Sunteți pe pagina 1din 11

BHAVANI ERECTORS PVT LTD

2x660MW SURATGARH POWER PROJECT


ERECTION PLAN FOR THE MONTH OF MAY-2016 OF UNIT # 8 Date: 02/05/2016
TARGET ERECTION
SL No. Activity REMARKS
WEIGHT

1 ESP 114MT

2 BOILER STRUCTURES 260MT

3 ROTATING PARTS 95MT

4 PRESSURE PARTS 24MT

5 DUCTING 260MT

6 COAL PIPING 70MT

7 PENT HOUSE 10MT

8 INSULATION & CLADDING 70MT

9 CRITICAL PIPING 110MT

TOTAL TONNAGE :- 1013MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT
ERECTION PLAN FOR THE MONTH OF MAY-2016OF ESP UNIT # 8 Date02/05/2016
PGMA
SL No. Activity TARGET ERECTION WEIGHT REMARKS
DETAILS
1 COLL ELECT RAPP MECH 79925 8.00MT
2 RECTIFIER HANDL SYST 79956 2.50MT
3 GAS DIST. ASSY 79908 2.00MT
4 OUTER ROOF-EP 79942 75.00MT
5 TRANSFORMERS 26.40MT

TOTAL TONNAGE(A,B,C&D PASS) :- 113.90MT


BHAVANI ERECTORS PVT LIMITED

2x660MW SURATGARH POWER PROJECT


Erection Plan of Boiler for the Month of MAY-2016, Unit # 8 Boiler
Date02/05/2016
Target Erection
SL No. Activity PGMA Remarks
weight

1 COLUMNS NEAR AIR PRE HEATERS 36-110 30.00MT

BEAMS AND BRACINGS NEAR AIR


2 36-150 25.00MT
PREHEATER

3 MISCELLANEOUS PLATFORMS-PART II 36-392 35.00MT

4 MAIN FLOOR I MBL 2ND PASS 36-312 10.00MT

NON-MBL FLOOR BETWEEN MBL I AND


5 36-313 10.00MT
II

NON-MBL FLOOR BETWEEN MBL I AND


6 36-315 40.00MT
II

NON-MBL FLOOR BETWEEN MBL I AND


7 36-316 25.00MT
II

8 MAIN FLOOR II MBL IST PASS 36-321 5.00MT


9 MAIN FLOOR II MBL 2ND PASS 36-322 10.00MT

NON-MBL FLOOR BETWEEN MBL II AND


10 36-324 20.00MT
III

NON-MBL FLOOR BETWEEN MBL II AND


11 36-326 10.00MT
III

NON-MBL FLOOR BETWEEN MBL III


12 36-333 10.00MT
AND IV

13 HOR BEAM-SECOND PASS- TIER-1 35-451 10.00MT

14 HOR BEAM-SECOND PASS- TIER-2 35-452 10.00MT

FLOORGRILLSANDGUARDPLATE
15 36-812 10.00MT
MIDDLE

Total Tonnage :- 260.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF MAY-2016 OF ROTATING MACHINES UNIT # 8


Date-Date Date02/05/2016
PGMA TARGET ERECTION
SL No. AREA Activity REMARKS
DETAILS WEIGHT

1 LARG AH-ROTORHOUSING 52-030 15.00MT

2 COLD END CONN PLATE 52-042 80.00MT

TOTAL TONNAGE :- 95.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF MAY-2016 OF PRESSURE PARTS UNIT # 8


Date Date02/05/2016
PGMA TARGET ERECTION
SL No. PASS Activity REMARKS
DETAILS WEIGHT

1 SOOT BLOWER'S 20-051 20.00MT


1ST &
2ND
PASS
2 SH PLATEN LOOSE TUBES 11-078 4.00MT

TOTAL TONNAGE :- 24.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT
ERECTION PLAN FOR THE MONTH OF MAY-2016 OF DUCTING UNIT # 8 Date Date02/05/2016
PGMA
SL No. Activity TARGET ERECTION WEIGHT REMARKS
DETAILS

1 DUCT - BET F.D FAN AND AIRHEATER 48-012 20.00MT

DUCT - S PRI FAN TO AIRHEATER


2 48-112 50.00MT
PRISID
DUCT - SAIRHEATER TO
3 48-202 50.00MT
WINDBOXDUCT

4 DUCT BELOW DIVERTOR 48-386 10.00MT

DUCT - BOILER OUTLET TO ELEC


5 48-462 15.00MT
PRECP

6 BEAMS AND BRACING BEFORE ESP 39-102 50.00MT

7 GATE-ESP INLET 57-460 20.00MT

8 COLUMNS BEFORE ESP 39-101 45.00MT

TOTAL TONNAGE :- 260.00MT


BHAVANI ERECTORS PVT LTD
2x660MW
SURATGARH POWER PROJECT
ERECTION PLAN FOR THE MONTH OF MAY-2016 OF COAL PIPING UNIT # 8
Date Date02/05/2016
TARGET ERECTION
SL No. Activity REMARKS
WEIGHT

1 ST PIPES&SHOP BENDS FOR A & B MILL 20.00MT

ST PIPES&SHOP BENDS FOR C & D MILL


2 & ST PIPES & SHOP BENDS FOR E & F 50.00MT
MILL

TOTAL TONNAGE :- 70.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF MAY-2016 OF PENT HOUSE UNIT # 8


Date Date02/05/2016
PGMA TARGET ERECTION
SL No. Activity REMARKS
DETAILS WEIGHT
MAIN BOILER ,VERTICAL ROOF
30-215 ,30-219
1 ENCLOSURE FRAMING & FIRST PASS 10.00MT
& 30-233
DECK SPRT AND SEAL

TOTAL TONNAGE :- 10.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF MAY-2016 OF INSULATION & CLADDINGUNIT # 8


Date Date02/05/2016
PGMA TARGET ERECTION
SL No. Activity REMARKS
DETAILS WEIGHT
BOILER INSULATION & CLADDING

BLR PR PARTS MINERAL WOOL & MAIN


1 33-021 &33-230 20.00MT
BLR POURABLE INSULATION

2 POURABLE INSULATION 33-230 40.00MT

ESP INSULATION & CLADDING

1 ESP HOPPER FUNNE50 MM THICK 79967 10.00MT

TOTAL TONNAGE :- 70.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF MAY-2016 OF CRITICAL PIPING UNIT # 8


Date Date02/05/2016
PGMA TARGET ERECTION
SL No. Activity REMARKS
DETAILS WEIGHT

1 CRH FROM TURBINE TO REHEATER 80-320 30MT

2 BFD FROM FINAL HPH TO SG TP 80-425 40MT

HRH FROM REHEATER TO


3 80-310 20MT
INTERCEPTOR

4 C-D BAY STRUCTURE 80-940 20MT

TOTAL TONNAGE :- 110.00MT