHAWELA/W/DB/2011/01
1 Key Plan TBM value and location shall be mentioned in key plan.
2 Pipe Detail Submit yard piping details drawing together.
3 Orientation of Chambers Noted.
4 Top Slab Opening Noted.
Submit detail drawings together (with material use for insert
5 Inside Ladder
plats).
6 In let Pipe Provide the inlet pipe through the wall (not in roof slab).
Inlet vertical pipe shall be closer to the wall. (interchange with
7 In let Pipe
overflow pipe)
Noted.
8 In let Pipe
Shift external ladder closer to the inlet pipe.
9 Puddle Pipe Contractor agreed, but not incorporated in drawing.
10 Drain Pipe Noted.
_________________________________________________________________________________________
Project Director
Polgahawela, Pothuhera and Alawwa Integrated Water Supply Project
No 301, Kurunegala Road, Bandawa, Polgahawela.
S.No Subject Client Comments
Please note that the design and built contractor is responsible for the conformity of the design with functional
requirements.
Thanking You.
Eng.G.M Thilakarathne
Project Director (PPAIWSP)
_________________________________________________________________________________________
Project Director
Polgahawela, Pothuhera and Alawwa Integrated Water Supply Project
No 301, Kurunegala Road, Bandawa, Polgahawela.