Daily Progress Report

Client Job No.


Location Contractor
COMPANY LOGO Contract No.
Project
Date 2/19/2011 Saturday
S.N Activities % of Completion Remarks
1
100%

2
100%
3 70%
4 60%
5
6
7
8
9
10
11
12
13
14
15
16

Man Power Own Sub-Cont Activities

Project Manager 1 Nill Over all Management


Project Engineer 1 Nill Site Management
Electrical QA/QC Engineer 1 Nill QA/QC
Electrical Site Engineer 1 Nill Site Supervision
Electrical Foreman 1 Nill Site Supervision
Civil Site Manager 1 Nill Civil Works
Civil Site Engineer 2 Nill Civil Works
Civil Foreman 1 Nill Civil Works
Surveyor 1 Nill Civil works
Labour 4 Nill Civil works
Drivers 1 Nill Civil works
Labour 2 Yes Water Proofing
Steel man 13 Yes Steel work

Equipment
S.N Type of Equipment No. of Equipment Activities
1 Steel Cutter 1 Cutting the steel

Contractor Project Manager Suadi Electricity Project Engineer


MR. ABC MR. XYZ
Activates to be done tomorrow
S.N Activities % of Completion Remarks
1
Steel placing for the raft foundation 80%

2
Water proofing in Transformer area 100%
3 RFI 100%
4
5
6
7
8
9
10
11
12
13
14
15
16

Problems or Obstacles
S.N Description Suggested Solution

3
4
5
6
7
8
9