Sunteți pe pagina 1din 284

5

FIFTY YEARS OF EXCHANGING IDEAS & EXPERIENCE


TSDOS

TRANSMISSION AND
SUBSTATION DESIGN
AND OPERATION
Since 1968 SYMPOSIUM
2017 TECHNICAL PAPERS
TABLE OF CONTENTS
SESSION TITLE AUTHOR(S) PAGE

Cory Spoonmore, P.E., Cameron Sims,


Hartburg Substation Flooding and Recovery 4 - 14
P.E.

The Catenary Exposed Understanding Theoretical


David C. Gelder, P.E. 15 - 30
Conductor Behavior in Transmission Lines

Advantages, Limitations and Development of Power


Diego M. Robalino, PhD 31 - 44
Transformer Insulation Diagnostics

Power Transformers Field Dry Out Optimization Dinesh Chhajer, PE,


45 - 62
Utilizing Dielectric Frequency Response Method Ian Kreher

Utilizing Visual and Thermal Video Analytics


E. Sotter, Ph.D., P. Fernandez, R. Harada 63 - 72
to Enhance Operational Efficiency

Earl L. Kirkpatrick, P.E., AKM Sydul


Designing Grounding Grids 73 - 83
Haque, PhD, P.E.

Transformer Tank Vibration Model to


Emilio Morales Cruz 84 - 90
Detect Winding Deformations

Guanqun Wang, PhD, Pradeep Tripathi,


Steady-State and Dynamic Transmission
Hyung Shin, PhD, Joseph Nichols, Ravi 91 - 104
System Model Validation (NERC MOD-033-1)
Varanasi, Jim Kelley, P.E., Miles Hammac
An Analysis of Phased Array Ultrasonic Testing
Garrett Ehler, AWS-CWI, ASNT/ACCP
versus Conventional Ultrasonic Testing in 105 - 113
Level III, Mihai Radu, ASNT Level III
the Utility Pole Industry

Drones: The Use of Unmanned Aerial Systems for


Surveying for Transmission Route Engineering, George R. Hill, RPLS 114 - 127
Substation Design and Installation of Facilities

Drones to the Rescue!


Airline to Holly – A Case Study on Grant T. Leaverton 128 - 138
UAV Based Tower Inspection

Transmission Line Drilled Pier Design, Limiting


Greg C. Parent, P.E., S.E. 139 - 150
Rotation and Creating a Balanced Performance Criteria

Deploying a New Fault Location Strategy


Jason Souchak 151 - 157
in a Large Utility- A Case Study

Pollution of AC Overhead Transmission Lines.


Jean-Marie George 158 - 164
Definitions, Mitigation Methods and Field Experience
TABLE OF CONTENTS CONTINUED
SESSION TITLE AUTHOR(S) PAGE

Utilizing the Design of Hybrid Transmission Jessica McLarty, P.E., James R. Childs, P.E.,
165 - 177
Line Structures in Flood Plain Regions John L. Webb, P.E.

Josh Ross, Andrew Johnson, P.E., Jack


Grauman, P.E., Cody Bingham, Carl Svard,
Xcel Energy AC Interference Program:
P.E., Brent Hanson, P.E., Jeff Giddings, P.E., 178 - 197
Metallic Pipelines
Glen Adams, R.G., Scott Marr, P.E., Mandy
Kondik

Considerations for a Comprehensive Review of


Kevin G. Verett, David T. Chessmore 198 - 207
Temporary Protective Grounding Procedures

Designer and Installation of Tubular Steel


Kent Lam, Thales Ramier 208-222
Poles 200 Feet and Taller

Substation Grounding and Step Over Native


Molli Dooley, P.E. 223 - 233
Concerns

Asset Management Analytics for a


Qasim Aziz & Gautam Sonde 234 - 246
Sustainable Grid

Comparative Analysis of Drilled Shafts


Sanchit Chitre, Joel Coker, P.E. 247 - 261
using LPile and MFAD

Start Sooner: Commissioning


Terry Harless 262 - 265
A Substation Security System

Reducing Misoperations through Improved


Tim Farrar 266 - 276
Quality Control in Protection System Design

Building Information Modeling (BIM) Technology


in Substation Construction Progress Visualization – Wolfgang Eyrich 277 - 283
BIM 4D

Visit www.tsdos.org for additional conference materials, including the speaker slides, presented at the 2017 TSDOS.
Additional 50th Annual TSDOS technical papers and the conference presentation slides are available at www.tsdos.org.
Technical papers available on flash drive sponsored by:
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

HARTBURG SUBSTATION FLOODING AND RECOVERY

Cory Spoonmore, P.E, Project Manager


Cameron Sims, P.E., Project Engineer
Black & Veatch Corporation

July 2017

Prepared for:
The 50th Annual
Transmission and Substation Design and Operation Symposium

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 4 of 284
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

Background

In 2015, Black & Veatch was retained by Entergy to provide full turn-key Engineering,
Procurement, and Construction (EPC) services for the expansion of their Hartburg substation
located in southeast Texas, near the city of Deweyville, along the Sabine River. The project
involved the addition of a new 500/230 kV auto-transformer and the build out of the 230 kV yard
into a four- position ring. The construction of the project was nearing completion by early 2016,
with a target in-service of July. As the construction crews began the final push in early March,
south Texas came under one of the heaviest rainfalls in recent times.

Some 60 miles north of the Hartburg substation, along the Sabine River is the Toledo Bend
Reservoir. Managed by the Sabine River Authority, the Reservoir was completed in 1969 to
provide a number of public benefits, including water supply, recreation and hydropower
production. It was never intended to be a flood control facility for the Sabine River. It covers over
180,000 acres, making it the fifth-largest man-made lake in the United States.

Hartburg substation is situated near the Sabine River, downstream of the Toledo Bend Reservoir..

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 5 of 284
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

The Flood

By spring 2016, the area had seen a steady return of rainfall after several years of severe drought,
which had brought the reservoir to near capacity. The heavy rains started on March 9 and dumped
18 to 24 inches of rain on the drainage basin for the upper Sabine River. With the water level
rising above record levels and threatening the integrity of the dam and spillways, the Sabine River
Authority opened the flood gates to substantially reduce the reservoir water level. During the
peak flow period on and around March 10, the flood gates released 1.5 million gallons of water
per second to flow down river- a flow rate that is more than double that of Niagara Falls. The
resulting deluge of water was expected to cause flooding in the lower Sabine River of two to six
feet.

Between March 11 and March 13, noticeable floodwaters started to affect the Hartburg
substation, which sits just two miles west of the main channel of the Sabine River and is at the
edge of inhabitable land. During this time Entergy’s crew and the Black & Veatch construction
crew (Overland Contracting, Inc.) did as much pre-flood preparation as possible to mitigate flood
damage. For example, Entergy’s crew installed temporary flood walls around each of the three
control enclosures to prevent floodwaters from seeping inside. Two of these control enclosures
existed prior to commencement of the project. The third control enclosure was installed as part of
this project and will be discussed in further detail later in this paper. Overland Contracting, Inc.
(OCI) relocated uninstalled equipment out of the substation and secured much of the loose
material that might float and cause damage during the flood. Coupling capacitor voltage
transformers (CCVT) that were still crated and yet to be installed were removed. The remainder
of the major equipment was already installed prior to the flood event.

On March 14, the floodwaters rolled in and submerged the substation under five to seven feet of
water. By the time the local residents got to safety, the waters were over nine feet above the 24-
foot flood stage. The Sabine River at Deweyville crested to an historical level of 33.24 feet on
March 15.

For a week, the Hartburg substation


remained underwater, accessible only by
boat.

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 6 of 284
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

Damage Assessment

For a week, the wide spread of the Sabine River covered the station. On March 21, the
floodwaters had subsided enough to safely gain access to the Hartburg substation and begin the
damage assessment. Entergy, Black & Veatch, and OCI were on site to perform a full walk down
to begin the process of determining the extent of the damage caused by the flood. Both the 500kV
yard and the 230kV yard had sustained flooding and subsequent damage. Since the original scope
of work of the project was limited to the 230kV yard, new autotransformer, and one 500kV
breaker and associated switches, Black & Veatch performed the restoration work in the 230kV
yard while coordinating closely with Entergy, who performed restoration for the remainder of the
existing 500kV yard. The following major equipment was damaged during the flood:

 230kV Control Enclosure

 230kV CCVT and Autotransformer Junction Boxes

 230kV Motor Operated Switch Control Cabinets

 500kV Motor Operated Switch Control Cabinets

 Control Conductor and ADSS Cable

The flood also damaged or swept away miscellaneous bus hardware, circuit breaker installation
material, cable trench lids, and transmission line hardware that crews did not have time to move
to safety.

Recovery Efforts

Shortly after the damage was assessed, Black & Veatch and Entergy worked together to come up
with a recovery plan, which would include the repair or replacement of equipment and the raising
of the major 230kV equipment. Some of the decisions to re-use or replace flood-affected material
were based on the recommendation of the manufacturers. However, the decision on how high to
raise the equipment required more review. The scope of the event was considered a 500-year
flood event, which set a clear flood stage level for the area. Given the known water line in most
of the control cabinets, Entergy decided on a net increase of six feet; from a base elevation of 21
feet to a new top-of-concrete (TOC) of 27 feet. The net increase of six feet included the known
high water mark of 24’, which represented three feet of the six feet total, and an additional three
feet to account for the projected peak of the flood event. The projected peak was provided by the
Sabine River Authority during their decision-making process to release water from Toledo Bend.

The following is a detailed description of the major equipment recovery and elevation changes:

230kV Control Enclosure

The 230kV control enclosure was installed as part of this project’s scope of work. The control
enclosure had already arrived on site, been set on piers, and installed per manufacturer’s
recommendations. Most of the control cable had been pulled between the control enclosure and
the 230kV equipment. Crews were working to complete wire terminations as news of the

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 7 of 284
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

projected flood event was relayed to the team. To mitigate damage to the installed equipment,
Entergy installed a temporary flood wall around the control enclosure.

Although there was a temporary flood wall around the 230kV control enclosure, two feet of water
penetrated the control enclosure and caused extensive damage to the flooring and the walls. The
control enclosure manufacturer and relay panel manufacturer sent an engineer to the site to assess
the damage from the flood and develop a plan for restoring the enclosure and equipment to pre-
flood conditions. Over five feet of the interior walls had to be gutted because of water damage to
the gypsum board. The floors had to be removed to enable replacement of the water-damaged
gypsum board and spray polyurethane foam. Any equipment inside of the control enclosure that
was submerged in floodwater was replaced. The manufacturer of the relay panels recommended
all the control/relay panels be removed and returned to their facility for testing, cleanup, and
repair or replacement because of their exposure to the humidity, floodwater contaminates, and
high temperatures for over five days. OCI removed the panels and equipment, sent them to the
vendor for refurbishment, and re-installed and re-wired all the equipment upon its return. In
addition, OCI refurbished the building including the gypsum board and the floor, following
recommendations of the control enclosure manufacturer.

A temporary flood wall was constructed


around the control enclosure to minimize
flooding within.

During the refurbishment, Black & Veatch & Entergy worked on a plan to raise the control
enclosure in a timely manner. Entergy requested that the top of concrete elevation for the control
enclosure be increased to 28 feet from the original design of 21 feet. The decision was made to
pour new drilled piers next to the existing location. This would limit the control enclosure to
being moved a single time and allow the refurbishment process of the control enclosure to
coincide with the installation of the new piers. The control enclosure manufacturer then
confirmed that the enclosure would be within its design parameters, even though it was going to
be installed seven feet above grade.

Once the control enclosure was completely refurbished and the relay/control panels re-installed,
Entergy and Black & Veatch worked with the building manufacturer on a lifting plan. The control
enclosure was originally shipped to the site in two halves and bolted together. Each half was 42
feet by 10 feet by 12 feet 2 inches tall, and weighed 45,000 pounds. This resulted in an installed
control enclosure that was 42 feet by 20 feet by 12 feet 2 inches tall, weighing 90,000 pounds.
The overall size of the control enclosure and the split design offered a unique set of challenges for

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 8 of 284
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

the lift. The lifting company was not able to use typical lifting beams, so they designed and
fabricated beams that could provide the necessary support to complete the lift. Multiple meetings
were held to discuss the lifting plan and to grant all stakeholders an opportunity to discuss
potential issues. A third party specializing in crane rigging and lift plans was brought in by
Entergy to review the lift plan to be certain that every potential issue was accounted for in the
final plan. Once Entergy, Black & Veatch, OCI, and the control enclosure manufacturer agreed
that the lifting plan mitigated all concerns with moving the control enclosure, the lift was
scheduled.

The photos below illustrate the lift. As can be seen, the building did not need to be moved far.
However, the split design of the building and the need for a tandem crane lift complicated the
move. The lift and relocation of the control enclosure went smoothly. The importance of having a
detailed lift plan as described above was crucial to the success of the lift.

The 45-ton control enclosure required a complex tandem crane lift.

230kV Breakers

Even though the floodwaters reached the bottom of the 230kV breaker mechanism cabinets, it did
not reach the equipment contained within. However, Entergy decided to raise the breakers to
ensure any future flood event would not damage the breaker mechanism cabinet. The minimum
elevation of the bottom of the breaker cabinet was set at 27 feet as discussed in the recovery
efforts section. Black & Veatch worked with the breaker vendor to determine the best option to
raise the breakers. The breaker vendor had a design for a breaker with taller legs. Fortunately,
these extended height legs would raise the bottom elevation of the breaker mechanism cabinet to
exceed the minimum required elevation of 27 feet. And perhaps as important, to minimize further
delays in the scheduled in-service, the vendor had leg extensions readily available on short notice.

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 9 of 284
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

Breakers were raised


using standard leg
extensions, which
enabled quick
installation.

500kV and 230kV Junction Boxes

The autotransformer current transformer (CT) junction box and 500kV and 230kV CCVT
junction boxes were damaged during the flood event. There was evidence that the floodwaters
had entered the junction boxes. The decision was made to raise the bottom of the junction box
elevation to 27 feet. This height was established based on the same criteria stated in the recovery
efforts section. For the autotransformer CT junction box, this was accomplished by installing a
new stand for the junction box. The 500kV CCVT junction boxes were remounted at a higher
elevation on the CCVT stands. The 230kV CCVT stands were replaced with taller stands to allow
for mounting the junction boxes at the proper heights.

500kV and 230kV Switch Motor Operators

The 500kV and 230kV switch motor operators were submerged during the flood and damaged.
All operators needed to be replaced. The decision was made to raise the motor operators to meet
the new 27 foot minimum elevation to bottom of equipment. It will be discussed later that the
500kV motor operators were moved to an elevation of 26 feet.

Raising the 230kV motor operators posed some unique challenges. The operators were mounted
on the leg of H-frame dead-end structures. The first thing that needed to be considered was
whether there would be clearance issues for the motor operator when mounted at a higher
elevation. There was much coordination between the substation packager and the switch vendor
to confirm that once the motor operators were raised they would be able to operate as intended.
To complete the installation, new mounting brackets were fabricated for the motor operators. The
switch vendor provided a field service representative on-site to mount new brackets and make
field adjustments as necessary. Once this was complete, OCI was able to install the new motor
operators. Installers discovered that the decreased length of pipe on the switch operator meant
that there was less room to mount some of the switch accessories. The switch status indicator
needed to be relocated to a different part of the operating mechanism as there was no longer room
for it to be installed as originally designed.

SSVT Disconnect Switch

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 10 of 284
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

The station service voltage transformer (SSVT) disconnect switch was damaged during the flood
event. The decision was made to raise it to the 27 foot minimum elevation using the criteria set
forth previously. There was discussion on whether or not to raise the SSVT. The vendor did not
have a design available for a taller stand and would not honor their seismic guarantees if the
existing stand was modified. Through a closer look at the SSVT it was determined that the
secondary cabinet on the SSVT was currently above the 27 foot minimum elevation. The SSVT
could remain at its present elevation. The disconnect switch was raised by replacing the existing
stand with a taller one.

500kV Breaker Cabinet

The 500kV breaker is an independent pole operated/operators (IPO) design and the marshalling
cabinet had a few inches of water inside. The decision was made to raise the cabinet to the 27 foot
minimum elevation using the criteria set forth previously. This presented another set of
challenges. Raising the marshalling cabinet resulted in the need for new cables to be supplied by
the vendor. The original cabinet location was located near the middle phase breaker. Raising it in
this location would create a phase-to-ground clearance violation between the cabinet and either of
the two other phases. There was not a location within the breaker footprint that allowed for the
cabinet to be raised to the required elevation. Ultimately, the cabinet was moved outside the bus
and breaker footprint by 20 feet and raised to meet the required minimum elevation. A new stand
was designed and installed to achieve the desired elevation.

Autotransformer Control Cabinet

There were several inches of water in the autotransformer control cabinets. The transformer
vendor determined it would take a significant amount of work to raise the cabinets on the
transformer in the field. The required amount the bottom of the cabinets needed to be raised was 3
feet. The transformer vendor recommended that the entire transformer be raised 3 feet to mitigate
future flooding issues with the control cabinets. Entergy’s field personnel were consulted, and it
was decided to leave the transformer cabinets and the transformer at their current elevation. Part
of this decision was based on the effort involved with moving three single-phase 500/230kV
autotransformers weighing over 330,000 pounds each. Each unit would also need over 12,000
gallons of oil removed and refilled after completion of the raised installation.

Control Conductor and ADSS

Most of the control cables necessary for completion of the project had been cut and pulled at the
time of the flood. OCI was in the process of terminating conductors at the panels and control
cabinets when pre-flood preparation began. Cable that was not terminated was left in the cable
trench, and cable that remained on the reel was left during the flood. Black & Veatch and OCI
worked with the cable manufacturer to determine if the cables on site during the flood could be
used post flood. Due to the fact that the ends of the cables were not sealed, it was determined by
the manufacturer that the cables could not be reused since it was possible that water had entered
the cable jacket.

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 11 of 284
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

Once the decision was made to raise and move the control enclosure and raise the control cabinets
in the yard, much of the existing cable would not have been available for reuse as the cut lengths
would be too short to reach the new connection locations.

Maintenance Platforms

Entergy requested that permanent maintenance platforms be installed for all equipment and
cabinets that were raised. This was requested so that maintenance, testing, and future construction
personnel would not need to perform work at the equipment while standing on ladders. Black &
Veatch worked with Entergy to establish criteria for the sizing and height of the maintenance
platforms. The criteria were based on providing field crews ample space to perform job tasks
safely and to allow maintenance work to be accomplished at a suitable height.

The following sizes and heights were determined to be appropriate for this application:
 500kV Motor operated switch (MOS) – 6-feet x 10-feet platform, 3 feet 3 inch height
 500kV Breaker Cabinet – 5-feet x 6-feet platform, 4 feet 3 inch height
 500kV CCVT – 5-feet x 5-feet platform, 3 feet 3 inch height
 230kV Equipment – 5-feet x 5-feet platform, 4 feet 3 inch height

The final heights for platforms were selected to minimize the number of unique platform
installations. Black & Veatch started with the preferred heights supplied by Entergy and
performed a National Electrical Safety Code (NESC) 124 clearance analysis. Platform heights
were adjusted as needed so that clearances could be met without the need for installation of
equipment safety guard rails. In the 230kV yard, there were clearance issues between the MOS
platforms and the installed surge arresters. Spacers were added to the surge arrester stands to
allow for the preferred MOS platform height.

Ultimately, it was determined that one height could be used for all 230kV equipment and thus one
platform design was utilized. Each piece of 500kV equipment had different workspace area needs
and resulted in three different designs.

Some consideration was given to shipping the platforms to the site pre-assembled. This would
reduce the amount of time required for installation; however, it would increase shipping costs due
to a higher number of trucks being required to complete the delivery. Ultimately, it was decided
to ship the platforms broken down and assemble on site.

Black & Veatch also designed and installed new stair platforms for the main entrance and the two
battery room entrances for the control enclosure. Any instances that led to equipment needing to
be turned 90 degrees to enter a doorway from the top of the stairs required a minimum of an
eight-feet by eight-feet platform. Instances that allowed for equipment to enter a doorway straight
from the stairs required a minimum of six-feet by six-feet platform. These criteria were used to
size the final platforms for the main control enclosure doors and the two battery room doors.

Lessons Learned

The successful outcome of these efforts exemplifies the team’s commitment to communication.
Black & Veatch, OCI, and Entergy held twice-weekly planning meetings in the weeks leading up
to the flood event and in the months after. The meetings were used to discuss mitigation plans and
to prepare for restoration activities. As needed, vendors were brought into the meetings to provide

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 12 of 284
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

status updates on deliveries. These meetings were crucial to the success of the project. By
meeting twice a week, all stakeholders were kept up to date on the status of all deliverables. It
also helped to determine which tasks were the critical paths.

Another lesson is to always take the time to step back and see the big picture. During the flood
mitigation and restoration efforts, it was determined that the backup station service padmount
transformers needed to be raised to the 27 foot minimum elevation. After some discussion
between Black & Veatch and Entergy, it was decided to keep this requirement in the final design.
The padmount transformer had already been purchased but had not arrived on site prior to the
flood event. Since the padmount had been purchased already, the design team looked into options
of building a stand for the padmount or pouring a pier with seven feet exposed similar to the
control buildings. It was ultimately determined to pour a pier with the seven foot reveal.

The station service transformer was raised 7 feet above grade with a massive pier foundation.

This may be the first and only pier mounted padmount-design station service transformer. After
seeing photos of the completed installation, a better approach may have been to purchase a pole
top transformer, install it on a wood pole in the same location, and mount the safety disconnect
switch to the pole. This would have been a less substantial installation, eliminating a large pier
and stand from the installation requirements.

Conclusion

Throughout the process, Black & Veatch worked closely with Entergy, thoroughly documenting
and reporting project activities while maintaining close communication with Entergy
management. This enabled Entergy to provide information to their internal organization and to
other stakeholders in a timely manner.

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 13 of 284
Entergy Services, Inc. Hartburg Substation Flooding and Recovery

The flood restoration and project adjustments took substantial collaboration between Black &
Veatch, Entergy, and multiple vendors. The unique design challenges required creative, efficient
solutions by the team. Despite the significant setbacks of the record-setting flood, the project was
only four weeks behind the original in-service schedule because of the responsive and proactive
mitigation efforts of the team.

© Black & Veatch Holding Company 2017. All Rights Reserved. The Black & Veatch name and logo are registered
trademarks of Black & Veatch Holding Company.

Black & Veatch July 2017


Page 14 of 284
The Catenary Exposed
Understanding Theoretical Conductor Behavior in Transmission Lines

Submitted To
50th Annual Transmission and Substation
Design and Operation Symposium (TSDOS)
of
The University of Texas at Arlington

David C. Gelder, P.E.


Senior Transmission Engineer
TRC
July 2017

Copyright © 2017 David C. Gelder


All Rights Reserved

Page 15 of 284
The Catenary Exposed
Understanding Theoretical Conductor Behavior in Transmission Lines

David C. Gelder, P.E.

ABSTRACT

The catenary describes the most unique and important shape in transmission engineering—the
hanging conductor. The loads imposed by conductors under various temperature, wind, and ice loading
conditions drive transmission line structural design. Fundamentals of catenary mechanics, including the
equations of position, tension, and elongation, are presented herein in a manner that is concise and easy to
understand. These catenary formulas can be used in simple spreadsheets to obtain results that agree with
sophisticated computer software packages for typical transmission line engineering problems. Recent
reliability and uprating work driven primarily by the North American Electric Reliability Corporation
(NERC), coupled with a retiring work force, have led to a significant influx of young engineers in the power
delivery industry over the last decade. Not surprisingly, many new engineers have quickly learned the trade
and become expert users of industry standard computer software. However, it is questionable how
effectively the knowledgebase of fundamental hand-calculation methods—used for over a century—are
being transferred to these young engineers. This practice, if not well-managed, may have unforeseen
consequences on various aspects of projects including budget, schedule, and safety of the design. This paper
aims to expose otherwise intimidating catenary formulas and to equip transmission engineers of all ages
with a deeper understanding of theoretical conductor behavior and useful hand-calculation methods.
Keywords: catenary, cable, transmission line

INTRODUCTION

The hanging cable is a fascinating structural member. While complex in regards to large
displacements, material nonlinearities, bimetallic or composite materials, and flexible boundary supports,
a small cable element is quite simple as loads are transferred via tension only and not bending. The hanging
cable deforms in the shape of a “catenary”—a word derived from Latin meaning “chain.” The catenary
describes a hanging wire or chain supported at ends under a uniform load. Mathematically, the catenary
shape is a function of the hyperbolic cosine. The catenary shape appears in many forms in nature including
a hanging chain, spider web, necklace, rope in moving water (supported at ends), etc. The catenary equation
was derived independently by mathematicians Leibniz, Huygens, and Johann Bernoulli in 1691 in response
to a challenge by Jakob Bernoulli (Weisstein 1999). Many relationships can be easily derived from the
basic catenary equation of position including slope, tension, length, sag, etc.

Page 16 of 284
While of paramount importance in transmission engineering, interestingly, few practicing
engineers seem to have taken time to become intimately acquainted with the catenary equation—probably
due, in part, to the perceived complexity. To illustrate, transmission engineers have long known that the
hanging conductor is a catenary, rather than a parabola, but have often used less computationally expensive
parabolic approximations since the two shapes are similar when curvature is small. In recent decades, with
the advent of the computer, the actual catenary equations (as opposed to parabolic approximations) are now
commonly utilized to compute tensions in software, but it appears that today a true working knowledge of
these equations is limited primarily to software engineers and academics. This should not be the case—
transmission engineering practitioners should also be well versed with the catenary equations. The shape
of the hanging conductor under uniform load is complex, but not complicated to understand.
Additionally, many fundamental catenary equations, though well published, are unfortunately not
readily accessible in compiled form, particularly for the beginning engineer. Today’s practicing
transmission engineer is often exposed to computer software so early that many fundamental theory and
hand-calculation methods are overlooked. The “sweet spot” of structural design and analysis is achieved
when using a combination of experimental and/or field data, mechanics analysis (i.e. hand-calculations),
and numerical analysis (e.g. finite element software) to determine results (Figure 1). Without all three of
these components, a structural design or analysis may appear sound, but could be off mark due to
complexities of actual structural behavior.
The purpose of this paper is to expose otherwise intimidating catenary formulas and to equip
transmission engineers with a deeper understanding of theoretical conductor behavior. Basic catenary
formulas are shared which can be easily programmed into simple spreadsheets to obtain results that agree
with sophisticated computer software packages for single-span problems. With a better grasp of
fundamental equations, engineers will be empowered to verify complex designs created using sophisticated
software tools, such as PLS-CADD® (1993), with simple hand-calculation methods.

“Sweet Spot” Experimental


and/or
Field Data

Mechanics Numerical
Analysis Analysis
(i.e. Hand- (e.g. Finite
Calcs) Element)

Figure 1: “Sweet Spot” of Engineering Design and Analysis Methodology

Page 17 of 284
RIGID BODY BEHAVIOR (STATICS)

The hanging cable may be considered a rigid body once at rest (Figure 2). The cable deforms so
that internal forces result in no shear or bending moment, only tension. To be a catenary, a member must
assume the following characteristics based on geometry, material properties, and boundary conditions:
1. Simply supported at ends;
2. Uniform force per unit length; and,
3. Perfectly flexible.
Note that for the rigid body discussion the member is also assumed inextensible.

y(x) = a * cosh(x/a) 2

h 3
w s
1
L

λ1 λ2

λ
a

x © 2017 D. Gelder. All Rights Reserved.

Figure 2: Free Body Diagram of Catenary Cable with Simple Supports

The catenary shown in Figure 2 is asymmetric. This is important as uneven end points are quite
typical in real-world applications. The symmetric catenary may be treated as a special case, but is very
useful for formulating approximate hand-calculation methods since symmetry simplifies the equations
greatly. As a side note, the well-known Ruling Span method (Thayer 1924) utilizes symmetry to determine
a stringing tension by idealizing a multi-span section as a single, weighted-average “ruling” span.
The discussion of the catenary begins with stress boundary conditions which include simple
supports at the ends and uniform force per unit length. The uniform force per unit length may be due to
either internal body forces (self-weight) or externally applied forces of surrounding fluid (wind, water, etc.).
The cable force per unit length, w, with cable material density, ρ, gravitational acceleration, g, and cable
cross-sectional area, A, is defined as:

𝑤 = 𝜌𝑔𝐴 (1)

Page 18 of 284
The member must also be perfectly flexible, which implies zero bending stiffness. To elaborate,
consider the difference between a simply-supported beam and a simply-supported cable, each supporting
self-weight only. The beam is highly rigid and supports self-weight by transferring shear via bending,
resulting in small deformations, forming the shape of a parabola. In contrast, the cable is highly flexible
and supports self-weight by transferring tension only, resulting in large deformations, forming the shape of
a catenary. Interestingly, a cable may be regarded as simply a very slender beam. Thus, a transition point
must exist in which an increasingly slender beam loses bending stiffness and begins to transfer tension
rather than shear, becoming a cable.
A derivation of the catenary equation is published by Hibbeler (2007). The equation of position in
2-dimensional Cartesian coordinate system is given in terms of the catenary constant, a:
𝑎
𝑦(𝑥) = 2 (𝑒 𝑥⁄𝑎 + 𝑒 −𝑥⁄𝑎 ) = 𝑎 ∗ 𝑐𝑜𝑠ℎ(𝑥/𝑎) (2)

It is important to note that most transmissions engineers are familiar with the basic catenary
equation of position. However, three main reasons why transmission engineers may likely be intimidated
by this equation are: 1) unfamiliarity with hyperbolic functions; 2) catenary constant must be solved
iteratively (not directly); and, 3) confusion regarding transformation from local to global coordinate systems
(e.g. transformation to station-elevation coordinates). This remainder of this section provides the engineer
instruction regarding these three concerns, indicates useful applications of the catenary used in computer
software, and introduces additional useful catenary equations—which may be derived from the basic
equation of position, including slope, arc length, sag, and tension.
1) Unfamiliarity with hyperbolic functions. Hyperbolic functions are simple and analogous to
trigonometric functions (very similar identities). However, in contrast to trigonometric functions which deal
with angles, hyperbolic functions deal in terms of Euler’s number, e = 2.718… The hyperbolic cosine
function is less intimidating when broken down in terms of this number. For example, Figure 3 shows that
the most basic catenary equation is simply a sum of ex and e-x, multiplied by ½. The figure depicts each of
these components, as well as the catenary equation with a constant equal to 1 (solid line).
For convenience, the definitions of the hyperbolic cosine and sine functions are provided. These
definitions will be useful for the remainder of the discussion:
1
𝑐𝑜𝑠ℎ(𝑢) = 2 (𝑒 𝑢 + 𝑒 −𝑢 ) (3a)
1
𝑠𝑖𝑛ℎ(𝑢) = 2 (𝑒 𝑢 − 𝑒 −𝑢 ) (3b)

2) Catenary constant must be solved iteratively. As far as solving for the catenary constant,
which cannot be solved directly, engineers designing a spreadsheet may take advantage of built-in
capabilities in common software, such as Excel’s Goal Seek functionality, to provide solutions. More

Page 19 of 284
ambitious engineers may wish to write custom root-finding algorithms using iterative techniques such as
Newton-Raphson.

Axis Title
4
y

y = ex + e-x
3

2
y = 1/2*(ex + e-x)
= cosh(x)
1
y = ex y = e-x
© 2017 D. Gelder
0
-4 -3 -2 -1 0 1 2 3 4
x

Figure 3: Basic Catenary Curve (catenary constant = 1.0)

3) Confusion regarding transformation from local to global coordinate systems. Another major
source of confusion is in regards to coordinate system transformation. The catenary equation is formulated
in terms of a local coordinate system located a distance, a, below the low point of the curve. However,
engineers typically use a global coordinate system relative to the transmission line alignment (e.g. station-
elevation) for drawings, calculations, etc. Thus, the local coordinate origin is typically back-calculated
based on some combination of known global coordinates and possibly tension or wire length. Note that for
all asymmetric catenary curves (most cases) as tension changes the local coordinate system becomes a
moving target relative to the global system. In other words, the low point of the curve moves relative to
fixed end points defined in global coordinates.
Transformation of the catenary equation from local (x,y) to global coordinates (X,Y), located a
distance (Δx,Δy) from the local coordinate system is demonstrated:

𝑋−∆𝑥
𝑌 − ∆𝑦 = 𝑎 ∗ 𝑐𝑜𝑠ℎ ( ) (4)
𝑎

where,

𝑋 = 𝑥 + ∆𝑥
{ (5)
𝑌 = 𝑦 + ∆𝑦

Page 20 of 284
A unique catenary oriented relative to a plane can be defined by three discrete points (Figure 2).
Therefore, the catenary equation may be transformed from local to global coordinates using a system of
equations which can be used to solve a variety of cases. Two possible cases—graphical sag and display
case—are discussed as follows.

𝑋1 −∆𝑥
𝑌1 − ∆𝑦 = 𝑎 ∗ 𝑐𝑜𝑠ℎ ( 𝑎
)
𝑋 −∆𝑥
𝑌2 − ∆𝑦 = 𝑎 ∗ 𝑐𝑜𝑠ℎ ( 2 𝑎 ) (6)
𝑋 −∆𝑥
{𝑌3 − ∆𝑦 = 𝑎 ∗ 𝑐𝑜𝑠ℎ ( 3 𝑎 )

Graphical Sag. The ‘Graphical Sag’ functionality in PLS-CADD® requires known end points,
(X1, Y1), (X2, Y2), and a graphically selected middle point, (X3, Y3) (Figure 2). With three sets of known
coordinates, three equations, and three remaining unknowns: a, Δx, and Δy, there exists a unique solution
which can be solved for iteratively. The tension is then simply calculated using the catenary constant, a.
Note that for the symmetric catenary: Y1 = Y2 and |X1 – X3| = |X2 – X3|. Knowing this, the equations simplify
nicely. In short, the graphical sag case requires known end points and a known third point.
Display Case. Conversely, when attempting to display a wire at a known tension or corresponding
catenary constant, a, and known end points, (X1, Y1), (X2, Y2), the remaining four unknowns: (X3, Y3), Δx,
and Δy can be solved using equations (5) and (6). The curve can then be drawn through a back-calculated
middle point, (X3, Y3). In short, the display case requires known end points and known tension.
The catenary constant, a, is a very useful value and is quite important to understand. The value
merely describes the inversely related terms of horizontal tension, FH (force), and cable unit weight, w
(force/length), and thus has corresponding units of length.
𝐹𝐻
𝑎= 𝑤
(7)

Figure 4 shows the catenary equation with increasing catenary constants equal to 1 through 10.
Notice that curvature decreases as the catenary constant increases. Hanging conductors in transmission lines
have relatively “flat” curvature, meaning a very high catenary constant—perhaps 300-3,000 m (~1,000-
10,000 ft). This means that the theoretical datum for a typical span lies thousands of feet below the surface
of the earth. Remember, the catenary constant should not be confused with distance of cable to ground. The
catenary constant is simply a mathematical tool denoting a local origin of coordinates directly below the
low point or “belly” of the curve at a distance equal to the catenary constant. Although challenging to
calculate by hand, it is very important to understand that computers first calculate the catenary constant in
order to display wires or print sag-tension values for a variety of temperature conditions. Thus, the catenary
constant is a critical intermediate value for determining sag-tension relationships.

Page 21 of 284
16

14
y = a cosh(x/a)

12

10
a = 10
a=9
8
y

a=8
a=7
6
a=6
a=5
4
a=4
a=3
2
a=2
© 2017 D. Gelder a=1
0
-8 -6 -4 -2 0 2 4 6 8
x

Figure 4: Catenary Curve with Different Catenary Constants

Many useful relationships may be derived from the equation of position including slope, which is
the derivative of position with respect to x:

𝑑𝑦 𝑠(𝑥)
𝑑𝑥
= 𝑠𝑖𝑛ℎ(𝑥/𝑎) = 𝑎
(8)

where arc length, s, as noted by Weisstein (1999), is defined as:

𝑠(𝑥) = 𝑎 ∗ 𝑠𝑖𝑛ℎ(𝑥/𝑎) (9)

For the symmetric catenary, mid-span sag is formulated based on the equation of position:

0.5𝜆
ℎ𝑥=0 = 𝑦(0.5𝜆) − 𝑦(0) = 𝑎 ∗ [𝑐𝑜𝑠ℎ ( 𝑎
)− 1] (10)

Finally, the following tension equations based on the horizontal tension, FH, are useful (PLS-CADD 1993):

𝐹𝑉 (𝑥) = 𝐹𝐻 ∗ 𝑠𝑖𝑛ℎ(𝑥/𝑎) = 𝑠(𝑥) ∗ 𝑤 (11)

𝑇(𝑥) = 𝐹𝐻 ∗ 𝑐𝑜𝑠ℎ(𝑥/𝑎) = 𝑦(𝑥) ∗ 𝑤 = √𝐹𝐻 2 + 𝐹𝑉 (𝑥)2 (12)

Figure 5 shows a catenary free-body diagram cut at the low point or “belly” with end reactions.
The figure shows an effective vertical force equal to the weight of the cable acting a distance d from end
point J. It is interesting to note that the force passes through the intersection of lines f1(x) and f2(x), defined
by the slope of the curve at point O and end point J, respectively. This is significant because the geometry

Page 22 of 284
of the curve confirms that summing the moments about point O is equal to zero, as originally postulated
regarding the catenary (i.e. tension only, zero bending stiffness).

FV

FH
J

h w

FH
O
d
λ2

© 2017 D. Gelder. All Rights Reserved.


x
Figure 5: Free Body Diagram of Catenary Cable Showing End Reactions

ELASTIC BEHAVIOR (MECHANICS)

The formulation of the equations defining elastic behavior, including linear stretch and linear
thermal expansion, are presented herein. The elastic catenary equations are of extreme importance in
transmission engineering. Transmission structures are designed to support a variety of loading
combinations for the wire—including temperature, wind, and ice—to maintain proper strength and
clearances “at all times” (NESC 2012). To simplify the discussion, the effects of ice and wind are not
considered herein. It is only noted that ice increases the unit weight in the same plane as gravity, while wind
increases the unit weight out-of-plane. Thus, an effective unit weight may be calculated as the resultant of
self-weight, ice, and wind, deforming still in the shape of a catenary, but swung out-of-plane.
One approach for calculating the sag-tension catenary relationship is presented as follows. The
formulation of equations includes equations of compatibility, geometry, conservation of mass, and
equilibrium.

Page 23 of 284
Compatibility. The following equation utilizes the concept of an “unstressed” cable length,
LUnstressed, in which there is zero tension and at a reference temperature. The cable length, L, can then be
calculated based on changes in tension, ΔLTension, and/or temperature, ΔLTemp.

𝐿 = 𝐿𝑈𝑛𝑠𝑡𝑟𝑒𝑠𝑠𝑒𝑑 + ∆𝐿 𝑇𝑒𝑛𝑠𝑖𝑜𝑛 + ∆𝐿 𝑇𝑒𝑚𝑝 (13)

The following equations for linear force-displacement are based on Hooke’s Law where k is cable
stiffness, E is modulus of elasticity, and A is cross-sectional area. Note that positive force implies tension
increase and negative force implies tension decrease.

∆𝐿 𝑇𝑒𝑛𝑠𝑖𝑜𝑛 ≈ 𝐹𝐻 /𝑘 (14)
𝑘 = 𝐸𝐴/𝐿𝑈𝑛𝑠𝑡𝑟𝑒𝑠𝑠𝑒𝑑 (15)

The following equation is for linear thermal expansion where α is the coefficient of thermal
expansion, TEMP is the conductor temperature, and TEMPREF is the reference conductor temperature
(typically 0°C or 32°F) (SAPS 1997).

∆𝐿 𝑇𝑒𝑚𝑝 = 𝐿𝑈𝑛𝑠𝑡𝑟𝑒𝑠𝑠𝑒𝑑 ∗ 𝛼 ∗ (𝑇𝐸𝑀𝑃 − 𝑇𝐸𝑀𝑃𝑅𝐸𝐹 ) (16)

Substituting, the equations simplifies to:

𝐻 𝐹
𝐿 = 𝐿𝑈𝑛𝑠𝑡𝑟𝑒𝑠𝑠𝑒𝑑 ∗ [1 + 𝐸𝐴 + 𝛼 ∗ (𝑇𝐸𝑀𝑃 − 𝑇𝐸𝑀𝑃𝑅𝐸𝐹 )] (17)

Geometry. The conductor length, L, of a symmetric catenary may be defined using the formula for
arc length, where x is equal to half of the span length, λ, and multiplying the arc length by two:

0.5𝜆
𝐿 = 2 ∗ 𝑎 ∗ 𝑠𝑖𝑛ℎ ( 𝑎
) (18)

Conservation of Mass. Based on the law of conservation of mass the total cable weight with fixed
ends, W, is constant regardless of changes due to tension or temperature. Thus,

𝑊 =𝐿∗𝑤 (19)

Solution. These equations can be combined into a solvable system of three equations with three
unknowns: L, FH, and a. These variables may be solved for iteratively using a spreadsheet or another tool.

𝐻 𝐹
𝐿 = 𝐿𝑈𝑛𝑠𝑡𝑟𝑒𝑠𝑠𝑒𝑑 ∗ [1 + 𝐸𝐴 + 𝛼 ∗ (𝑇𝐸𝑀𝑃 − 𝑇𝐸𝑀𝑃𝑅𝐸𝐹 )]
0.5𝜆
𝐿 = 2 ∗ 𝑎 ∗ 𝑠𝑖𝑛ℎ ( ) (20)
𝑎
𝑊
{ 𝐿= 𝑤

Equilibrium. The solution may be checked using an observation that the effective moment in
balance, M, equal to the product of horizontal tension and sag, is approximately constant regardless of

Page 24 of 284
changes in tension or temperature. This is essentially the same conclusion as proposed by the general cable
theorem which states that, “any point multiplied by the cable sag at this point is equal in magnitude to the
moment at the corresponding position in a simply supported beam of the same length and carrying the same
vertical loads” (Muvdi et al. 1997).

𝑀 = 𝐹𝐻 ∗ ℎ ≈ 𝑐𝑜𝑛𝑠𝑡𝑎𝑛𝑡 (21)

To demonstrate that these equations may be used in a spreadsheet to obtain valid results, sample
sag-tension data is provided. The data is for a 122 m (400 ft) span of Marigold AAC conductor strung at
8,900 N (2,000 lbs) at 15.6°C (60°F). Input data is listed in Table 1. Sag-tension results for a variety of
temperatures are listed in Table 2. Results from PLS-CADD® are also listed in Table 2 for comparison.
Comparing the last four columns in Table 2 for horizontal force, FH, and sag, h, shows that results
corroborate.

Table 1: Input Data for Sag-Tension Calculations

Conductor Marigold AAC


Conductor

Unit Weight, w 15.25 N/m (1.045 lbs/ft)


Cross Sectional Area, A 564.1 mm² (0.8744 in²)
Mod. Of Elasticity, E 59.3 GPa (8600 ksi)
Coef. Thermal Expansion, α 2.30E-05/°K (1.28E-05/°F)
Span Length, λ 121.9 m (400 ft)
Horizontal Tension, FH 8897 N (2000 lbs)
Span

Cond Temperature, TEMP 15.6 °C (60 °F)


Ref Cond Temp, TEMP_REF 0 °C (32 °F)
Catenary Constant, a 583.4 m (1914 ft)
Mid-span Sag, h 3.188 m (10.459 ft)
Sag-Tension Product, M 28.36 kN-m (20.92 kip-ft)
Calculations

Cable Length, L 122.142 m (400.728 ft)


Weight, W 1862.7 N (418.74 lbs)
Delta Length Temp, ΔL_Temp -0.044 m (-0.144 ft)
Stiffness, k 273.86 kN/m (18.77 kip/ft)
Delta Length Stretch, ΔL_Tension -0.032 m (-0.107 ft)
Unstressed Length, L_Unstressed 122.066 m (400.478 ft)

Page 25 of 284
Table 2: Sag-Tension Data Produced with Spreadsheet for Marigold AAC Conductor
TEMP ΔL_Tension ΔL_Temp L a w FH h FH (PLS) h (PLS)
°C (°F) m (ft) m (ft) m (ft) m (ft) N/m (lbs/ft) kN (kips) m (ft) kN (kips) m (ft)
-51 (-60) 0.06 (0.20) -0.14 (-0.47) 121.98 (400.2) 1093 (3586) 15.27 (1.046) 16.7 (3.8) 1.7 (5.6) 16.8 (3.8) 1.7 (5.6)
-46 (-50) 0.06 (0.18) -0.13 (-0.42) 121.99 (400.2) 1009 (3311) 15.27 (1.046) 15.4 (3.5) 1.8 (6.0) 15.5 (3.5) 1.8 (6.0)
-40 (-40) 0.05 (0.17) -0.11 (-0.37) 122.01 (400.3) 939 (3081) 15.27 (1.046) 14.3 (3.2) 2.0 (6.5) 14.4 (3.2) 2.0 (6.5)
-34 (-30) 0.05 (0.16) -0.10 (-0.32) 122.02 (400.3) 877 (2878) 15.27 (1.046) 13.4 (3.0) 2.1 (7.0) 13.4 (3.0) 2.1 (6.9)
-29 (-20) 0.05 (0.15) -0.08 (-0.27) 122.03 (400.4) 824 (2704) 15.26 (1.046) 12.6 (2.8) 2.3 (7.4) 12.6 (2.8) 2.2 (7.4)
-23 (-10) 0.04 (0.14) -0.07 (-0.22) 122.04 (400.4) 783 (2567) 15.26 (1.046) 11.9 (2.7) 2.4 (7.8) 11.9 (2.7) 2.4 (7.8)
-18 (0) 0.04 (0.14) -0.05 (-0.16) 122.06 (400.4) 743 (2438) 15.26 (1.046) 11.3 (2.5) 2.5 (8.2) 11.3 (2.5) 2.5 (8.2)
-12 (10) 0.04 (0.13) -0.03 (-0.11) 122.07 (400.5) 706 (2317) 15.26 (1.046) 10.8 (2.4) 2.6 (8.6) 10.8 (2.4) 2.6 (8.6)
-7 (20) 0.04 (0.12) -0.02 (-0.06) 122.08 (400.5) 676 (2218) 15.26 (1.045) 10.3 (2.3) 2.8 (9.0) 10.3 (2.3) 2.7 (9.0)
-1 (30) 0.04 (0.12) -0.00 (-0.01) 122.10 (400.6) 649 (2129) 15.26 (1.045) 9.9 (2.2) 2.9 (9.4) 9.9 (2.2) 2.9 (9.4)
4 (40) 0.03 (0.11) 0.01 (0.04) 122.11 (400.6) 625 (2049) 15.25 (1.045) 9.5 (2.1) 3.0 (9.8) 9.6 (2.1) 3.0 (9.7)

Page 26 of 284
10 (50) 0.03 (0.11) 0.03 (0.09) 122.13 (400.7) 603 (1978) 15.25 (1.045) 9.2 (2.1) 3.1 (10.1) 9.2 (2.1) 3.1 (10.1)
16 (60) 0.03 (0.11) 0.04 (0.14) 122.14 (400.7) 583 (1912) 15.25 (1.045) 8.9 (2.0) 3.2 (10.5) 8.9 (2.0) 3.2 (10.5)
21 (70) 0.03 (0.10) 0.06 (0.19) 122.16 (400.8) 565 (1853) 15.25 (1.045) 8.6 (1.9) 3.3 (10.8) 8.6 (1.9) 3.3 (10.8)
27 (80) 0.03 (0.10) 0.07 (0.25) 122.17 (400.8) 548 (1798) 15.25 (1.045) 8.4 (1.9) 3.4 (11.1) 8.4 (1.9) 3.4 (11.1)
32 (90) 0.03 (0.10) 0.09 (0.30) 122.19 (400.9) 534 (1751) 15.24 (1.045) 8.1 (1.8) 3.5 (11.4) 8.1 (1.8) 3.5 (11.4)
38 (100) 0.03 (0.09) 0.11 (0.35) 122.20 (400.9) 519 (1703) 15.24 (1.044) 7.9 (1.8) 3.6 (11.8) 7.9 (1.8) 3.6 (11.8)
43 (110) 0.03 (0.09) 0.12 (0.40) 122.22 (401.0) 505 (1658) 15.24 (1.044) 7.7 (1.7) 3.7 (12.1) 7.7 (1.7) 3.7 (12.1)
49 (120) 0.03 (0.09) 0.14 (0.45) 122.23 (401.0) 493 (1617) 15.24 (1.044) 7.5 (1.7) 3.8 (12.4) 7.5 (1.7) 3.8 (12.4)
54 (130) 0.03 (0.09) 0.15 (0.50) 122.25 (401.1) 482 (1581) 15.24 (1.044) 7.3 (1.7) 3.9 (12.7) 7.3 (1.7) 3.9 (12.7)
60 (140) 0.03 (0.09) 0.17 (0.55) 122.26 (401.1) 471 (1545) 15.24 (1.044) 7.2 (1.6) 4.0 (13.0) 7.2 (1.6) 3.9 (13.0)
66 (150) 0.03 (0.08) 0.18 (0.60) 122.28 (401.2) 461 (1512) 15.23 (1.044) 7.0 (1.6) 4.0 (13.2) 7.0 (1.6) 4.0 (13.2)
71 (160) 0.03 (0.08) 0.20 (0.66) 122.29 (401.2) 451 (1481) 15.23 (1.044) 6.9 (1.5) 4.1 (13.5) 6.9 (1.5) 4.1 (13.5)
77 (170) 0.02 (0.08) 0.22 (0.71) 122.31 (401.3) 442 (1452) 15.23 (1.044) 6.7 (1.5) 4.2 (13.8) 6.7 (1.5) 4.2 (13.8)
82 (180) 0.02 (0.08) 0.23 (0.76) 122.32 (401.3) 434 (1424) 15.23 (1.043) 6.6 (1.5) 4.3 (14.1) 6.6 (1.5) 4.3 (14.1)
88 (190) 0.02 (0.08) 0.25 (0.81) 122.34 (401.4) 426 (1398) 15.23 (1.043) 6.5 (1.5) 4.4 (14.3) 6.5 (1.5) 4.4 (14.3)
93 (200) 0.02 (0.08) 0.26 (0.86) 122.35 (401.4) 419 (1373) 15.22 (1.043) 6.4 (1.4) 4.4 (14.6) 6.4 (1.4) 4.4 (14.6)
NONLINEAR BEHAVIOR (ADVANCED MECHANICS)

The catenary further complicates itself when considering nonlinear effects including creep, material
nonlinearities, bimetallic or composite material, flexible end supports, etc. These effects are the substance
of advanced mechanics of materials and are of great importance in transmission engineering. Many
nonlinear effects exceed the typical scope of hand-calculations and require substantial programming to be
utilized effectively. Additionally, to capture nonlinear effects, numerical models—such as finite element—
are often required. Thus, the formulation of nonlinear equations is not within the scope of this paper. Rather,
the concepts and some results produced using PLS-CADD® software are briefly presented.
Of great importance is permanent cable deformation due to excessive load and/or creep. While
several approaches exist, PLS-CADD® uses fourth order polynomials to model both stress-strain and creep.
The stress-strain of bimetallic conductors is treated as a weighted-average based on cross-sectional area.

𝜎 = 𝑘0 + 𝑘1 𝜀 + 𝑘2 𝜀 2 + 𝑘3 𝜀 3 + 𝑘4 𝜀 4 (22)

Figure 6 shows horizontal tension vs. conductor sag relationship. Figure 7 shows conductor sag vs.
conductor temperature. Figure 8 shows horizontal tension vs. conductor temperature. Each figure plots
“Linear Material,” as well as “Nonlinear Material” curves for “Initial” and “Creep” conditions.

Axis Title
0 ft 3 ft 6 ft 9 ft 12 ft 15 ft 18 ft 21 ft
20 kN
Linear Material
Nonlinear Material, Initial Condition
Nonlinear Material, Creep Condition
4 kips

16 kN

3 kips
Horizontal Tension

12 kN
Axis Title

y = 28301x-0.998
R² = 1
2 kips
8 kN

Conductor: Marigold AAC 1113 kcmil 1 kips


4 kN
Span: 122 m (400 ft)
Sag Temp.: 15.6 °C (60 °F)
Sag Tension: 8.9 kN (2.0 kips)
Unit Weight: 15.25 N/m (1.045 lbs/ft)
Ult. Tension: 87.6 kN (19.7 kips) © 2017 D. Gelder. All Rights Reserved.
0 kN 0 kips
0m 1m 2m 3m 4m 5m 6m 7m
Conductor Sag

Figure 6: Horizontal Tension vs. Conductor Sag

Page 27 of 284
Axis Title
-150 °F -50 °F 50 °F 150 °F 250 °F 350 °F 450 °F
7m
Linear Material
Nonlinear Material, Initial Condition
Nonlinear Material, Creep Condition 21 ft
6m

18 ft

5m
15 ft
Conductor Sag

4m

Axis Title
12 ft

3m
9 ft

2m
6 ft
Conductor: Marigold AAC 1113 kcmil
Span: 122 m (400 ft)
1m Sag Temp.: 15.6 °C (60 °F) 3 ft
Sag Tension: 8.9 kN (2.0 kips)
Unit Weight: 15.25 N/m (1.045 lbs/ft)
© 2017 D. Gelder. All Rights Reserved. Ult. Tension: 87.6 kN (19.7 kips)
0m 0 ft
-100 °C -50 °C 0 °C 50 °C 100 °C 150 °C 200 °C 250 °C
Conductor Temperature

Figure 7: Conductor Sag vs. Conductor Temperature

Axis Title
-150 °F -50 °F 50 °F 150 °F 250 °F 350 °F 450 °F
20 kN
Linear Material
Nonlinear Material, Initial Condition
Nonlinear Material, Creep Condition
4 kips

16 kN

3 kips
Horizontal Tension

12 kN
Axis Title

2 kips
8 kN

Conductor: Marigold AAC 1113 kcmil 1 kips


4 kN
Span: 122 m (400 ft)
Sag Temp.: 15.6 °C (60 °F)
Sag Tension: 8.9 kN (2.0 kips)
Unit Weight: 15.25 N/m (1.045 lbs/ft)
Ult. Tension: 87.6 kN (19.7 kips) © 2017 D. Gelder. All Rights Reserved.
0 kN 0 kips
-100 °C -50 °C 0 °C 50 °C 100 °C 150 °C 200 °C 250 °C
Conductor Temperature

Figure 8: Horizontal Tension vs. Conductor Temperature

Page 28 of 284
In transmission engineering, the rigidity of end supports is also of great interest—particularly when
modeling existing transmission lines. Central to this discussion is the timeless lesson: boundary conditions
matter. Various models for wire-to-structure boundary conditions have been proposed for multi-span
problems including the classic Ruling Span method (Thayer 1924). It is important to note that Ruling Span
was originally intended for deriving stringing tensions, in which wires are pulled through roller
attachments. Once strung, wires are clipped to the insulators, thus engaging the structure. ‘Pulley’ and ‘clip’
elements have been proposed to capture the various effects of clipping wires to insulators and engaging
structure flexibility (Peyrot and Goulois 1978; Peyrot and Goulois 1979; McDonald and Peyrot 1990).
Today’s most commonly used transmission design software, PLS-CADD® (1993), provides a means of
analyzing transmission lines under four different sets of boundary condition assumptions. These “analysis
levels” each have assumptions which may produce very different results in terms of structure loads from
wires. Scenarios provoking differences include: short-span-long-span, heavy angles, steep terrain, true
dead-ending, false dead-ending, single-span, guying, taps/intersections, flexible or rigid attachments, etc.
In current practice, many engineers modeling transmission lines typically select a single analysis level to
be used for checking designs. This is sufficient for preliminary design, but may expose final results to
pitfalls of the selected analysis level. As an alternative, it is recommended that transmission engineers
compare and contrast results using multiple PLS-CADD® analysis levels and employ good engineering
judgment to control variation in results.

CONCLUSION

The goals of this paper were to present the catenary equations of position, tension, and elongation
in a manner useful to a transmission engineering audience and to make equations seem less intimidating to
transmission engineers. These equations are of great importance to the design and analysis of transmission
lines. As transmission engineers explore, understand, and use these equations, minds will be empowered
and designs will improve.

Page 29 of 284
REFERENCES

Hibbeler, R.C. (2007). Engineering Mechanics Statics, 11th Ed., Pearson Prentice Hall, New Jersey.
McDonald, B. and Peyrot, A. (1990), “Sag-Tension Calculations Valid for Any Line Geometry.” Journal
of Structural Engineering, 116(9), 2374-2386.
Muvdi, B., Al-Khafaji, A., and McNabb, J. (1997). Statics for Engineers, Springer-Verlag, New York, NY.
Peyrot, A.H and Goulois, A.M. (1978), “Analysis of Flexible Transmission Lines.” Journal of the Structural
Division, ASCE, 104(ST5), 763-779.
Peyrot, A.H. and Goulois, A.M. (1979), “Analysis of Cable Structures.” Computers and Structures, 10(5),
805-813.
NESC (2012 and older editions), National Electrical Safety Code, IEEE, New York, NY.
PLS-CADD (1993 and newer versions), A Computer Program for the Integrated Analysis and Design of a
Transmission Lines (including spotting optimization), Power Line Systems, Madison, WI.
SAPS (1997), A Computer Program for the Nonlinear Structural Analysis of Power and Communication
Systems, Power Line Systems, Madison, WI.
Thayer, E.S. (1924), “Computing tensions in transmission lines”, Electrical World, 84(2), 72-73.
Weisstein, E. W. (1999), “Catenary.” MathWorld—A Wolfram Web Resource,
<http://mathworld.wolfram.com/Catenary.html> (June 9, 2015).

NOMENCLATURE

a Catenary constant (m or ft)


A Cable cross-sectional area (mm2 or in2)
E Cable elastic modulus (GPa or ksi)
e Mathematical constant, Euler’s number (2.71828…)
FH Horizontal component of cable tension (kN or kips)
FV Vertical component of cable tension (kN or kips)
g Gravitational acceleration (9.81 m/s2 or 32.2 ft/s2)
h Mid-span cable sag (m or ft)
i Index varying from 1 to n
J End support
k Cable stiffness (kN/m or kip/ft)
ki Coefficient of polynomial creep or stress-strain model
L Cable length at temperature T (m or ft)
LUnstressed Unstressed cable length at reference cable temperature (m or ft)
ΔLTension Change in length due to change in cable tension (m or ft)
ΔLTemp Change in length due to change in cable temperature (m or ft)
M Bending moment (kN-m or kip-ft)
T Cable tension (kN of kips)
TEMP Cable temperature (°C or °F)
TEMPREF Reference cable temperature (typically 0 °C or 32 °F)
w Cable force per unit length (N/m or lbs/ft)
W Total cable weight (N or lbs)
(x,y) Local Cartesian coordinate system
(X,Y) Global Cartesian coordinate system
α Coefficient of thermal expansion (1/°K or 1/°F)
ε Cable strain (elongation in unit length in percent)
λ Span length (m or ft)
ρ Cable material density (kg/mm3 or slugs/in3)
σ Average axial stress (kPa or ksi)

Page 30 of 284
50th Annual
Transmission and Substation Design and
Operation Symposium

Advantages, limitations and development of


power transformer insulation diagnostics

By

Diego M. Robalino, PhD


Principal Engineer
Megger North America
Dallas, TX, USA

Page 31 of 284
Abstract
For decades, power factor / dissipation factor testing has been used throughout the electrical industry
and has triggered the attention of many who are directly involved in electrical equipment operation,
maintenance and asset management. The predominant question today is no longer about how to perform
this test but how to move forward with this technology understanding its advantages, limitations and the
way to overcome such limitations.

It has been over a century since the first insulation material was used to isolate two different potential
levels. Different methods have become available in the form of DC and AC techniques to quantify dielectric
losses within the insulation material. The power factor/dissipation factor testing technique has evolved
accompanied by the development of more sophisticated and reliable electronic components and IT
solutions. National and international standards now address power factor testing as a routine method for
insulation condition assessment and provide reference values establishing boundaries to guide operators
and maintenance personnel on when to resume operation, perform additional investigation, or remove from
operation. Trending analysis, however, remains the most reliable approach to analyze power factor results
but is still not without limitations. No matter the analytic approach used, a single power factor measurement
at line-frequency may mask important information needed to make sound technical recommendations and
avoid unwarranted actions that may compromise the reliability of the operation.

Line-frequency power factor values can increase due to moisture contamination, insulation degradation,
aging or mechanical damage, but it is quite complicated to determine the cause for elevated (or too low)
line-frequency power factor values. Moreover, power factor is temperature and frequency dependent;
therefore, variations of temperature and frequency may lead to incorrect interpretation of results. Proper
correction is needed. The use of the Individual Temperature Correction (ITC) algorithm is presented in this
paper giving field operators a realistic correction based on the unique dielectric response of the specimen
under test.

Linearity and non-linearity of the dielectric system may unknowingly change the analysis approach
from one only comprised of dielectric loses to another one including loses due to discharge activity. The
voltage dependence detection (VDD) algorithm is discussed as an evaluation tool in the power factor test
to identify non-linearity of the dielectric system.

In addition to power factor testing of the liquid-impregnated insulation, guidelines are provided for
liquid insulation dissipation factor test in the field and the importance of advanced applications of line-
frequency power factor test in the frequency domain spectroscopy analysis is reviewed.

This paper summarizes the latest development in power factor testing for insulation assessment of
power and distribution transformers in the field. Comprehensive guidelines described in the document will
improve the decision making process, will clarify doubtable results, will allow prioritization of maintenance
activities and will prevent failure and accelerated degradation of the insulation system.

Page 32 of 284
I. INTRODUCTION
An insulation system is represented in electric circuits by a capacitor. Two electrodes separated by a
dielectric form a capacitor same as two conductive surfaces separated by an insulating material form an
insulating system. A perfect or ideal capacitor would have no other component of current except the
capacitance component. However, no dielectric materials, not even vacuums, are perfect. There are always
nonconforming electrons that form part of the conduction or loss component of current. The number of free
electrons depends on the molecular structure of the material, contaminants (particularly moisture), and
temperature.

For power transformers, the service life is estimated based on the analysis of the capacitive components
or the dielectric insulation system and dielectric mode failures are the highest contributor of failure modes,
irrespective of transformer application. Dielectric mode failures on fluid-immersed transformers may result
in fire, explosions and damage to surrounding equipment and/or personnel.

To assess the condition of the dielectric system, off-line dielectric response techniques are readily
available and are commonly used. The dielectric response can be obtained in the time domain (DC
Insulation resistance, polarization Index, polarization-depolarization current) and/or in the frequency
domain (line frequency power factor and frequency domain spectroscopy).

Historically, the DC insulation resistance method pioneered the industry of insulation diagnostics and
has evolved for over a century. The portability of DC equipment made it ideal for field condition assessment
of medium, high and extra-high voltage apparatuses. AC testing equipment were bulky and difficult to
transport, but the continuous development of power electronics, communications and materials technology
has promoted the AC testing equipment forward and its application for insulation diagnostics has spread
globally.

The electrical power industry has relied on single frequency (line frequency) power factor/ dissipation
factor and capacitance testing to assess electrical insulation for almost a century. Industry specialists,
researchers and instrument manufacturers have worked together to provide advanced features to improve
and expand the information obtained from line-frequency power factor testing on fluid-filled transformers.

II. TIME DOMAIN INSULATION DIAGNOSTICS ON POWER TRANSFORMERS


In the time domain method, measurement of insulation resistance constitutes a direct-voltage test
restricted to a value appropriate to the voltage rating of the winding and the basic insulation condition.
Insulation diagnostics methods do not intend to overstress the insulation but rather try to determine the
dielectric parameters measurable in that insulation. This is particularly important in the case of low-voltage
or wet systems.

Insulation resistance tests are usually conducted at constant direct voltages of 100 – 15,000 V having
negative polarity and measurements can go from the megaohm (M) range up to teraohms (T). Negative
polarity is preferred to accommodate the phenomenon of electro-endosmosis [1]. Readings of insulation
resistance are taken after the test direct voltage has been applied for 1 minute. Most important to understand
is that for insulation resistance (IR), there is no need to overstress the insulation material, the idea is to

Page 33 of 284
measure the dielectric properties of the capacitance under test. The amount of power produced is very low,
the test is considered non-destructive as well as non-intrusive.

IR test is recommended during commissioning and after protection trip due to internal fault in power
and distributions transformers [2]. IR tests are made to determine the insulation resistance magnitude from
individual windings to ground or between individual windings. In transformers, the recommended practice
in measuring IR is to always ground the tank (and the core). Short-circuit each winding of the transformer
at the bushing terminals. IR measurements are then made between each winding and all other windings
grounded.

Connections for IR on transformers are described below:

a. Two-winding transformer
o (HV + LV) to GND
o HV to (LV + GND)
o LV to (HV + GND)

b. Three-winding transformer
o HV to (LV + TV + GND)
o LV to (HV + TV + GND)
o (HV + LV + TV) to GND
o TV to (HV + LV + GND)

c. Autotransformer (two winding)


o (HV + LV) to GND

d. Autotransformer (three winding)


o (HV + LV) to (TV + GND)

Notice that on the recommended hook-up connections above, “guard” is not used. The guard line is at
the same potential as the DC source generator potential. For a HV winding, 5kVDC might be OK, but not
for a 480V LV winding.

Interpretation of IR results is based on historical data, transformer design, type of insulating material,
and contamination level. Transformers filled with natural ester-based liquid generally have lower insulation
resistance compared with ones filled with mineral oil [2]. Trending analysis of IR results is more significant
than the instantaneous measurement; keep a record of the voltage used for testing and the obtained values
corrected to 20°C.

Figure 1 shows two different specimens tested for IR. One has a significant change of IR from high G
values while the other one has not changed significantly and numbers remain steady even in the M range.
The insulation temperature also affects the readings, typically testing at higher temperature results in lower
insulation resistance.

Page 34 of 284
Figure 1 Trending of Insulation Resistance values of two different specimens.

Very low values of IR are indicative of a breakdown in the insulation to ground or between windings,
high moisture, or heavy carbon tracking. Additional tests such as polarization index, insulation PF, or
dielectric frequency response are required to validate and better determine the reason for low IR values.

III. FREQUENCY DOMAIN INSULATION DIAGNOSTICS ON POWER TRANSFORMERS


For over 80 years, the use of AC voltage to assess the condition of transformers’ insulation has become
fundamental. When an AC voltage is applied across a typical insulation system, while most of the resulting
current that flows through the insulation is capacitive (representing the energy being stored by the
insulation), resistive current results as well. This resistive component, IR, which is in-phase with the AC
voltage, is associated with the insulation dielectric loses. The total resulting current that flows through the
insulation, IT, is the vector sum of the capacitive current, IC, and resistive current, IR, as given in Figure 2.

Figure 2 Total resulting current in a real insulation system

Page 35 of 284
Dielectric loss is the energy lost or released as heat when an electrostatic field is present across an
insulation system. Losses can be broadly classified as conductive losses, arising from leakage current, or
polarization losses. The total losses (IR ∙ V) in a dielectric are equal to the combined polarization losses and
conductive losses present.

Dielectrics perform best when they are clean, dry, relatively void-free, and utilized within a certain
temperature range. Adversaries to a dielectric’s continued good health are heat, moisture and oxygen.
Continuous degradation of the insulation system is observed when power factor/dissipation factor test
reports higher dielectric loses. Normal transformer service shows a slow increase of these dielectric losses
and that is expected to see during normal and/or routine maintenance testing. Nevertheless, rapid increase
of losses are indication of an active failure condition that may lead into dielectric breakdown.

Power Factor (1) is the cosine of  (the complementary angle of the “loss angle”) while Dissipation
Factor (2) is the tangent of , or the loss angle. As described in [2], the normal in-service and new PF limit
for mineral-oil-filled power transformers < 230 kV is 0.5% PF at 20 °C, and the normal and new limit for
transformers  230 kV is 0.4%. To help reduce the risk of catastrophic failure, the limit for serviceability
of all mineral-oil-filled transformers is 1.0% PF at 20 °C. PFs between 0.5% and 1.0% at 20 °C require
additional testing and investigation to confirm that a problem is not worsening.

IR
Power Factor: % PF  cos   100 %   100 % (1)
IT
IR
Dissipation Factor: % DF  tg   100 %   100 % (2)
IC

IV. LIMITATIONS OF THE LINE FREQUENCY POWER FACTOR

A. One single reference point


Insulation systems typically have losses, even when brand new. As an insulation ages or becomes
contaminated, the power factor/ dissipation factor will often increase. Interpretation of power factor results
Trending analysis used for interpretation of power factor results relies on one single frequency measurement
taken and assumes proper thermal correction of this measured value.

Power factor/ dissipation factor represents the average condition of the total insulation system under
test. If the system is big enough, some localized contamination may be impossible to see. On a large single-
phase autotransformer with an embedded tertiary with no external access, only one power factor/dissipation
factor and capacitance measurement can be performed on such a transformer (all the winding terminals are
connected together and energized for a winding to ground insulation measurement). Degradation or
contamination might be difficult to pinpoint.

Increasing levels of some contaminants might not provide notable change in power factor/ dissipation
factor at line frequency and depending on the conductivity of the material, the effect of contamination may
be observed at a frequency different from 50/60Hz.

To overcome this limitation, a dielectric frequency sweep in the range between 1 – 500 Hz is required.

Page 36 of 284
B. Thermal dependence
On this point and from IEEE Std. C57.12.90, the following is extracted as published:

“NOTE 3— b) Experience has shown that the variation in power factor with temperature is substantial
and erratic so that no single correction curve will fit all cases. The power factor shall be reported along with
the top oil temperature measured and the bottom oil temperature if available. No temperature correction
shall be applied. Temperature correction of the power factor results for trending basis may be applied by
the purchaser”.

IEEE Std. C57.152 section 7.2.14.5 states:

“…The loss factor of insulation can be sensitive to variations in temperature, in which case a correction
factor needs to be applied to measured values. This is done to allow comparison of tests performed at
different temperatures. The reference temperature used is 20 °C. Correction factors may be available from
equipment manufacturers and test equipment manufacturers. (Additional correction factors were available
in IEEE Std. C57.12.90-2006, 10.10.5, which was removed in IEEE Std. C57.12.90-2010.)...”

The standards clearly indicate that measurements of losses in the dielectric material are sensitive to
temperature variation as well as dielectric condition changes. Changes in power factor due to moisture,
contamination or degradation of the insulation material is unique to the asset and cannot be duplicated in
another asset, even one with an identical nameplate, because of different insulation condition, electrical,
thermal and/or mechanical stress, operation condition, maintenance work, etc.

To overcome this limitation, an algorithm to estimate the individual temperature correction is required.

C. Voltage Dependence
The voltage dependence phenomenon in solid insulation during line-frequency PF/DF test is well
described in [3] and [4]. The losses measured in the insulation system when a line-frequency (50/60Hz)
signal is applied, is a composite of dielectric losses which are constant with voltage and power loss due to
discharges. Mathematically this can be expressed as the total conductance of the system in (3)

1
f
2 f
G   C 0 tan  0 
Vm
  Q i sin  t i (3)
0

Based on (3), if no discharges occur, the amount of charge increase on the electrodes or conductors as
a result of internal discharges (Qi) equals zero. To visualize this effect, a narrow band DFR test at different
voltage levels carried out on epoxy type MV equipment is presented in Figure 3.

Page 37 of 284
Figure 3 DFR obtained from MV epoxy-type insulation specimen at different voltages

It is clear from Figure 3 that the voltage dependence of an insulation system can not be determined by
a single voltage test. In the specific case of oil-impregnated insulation, the expected condition is to measure
PF/DF at line frequency at a single voltage and that the value under ideal conditions will not change. A
deviation from this statement will indicate that the ideal condition has been altered and potential degradation
is taking place within the insulation system of the transformer. Figure 4 shows an ideal condition of the
insulation inside the transformer in a tip-up test.

Figure 4 Tip up test carried out on a 1991 Dyn1, 67/13.09 kV, 25MVA

The limitation of power factor test at line frequency is to have a single voltage test value for a specific
capacitive zone. To overcome this limitation, a technical approach to determine voltage dependency is
required. %VDF (percentage voltage dependence factor) is a very small value, typically below 0.1% for
linear %PF response.

Page 38 of 284
V. DEVELOPMENT OF INSULATION DIAGNOSTICS ON POWER TRANSFORMERS

A. Narrow band dielectric frequency response (DFR)

As discussed in section IV.A., the single frequency power factor measurement has limited information
regarding the factor affecting the insulation system. Moreover, similar PF values might be obtained out of
different specimens even though the insulation condition is different.

Figure 5 describes six different examples of insulation conditions where line frequency power factor is
the same or very close on all of them. The reality shows that a dielectric frequency response between 1 and
500 Hz helps visualization of potential factors affecting the condition of the insulation.

Figure 5 Narrow band DFR of different insulation conditions

The research presented in [5] shows the importance of the narrow band dielectric response. The specific
application on oil-impregnated paper (OIP) HV bushings allows a better assessment of the insulation at
1Hz. It is recommended to plot the narrow band dielectric response in a logarithmic scale (as shown in
Figure 5), otherwise the smallest decade (1 – 10Hz) is not clearly visualized.

Narrow band DFR from 1 to 500Hz has been already implemented in state-of-the-art power factor test
sets and its use has more applications as it is discussed in the next section.

B. Individual Temperature Correction (ITC)

As mentioned in the previous section, narrow band DFR has an additional application when used for
advanced diagnostics in power factor testing.

Figure 6 clearly shows how the dielectric response in the frequency domain and in the thermal domain
change based on the condition of the insulation system and therefore the use of tables and average correction
factor values might be misleading and not accurate.

Page 39 of 284
(a) (b)

Figure 6 Influence of temperature on: (a) DFR of insulation with 1% mc; (b) DFR of insulation with 3.5% mc

The obtained narrow band DFR from the inter-winding insulation is used now to determine the
individual temperature correction of the line frequency power factor measured at temperatures different
from 20°C.

The mathematical approach used to correlate line-frequency power factor with temperature is an
Arrhenius-based equation (4). This approach describes the ‘frequency shift’ factor, which is dependent on
the temperature difference between the temperature of the measurement T2 and the reference temperature
T1 (expressed in Kelvin).

 Ex,y  1 1 
  
T  (4)
A x , y T1 , T 2   e
kB  2 T 1 

The equation considers an exponential function related to temperature (T), Boltzmann constant (kB)
and the activation energy value (Ex,y) of the material. It has been found that the shape of the dielectric
response (PF/DF versus frequency) does not change very drastically with temperature for quite a large
group of solid dielectric materials; rather, as temperature changes, the response (a spectral shape) shifts
with respect to frequency while remaining intact. This means that a PF/DF value measured at line frequency
and the temperature at time of test, is the exact same PF/DF that would be measured at the reference
temperature of 20°C with the big exception that it would occur at a frequency shifted from and different
than line frequency

Therefore, using narrow band DFR, the individual temperature correction (ITC) factor can be estimated
for the line frequency power factor based on the real insulation condition [6].

Page 40 of 284
C. Voltage Dependence Detection (VDD)

The effect of voltage over an insulation system is not observed by a single voltage, single frequency
power factor test. The voltage dependency effect has been observed and studied and the new power factor
technology uses the so called percentage voltage dependence factor (%VDF) representing the distortion of
the measured current with respect to its fundamental. The distortion in the measured current signal, as
represented in Figure 7, implies that the insulation system has lost its linearity [7].

Figure 7 Applied Voltage and measured current through a voltage dependent insulation system

Therefore, the %VDF can be calculated in a similar way as the total harmonic distortion (THD) of the
measured current signal as presented in (5):


2
Ih
h2
(5)
% VDF   100 %
I1

The application of the VDF is easily demonstrated testing solid insulation specimens such as epoxy
filled MV instrument transformers. It is clear the effect of voltage dependency and non-linearity of the
dielectric system by performing a tip-up test on the insulation and monitoring the %VDF as presented in
Figure 8. The ideal oil-paper insulation presented in Figure 4 compared to the plot in Figure 8 clearly
support the need to have implemented voltage dependence detection algorithms in the power factor testing
instrument.

Figure 8 (b) shows that as soon as the voltage reaches the point where the %PF loses linearity, the
%VDF follows the non-linear effect. If the insulation shows deterioration, PD activity or contamination,
%VDF provides a warning flag to the end user “suggesting” to add a tip-up test to the series of tests carried
out on that specific transformer.

Page 41 of 284
(a) (b)

Figure 8 Tip-up test on MV PT: (a) test hook-up; (b) %PF and %VDF as a function of test voltage

VI. ADVANCED DIAGNOSTICS BY MEANS OF DIELECTRIC FREQUENCY RESPONSE


Frequency Domain Spectroscopy (FDS) also known as Dielectric Frequency Response (DFR) is an
advanced application of the power factor test to determine the condition of the insulation system in power
and distribution transformers.

In the frequency domain, the dielectric spectrum is obtained applying a low voltage AC excitation
signal (140 Vrms) to the insulation system. The frequency spectrum is typically obtained between 1 kHz and
1 mHz as shown in Figure 9.

Figure 9 DFR of a fluid-filled power transformer and zones of influence

The response is analyzed based on mathematical modeling and comparative analysis against a well-
documented materials’ database to determine primarily:

 Percentage moisture concentration in the solid insulation, and;


 Conductivity of the liquid insulation

In addition, DFR provides information of the presence of contaminants by non-typical responses and
the information can be converted from the frequency domain into the thermal domain providing the
dielectric thermal response of the insulation system as a plot of %PF or %DF vs. insulation temperature as
shown in Figure 10.

Page 42 of 284
Figure 10 Example of dielectric thermal response of a fluid-filled power transformer

The IEEE transformers committee is finalizing the work to generate the guidelines for DFR application
on power and distribution transformers. The document is expected to be published in 2018 under the
designation IEEE Std C57.161.

VII. SUMMARY
As presented in this article, condition assessment of transformer insulation is not a simple task. Limited
information obtained by a single frequency power factor may not be conclusive in the analysis and the
features developed are tools that need to be properly understood and applied.

Characteristic Limitation Development Comments


The DFR obtained between
PF measurement Narrow band dielectric 500Hz – 1Hz shows the unique
One single point for
at line frequency frequency response (or narrow dielectric condition of the unit.
analysis
(50/60Hz) band DFR) Special attention at 1Hz on
bushings.
The variation in power
factor with
ITC – Individual Temperature
PF measurement temperature is ITC is obtained by measurement
Correction, based on the unique
is temperature substantial and erratic of PF at different frequencies in
dielectric response of the
dependent so that no single the range from 1 – 500Hz.
transformer
correction curve will
fit all cases
PF under ideal
Single frequency %VDF - %Voltage dependence
conditions in oil- %VDF is calculated from the
measurement can not Factor provides a warning
paper insulation distortion of the measured
detect voltage signal with only one
is not voltage signal.
dependency measurement at test voltage
dependent
DFR – Dielectric frequency
High or low values of
response allows advanced DFR is typically obtained at low
Condition PF might be related to
condition of transformer voltage AC signal of 140Vrms
Assessment with contamination,
insulation: moisture in the solid in the frequency range from
PF degradation, moisture,
insulation and conductivity of 1000Hz to 1mHz.
aging.
the liquid insulation

Page 43 of 284
VIII. REFERENCES
[1] IEEE Recommended Practice for testing Insulation resistance of Rotating Machinery. IEEE Std
43-2000 (R2006).
[2] IEEE Guide for Diagnostic Field Testing of Fluid-Filled Power Transformers, Regulators, and
Reactors. IEEE Std C57.152TM-2013.
[3] IEEE Std. 286-2000 (R2012). “IEEE Recommended practice for measurement of power factor tip-
up of Electric machinery Stator Coil insulation”.
[4] T. W. Dakin, “The Relation of Capacitance Increase with High Voltages to Internal Electric
Discharges and Discharging Void Volume”. AIEE Transactions. Part III, Issue 3, 1959
[5] D. Robalino, I. Guener, P. Werelius, “Analysis of HV Bushing Insulation by Dielectric Frequency
Response”. Proceedings from the IEEE EIC Conference 2016.
[6] D. Robalino, “Individual Temperature Compensation – benefits of dielectric response
measurements”. Transformers magazine, Vol. 2, Issue 3. 2015.
[7] Dielectric Frequency Response Measurement Technology for Measurements in High Interference
AC and HVDC Substations”. 2011 TechCon Asia-Pacific, Sydney, Australia

Page 44 of 284
50th Annual
Transmission and Substation Design and
Operation Symposium

Power Transformers Field Dry Out Optimization


Utilizing

Dielectric Frequency Response Method

By

Dinesh Chhajer, PE Ian Kreher


Manager, Technical Support Group Engineer – Transmission Field Services
Megger North America American Electric Power
Dallas, TX USA Roanoke, VA USA

Page 45 of 284
Abstract
A transformer is one of the most important assets in a high voltage substation. The life
expectancy of a power transformer can be drastically reduced by the presence of internal moisture.
Excessive amounts of moisture in paper insulation can degrade the thermal characteristics and loading
capabilities of a power transformer. With the transformer aging, loading, thermal and electrical stresses,
degradation of solid insulation and other factors, the moisture content increases over time reducing the
dielectric strength of the insulation system.

Oil impregnated paper insulation is hygroscopic in nature and retains the maximum amount of
moisture when compared against the insulating oil. Depending on equipment availability and company
operating procedures, each utility uses different field dry out techniques such as hot air or oil
circulation, vacuum only or heat and vacuum methods to extract the moisture from the windings. The
dry out process helps in slowing down the rate of aging of the cellulose material. Low moisture levels as
recommended in different IEEE standards provide power system operators confidence in the dielectric
integrity of the transformer and its reliable operation.

Utility operators utilizing field dry out techniques often run into a challenge to determine the
remaining moisture and appropriate time to stop the process. There are traditional methods available to
estimate the moisture in solid insulation, however many of them rely upon a state of thermal
equilibrium or other charts; that only provide approximation of the remaining moisture in the insulation.
This uncertainty in moisture estimation could prompt operators to longer dry out durations and at times
lead to the risk of excessive dryness making paper insulation too brittle that reduces the tensile strength
and Degree of Polymerization.

This paper will introduce the Dielectric Frequency Response (DFR) measurement technique that
allows a user to determine the moisture content in solid insulation before, during and at the completion
of dry out process. It helps in determining efficiency of the process, indication of acceptable moisture
levels and appropriate time to stop the process. This paper will include field measurements on Extra
High Voltage (EHV) transformer and reactors with assessment of dry out results utilizing the DFR test
method. A comparative analysis of DFR technique against the traditional moisture estimation methods
will be provided to highlight the application of DFR during the dry out operation.

I. Introduction
Power Transformers reliable operation is very critical for the electric power system. The life of a
transformer is primarily based upon the health of its insulation system. Transformers are subjected to
electrical and thermal stresses throughout their life cycle. It is a well-known fact that moisture, oxygen
and temperature are the major factors that can cause accelerated aging and would drastically reduce
the insulation life [1]. Temperature is dependent on the loading and ambient conditions during
transformer operation. Operating a transformer at full load conditions and longtime emergency
overloading cycles should be controlled to avoid reaching limits of hot spot temperature as any increase
in temperature above those limits for an extended period of time can seriously accelerate the aging
process of the insulation. Oxygen can get into the transformer through gasket leaks, exposure to
atmosphere, the air breathing conservator, leaky bladder, as a byproduct of insulation degradation and
several other external sources [2]. Oxidation of the insulating oil leads to acid and sludge formation that

Page 46 of 284
further degrades the paper and obstructs the natural flow of oil, thus restricting the cooling process [3].
Oil preservation system and oil inhibitors are used to prevent oxygen from entering into the system,
control the levels of oxygen and its reaction with the insulating oil [4]. Moisture in transformer, even
though not desired, cannot be completely avoided. Cellulose insulation is hygroscopic in nature and has
great affinity to absorb and retain moisture. Moisture in solid insulation reduces the dielectric strength,
restrict the maximum thermal loading capabilities, accelerates the aging process, and causes
degradation of cellulose, which in turn, will produce more water as a byproduct of paper disintegration.
This leads to lower tensile strength and the insulation’s ability to handle mechanical stresses is
compromised. The oxygen moisture combination at high temperatures cause accelerated degradation of
the cellulose and directly impacts the remaining useful life of a transformer.

Although, aging of the insulation cannot be stopped, it can certainly be slowed down and
prolonged to extend the life of a transformer. Moisture is one of the factors that can be controlled. A
new transformer coming out of the factory is expected to have a moisture concentration at or below
0.5% of the weight of the solid insulation. Before commissioning, utility operators put all the efforts to
extract as much moisture as possible from the solid insulation to have a “dry” transformer. Oil filtration
techniques can take moisture and other contaminants out of the oil only. In order for moisture to be
extracted from solid insulation, usually a combination of high temperature and vacuum is used.
Different field dry out techniques such as hot air or oil circulation, vacuum only or heat and vacuum
methods are used to extract the moisture from the windings. Some methods use cold trap for moisture
extraction and to estimate the rate and volume of moisture extraction from the insulation.

One of the challenges experienced by utility operators is to correctly estimate the moisture
present in the solid insulation of a new or service aged transformer before and after the field dry out
process. An additional challenge encountered is to determine the efficiency of the dry out system and
optimize it so that the correct time to stop the process can be identified. Based upon the voltage class
rating of a transformer, guidelines are provided in IEEE C57.93 “Guide for Installation and Maintenance
of Liquid-Immersed Power Transformers” [5] for the durations related to vacuum hold time, minimum
set and energization time. However, since each transformer is unique and the initial moisture
concentration may be different, which along with efficiency of the dry out system would determine the
duration of the whole process to reach the desired final moisture concentration in solid insulation. New
and service aged transformers of same voltage class need to be treated differently as the amount of
moisture that can be extracted would differ. The recommendations made in the IEEE C57.93 standard
are general guidelines and are to be used in absence of any other recommendations set by a utility or a
manufacturer.

It is imperative to know the amount of moisture present before the dry out process is initiated.
Additionally, determining the moisture throughout the process is of great benefit. The traditional
methods used are tests relying upon a state of equilibrium or charts correlating moisture, vapor
pressure and temperature. The DFR technique for field applications has been in existence since early
1990’s and operators are now utilizing it to better estimate the moisture concentration during the dry
out operation. It not only helps in optimizing the process but also allows to prevent the risk of excessive
dryness making paper insulation too brittle and reducing its tensile strength.

Page 47 of 284
II. Dielectric Frequency Response
AC insulation Power Factor (PF) is a routine test performed on power and distribution
transformers to assess the condition of the insulation system. High PF values may point towards
presence of high moisture, contamination and possible deterioration of insulation as it ages. However, it
has been found that PF values do not directly relate to moisture present in the insulation system.

As discussed earlier, cellulose or paper has great affinity towards moisture or water. Per IEEE
C57.152-2013 “IEEE Guide for Diagnostic Field Testing of Fluid-Filled Power Transformers, Regulators,
and Reactors” water migrates between the solid and liquid insulation in a transformer with changes in
load and, therefore, temperature. Consequently, the concentration of water in the insulating liquid
alone, expressed in ppm, does not provide sufficient information to obtain an adequate evaluation of
the insulation system dryness [6]. There are moisture equilibrium curves available to estimate the
moisture in paper based upon the moisture in oil of an oil-paper based insulation system. IEEE Std
C57.106 “IEEE Guide for Acceptance and Maintenance of Insulating Mineral Oil in Electrical Equipment”
discusses the absence of thermodynamic equilibrium in an operating transformer. This leads to the
conclusion that a quantitative correlation of moisture in liquid to moisture in paper is not currently
feasible [7]. Cautions have been issued to not use these curves to determine the dryness level of the
solid insulation in an operating transformer [6]. Moisture concentration in paper is one of the critical
information that power system operators should know to maintain and extend the life of a transformer
insulation system.

Dielectric Frequency Response (DFR) also known as Frequency Domain Spectroscopy (FDS) is an
insulation diagnostic technique that uses the concept of insulation PF and capacitance measurement at
different frequencies (1 mHz -1000 Hz) to determine the dielectric response of the insulation [8]. The
results are used to determine the moisture content in cellulose (oil impregnated paper/pressboard)
insulation of power and distribution transformers.

Figure 1: DFR connection diagram for a two winding transformer

A DFR measurement is typically performed in the field as per Figure 1. A step by step method to
perform DFR measurement is described in [9]. It measures the impedance of the system and with
impedance’s complex capacitance model, it calculates the capacitance, loss factor and PF at discrete
frequencies as shown in equation (1) to (5) to obtain a DFR curve between PF and frequency.

Page 48 of 284
1
𝑍= (1)
𝑗𝜔𝐶

𝐶 = 𝐶 ′ − 𝑗𝐶" (2)
1
𝐶′ = 𝑅𝑒 { } (3)
𝑗𝜔𝑍

1
𝐶" = −𝐼𝑚 { } (4)
𝑗𝜔𝑍

𝑅𝑒{𝑍}
𝑃𝐹 = (5)
|𝑍|

Where,

Z = Impedance

ω = Angular Frequency

C’ = Capacitance

C” = Loss Factor

PF = Power Factor
Power Factor

Frequency
Figure 2: DFR response of a two winding transformer with 0.4% moisture at 22 ⁰C

The DFR curve as shown in Figure 2 shows the response of a two winding transformer CHL
insulation with a moisture concentration of 0.4% at insulation temperature of 22 ⁰C. With its wide
frequency range, DFR has the advantage to separate the dielectric response of solid and liquid
insulation. The higher and lower frequencies response is primarily influenced by moisture in paper and
the middle frequencies predominantly show the dielectric loss response of the insulating liquid. The DFR
measurement is analyzed utilizing the modeling technique to provide percent moisture concentration

Page 49 of 284
present in the solid insulation along with capacitance, PF value at 60 Hz normalized to 20 ⁰C and oil
conductivity as shown in Figure 3.

Figure 3: Moisture concentration in CHL insulation from DFR measurements

The PF values are temperature dependent and since the DFR curve is basically PF measurements
at different frequencies, the DFR response is also temperature dependent. Temperature is a very
important parameter to be recorded for the DFR measurement. It helps in accurate estimation of bulk
moisture concentration present in the solid insulation. Additionally, the correct insulation temperature
recording allows selection of appropriate frequency range required to perform the test and obtain
reliable measurements.

DFR can be utilized as a powerful tool before, during and after the dry out operation to
determine the moisture present and increase the efficiency of the process. At the completion of final oil
fill and after a wait time of 24 hours to allow time for oil impregnation, DFR is recommended to be
performed on final oil-paper insulation system assembly. That measurement would provide operators a
reference moisture value that could be used for trending and future benchmarking.

III. Field Dry Out Process


Upon receiving a power transformer or reactor at site, temperature and pressure of the main
tank is recorded and dew point measurement is performed on the dry air or nitrogen gas inside the tank
of the transformer to assess the dryness of the insulation. An internal inspection is performed before
the assembly to check for any loose materials, foreign parts, internal leads and bus connections [10].
During the open time for inspection, the transformer is exposed to atmospheric air for several hours. A
steady stream of dry breathing air is passed through the hose from the opening of the tank during
inspection. When the inspection is complete the transformer is sealed and pressurized with dry air. The
moisture absorbed during the exposure period and field assembly process diffuses deeper into the inner
layers of the insulation structure. At the completion of final assembly, inspection and a stand time of 24
hours, dew point measurement is taken again utilizing the dry air inside the tank under positive
pressure. Preliminary determination of moisture content is made using that measurement. Additional
couple of measurements are taken at further 6 hour intervals to ensure stability has been reached.

Field dry out is conducted on power transformers and reactors to extract as much moisture as
possible absorbed in the oil impregnated paper due to atmospheric exposure, and during the
construction and assembly process. A combination of heat and vacuum cycle as shown in Figure 4 yields
the best results for moisture extraction. Vacuum pressure and inside temperature is constantly
monitored to determine the remaining moisture concentration in the paper insulation.

Page 50 of 284
Figure 4: A typical setup for field dry out system [11]

The following steps based upon reference [10] are conducted for the field dry out:

 Insulating oil to be used during dry out is tested for moisture, specific gravity, interfacial tension,
dielectric strength and Dissolved Gas Analysis.
 Winding temperature is measured by measuring the winding resistance (with 1 A at 50 V DC) on
any one phase before the start and throughout the dry out process. Reference temperature and
reference winding resistance reading should be known to calculate the winding temperature.
 Insulating oil is preprocessed in the vacuum oil processor unit to remove excess water and gas.
It is passed through power heaters to heat up the oil to 60-65 ⁰C.
 Vacuum pump is used to draw preliminary vacuum on the tank of the transformer
 An auxiliary vacuum pump is used along with vacuum oil processor unit to reach acceptable
stable vacuum levels and maintain them during the final vacuum and final oil filling stages.
 Vacuum degassed hot oil (50-60 ⁰C) is filled in the transformer tank to about 30-60% of
nameplate oil volume quantity.
 The hot oil is circulated through the processing unit, discharging oil into the transformer at 60 ⁰C
from the top valve until the oil coming out of the transformer from the bottom drain valve has
reached 50 ⁰C.
 The heat cycle is continued for six hours once 50 ⁰C mark is reached. This is done for the
preliminary vacuum to reach the required vacuum level and to reduce overall time duration for
processing.
 One or more heat cycle may be required based upon the transformer dew point, length of
storage under dry air, or if the temperature is below the minimum requirement.
 Oil is drained from the transformer to begin the first stage of high vacuum.

Page 51 of 284
 Based upon piper chart as shown in Figure 5, vacuum is drawn to a suitable micron level
appropriate for the winding temperature.
 Winding temperature and vacuum levels are recorded every 30 mins in the dry out log.
 Stable vacuum is reached when the vacuum has not drifted more than 100 microns during a six-
hour period.
 Perform a vacuum leak test as required or if vacuum levels have drifted more than 100 microns
in a six-hour period.
 Continue vacuum set time for a period of time defined by the voltage class of the transformer.
Upon completion, using piper chart compare the stable vacuum level against the winding
temperature to estimate the moisture in cellulose insulation.

Figure 5: Piper chart for moisture estimation in cellulose insulation [12]

Final oil fill is done without any stoppage, interruption or break of the vacuum. Filling is done
through top valve and completed by closely monitoring the fill rate as to not allow transformer tank
vacuum to change more than 100 microns from the target micron level during filling. Final fill should
cease at 4-6 inches from the top of a conservator unit. The fill is allowed to go slightly over expected
volume to allow for oil contraction with cooling and when vacuum is relieved. At the end of final fill,
vacuum pull on the main tank is stopped by closing off the vacuum hose. Once the vacuum is broken, fill
of the conservator unit can be completed to finish the topping off process [10]. At the end, as per IEEE
C57.93 standard, based upon the voltage class of the transformer, a minimum amount of set time is
required before the unit can be energized. This time allows for full oil impregnation of the cellulose
insulation. The set time can also be used for electrical tests to be performed on the unit.

Page 52 of 284
A single phase 765 kV 750 MVA auto transformer field dry out results are shown below to
indicate the rate of change of temperature and vapor pressure during the vacuum cycle.

Figure 6: Dry out data of a 765 kV single phase auto transformer

As shown in Figure 6, it can be noted that there was a change of more than 100 microns in a six-
hour period and in that condition the vacuum set time is reset back to 24 hours for 765 kV class
transformer. 24-hour vacuum set time was based upon utility guidelines. At the completion of vacuum
cycle, the vapor pressure value was 150 and temperature of the windings was close to 48 ⁰C. Based
upon the piper chart information, moisture in the paper insulation was estimated to be close to 0.20%.

IV. Field Dry Out Process Optimization


To optimize the life of a transformer, it is important to extract as much moisture as possible to
extend the life of its insulation. As mentioned in section III, field dry out is performed to achieve this
goal. To optimize this process, the following factors should be considered:

 Before beginning the dry out process, it is important to know the moisture currently present in
the paper insulation.
 During the process, operators should be able to determine system efficiency by measuring:
o At what rate percentage moisture is coming down and
o How much moisture is remaining in the solid insulation.

Based upon those two factors, a decision can be made as when to stop the process.

 Once the process is complete and final oil fill is finished, percentage moisture should be
measured. A stand time of 24 to 48 hrs should be allowed to measure the final moisture
concentration in solid insulation before the transformer is commissioned.

Page 53 of 284
DFR measurements can be used to achieve all the tasks mentioned above. The following section will
show case examples of application of DFR technique for process optimization. The DFR results are
compared with the existing methods to prove the validity and suitability of the method in the field
environment.

A. Moisture estimation before the field dry out:


A transformer is usually filled with dry air or nitrogen under positive pressure after it has been
shipped to the site from the factory. Dew point measurement of the dry air inside the tank is taken to
estimate the average surface moisture content of the cellulose insulation after reaching steady-state
temperatures. Dew point is defined as the temperature to which air must be cooled for water
condensation to begin. At dew point, the partial water vapor pressure in air equals the water vapor
saturation pressure. In this state, condensation and evaporation are in equilibrium and take place at the
same rate [13]. The dew point inside a transformer can be related to the vapor pressure at the surface
of the insulation material. The vapor pressure and the temperature of the insulation material determine
the moisture content, in percent by weight, at the surface of the insulation material. Therefore, it is
critical that all partial pressures of gases in the gas space and in the insulation have come to equilibrium
[13]. After a unit has been pressurized with dry air or nitrogen, the unit must sit for 6 to 12 hours (ideally
24 hours) to allow for temperature and moisture stabilization. Dew point method has been used very
commonly in the field to determine the initial moisture levels, however, an alternative method of DFR
can be used as discussed below.

Dew point measurement was taken on a 765 kV, 100 MVAr single phase reactor before the dry out
process. Based upon the measurement of dew point, pressure and temperature inside the tank, the
average moisture at the surface of the insulation was estimated to be about 1.4 %.

Figure 7: DFR measurement before the dry out on a 765 kV single phase reactor

Page 54 of 284
DFR measurement was conducted before the dry out at 100 V with a frequency range of 1000
Hz to 2 mHz. Insulation temperature was 32 ⁰C. The DFR response is shown above in Figure 7. Based
upon the DFR curve and modeling analysis, the moisture in solid insulation was estimated to be 1.5 %.
The results compared very well with dew point measurement. One thing to note is that DFR
measurement doesn’t require any wait time for equilibrium as it provides the bulk moisture
concentration whereas for dew point method that provides the average surface moisture of the
cellulose insulation, enough time needs to be provided for equilibrium and stabilization of moisture
before a measurement can be taken. If this is followed, dew point and DFR results will be very
comparable.

B. Moisture estimation during the field dry out:


From the case study presented in [14], A 5 MVA 69/12.47 kV Delta Wye transformer installed in
1950’s was taken out of service based upon a high 60 Hz PF value of 0.9% at 20 ⁰C. To demonstrate the
field application of DFR an initial DFR measurement was performed with insulation temperature of 20 ⁰C
and the results showed a moisture content of 3.5 % in the paper insulation. The results of the DFR
measurement is shown in Figure 8 below:

Figure 8: DFR measurement of a three phase 5 MVA two winding transformer

It was decided to perform a field dry out on the unit using a combination of hot oil circulation
and vacuum cycles. Hot oil was circulated to bring the winding temperature to above 60 ⁰C. During the
vacuum cycles DFR data was obtained at an interval of every six hours. During the DFR measurement, it
is recommended to close the vacuum valve to prevent any vacuum pull during the measurement.
Following graph shows the dielectric response in the first 24 hours of vacuum cycle.

Page 55 of 284
Figure 9: DFR measurements in the first 24 hours of vacuum cycle

It can be observed in Figure 9 that compared to initial measurement (t=0h) there was an
appreciable change in DFR response in first six hours (t=6h) of vacuum cycle after the hot oil circulation.
The difference between the two curves is attributed to different temperature and high rate of moisture
extraction in the initial phase of vacuum cycle. After 6 hours, for the next 18 hours there was a uniform
change in DFR response every 6 hours indicating steady reduction in moisture concentration.

Figure 10: DFR measurements in the next 30 hours of vacuum cycle

Page 56 of 284
The results in the next 30 hours of vacuum cycle as shown in Figure 10 did not show any
appreciable difference in the dielectric response of the system indicating a reduced efficiency of the dry
out system after first 24 hours. Utilizing the DFR data it could easily be concluded that the vacuum cycle
can be stopped as gain in moisture extraction compared to prolonged exposure of vacuum to winding
insulation would be of limited benefit. Once the system reaches low efficiency point, it is recommended
to perform another hot oil circulation and initiate a second vacuum cycle.

In this case, a second vacuum cycle did not show any major changes in dielectric response either
and it was decided to stop the process. Final moisture at the end of whole process was estimated to be
2.6%. Taking into account the age of the transformer and its operational history, final moisture levels
were considered to be in acceptable range by engineers and field operators. Service aged transformers
degradation of insulation over its life cycle cannot be reversed and moisture cannot be brought back to
very low levels as desired. Optimizing the dry out process is critical as many aged insulations cannot
sustain a long vacuum hold time that could impact the tensile strength of the insulation and can cause
serious damage to the insulation.

DFR technique could be used to determine the efficiency of the system and help in deciding the
opportune time to finish the process. It can also indicate the condition when no further moisture can be
extracted from the solid insulation without compromising the integrity of the insulation system.

C. Moisture estimation at the completion of the field dry out:


It is important to know what is the final moisture content once final oil fill is completed after the dry
out. Moisture obtained at the end of dry out using vapor pressure and inside tank temperature is
recorded for future reference. For a 765 kV 100 MVAr single phase reactor following vapor pressure and
winding temperature was collected during the dry out vacuum cycle.

Figure 11: Dry out data of a 765 kV 100 MVAr single phase reactor

Page 57 of 284
As observed in Figure 11, vacuum cycle was carried out for close to 32 hours to take into
account more than 100 microns change in a six-hour time period. At the end of vacuum cycle and just
before the final oil fill vapor pressure was recorded at 130 microns and winding temperature was
recorded at 60 ⁰C. Based upon piper chart information, moisture was estimated to be close to 0.15%.

Utility operators are always interested in percentage moisture in solid insulation after the final
oil fill to determine the transformer insulation condition before it will be commissioned. This embarks
the start of the life of the transformer. DFR measurement was conducted at the end of final fill on an oil
and paper insulation system and after a set time of 24 hours to allow for oil impregnation of the paper.

Figure 12: DFR response of a single phase reactor after the final oil fill

The insulation temperature was 26 ⁰C. The results are shown in the Figure 12 above. Percentage
moisture concentration was estimated to be 0.2 % of the weight of solid insulation. If possible, it is
recommended to perform the measurement at the end of one-week time period to ensure moisture
content is the same. The moisture estimated from vapor pressure and winding resistance data matched
very closely with the DFR moisture estimation.

Temperature dependence of the insulation system can be explored through DFR modeling. By
accurately taking the temperature effect into account, DFR modeling can be used to model the
temperature dependence of power factor over a wide temperature range based on measurements over
a frequency range [15]. From DFR technique the thermal profile of a dielectric insulation system can be
obtained. The thermal profile is shown by insulation power factor response as a function of
temperature. As discussed earlier, temperature, moisture and oxygen impact the life of a transformer
insulation the most, knowing insulation behavior at higher operating temperatures is of great value to

Page 58 of 284
the operators. Figure 13 below shows the comparison of thermal response before the dry out and after
the final oil fill.

Figure 13: Thermal response of dielectric insulation before dry out and after final oil fill

It can be observed that before the dry out (without oil), insulation power factor had a strong
temperature dependence especially at higher temperatures. However, dry out process was effectively
able to extract moisture from the solid insulation to below 0.25% limits and the insulation at the
completion of final oil fill had a very flat response to the change in temperature. It is to be noted that PF
values at 20 ⁰C did not show any significant change, this correlates well with the previous discussion of
PF not being a direct indicator of moisture present in the solid insulation.

Based upon the cases discussed in this section, it can be seen that DFR can be used to optimize
the process by knowing the initial moisture content before the dry out. The DFR data is then obtained at
every 6 hours interval during the dry out to identify the decrease in moisture content with time and find
out the efficiency of the process. Based upon the rate of decrease in moisture, decision can be made as
when to stop the process. At the completion of dry out and final oil fill, after a wait time of 24 hours
final measurement can be made to determine the reference moisture content in the solid insulation for
future trending during the life of a transformer or reactor.

V. Practical Challenges and Observations from Field Dry Out


 Currently a standard vacuum set time is used based upon the voltage class of the transformer.
However, from the case described, observing the vapor pressure and temperature graph and also
with the DFR data it can be seen that after a certain time period no appreciable gain in moisture
reduction is achieved by continuing the vacuum cycle. This time period would vary from one dry out
to other and should be closely monitored.

Page 59 of 284
 The correct time to stop the process based upon the rate of extraction and final moisture content is
a matter of debate. Optimizing this will prevent the exposure of insulation to prolonged hours of
vacuum and avoid any possible damage to the insulation.
 Moisture estimation before and after the dry out are critically important for measuring the
effectiveness of the dry out system.
 Dew point measurement only provides the average surface moisture content of the solid insulation.
A wait time of 12-24 hours should be allowed for equilibrium before the measurement is taken.
 Power factor values do not directly correlate to the moisture present in the solid insulation.
 Estimating moisture during the dry out using vapor pressure and winding temperature although
reliable will have its own sources of error.
 Winding to winding insulation is recommended for DFR moisture estimation. In absence of that,
winding to ground insulation can be used for DFR measurement.
 Running the DFR test during the vacuum process requires some setup that needs to be followed to
obtain reliable measurements.
 Under vacuum it is not recommended to apply more than 50 V test signal for DFR measurement. In
an energized EHV station, lower frequency measurements may get influenced by static noise
present in the system.
 Because of high winding temperatures during the dry out, DFR test can be conducted down to a stop
frequency of 5 mHz only for correct moisture estimation. This allows test to be completed faster, in
about 8 mins.
 It is recommended to measure DFR every 6 hours during the vacuum cycle. However, measurements
made at night can be influenced by the condensation and humidity present in the atmosphere.
 Moisture estimation using DFR during the dry out requires preliminary information about the
transformer or reactor for correct modeling, knowledge about the setup and factors that can affect
the measurements.
 DFR during the dry out can be utilized to understand the efficiency of the process and helps in
making a decision as to when to stop the process based upon the gain with respect to vacuum time.
 When performing the DFR measurement after the final oil fill on an EHV transformer or reactor, it is
recommended to use high test voltage signal (1400 V) to obtain more accurate measurements.

VI. Summary and Conclusions


Transformers will continue to be one of the most critical asset that need to be maintained by
power system operators. Moisture present in solid insulation, if not controlled, can accelerate the aging
process and seriously reduce the life expectancy of transformer insulation. Factory and field methods
are used to extract moisture from paper and keep the transformer “dry”. In field, both new and service
aged transformers and reactors are dried out to prolong the aging process and optimize the insulation
quality. The field dry out poses its own set of challenges ranging from control of vacuum, maintaining
the tank temperature from hot oil circulation, vacuum leaks, reduced process efficiency and decision
making of continuing or stopping the process based upon remaining moisture and rate of extraction.
Traditional methods like dew point and piper chart have been used to estimate the moisture with some
limitations.

Page 60 of 284
The DFR application proposed in the paper can be used in improving the efficiency of the field
dry out process. It can help in determining the stage in the dry out operation where moisture extraction
process is no longer effective. This allow operators to decide if another heat and vacuum cycle should be
carried out or stop the process as further moisture extraction would be difficult to achieve without
affecting the integrity of the insulting system. DFR also provides thermal profile of the insulation system
indicating the temperature dependence and insulation behavior at those operating temperatures. As
described in the paper, DFR should be performed carefully, requires preliminary information of the
system to be tested and can be subjected to some of the field limitations during the vacuum cycle. From
cases described, it can be seen that DFR could be used as a powerful tool before, during and after the
dry out process to increase the confidence of operators by accurately knowing the percentage moisture
concentration in the solid insulation and hence, the condition of the insulation before transformers are
put in service.

VII. References
[1] “Field drying of transformer insulation Siemens”, Smart Grid Solutions

[2] “Dissolved Gas Analysis in transformer maintenance”, Engr. Inigo V. Escopete, Jr., AP renewables Inc.

[3] “Transformer maintenance: Facilities instructions, standards and techniques.” US Department of the
interior Bureau of Reclamation, Denver, CO

[4] “Oxidation Inhibitor and Reinhibiting Oil-Filled Transformers”, Andy Skholnik, Technical Brief, SD
Meyers.

[5] IEEE Std. C57.93-2007 “IEEE Guide for Installation and Maintenance of Liquid-Immersed Power
Transformers”.

[6] IEEE Std. C57.152-2013 “IEEE Guide for Diagnostic Field Testing of Fluid-Filled Power Transformers,
Regulators, and Reactors”.

[7] IEEE C57.106-2015 “IEEE Guide for Acceptance and Maintenance of Insulating Mineral Oil in Electrical
Equipment”.

[8] “Preventing Transformer Winding and Insulation Failure: SFRA and DFR”, Dinesh Chhajer, Weidmann
Annual Technical Conference, 2012.

[9] “IDAX User’s Manual”, 2008, PAX Diagnostics AB, Megger, Taby Sweden.

[10] “Final assembly, oil fill and processing specification for large power transformers.” American electric
Power.

[11] “Field processing methods for transformer dry out”, Weidmann Annual Technical Conference 2012,
Derek Baranowski, Baron USA.

Page 61 of 284
[12] “Theoretical Vapor Pressure Equilibria for Cellulose, air and oil”, Piper chart Source: American
Electric Power.

[13] “Transformer dew point measurement and insulation moisture estimation”, Part 1 & 2. Siemens
Smart Grid Solutions.

[14] “Continuous Monitoring of Power Transformer Solid Insulation Dry-out Process – Application of
Dielectric Frequency Response” Electrical Insulation Conference 2013, Diego Robalino.

[15] “Dielectric frequency response measurements and dissipation factor temperature dependence”
Electrical Insulation (ISEI) Conference, June 2012, Peter Werelius, Matz Ohlen, Diego Robalino, Jialu
Cheng.

VIII. Acknowledgment
The authors gratefully acknowledge the contributions of Dave Bush, Station Supervisor,
Transmission Field Services (American Electric Power) and Dr. Diego Robalino, Principal Engineer,
Technical Support Group (Megger) to this paper.

IX. Authors
Dinesh Chhajer received his Master of Science in Electrical Engineering
from University of Texas at Arlington. He is the Manager of Technical
Support Group at Megger USA. His responsibilities include providing
engineering consultation and recommendations in relation to testing of
transformers, circuit breakers and other substation assets. He has
presented a number of white papers related to asset maintenance and
testing at various conferences within power industry. He has previously
worked as an applications engineer at Megger and substation and
design engineer at Power Engineers Inc. He is currently a licensed
professional engineer in the state of Texas.

Ian Kreher received his Bachelor of Science in Electrical Engineering


with a Power Emphasis from Missouri University of Science and
Technology. He is currently an Engineer for American Electric Power in
Roanoke, Virginia in their Transmission Field Services department
where he provides technical oversight and assistance for substation
asset commissioning and maintenance. Ian is also heavily involved with
new substation construction coordination and system capital
improvements, as well as mobile substation equipment usage. Outside
of professional interests, Ian enjoys outdoor activities and travel.

Page 62 of 284
Utilizing Visual and Thermal Video Analytics to
Enhance Operational Efficiency
Systems With Intelligence Inc.

E. Sotter, Ph.D.
P. Fernandez
R. Harada

Page 63 of 284
Utilizing Visual and Thermal Video Analytics to Enhance Operational Efficiency
E. Sotter, Ph.D., P. Fernandez, R. Harada
Systems With Intelligence Inc.

Abstract: Gone are the days of dedicated live view video screens that are manually monitored by
personnel. Advances in communications and software technology allow utility operators to be alerted of
events captured by these cameras as they happen. While physical security applications have seen the most
adoption of these video technologies within electric substations, visual and thermal monitoring can be
automated to run in a continuous manner to improve the reliability of the substation operation.

Real-time alerting and alarming of intruders within a substation, an impending equipment failure,
operation, or arc flash event directly to an operator or dispatcher, can take the most effective action.
Continuous thermal monitoring automates the manual “hand-held thermal scan” process that many
utilities practice. Utilizing thermal cameras systems with sophisticated video analytics algorithms for
anomaly detection can trigger automated alarms of possible issues directly to an operator who can make
an informed operational decision.

I. Introduction

Automated video systems provide utilities with real-time visualization of the substation allowing them to
make key decisions designed to prevent outages, save time and reduce costs. Substation video systems
use sophisticated multifunctional sensors in conjunction with video and thermal analytics to provide real-
time information for input into substation maintenance and operations programs. Using the latest
technology in video automation, these systems monitor key points in the substation providing visual and
thermal imaging that ties into the utility visualization and operation system (e.g. SCADA). Operators are
provided real-time visualization of the substation assets and are automatically notified when normal
operating conditions are not being met.

II. Visual and Thermal Monitoring Systems for Substation Automation

Substation monitoring systems differ from conventional video systems in function and application. A
substation monitoring system is designed to give utilities a real-time view of the operational status of high
value assets at remote substations from both the visual and thermal perspective. This differs from the
conventional video system that is focused on physical security. A substation monitoring system can
provide both operational and security functions [1].

The data obtained from video and thermal sensors deployed throughout the substation is processed by
an analytics engine in a server located on premise at the substation. These systems monitor the condition
on site and determine if an alert should be sent to the operations and control center. A typical substation
can have several video and thermal sensors deployed and it is not possible for operators to constantly
monitor them all, especially when multiple substations are involved. Traditional video systems require

Page 64 of 284
continuous manual human monitoring of a live stream of video. Video and thermal analytics automate
the monitoring process and provide the alerts directly to utility operational software systems, such as
SCADA, when further action is required. Operators can open the alert message to view a video snap-shot
of the event and open a real-time video feed from the substation to view the live scene (Figure 1). All the
video and alerts are recorded at the substation for review and archiving.

Figure 1: Embedded Video Snapshot

III. Visual Monitoring and Analytics

Visual monitoring has multiple operational, maintenance and safety applications in a substation that can
be done without sending a crew to the site:

Operational/Maintenance:

- Automated detection of events such as arc flash and switch arm movement
- Confirmation of remote controlled operations such as switch opening/closing
- Detection of animals around lines, switches, transformers

Safety:

- Ensuring safe conditions for the public and work crews at remote sites
- Witness and record that proper operational procedures are followed
- Intrusion detection, tampering, vandalism

To use the input from all video cameras installed in all substations for the tasks mentioned above, a
constant monitoring is required. However, simultaneously monitoring the video channels from all
substation is an impossible task for one human operator. Here is where the use of video analytics becomes
crucial.

Video analytics have been used for security video systems for many years. Most of these analytics utilize
algorithms that subtract the picture background from a video feed then analyze the shape and behavior

Page 65 of 284
of the objects left in the foreground. All these techniques have been mostly used to create video analytics
routines for security purposes (e.g. motion detection, virtual tripwires, loitering alarms, etc.) [2], however,
using the same concepts and algorithms, analytics can be manipulated to perform functions that are
specific to electric power applications. For example, if the analytic is fine tuned to a specific area and type
of movement, the analytics can determine the position of a disconnect switch arm and if it has moved.
Similarly, analytics can be tuned and focused on the switch contacts to detect an arc flash event that can
provide an operator information about an unintentional event or operation. Problems in a substation like
a fire or explosion can also be detected with this type of analytics (Figure 2).

Figure 2. Explosion due to a lightning arrester failure captured by a substation video monitoring system

IV. Thermal Monitoring and Analytics

For several years, infrared thermographic inspection has played a key role in maintenance plans in
electrical utilities due to its non-invasiveness, safety and relatively low-cost approach [3]. This technology
detects and measures infrared (IR) radiation coming from objects in the field of view of the thermal
camera and turns it into a visual image that represents the temperature of the objects. Traditionally, IR
thermographic inspections are done by technical experts using handheld thermal imaging cameras
targeting specific components in a substation like transformers, breakers, capacitor banks, control
cabinets, cable joints and insulation, etc. Due to the manual nature of the inspection, it cannot be done
continuously and it is very common to have several months pass between two consecutive thermal
inspections at a same site. Even though it is still a helpful tool to locate potential issues with components
in a substation, the prolonged period between manual thermal inspections makes it impractical for real
preventive and predictive maintenance. Furthermore, issues can arise very quickly in an electrical
substation causing considerable damage before a scheduled inspection takes place. Similarly, to a
permanently installed video security system, a fully automated thermal monitoring system that can run
continuously in a substation would be the adequate tool to support a preventive and predictive
maintenance plan.

Page 66 of 284
Every component or equipment in a substation has a normal temperature range of operation.
Components in the path of an electric current will dissipate power in the form of heat proportional to its
resistance to the current. Electromagnetic induction generates heat in the core of transformers which is
usually dissipated with radiator fins. Insulators on the other hand are not in the path of current, so they
should be at ambient temperature if they are in good condition. Understanding the temperature behavior
of critical components in the substation is crucial to establish the targets for an automated thermal
system: It is not always about finding the hot spot, but also the not-hot spot.

Here are some examples of situations with critical components in a substation that can be detected using
thermal cameras:

a. Transformers: Electromagnetic induction generates heat in the core of a transformer so a


working temperature higher than ambient is usually expected, however, defects in the structure
will create hot spots in unusual places around the body of the transformer. Other components
that can have unusual temperature behavior are:

- Primary and secondary bushing connections: Loose or dirty connections, unbalance and
overloading problems can cause overheating in the connections (Figure 3). The connection with
the problem will be hotter than the connections of other phases.

Figure 3. Transformer showing center primary side bushing with external connection problem [4]

- Cooling fins: Cooling fins normally appear warm as they dissipate the heat generated in the core
and windings of a transformer. If it is seen that one or more fins have lower temperature than the
other fins (Figure 4.), then it can be concluded that the circulation of oil is being limited in those
fins, probably due to low oil level, flow obstruction, a closed valve, or perhaps the apparatus is
out of level [5,6]. An automated thermal system can detect an increment of the delta temperature
between fins and report it to an SCADA system.

Page 67 of 284
Figure 4. Transformer showing a problem with a cooling fin [6].

- Internal problems in bushings: A study found that, out of the problems a transformer can have,
bushing failures are the ones that most often lead to fire in a substation [7]. Thermal imaging can
show internal defects or connection problems in the bushing (Figure 5). It is important to
remember that the temperature inside the bushing will be much higher than surface temperature
detected by the camera.

Figure 5. Transformer showing left and right primary side bushings with internal problems [8].

b. Circuit breakers: Several different problems with circuit breakers can be detected by using
thermography (Figure 6). Like transformers, a faulty or dirty connection between bushing and
conductor cable or a bushing with structural damages will overheat during operation, which can
be detected with a thermal camera.

Page 68 of 284
Figure 6. Circuit breaker with a problem on the test tap cone [8]

V. Methods of Thermal Measurement

There are two common ways to assess the thermal condition of components in a substation. One is
quantitative, where the objective is to get a fairly accurate temperature of the equipment. The other way
is qualitative, where the goal is to find difference in temperature between two components that should
have a similar temperature, which can be understood as a hot or cold spot [3]. Each technique has pros
and cons, and should be used depending on the type of automation process that is required. A good
thermal camera system should provide tools to use both methods.

a- Quantitative method

In this method, the temperature readings from the IR camera are used as the real temperature of the
component. This temperature reading can then be compared to a threshold set by the component
manufacturer for normal operation, and trigger alarms when the temperature passes that threshold. It
can also be used to create models that can help to predict when a component may break.

The problem with this method is the factors intrinsic to the component in which temperature is being
measured (i.e. emissivity, size and distance from the camera), as well as environmental (i.e. ambient
temperature, humidity, rain, wind, velocity and solar radiation), that affect the IR light reaching the
camera [9]. All these factors should be taken into account when the temperature reading is calculated to
have a valid useful temperature value. Factors related to the component can be provided by the
manufacturer or measured directly in the substation. Some electrical substations have weather stations
that can be used to provide the required environmental inputs to the thermal system. However most of
the times these factors are unknown. This is when the qualitative method is used.

b- Qualitative method

In this method the temperature readings from two components, whose difference in temperature or delta
temperature (∆T) is known, are compared. If the ∆T obtained from the measurements is different than
the expected ∆T then an alarm is triggered. For this method to work, the components that are being
compared should be made of the same material and be at a similar distance from the IR camera. As both

Page 69 of 284
components are affected by the same factors, those factors can be ignored from the calculations and still
obtain a fairly accurate measurement of the ∆T between the two components.

This method can easily detect problems in the substation, however it cannot be used for modeling and
failure prediction as it does not guarantee an accurate reading of the temperature of the component.

VI. Visual and Thermal Monitoring on Industrial Process Networks

IP networks are commonly deployed in substations and other industrial applications to connect Intelligent
Electronic Devices (IEDs), Remote Terminal Units (RTUs), and other protection and control equipment to
each other and to the SCADA system [10,11]. Substation automation networks are industrial, process
based networks that run critical applications to keep substation equipment and the power system
protected and running safely [12]. Process based communications is machine to machine so uninterrupted
and timely delivery of data is critical to keep processes running correctly. Process based networks must
therefore be kept isolated from the Internet and other corporate traffic to ensure that the data flow is
secure and free of losses. In an IP network, technologies such as Virtual Private Networks, (VPNs), subnets
and firewalls are used to keep the substation network isolated from the rest of the corporate LAN [13].

The video monitoring system is connected on the substation network so it can communicate with the
SCADA system at the control center with alarms, messages, visual and thermal information of the
operating conditions at the substation. The information can be fed into the control system for automated
responses or for operators to make decisions and take actions. Since the substation network requires
access privileges, the video and SCADA systems are not accessible to personnel without proper
authorization.

VII. Visualization in Utility Operational Software Systems

Representation of an electric power system traditionally consists of a one-line diagram that shows
essential information such as current and voltage levels, switch status etc. in a two-dimensional map. The
information is real time and shown on the Human Machine Interface (HMI) of the utility SCADA system.
Integrating a video system with SCADA adds another dimension of real time visualization critical in
ensuring more informed operational decisions to minimize outage times when unavoidable, while also
providing trending analysis input to prevent outages and prolong the life of high value assets.

While a SCADA or OMS/DMS system can provide critical information on the status of the system such as
a breaker trip and power outage, visual and thermal video information can provide confirmation of the
cause of the event and enhance real time situational awareness. Visualization may be able to provide
insights as to why the breaker operated? What is happening now at the remote site? Is a power line down?
Is there a fire or leakage? With this visual information, the utility can safely and securely reduce the outage
time by having knowledge of the problem before rolling the truck and sending personnel into the area.

More importantly, video and thermal information can reveal system inefficiencies by finding temperature
hotspots in the system so the utility can make repairs before the failure occurs. Transformer losses,
voltage drops and load imbalances can be caused by leakage current in insulators or high resistance
connections in power system components. These components will often show increased heat buildup that

Page 70 of 284
can be detected by monitoring with thermal cameras. Continuous monitoring will provide alerts and
trending data as the system goes through load cycles allowing the utility to perform condition based
maintenance on the system before failures and outages occur.

VIII. Conclusion

Utilities are faced with the challenge of maintaining/improving service reliability without increasing costs.
Video automation can remotely predict failures before they happen and detect and diagnose problems
when they do. Video analytics automate the monitoring process to minimize the workload on operators
and provide visual confirmation of the conditions at the substation. Through (1) automated remote visual
inspections that reduce the number of trips to remote sites and (2) continuous thermal monitoring that
analyzes the operating temperature of components in the power system driving condition based
maintenance activities, automated visual and thermal monitoring can enable more efficient electric utility
operations

IX. References

[1] E. Sotter, G.P. Porciello and J. McClean, Video monitoring solutions for electric utilities: Issues,
requirements and examples, Electric Energy T&D Magazine, Jan-Feb, 1 (17) (2013) p.39-43

[2] S. Velastin, CCTV video analytics: Recent advances and limitations, Lecture notes in computer
science, Vol 5857 (2009) p.22-34

[3] M. Jadin and S. Taib, Recent progress in diagnosing the reliability of electrical equipment by using
infrared thermography, Infrared Physics & Technology 55 (2012) p236–245

[4] S. James, Common thermography uses and applications within the petrochemical, offshore oil and
gas, chemical, and power generation industries. http://www.irinfo.org/02-01-2009-james/

[5] A. Huda and S. Taib, Application of infrared thermography for predictive/preventive maintenance of
thermal defect in electrical equipment, Applied Thermal Engineering 61 (2013) p220-227

[6] Transformer cooling tubes, Thermal Imaging Blog. http://thermal-imaging-blog.com.

[7] F. Vahidi and S. Tenbohlen, Statistical failure analysis of european substation transformers, ETG-Fb.
144: Diagnostik elektrischer Betriebsmittel 2014, p.5-9

[8] M. Ralph, Power plant thermography–wide range of applications, Inframation 2004, Proceedings vol.
5, p241-258

[9] L. Dos Santos, Infrared thermography applied for outdoor power substations, Thermosense XXX Proc.
of SPIE Vol. 6939, 69390R, (2008)

[10] K.H Mak and B. Holland, Migrating electrical power network SCADA system to TCP/IP and Ethernet
netwroking, Power Engineering Journal, 16(6) (2002) p.305-311

Page 71 of 284
[11] C. Wester and M. Adamiak, Practical applications of Ethernet in substations and industrial facilities,
Conference Record of Annual Pulp and Paper Industry Technical Conference,(2011) p.55-66

[12] C. Hoga, New Ethernet technologies for substation automation, 2007 IEEE Lausanne Powertech,
Vols 1-5 (2007) p.707-712

[13] S. Wu, C. Kiu and A. Stefanov, Distributed specification-based firewalls for power grid substations,
IEEE PES Innovative Smart Grid Technologies Conference Europe (2014)

Page 72 of 284
DESIGNING GROUNDING GRIDS

BY

EARL L. KIRKPATRICK, P.E.

Chief Engineer

ELK ENGINEERING ASSOCIATES, INC.

8950 FORUM WAY

FORT WORTH, TEXAS 76140

PHONE: 817-568-8585, FAX: 817.568.8590

And

Dr. AKM Sydul Haque, PhD, P.E.

ELK ENGINEERING ASSOCIATES, INC.

8950 FORUM WAY

FORT WORTH, TEXAS 76140

PHONE: 817-568-8585, FAX: 817.568.8590

Page 73 of 284
Designing Grounding Grids

Abstract:

Modeling/designing existing or new grounding grid is a challenge for designer. Grounding grids

usually consist of ground conductors, ground rods, and/or UFER grounds. The various

grounding elements are installed at different depths. Soil resistivity may vary significantly

throughout the site. This presentation will discuss the modeling of two large fossil fuel

generating stations in Texas. One generating station was constructed with zinc ground rods

and insulated conductors for connecting the rods. The other was constructed with UFER

grounds, copper clad ground rods, and bare copper grounding conductors. This paper will

discuss different techniques employed for successful solutions.

Introduction

Electrical grounding system serves many purposes. It adequately relays the fault. An effective

electrical ground must have a low enough Resistance-to-Remote Earth to assure an essentially

instantaneous trip to the largest breaker in the facility. Effective grounding and bonding of

cabinets, enclosures, and other structural components assures personnel safety when

contacting non-energized components. A properly designed electrical safety grounding grid

(ESG) assures safe step, touch, and mesh potentials throughout the facility. Signal to reference

grounds are essential for reliable operation on modern computerized Distributed Control

Systems (DCS).

Page 74 of 284
Case History 1:

A large, three-units lignite-fired steam electric station was designed and constructed in East

Texas with a total capacity of 1880 mW. Unit 1 and 2 are each rated 565 mW and constructed

in 1974 and 1976. Unit 3 is rated at 750 mW and constructed in 1978. The purposes of this

study were to evaluate the present condition of Electrical Safety Grid and make

recommendations for repairs or upgrades that might be necessary for adequate relaying and to

assure personnel safety plant wide.

Underground utilities at the plant site include, at a minimum, the following components:

Compressed air lines, service water lines, DI pipe, firewater, and potable water lines that may or

may not be coated. Bar grilles, traveling screens, and circulating water pumps at the intake

structure. Dual prestressed concrete pipe circulating water lines, various control lines, electrical

conduit, and foundation rebar. An extensive bare-copper grounding grid containing 500-MCM

and 4/0-AWG conductor with 10 foot driven-copper ground rods.

Point-to-point (PTP) resistance measurements were made between critical grounding points

throughout the facility. During the course of this study 436 test points were established. PTP

resistance measurements of 0.002 ohm, or less, are taken as a clear indication of effective

electrical continuity, not necessarily requiring calculation of the theoretical PTP resistance. For

resistance measurements to a higher value, the theoretical PTP resistance for a single Number

4/0 AWG or larger conductor for the circuit path is calculated. If values fall within 110 percent of

the theoretical value, adequate electrical continuity is also indicated. Many of the measured

values fall far below the theoretical resistance for a single conductor of measured length due to

the presence of multiple parallel current paths. Some of these alternative current paths may

Page 75 of 284
include underground metallic piping, such as fire lines within the facility. Metallic piping in never

accounted for in grid design calculations. Due to the presence of mechanical fittings in piping

runs, such as valves or bell and spigot joints, adequate electrical continuity is not always

assured. One hundred forty-seven (147) measurements or 33.3 percent failed, indicating

somewhat excessive resistance between those particular points. Most of the failures were tests

to fire hydrants (mechanical fittings) and a few were to isolated lighting standards. Cut, missing,

or broken short conductor segments within the interior of a large grid may be safely tolerated

since mesh voltages are expected to be much lower than for similar sized meshes at the

perimeter of the grid. However, it is not safe to make such as assumption without careful

modeling of the grid. In each case, we determined that the lighting standards were adequately

grounded for electrical safety.

The results of our etap modeling efforts showed a basically safe grid with the unsafe regions, for

touch potential only, confined to perimeter areas of the grid. An inspection of the etap plots for

step potential and for touch potential confirmed very low mesh potentials within the interior of

the grid. Therefore, the few cut, broken, or missing conductors identified within the grid interior

by this study did not require repair or replacement.

For electrically unsafe grids, or small segments of a grid, any one or a combination of the

following techniques may be employed to assure personnel safety. Add grid conductor,

increase the area of the grid, install additional groundrods, include interior perimeter fence

grounding and/or groundrods with the internal grid, install additional perimeter conductor fence

grounding outside of the fence, install or improve surface treatments, reduce mesh size/area in

limited areas of the grid where unsafe step or touch potentials are shown to exist.

Assuming an adequately low grid resistance to meet system standards, our first preference

Page 76 of 284
would be to employ surface treatments for personnel safety to small local areas where unsafe

touch potentials might exist. In each instance, we have recommended the lowest cost safe fix

that also has the least adverse effect on system operation during construction of the

modifications.

We measured 0 – 2.5 foot soil resistivity measurements at multiple locations within the plant

boundaries, these data are used for the step and touch voltage calculations. In the interest of

assuring adequate electrical safety throughout the ESG, we utilized a value of 18.6 Ohm/meter

in the calculations, which was the lowest measured value for surface soil resistivity within the

facility. This results the calculated safe step and touch voltages for a 50-kg body weight using

the lowest measured resistivity of 309.6 V for safe step potential in bare earth, 267.2 V for safe

touch potential in bare earth. These values make no allowance for surface material (crushed

rock or pavement) to increase human contact resistance to earth, but assume a bare earth

model throughout the grid (based upon 0-2.5 foot soil resistivity measurements) for calculation

of tolerable step and touch voltages. For the case of 3 inches of asphalt, 506.0 V is a safe

touch potential. Maximum clearing times are conservative estimates based upon best available

information provided to us by the client.

This site contains a very large ESG which initially stretched the finite element component of the

etap grid module beyond its limit. We made multiple runs, gradually changing default settings

within the program. It was necessary to change the default setting for the finite element length

from three (3) feet to ten (10) feet. Other simplifications were also necessary. One of the runs

required seven (7) days to reach a solution using an engineering work station with a very fast

CPU. For the initial grid in question, as found, the etap model calculated a resistance-to-remote

earth of 0.02 ohm for the entire ESG. For the given maximum system fault current, this results

in a grid potential rise (GPR) of 926.4 Volts. Maximum calculated step potential for any mesh

Page 77 of 284
within the grid is 121.0 Volts which is only 39.1% of the calculated safe limit. However, touch

potential was another matter. Maximum calculated touch potential for any mesh within the grid

was 502.3 Volts which was 88.0% higher than a safe value.

A careful assessment of unsafe touch potential regions within the grid, or its perimeter, identified

many areas where there are no grounded structures with which to come in contact. Therefore,

no remediation was required at that time. We identified five (5) areas of the grid where plant

personnel could come into contact with a grounded structure that would be unsafe under a

system fault condition. Two (2) of those areas did require the addition of additional 4/0 grid

conductor. One of those areas required two (2) additional ground rods. In the other three (3)

cases it was far more economical to provide some form of surface treatment than to install very

significant lengths of additional grid conductor. Asphalt paving met that requirement in each of

those areas. The limited grid additions did result in slight improvements in the form of reduced

GPR and mesh potentials. GPR was reduced from 926.4 Volts to 917.9 Volts and maximum

touch potential was reduced from 502.3 Volts to 492.8 Volts, a 1.89 percent reduction.

Case History 2:

A 1025 mW capacity large, gas-fired steam electric station was designed and constructed in

Houston, Texas in 1960. Some real estate of the station was sold to other business and

removed from original construction of the plant. This activity was partially driven by grid

discrepancies that were unearthed when troubleshooting damaged header cables in a cathodic

protection rectifier groundbed. Rectifier current output significantly declined in 2010 when the

current output fell to about 15 percent if its previous value. Subsequent exploratory repairs

revealed serious damage to the header cables in the groundbed at multiple locations. It is

speculated that grounding grid conductors were cut at the same time, rendering the cooling

Page 78 of 284
tower grid isolated from the main plant grid. Therefore, it was necessary to turn off the rectifier

in order to avoid serious corrosion to sections of the grid and buried plant piping (BPP) due to

cathodic interference. This unit was returned to service after the appropriate grid repairs were

made. The purposes of this study were to evaluate the present condition of the ESG and to

make recommendations for such repairs or upgrades that might be necessary to assure

adequate relaying and to assure personnel safety plant wide. Here the grounding grid was

constructed with insulated copper conductors and bare zinc anodes serving as ground rods.

During the course of this study 237 test points were established. Point to point (PTP) resistance

measurements criterion were the same as for case 1. There is a small amount of larger 500

MCM conductor installed around transformers or other high current areas of the plant. In those

instances, resistance calculations were performed with the appropriate linear resistance value.

Whenever the second etap© grid model showed unsafe touch potentials, the appropriate grid

repairs were recommended.

The testing revealed serious electrical discontinuities in the ESG requiring immediate repair.

Seventy six (76) measurements or 32.76 percent failed to show adequate electrical conductivity,

indicating excessive resistance between those particular points of measurement. At five (5) of

the locations tested we found broken grounding pigtails aboveground that also required repair.

We measured 0 – 2.5 foot soil resistivity at multiple locations within the plant boundaries, these

data are used for the following step and touch potential calculations. In the interest of assuring

adequate electrical safety throughout the ESG, we utilized a value of 10 ohm/meter in the

calculations, which was the lowest measured value for surface soil resistivity within the facility.

Under a system fault, for a 50-kg body weight using the lowest measured resistivity for the bare

Page 79 of 284
earth condition, the safe step potential was calculated as 445.9 V and safe touch potential was

468.1 V.

Higher tolerable Voltages would apply for an individual standing on asphalt or concrete

pavements, such as within the power bock. But we do not design to those conditions when the

majority of the plant is defined by the bare earth condition. Therefore, these values make no

allowance for surface material (crushed rock or pavement) to increase human contact

resistance to earth, but assume a bare earth model throughout the grid for calculation of

tolerable step and touch voltages. Maximum clearing times are conservative estimates based

upon best available information provided to us by client. We made multiple etap© runs, to

simulate the various conditions encountered. The following individual conditions or case studies

were modeled:

Grid 1 – The entire plant grid as originally designed, board drawn, and constructed. The model

shows a safe grid with the highest calculated touch potential of 365.4 Volts or 80 percent of the

safe limit. Maximum calculated step potential was 137.08 Volts or only 29.5 percent of the safe

limit. For the initial grid in question, as found, the etap© model calculated a resistance-to-

remote earth of 0.01 ohm for the entire ESG. Under the given maximum system fault current,

this would result in a GPR of 704.6 Volts.

Grid 2 – The plant grid was originally designed and constructed with a contigous grid within the

fuel oil tank farm. During a change of ownership, the tank farm was sold to others and the tank

farm grid was no longer connected to the plant grid. When designing an ESG, the initial

Page 80 of 284
parameter, and generally the most significant, is the surface area covered by the grid. By

removing the tank farm bottoms, fuel piping and ESG elements within the tank farm, the surface

area of the grid was reduced by about 37.5 percent. This resulted in a nineteen (19) percent

increase in grid resistance-to-remote earth and, correspondingly, GPR under fault conditions.

The model clearly showed an unsafe grid with the highest calculated touch potential of 462.3

Volts or 103.7 percent of the safe limit. This touch Voltage is 26.5 percent higher than was the

case for the original grid. Maximum calculated step Voltage is only 34.7 percent of the safe

limit. This is an unintentional consequence of selling the tank farm to another entity and

disconnecting fuel piping and grid conductors from the main plant grid. Therefore, some of the

eastern side of the plant yard was unsafe for human contact under fault conditions.

Grid 3 – The plant grid as configured with all identified electrical discontinuities modeled. This

model also showed an unsafe grid with the highest calculated touch potential at 103.6 percent

of the safe limit. Maximum calculated step potential is only 34.7 percent of the safe limit.

Grid 4 – The cooling tower (CT) grid that was isolated from the main plant grid the cooling tower

area was very unsafe for human occupancy. The estimated maximum fault current and clearing

time was derived from the I2t curves published by GE for the Type AK2A-25-1 Low Voltage

Power Circuit Breakers used to protect the circulating water pumps at the cooling tower. When

the three grid stingers from the CT to the power block were intact the vast majority of the fault

current would return to generation via the three stingers resulting in very little local earth GPR.

With all the three cut stingers, all of the fault current must return to generation via discharge

from the CT local ESG grounding electrodes. The etap© model for a fault at the CT with three

cut stingers showed an extremely unsafe CT grid with the highest calculated touch Voltage at

Page 81 of 284
635 percent of the safe limit. Maximum calculated step Voltage was also unsafe at 350 percent

of the safe limit. Therefore, we could expect to have a fatality for anyone in direct contact with

the structure or possibly even if standing close to the CT should one of the circulating water

pumps fault to ground. Plant personnel were directed to barricade off the entire area. Entry

was not permitted with the pumps energized until grid repairs were completed.

Grid 5 – The entire plant grid as constructed after the required repairs were completed. The

etap© model shows a safe grid with the highest calculated touch potential of 331.8 Volts or 74.4

percent of the safe limit. The maximum calculated step potential is 171.4 Volts or only 37.2

percent of the safe limit. There are many other repairs that could have been made, but the

recommendations contained in the report provided the minimum effort that was necessary in

order to assure a safe grid, plant wide. An inspection of the etap© plots for step potential and

for touch potential confirmed very low mesh potentials within the interior of the grid. Therefore,

most of the few cut, broken, or missing conductors identified within the grid interior by this study

did not require repair or replacement. Repairs to existing grid conductors were made with like

kind ie. Number 4/0 AWG insulated copper conductor. However, for the additional grounding

required in order to assure a safe grid, we made a better conductor choice. We recommend the

installation of bare galvanized steel ½ inch diameter wire rope. This material is much less costly

than copper, is fully compatible with the plant wide Cathodic Protection system, and has the

added benefit of providing additional grounding to supplement the few proposed additional

ground rods that were required. This significantly reduced the number of additional ground rods

that had to be installed.

Page 82 of 284
Conclusions:

Modeling of two large grounding grids has been discussed. One grounding grid solution was

provided that did not make the whole plant area “safe” for touch potential. The objective was

making the plant area safe for Touch Potential where human contact was possible. The

solution was provided by adding additional conductors, ground rods, or surface treatment where

necessary. The other grounding grid solution was provided by adding galvanized aircraft cable

grounding conductors instead of insulated ground conductors and supplemented with bare

anodes in special backfill. This conductor can use where plant is cathodically protected. This

barely increased the current requirement for total cathodic protection.

These two case histories clearly document that electrical grounding cannot be taken for granted,

assuming that all is well. If grid resistance-to-remote earth is too high, relays will not trip out as

quickly as designed resulting in excessive damage to equipment and/or conductors. Extended

clearing times can render an otherwise safe grid unsafe for human occupancy. And an

inherently unsafe grid must not be allowed to remain in that condition.

Page 83 of 284
Transformer tank vibration model to
detect winding deformations

By

Emilio Morales Cruz

Page 84 of 284
Abstract

Twelve to fifteen percent of transformer failures are caused by winding deformation due to the
high electrodynamic forces that appear during through faults. These geometric variations lead to
a pattern change and an increase of the winding vibration and, consequently, to an increase of the
solid insulation mechanical fatigue, the insulation then can be degraded and short circuits
between turns will show up. These winding deformations can also change the distance between
conductors changing its dielectric withstand capability as well as the windings series and shunt
capacitances and, thus, the voltage distribution in case of lightning or switching over voltages,
making it different from what the transformer was designed to withstand for, increasing the risk
of failure. These considerations make clear the relevance of an early detection of winding
deformations.
The vibration model will determine the vibration pattern of the transformer tank as a way to
detect transformer winding deformations, and it is proposed as a complementary technique to
Frequency Response Analysis (FRA) or Leakage Reactance Measurement (LRM) having the
advantage that it can be used for online monitoring and, thus, catastrophic failures can be
avoided between successive maintenance outages.

Introduction

Vibration analysis is a key test in rotating machines’ predictive maintenance programs and is
widely used to detect on load tap changer failures by means of the noise signature analysis
during tap regulation. Use of the main tank vibration as a diagnosis tool is not very common,
nonetheless some references have been found as to the monitoring of this variable.
In this paper, the use of a model to monitor tank vibration developed in the University Carlos III
of Madrid [1] is presented. The strategy of model-based transformer monitoring systems was
proposed by MIT researchers [2] with the aim of allowing the early detection of failures in a
transformer. For this purpose, some transformer key variables are calculated by models from
some input variables. A great difference between calculated and measured values is an indication
as to a structural change in the transformer, and an alarm is then emitted. The advantage of
model-based monitoring in contrast to a traditional threshold-based one is that transformer global
working conditions are taken into account when emitting an alarm.

Transformer Vibration Sources

Vibrations in a transformer are generated by the different forces appearing in the core and in the
windings during the operation. The main sources of vibration are mainly voltage and load current
depend.

Voltage-dependent vibration

Voltage-dependent vibration is originated by magnetostriction leading to oscillations of the core


(lamination sheets). Magnetostriction is a property of ferromagnetic materials that causes them to

Page 85 of 284
change their shape when subjected to a magnetic field. The Weis Domains in metal align
themselves along the time-varying magnetic main flux induced by the applied voltage. The
changing magnetic flux density forces the Weiss Domains to follow the flux by rotation which
claims certain area in the material, their movement result in a changing length of the whole
material. Expanding and tightening lamination sheets causes mechanical vibration. The
mechanical orientation of the Weiss Domains at the positive and negative maximum of the
magnetic flux density is the same. One electrical period leads to two maxima of material
expansion. Therefore the basic oscillation is double the fundamental electrical frequency. Fig. 2
shows the relationship between length variation (in %) and iron magnetic flux density. As it can
be seen, the curve represents hysteresis. Neglecting the hysteresis effect, this curve (plotted in
the continuous line in Fig. 1) can be replaced by the idealized curve plotted in the dashed line in
Fig. 2. The mathematical expression of the idealized curve can be approximated to a quadratic
law, establishing a linear relation between the elongation and the flux density squared. Taking
into account the relation between applied voltage and flux density and admitting the elongation is
proportional to the force, the result is magnetostriction forces being proportional to voltage
squared

Fig. 1 Iron magnetostriction as a function of induction

Load-dependent vibration

Load-dependent vibration is originated by the load current in the windings due to electrodynamic
forces caused by the interaction of the current in a winding with leakage flux. These forces are

Page 86 of 284
proportional to the current squared and they have components in axial and radial directions.
Axial forces tend to compress the winding vertically. In a simple case of a two-winding
transformer, radial forces tend to compress the internal winding and to expand the external one,
since currents in both windings flow in opposite directions. Fig. 2 shows the directions of radial
and axial forces and their relative magnitude depending on the height and the radius of the
transformer winding.

Fig. 2 Forces distribution within the windings

At load condition, current-related effects superimpose magnetostriction. Forces of the alternating


magnetic field affect current-carrying windings leading to vibration also with doubled the
fundamental frequency. As magnetic leakages flux increases, magnetostriction in leakage flux
increases in shunts leading them to vibration as well.

Vibration Model

The frequency spectrum of a transformer therefore consists of superimposed frequencies


originated by its mechanics. The vibration model determines the vibration of the transformer
tank as a way to detect transformer winding deformations. It calculates the vibration main
component on the tank wall under given working conditions. The model takes in to account how
vibrations are generated in different transformer components and how these vibrations are
superposed and transmitted until reaching the tank. Comparing the calculated vibration with the
measured one, the model will be able to detect winding deformations that leads to a change in the
transformer vibration pattern. Differences between measured and computed vibration can also be
due to looseness of windings or core. To make the model applicable both to new and to in-

Page 87 of 284
service transformers, all of the input and output variables are measured using external sensors
only.

The forces analyzed in the previous section give rise to vibrations in the core and in the winding
in various directions. Core and winding vibrations interact and transmit through the oil and the
transformer supporting elements to the tank. To establish the model equation, it is assumed that
the tank vibration in a given direction results from the addition of the winding and core
vibrations in that direction multiplied by corresponding transmission coefficients (1).

vtank = t1 vwinding + t2 vcore (1)

Taking into account that winding and core vibration are proportional to current and voltage
squared, respectively, and that both variables present their main components at 60-Hz frequency,
the result is (2).

Vtank,120 = t1 i²60 + t2 u²60 (2)

To compute tank vibration from the superposition of core and winding vibration, the relative
phase angle between both vibrations must be taken into account. As winding and core vibration
depend on current and voltage, respectively, the phase angle between them depends on the power
factor of the electrical load being transmitted through the transformer. To consider the phase
angle between vibrations, the model is formulated in complex variables.

Temperature Influence

To model vibrations properly, transformer temperature influence must be properly addressed.


There are several physical processes by which temperature influences vibration. First of all,
magnetostriction is a nonlinear phenomenon which is dependent on temperature [3]. Moreover,
temperature changes give rise to a change in oil viscosity that influences vibration transmission
to the tank. Finally, temperature variations cause dilatation or compression of structural elements
changing their natural vibration frequencies as well as the amplitude of forced oscillations. It is
clear that temperature must not be included in the model as a system excitation, but must be
introduced by a variation on the equation parameters instead. A simplified form to take into
account temperature effects is given by

Vtank,120 = ( + t)i²60 + ( + t) u²60 (2)

The vibration model algorithm is given by (2), where Vtank, i and u are complex variables that
correspond to the real and imaginary parts of the tank vibration, current, and voltage main
frequency components, , , , and  are complex parameters whose value depends on
transformer geometry and which must be computed from data measured on the transformer and

Page 88 of 284
t is the oil temperature. The parameters in (6) change slowly in time as the transformer ages,
clamping pressure decreases, so vibration becomes greater. Because of that, parameters must be
recalculated after some years using the model.

Other Vibration Sources

The model described in this paper is based in the analysis of the periodic vibrations and does not
consider the LTC vibrations as they appear only after an LTC operation, producing transient
vibrations that are added to the periodic ones caused by the core and the windings. The elements
of the cooling system (i.e., oil pumps and fans) also generate vibrations that are added to the
main vibrations. These elements do not operate in a continuous way, as they are switched on or
off depending on the transformer working temperature, but when they work, a periodic vibration
signal appears, the effect of this vibration is considered by the model by a different set of model
parameters.

Vibration Model Test

WEG Mexico allowed us to test the model in one of their transformers. A set of measurements
was performed on a transformer to adequately choose the point of the tank where vibrations
should be measured, so that it reflects the transformer internal behavior as well as possible. The
test transformer was fitted with external accelerometers and WEG’s test facility we were only
able to simulate no-load and load conditions one at a time. Disappointedly it was found out that
the model didn’t work out under no-load conditions because there was no load current, but it did
work under load conditions even with only impedance voltage present. Fig. 3 shows the vibration
model output compared to actual data taken during one of the test performed

Fig. 3 Actual data measured versus vibration model predicted data

Page 89 of 284
As mentioned it was not possible to simulate real operating conditions, therefore the next step is
to test the model in an actual transformer in service where voltage and load current will be
present at the same time so the model can be fully tested.

Conclusion

In this paper, tank vibration monitoring has been proposed as an on line method to detect
winding deformations in power transformers. The model was developed to calculate tank
vibrations, taking into account transformer operating conditions. The vibration calculated value
is compared with the measured one being a great discordance between both values a sign of a
possible change in the transformer geometry. The model takes into account how the vibrations
are generated at different transformer components. The model includes the effects of temperature
on vibration generation, superposition, and transmission to the tank. Only the main component of
tank vibration is used in the model, as higher harmonics are much lower and do not show a
strong dependence with current. Tests were carried out to localize the best point of the tank to
place the accelerometers to measure vibrations. The test results are promising but need to be
confirm a transformer under actual operating conditions.

References

1. B. García, J. C. BurgosJ, and A. Alonso, “Transformer Tank Vibration Modeling as a


Method of Detecting Winding Deformations—Part I:Theoretical Foundation”
2. W. H. Hagman, T. H. Crowley, R. D. Tabors, and F. C. Schweppes, “An adaptive
transformer monitoring system,” presented at the Int. Symp. Demonstrations Expert
System Applications to Power Industry, Montreal, QC, Canada, May 7–12, 1989.
3. R. M. Bozorth, Ferromagnetism. New York: IEEE Press, 1993.

Biography

Emilio Morales is a Technical Application Specialist in Transformer applications at Qualitrol


Company LLC. His main focus is to support solutions in comprehensive monitoring for
Transformer applications
Emilio attended Nuevo Leon State University in Mexico from 1975 to 1979, receiving his
Bachelor of Science degree in Electro Mechanical Engineering in 1980. Emilio has over 30 years
of experience in power transformer design. He is member of the IEEE/PES Transformer
Committee, IEC and CIGRE and actively participating in different task forces.
Emilio previously worked with GE-Prolec , Ohio Transformer, Sunbelt Transformer and Efacec
Power Transformers.

Page 90 of 284
Steady-State and Dynamic
Transmission System Model
Validation (NERC MOD-033-1)
Prepared for

July 12, 2017

Prepared By

Jim Kelley (PE), Miles Hammac


PowerSouth Energy Cooperative

Guanqun Wang (PhD), Pradeep Tripathi,


Hyung Shin (PhD), Joseph Nichols, Ravi Varanasi
Burns & McDonnell Engineering Company, Inc.

Page 91 of 284
Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER
TABLE OF CONTENTS
Page No.
1.0 ABSTRACT .......................................................................................................... 2
2.0 INTRODUCTION .................................................................................................. 2
3.0 POWER FLOW MODEL VALIDATION PROCESS ............................................. 2
3.1 Model and Data Preparation ....................................................................................3
3.2 Adjustment of Planning Case to Match Selected System Conditions .....................4
3.3 Solving Power Flow and Comparison of Key Quantities ........................................4
4.0 DYNAMIC MODEL VALIDATION PROCESS...................................................... 4
4.1 Model and Data Preparation ....................................................................................5
4.2 Adjustment of Power Flow and Dynamics Cases ....................................................6
4.3 Simulation of Dynamic Event and Comparison ......................................................6
5.0 POWER FLOW MODEL VALIDATION RESULTS .............................................. 6
5.1 Model and Data Preparation ....................................................................................6
5.2 Adjustment of Planning Case to Match Selected System Conditions .....................7
5.3 Solving Power Flow and Comparison of Key Quantities ........................................7
5.4 Model Enhancement ................................................................................................8
6.0 DYNAMIC MODEL VALIDATION RESULTS ...................................................... 8
6.1 Selection of Event for Validation ............................................................................8
6.2 Model and Data Preparation ....................................................................................9
6.3 Simulation of Dynamic Event and Comparison ......................................................9
6.3.1 Bus Voltage Comparison (DFR Vs PMU Vs PSS/E) .............................10
6.3.2 Real Power (MW) Flow from McWilliams 115 kV Bus ........................10
6.3.3 Reactive Power (MVAr) Flow from McWilliams 115 kV Bus ..............10
7.0 MODEL VALIDATION RESULT ANALYSIS AND CONCLUSIONS ................. 11
7.1.1 Power Flow Model Validation ................................................................11
7.1.2 Dynamic Model Validation.....................................................................12
ACKNOWLEDGEMENTS ............................................................................................. 13
REFERENCES .............................................................................................................. 13

LIST OF TABLES
Page No.
Table 5-1: Total In-Service Load Comparison ................................................................................7
Table 5-2: Total Tie Flow Comparison ...........................................................................................7
Table 5-3: Branch Flow Comparison ...............................................................................................7
Table 5-5: Branch Flow Comparison ...............................................................................................8

LIST OF FIGURES
Page No.
Figure 3-1: Power Flow Model Validation Workflow ....................................................................3
Figure 4-1: Dynamic Model Validation Work Flow .......................................................................5
Figure 6-1: Location of Disturbance on April 05, 2017 ..................................................................8
Figure 6-2: Voltage Comparison (DFR Vs PSS/E) .......................................................................10
Figure 6-3: MW Flow Comparison (PMU Vs PSS/E) ..................................................................10
Figure 6-4: MVAr Flow Comparison (PMU Vs PSS/E) ...............................................................11
Figure 7-1: Alternative Tie-Line Flow Equivalent ........................................................................12

Page 92 of 284
Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER

1.0 ABSTRACT

The design, planning and daily operation of power systems depend on the accurate modeling of system
elements such as power plants, transmission lines and loads. The NERC (North American Electric
Reliability Cooperation) MOD-033-1 standard establishes new requirements for the validation and testing
of steady-state and dynamic planning models. PowerSouth Energy Cooperative has completed its first
round of NERC MOD-033-1 compliance studies: creating validation guidelines and metrics, and validating
the steady-state and dynamic planning models utilizing PSS ODMS State Estimator cases, and PMU
(phasor measurement unit) values. The compliance study solved many practical challenges within the
model validation process and revealed opportunities for improved modeling & testing in the future.

2.0 INTRODUCTION
The validity and usefulness of planning studies depends on accurate modeling of steady-state and dynamic
power systems. Inaccurate modeling can produce major discrepancies between simulated and actual system
responses, which will further lead to incorrect prediction of system behavior [1][2]. The North American
Electric Reliability Cooperation (NERC) developed the MOD-033-1 standard [3] to “establish consistent
validation requirements to facilitate the collection of accurate data and building of planning models to
analyze the reliability of the interconnected transmission system” and requires all planning coordinators,
reliability coordinators and transmission operators to comply, starting in 2017.

To comply with the NERC MOD-033-1 standard, Burns & McDonnell and PowerSouth Energy
Cooperative (PowerSouth) developed a set of procedures and guidelines for validation of PowerSouth’s
steady-state and dynamic planning models, and validated the current planning models against real-time
system conditions and actual system responses to a disturbance event.

3.0 POWER FLOW MODEL VALIDATION PROCESS


The following section outlines the process and methodologies for power flow model validation within the
PowerSouth system, utilizing a state estimator case and real-time data sources to represent actual system
behavior. Figure 3-1 illustrates the power flow model validation workflow.

Page 93 of 284
Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER
Figure 3-1: Power Flow Model Validation Workflow

3.1 Model and Data Preparation


The NERC standard [3], recommends that the system conditions utilized for validation be made as close to
system peak as possible. Therefore, the first three steps in Figure 3-1 include the selection of system
conditions to be studied and obtaining the corresponding PSS ODMS real-time case and planning power
flow model. For each study iteration, once the near-term system peak condition is achieved, the
corresponding year (or next calendar year) peak load planning model and the PSS ODMS real-time case
are selected. PowerSouth’s PSS ODMS software generates and archives real-time cases utilizing real-time
system telemetry and a state estimation process at regular intervals (typically every 1 to 5 minutes). Data
recorded include MW, MVAr flow, bus voltages, switch and breaker status, generator outputs, tie-line
flows, capacitor status/output and individual station and total system load. Construction and maintenance
outages at the time of the capture are also recorded and verified by the energy control group.

Page 94 of 284
Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER

3.2 Adjustment of Planning Case to Match Selected System Conditions


Since, power flow planning models contain projected system conditions, and the power flow model selected
in Section 3.1 may contain future conditions and/or topology, the planning model must be adjusted to reflect
the studied conditions and configurations. At a minimum, the following items must be validated/adjusted
during the model preparation process:

1. Generation MW Dispatch
2. Transmission topology
3. Station loads (MW, MVAr)
4. Switch shunt status/output
5. Transformer tap positions

Additionally, two model component states must be adjusted indirectly to bring better alignment between
the planning model and the state estimator case: tie-line MW flows and MVAr flows, and generator MVAr
outputs. To reconcile tie-line flows, artificial loads are placed at the boundary buses and adjusted until the
tie-line flows match the state estimator case. To reconcile the generator MVAr outputs, the unit terminal
voltage is adjusted until the outputs match the state estimator case.

3.3 Solving Power Flow and Comparison of Key Quantities


After the planning model adjustments, the power flow results are compared to the actual system behavior
contained in the PSS ODMS real-time case. The following quantities within the adjusted planning model
and the PSS ODMS real-time case are compared:

• Generator MW output, MVAr output, and voltage


• Bulk Electric System (BES) bus voltages (100kV and above)
• BES transmission line MW and MVAr flows.

The comparison results are recorded and utilized for planning model enhancements.

4.0 DYNAMIC MODEL VALIDATION PROCESS


The following section outlines the process and methodologies for dynamic flow model validation, within
the PowerSouth system, utilizing Phasor Measurement Units (PMU) and Digital Fault Recorders (DFR) to
represent actual system behavior. Figure 4-1 illustrates the dynamic model validation process.

Page 95 of 284
Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER
Figure 4-1: Dynamic Model Validation Work Flow

4.1 Model and Data Preparation


Similar to the Power Flow Model Validation Process (outlined in Section 3.0), the initial steps in the
Dynamic Model Validation Process include event and model selection and validation of event data for
completeness. Within PowerSouth’s system, the event data is recorded by devices such as PMUs and DFRs.

Page 96 of 284
Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER

4.2 Adjustment of Power Flow and Dynamics Cases


Next, the power flow and dynamics cases are adjusted to reflect the system conditions immediately prior
to the event (following the process described in Section 3.2). After the adjustments, baseline dynamics
functional tests are performed on the cases including: no-fault and ring down tests to verify the validity of
the revised case configuration.

4.3 Simulation of Dynamic Event and Comparison


Then, the dynamic event is simulated on the adjusted case by matching the following parameters:

1. Fault type, locations and duration.


2. The relay actions during the fault.
3. Fault current, fault admittance and corresponding time.

The system responses within the adjusted cases are plotted and compared to the real-time event recordings
(PMU and DFR). Unlike the steady-state model validation, the dynamic model validation is qualitative.
Meaning, the plots of actual system responses versus simulated system responses must be visually
compared rather than measured against discrete criteria. The following lists the aspects of the event that
should be compared.

1. Oscillations – frequency, damping, initial amplitude


2. Initial and final state of the dynamic event
3. Minimum and maximum values of the waveforms
4. Rates of change of the waveforms
5. Rise time of system response

The comparison results with major discrepancies will be analyzed and utilized for planning model
enhancement.

5.0 POWER FLOW MODEL VALIDATION RESULTS


This section provides the results for power flow model validation for the PowerSouth system, following the
process described in Section 3.0.

5.1 Model and Data Preparation


For the study year 2016/2017, PowerSouth reached its peak load condition of 2,100 MW on January 8th,
2017 at 07:34 AM. The 2018 Winter Peak power flow planning model was selected as a baseline due to its
dispatch and topology similarities to the January 8th, 2017 system conditions.

Page 97 of 284
Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER

5.2 Adjustment of Planning Case to Match Selected System Conditions


Then, the 2018 winter peak planning power flow model was calibrated to match the 2017 winter peak
conditions recorded in the PSS ODMS real-time case per the process outlined in Section 3.0. The
comparison results between adjusted planning power flow model and the real-time snapshot on total in-
service load in PowerSouth system and Total interchange power from PowerSouth area are shown in Table
5-1 and Table 5-2.

Table 5-1: Total In-Service Load Comparison


ODMS PSS/E Difference
MW MVAr Power Factor MW MVAr Power Factor ∆ MW ∆ MVAr
2103 -15.7 1.000 2109.3 -22.2 0.9999 6.3 -6.5

Table 5-2: Total Tie Flow Comparison


ODMS PSS/E Difference
From Area To Area
MW MVAr MW MVAr ∆ MW ∆ MVAr
PS SOCO 157.8 19.6 153.1 29.6 -4.7 10
PS_BC_AREA SOCO -192.5 17.4 -192.4 17.7 0.1 0.3
PS SMEPA 48.7 -18.7 53.1 -19.7 4.4 -1

The results show that the adjusted power flow planning model had only minor discrepancies with the real-
time snapshot on system level, thus is valid for further comparison.

5.3 Solving Power Flow and Comparison of Key Quantities


After adjustment to the planning case, the power flow was solved and the quantities listed in Section 3.3,
within the adjusted planning model, were compared to the actual system behavior at the time of the peak.
The comparison found that all BES bus voltages were within ±3% of the actual system bus voltages at the
time of the peak and the MW and MVAr flows on the BES branches were within ±10 MW/MVAr except
for Belleville to Gantt 230 kV line as illustrated in Table 5-3.

Table 5-3: Branch Flow Comparison


Base ODMS PSS/E Compare
Transmission Line
kV MW MVAr MW MVAr ∆ MW ∆ MVAr
230 Belleville - Gantt -40.1 -1.9 -51.1 -2.6 11 0.7

Additionally, all MW and MVAr flows on the PowerSouth tie-lines and transformers were within ±10
MW/MVAr. All generator MW outputs matched the realtime values, MVAr outputs were with within ±10
MVAr and the terminal voltages were within ±3%.

Page 98 of 284
Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER

5.4 Model Enhancement


Further investigation after the initial quantity comparison determined that the branch flow discrepancy
noted Table 5-3 was caused by various small transformer and branch impedance differences between the
adjusted planning model and the real-time PSS ODMS case. Therefore, all the unmatched parameters were
updated to match the ODMS case values. With this resolution, all the branch and transformer flow
differences were within ±10 MW/MVAr (revised Belleville – Gantt flows shown in Table 5-4).

Table 5-4: Branch Flow Comparison


ODMS PSS/E Difference
Base kV Transmission Line
MW MVAr MW MVAr ∆ MW ∆ MVAr
230 Belleville - Gantt -40.1 -1.9 -42.2 -4.3 2.1 2.4

6.0 DYNAMIC MODEL VALIDATION RESULTS


This section provides the results for dynamic model validation for the PowerSouth system, following the
process described in Section 4.0.

6.1 Selection of Event for Validation


On April 05th, 2017 at 12:29 PM, a tree branch fell on the 33.65-mile 115kV transmission line between
McWilliams and Victoria Junction substations at a location approximately 29.65 miles from McWilliams
or 4 miles from Victoria Junction substation. The event was a single line to ground fault occurring on C
Phase. Figure 6-1 shows the location of the disturbance.

Figure 6-1: Location of Disturbance on April 05, 2017

Page 99 of 284
Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER
The transient disturbance event was recorded in Digital Fault Recordings (DFR) and Phasor Measurement
Units (PMU). The DFRs are located on various circuit breakers and PMU units are available in specific
115 kV buses within the PowerSouth system.

6.2 Model and Data Preparation


PSS/E uses positive sequence data for all fault calculations and simulations. Therefore, the DFR voltage
and current data (by phase) was converted to the positive sequence data using Equation 6.1, 6.2, and 6.3.
I + a IB + a 2IC 6.1
A
I1 =
3
V A + a V B + a 2V C 6.2
V1 =
3
6.3
a = 1∠ 120 °
The total fault current equals the sum of positive sequence current from Brundidge side and positive
sequence current from McWilliams side. The total positive sequence current was used to calculate the fault
admittance. Additionally, for the April 5th, 2017 event, PMU data recordings were available on four 115
kV buses: McWilliams, Dublin, Atmore and Brewton.

The 2018 off-peak power flow planning model along with a corresponding dynamic model was selected as
a baseline due to its dispatch and topology similarities to the April 5th, 2017 system conditions. Using the
process outlined in Section 3.0, the 2018 off-peak planning power flow model was adjusted to match the
system conditions at a specific time of the dynamic event.

6.3 Simulation of Dynamic Event and Comparison


After model adjustments, two snapshots were created to represent different dynamics load modeling
scenarios: ZIP model and 50% small induction motor load model, and the transient fault was simulated
mimicking the characteristics captured in the April 5th event data recordings. The simulation was run for 20
seconds to capture system behavior before the fault, during the fault and after the fault was cleared.
Waveforms of the simulation results were compared with the dynamic data recordings from DFR and PMU
units. The following quantities were compared:

1. Bus voltage magnitude


2. Real power (MW) flow on branches from McWilliams 115 kV bus
3. Reactive power (MVAr) flow on branches from McWilliams 115 kV bus

Page 100 of 284


Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER

6.3.1 Bus Voltage Comparison (DFR Vs PMU Vs PSS/E)


Bus voltage magnitude recordings in PMU and DFR were compared with the PSS/E simulations. The bus
voltage comparisons for the Brundidge 115 kV bus and the McWilliams 115 kV bus are shown in Figure
6-2.

Figure 6-2: Voltage Comparison (DFR Vs PSS/E)


(a) Brundidge 115 kV bus (b) McWilliams 115 kV bus

6.3.2 Real Power (MW) Flow from McWilliams 115 kV Bus


The MW flow comparisons for the McWilliams to Victoria Junction 115 kV transmission line, and the
McWilliams to Wiggins Junction 115 kV transmission line, are shown in Figure 6-3.

Figure 6-3: MW Flow Comparison (PMU Vs PSS/E)


(a) McWilliams – Victoria Junction (b) McWilliams – Wiggins Junction

6.3.3 Reactive Power (MVAr) Flow from McWilliams 115 kV Bus

The MVAr flow comparisons for the McWilliams to Victoria Junction 115 kV transmission line, and the
McWilliams to Wiggins Junction 115 kV transmission line, are shown in Figure 6-4.

Page 101 of 284


Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER
Figure 6-4: MVAr Flow Comparison (PMU Vs PSS/E)
(a) McWilliams – Victoria Junction (b) McWilliams – Wiggins Junction

7.0 MODEL VALIDATION RESULT ANALYSIS AND CONCLUSIONS

7.1.1 Power Flow Model Validation

The 2017 winter peak power flow planning model closely matched the characteristics of the system peak
conditions observed on January 8th, 2017. The recommended comparison criteria are as follows:

• Unit MW and MVAr output, generator voltage, and BES bus voltages should be within 3% of the
state estimator value.
• MW and MVAr flows on BES transmission lines, tie-lines and transformers should be within
10MW/MVAr of the state estimator value.

The following recommendations would enhance the future development of the power flow planning models
and adjusted power flow planning models to comply with NERC MOD-033-1 requirements:

1. Closely compare the transmission line, tie-line and transformer impedances between the
PSS/ODMS case and the planning model.
2. To mitigate tie-line flow discrepancies, consider replacing the tie-lines (within the adjusted
planning model) with two artificial loads (added at both ends of the tie-line) to force the exact tie-
line flow, as shown in Figure 7-1.

Page 102 of 284


Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER
Figure 7-1: Alternative Tie-Line Flow Equivalent

Artificial Load
Artificial Load

PowerSouth Area

Boundary Bus

7.1.2 Dynamic Model Validation


The 2017 off-peak dynamics planning model exhibited a system response similar to the disturbance event
recordings of DFRs and PMUs for the studied event. Using the engineering judgement on the parameters
compared in Section 4.3, the dynamics modeling and compatible power flow model are adequately
developed to satisfy the NERC compliance requirements of PowerSouth system.

The following recommendations would enhance the future development of the dynamic planning models
to comply with NERC MOD-033-1 requirements:

1. Audit the PMU measurements and time stamps to verify their accuracy, as the DFR and PMU
measurements during the study revealed a consistent time delay in the PMU measurements.
2. Record the quantities from all the generating units to aid in comparison of the simulation of
dynamic response to that of the on-line generating units.
3. Consider the utilization of more accurate load models, such as the composite load model, and verify
the dynamic generator models to capture the dynamic features of the real system. (In this study, the
PMU waveforms had a slower and smoother recovery than the PSS/E simulation results).

Page 103 of 284


Steady-State and Dynamic Transmission System Model Validation
(NERC MOD-033-1)
TECHNICAL PAPER

ACKNOWLEDGEMENTS

In addition to the authors of this paper, the analyses presented therein were completed with the assistance
of the following PowerSouth personnel – Jay Farrington and Brandon Horn.

REFERENCES

[1] D. N. Kosterev, C. W. Taylor, and W. A. Mittelstadt, “Model Validation for the August 10, 1996 WSCC
System Outage,” IEEE Transactions on Power Systems, 14(3), 1999.
[2] D. N. Kosterev, “Hydro Turbine-Governor Model Validation in Pacific Northwest,” IEEE Transactions
on Power Systems, 19(2), 2004.
[3] NERC MOD-033-1 Standard “B. Requirements and Measures

Page 104 of 284


An Analysis of Phased Array Ultrasonic Testing versus
Conventional Ultrasonic Testing in the Utility Pole Industry
Authors:
Garrett Ehler, AWS-CWI, ASNT/ACCP Level III
Mihai Radu, ASNT Level III

Abstract
For years, conventional ultrasonic testing (UT) systems have aided manufactures and utilities in weld
inspection and crack identification, both during fabrication and during in-service maintenance checks.
Ultrasonic technology has advanced over the years but the fundamentals of how sound propagate
through materials have not changed. An important advancement has been the development of Phased
Array UT (PAUT) which enables the inspector to use a probe with multiple elements to focus, steer and
scan with a single transducer, greatly improving the inspection of complex weld geometries.
This paper will discuss the advantages and disadvantages of PAUT and Conventional UT in the utility pole
industry and will show how Phased Array Ultrasonic Testing is a viable technological advancement and
should be included as a tool in the arsenal of the utility pole inspection team.

Page 105 of 284


An Analysis of Phased Array Ultrasonic Testing versus
Conventional Ultrasonic Testing in the Utility Pole Industry
1. Introduction

Conventional ultrasonic flaw detectors have been used for years in the inspection
of materials, fabricated parts, and as an in-service maintenance tool used by
inspectors across many industries including the utility field. As technology
advances, the standards that govern the processes may occasionally lag behind
causing older technologies to be used in lieu of newer systems Phased array
ultrasonic testing (PAUT) is the younger sibling of conventional UT that could
become the method of choice.

Ultrasonic phased array systems can be employed for almost any situation where
conventional ultrasonic flaw detectors have traditionally been used. Weld
inspection and crack detection are the most important applications and these
tests are done across a wide range of industries including aerospace, power
generation, pipeline construction, general manufacturing, and the utility industry.

The benefit of phased array technology over conventional UT comes from its
ability to use multiple elements to steer, focus, and scan beams with a single
transducer assembly. Beam steering, commonly referred to as sectorial scanning,
can be used for mapping components at appropriate angles. This can greatly
simplify the inspection of components with complex geometry. The small
footprint of the transducer and the ability to sweep the beam without moving the
probe also aids in inspecting such components in situations where access for
mechanical scanning is limited. Sectorial scanning is also typically used for weld
inspection. The ability to test welds with multiple angles from a single probe
greatly increases the probability of detection of discontinuities.

Page 106 of 284


Phased array UT works by implementing multi-element transducers rather than
the single-element transducers typically used in conventional ultrasonics. This
provides the ability to sweep the sound field through multiple angles or raster
through a series of the same angle from one probe (Fig 1).

Fig. 1 – Phased array sectorial and linear scan

The system can be configured to collect data from multiple probes in sequence to
optimize data collection from opposite sides of the weld or multiple positions
from the same side of the weld in one scan (Fig 2).

Fig. 2- Multiprobe data collection

2. Application of Phased Array to AWS D1.1

American Welding Society’s D1.1:2015 “Structural Welding Code – Steel”


Annex Q Provides an alternative and more conducive avenue for applying
Phased Array UT in accordance with the current code and may be used with
Engineer`s approval. The American Welding Society is currently seeking
adoption of a PAUT specific annex into the D1.1 and D1.5 (Bridge) Codes. The
end goal is to define the essential parameters and acceptance criteria

Page 107 of 284


regarding PAUT application and allow users to access the benefits of this new
technology.

3. Phased array vs. Conventional UT

The conventional UT equipment uses a single element acoustical probe to emit


an ultrasonic beam in a fixed direction using an echo-location approach to
determine the presence and position of flaws. The conventional ultrasonic
inspection is a well-established method for decades. The presentation of
defects in an A-scan (Fig.3) is very abstract and the evaluation needs well-
experienced operators. The documentation is difficult because of missing
imaging and a later data analysis is not possible due to missing data recording.

Fig. 3- Typical Conventional UT A-scan presentation

In contrast to conventional UT, the beam from a phased array probe can be
moved electronically, without moving the probe, and can be swept through a
wide volume of material at high speed. Due to imaging by B, C, S, and L-scans
(Fig.4) the evaluation and documentation of PAUT is easier. The inspection
speed is higher because of fast scanning in combination with electronic beam
steering.

Page 108 of 284


Fig. 4- Typical PAUT imaging views.

Phased array’s limitations are initial equipment costs, extended training


requirements and a formal recognized code. PAUT equipment costs are coming
down but compared to conventional UT are still substantially higher. PAUT also
requires 80 hours of formal classroom training and an additional 160 hours of on
the job training on top of a conventional UT certification, per ASNT’s SNT-TC-1A:
Guideline for the Qualification and Certification of NDT Personnel. The additional
qualification requirements equate to more expensive technician/third party costs,
and, if those training requirements are not met, the potential for
underqualified/poorly trained technicians can propagate.

AWS D1.1’s Annex Q gives the engineer that ability to allow PAUT in lieu of
conventional, but a more formal procedure within Clause 6 with
acceptance/rejection criteria would eliminate some of the variations caused by
Annex Q.

4. Phased Array UT in the Manufacturing Environment

Page 109 of 284


In the manufacturing environment, the PAUT inspection can be achieved on a
variety of platforms such as the Olympus Omni scan MX-2 unit (Fig. 5). The
market for ultrasonic NDT inspection, both PAUT and Conventional UT, has
grown immensely since the introduction of portable equipment. PAUT has
become more feasible making its accuracy a valuable choice. In addition,
current research and development is being focused on this technique, yielding
key developments for the field.

Fig. 5- Olympus Omni scan MX-2

The images below present an example of inspection results conducted at Pelco


Structural L.L.C. using both conventional UT and Phased array techniques
investigating the same defect.

Page 110 of 284


5. Conclusion

Phased array ultrasonic testing is a viable alternative to conventional ultrasonics


for volumetric assessment of structural components. The technology can be
adapted to the current version of the AWS D1.1 code. The sectorial scan is
produced in real time to continually offer dynamic imaging with transducer
movement. This is very useful for defect visualization and increases probability of
detection, especially with respect to randomly oriented defects, as many
inspection angles can be used at once.

Page 111 of 284


6. References:

1. “Application of Phased Array Ultrasonics to AWS Codes.” University


of Ultrasonics Parrish A. Furr.
2. “Manual Weld Inspection with Ultrasound- Conventionally or with
Phased Array?” Karl Deutch, Wolfram A., Stefan Kierspel
3. “AWS D1.1/D1.1M:2015 Structural Welding Code-Steel” American
Welding Society.
4. OLYMPUS WEBSITE www. olympus-ims .com
5. “Materials for Ultra-supercritical and Advanced Ultra-Supercritical
Power Plants” Augusto Di Gianfrancesco.

Page 112 of 284


For further information, or questions, please contact:

Garrett Ehler, AWS-CWI, ASNT Level III


Vice-President/General Manager
Texas Nondestructive Testing Academy
Phone: 281-231-0001
Email: Gehler@TXNDT.com

About the Presenter: Mr. Garrett Ehler

Mr. Ehler is a 1998 graduate of Baylor University in Waco, Texas with dual degrees in
Environmental Science and Psychology. After spending several years in the heavy construction
and utility industries, Mr. Ehler was one of the founding employees of ReliaPOLE Inspection
Services Company, a Houston based inspection firm focused on the global pole and lattice tower
industries. In 2015, Mr. Ehler and ReliaPOLE branched out to form Texas NDT Academy. As
TXNDT’s Senior Instructor and General Manager, Mr. Ehler is committed to providing his
students with the ideal curriculum consisting of both the theories and science behind each course
offered, but also their use in real world applications and best practices.

Certifications:
AWS CWI – 13071361
ASNT/ACCP Level III – 229488 UT/MT/PT/VT
NACE CIP I
AGA Certified Inspector

Co-Author:
Mihai Radu, ASNT Level III
About the Presenter: Mr. Mihai Radu

Mr. Mihai Radu obtained a Bachelor in Mechanical Engineering – 5 year University Degree
from the Polytechnic University of Timisoara – Romania. After relocating to United States from
Romania, Mr. Radu began specializing in Quality Control and Non-Destructive Testing. He
obtained ASNT Level III certifications in MT, UT, and PT. Mr. Radu served as the NDT Level
III at Pelco Structural where, in addition to his NDT duties, he acquired working knowledge and
experience with Phased Array Equipment. Currently, Mr. Radu is the NDT/LAB Manager at
TMK-Ipsco in Catoosa, OK.

Page 113 of 284


SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

`
Drones: The Use of Unmanned Aerial Systems for
Surveying for Transmission Route Engineering,
Substation Design and Installation of Facilities

A Technical Paper Presented at


UT Arlington
Transmission and Substation Design and Operations Symposium
September 6-8, 2017

By George R. Hill, RPLS


UAS Remote Pilot
Director, Sempco Drone Operations

Table of Contents:

Index……………………….....................................................................................................1

Introduction…………………………………………………………………………………..2

FAA Regulations……………………………………………………………………………..3

FAA Issues and studies………………………………………………………………………4

Airspace……………………………………………………………………………………....6

Aeronautical Charts………………………………………………………………………......7

Applications for Drones……………………………………………………………………....8

Key elements of a UAS Program……………………………………………………………..9

Types of Drones………………………………………………………………..…………….10

Cameras and LIDAR Scanners………...………………………………………………….....11

Software……………………………………………………………………………………...12

Conclusions…………………………………………………………………………………..13

References and Links………………………………………………………………………...14

Portions not credited © Sempco Surveying, Inc 2017


Page 114 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

Introduction

Drones, were officially termed by the Department of Defense in 2005 as Unmanned Aircraft Systems or
UAS. They are being used for an increasing number of applications world-wide. This paper will review
some of the UAS issues and drone applications of interest to engineers for designing facilities and
infrastructure, conducting inspections, planning improvements and documenting construction.

The combination of using lithium polymer batteries, light-weight materials, wireless technology and GPS
provides the basis for controlled unmanned flight. Advances in camera and LIDAR hardware and
specialized software development have provided a way to capture and process images and translate them
into hard data. This has resulted in an explosion in the UAS industry for the engineering disciplines, as
the use of drones and related technology has proven to be an ideal solution for data acquisition.

Drones are now regulated by the FAA. Revisions to recent regulations make operating drones for
commercial purposes practical. However, the use of drones has created controversy and has raised
concerns. The right to privacy is a hot topic, as is safety and integration into the national airspace.

Previously, photogrammetric mapping was done by using cameras mounted in a standard fixed wing
aircraft flying between 1500 feet and 12,000 feet. The data was gathered, downloaded, analyzed, post-
processed and delivered. The procedure was costly, cumbersome and caused delays. At the present time,
almost anything can be mapped by using UAS/drone based camera imaging and scanning hardware.
Results are immediately available, and real-time conditions can be viewed and documented.

Advances in photogrammetric software allow photo images to generate point clouds, which can be
converted into high quality aerial maps or topographic digital surface terrain models. Advances in
hardware development reducing the size of LIDAR scanners has resulted in a cost-effective way to
conduct 3D scanning and modeling. A variety of industrial sized drones are now available, Cameras are
becoming more sophisticated and powerful and integrated software provides flight planning and
automatic operation. These advances provide the engineer with many choices. This paper will present:

 FAA regulations
 An overview of present studies and future issues
 Flight parameters and restrictions
 Key Elements of a UAS Program
 Drone types and uses
 Camera types and uses
 Software development for flight planning and drone operation
 Conclusions, references and links

Disclaimer: The contents of this technical paper represent the perceptions, opinions and conclusions of
the author, and may reference commercial, government and non-profit sites. The contents do not reflect
the views and opinions of UTA/TSDOS or Sempco Surveying, Inc. and are not to be considered legal
advice. The information and links may not represent current sites, rules and content. No liability is
expressed, implied or assumed by UTA/TSDOS, Sempco Surveying Inc or this author for any damages
for the use of the contents. The author has not asked for nor obtained any compensation from any person,
company or organization for the use of names or images of products and makes no specific
recommendations. All trade names are trademarked and/or copywritten by their respective companies.

Portions not credited © Sempco Surveying, Inc 2017


Page 115 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

FAA Regulations

In August 2016 the FAA revised the requirements for those who operate a drone for commercial
purposes. They also set guidelines for where you can fly, the maximum elevation for drone flights, the
weight of the UAS system and outline additional requirements for UAS operation.

The FAA rules for operating an unmanned aircraft for commercial purposes are as follows:

Pilot Requirements: Must have Remote Pilot Airman Certificate


Must be 16 years old
Must pass TSA vetting

Aircraft Requirements Must be less than 55 lbs.


Must be registered if over 0.55 lbs. (online)
Must undergo pre-flight check to ensure UAS is in condition for
safe operation

Location Requirements Class G airspace*

Operating Rules Must keep the aircraft in sight (visual line-of-sight)*


Must fly under 400 feet*
Must fly during the day*
Must fly at or below 100 mph*
Must yield right of way to manned aircraft*
Must NOT fly over people*
Must NOT fly from a moving vehicle*

*These rules are subject to waiver (1)

Regulatory Basis Title 14 of the Code of Federal Regulation (14 CFR) Part 107

Remote Pilot Certification involves passing a written and proxied test on general airman knowledge, with
an emphasis on section 107 covering the rules for UAS flight. In addition, there are questions on weather,
risk factors, airspace, aeronautical charts and UAV maintenance, care and record keeping.

The UAV team structure is not defined, but there shall be a FAA certified Remote Pilot present, as well as
a Visual Observer at a minimum. Under certain conditions, additional team members would be on hand
for public relation questions, security, safety and for establishing ground control points. Each team
member should be dedicated to that individual role so all tasks are accomplished.

Pre-flight briefings are essential so that all personnel understand responsibilities and have a good working
knowledge of flight parameters, risks, and response options should there be a flight malfunction. A clear
plan of action in the event of an emergency should be part of every briefing, with adequate personnel on
hand for effective response.

Portions not credited © Sempco Surveying, Inc 2017


Page 116 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

FAA Issues

The FAA is currently conducting studies nation-wide on how to integrate drones into the US
Airspace. Everyone from major online distributors to local police departments, motion picture
companies, real estate and news agencies, utility companies, agricultural inspectors, farmers,
photographers, engineers and surveyors operating drones, there will be more interaction between
unmanned aerial vehicles and manned aircraft. In March (2017) a Canadian 767 had made its
final approach in Ft Lauderdale when a crew observed a UAV passing about 10 feet over its left
wing. Two weeks later a West-jet 737 encountered a “rotary UAV” during a departure. (2)

In the last 3 months of 2016, the FAA listed 399 sightings as “hazardous/ or unauthorized
activities.

The FAA’s overall vision is to allow drones to operate into the National Air Space, side-by-side
with manned aircraft, as opposed to prohibiting this technology. This will only occur if there is
cooperation between industry, professional consultants, the private sector as operators, federal
state and local agencies, political subdivisions, and the academic world.

The FAA “UAS Center of Excellence” (COE) has created an organization, the Alliance for
System Safety of UAS through Research Excellence (ASSURE) which is a global think tank of 23
of the world’s leading research institutions working with thirteen universities and over one
hundred leading industry and government partners, to focus on research, education and training
in areas critical to safe and successful integration of drones into the nation’s airspace.

ASSURE…features expertise across a broad spectrum of research areas including:

 Air traffic control interoperability


 UAS airport ground operations, control and communications
 Detect and avoid
 Human factors
 UAS noise reduction
 Wake signatures
 Unmanned aircraft pilot training and certification
 Altitude operations safety
 Spectrum management
 UAS traffic management

Their mission is to provide the FAA the research they need to quickly, safely and efficiently
integrate unmanned aerial systems into our National Airspace System with minimal changes to
our current system.

The ASSURE vision is to help the Unmanned Aerial System market grow into its multi-billion
dollar market potential by conducting research that quickly, safely and effectively get UAS
flying alongside manned aircraft around the world. (3)

Portions not credited © Sempco Surveying, Inc 2017


Page 117 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

This graphic shows the location of these partners. White Papers are published with results of the
studies and recommendations for FAA review and/or approval. A copy of the ASSURE 2016
Annual report is attached and an electronic link is provided in the reference section. (4)

(5)

Two major issues are BVLOS, Beyond Visual Line of Sight, and flights over people and
structures. Privacy issues occur when flying over parks or neighborhoods. Safety issues surround
flights over highways and anywhere vehicular traffic is present. Data security and management,
adequate maintenance standards, human factors, detection near airports or special events, risk
assessments, and public acceptance and trust are other issues being studied.

Portions not credited © Sempco Surveying, Inc 2017


Page 118 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

FAA Airspace

Airspace is a dynamic issue that needs to be understood to operate a UAV. Airspace is divided into 7
different categories. A through G, with A being that area above 18,000 feet and G being the area from the
ground up to either 700’ or 1200’. The graphic would look like this:

(6)

Generally, a commercial drone can operate from the ground up to 400 feet above ground level. If the
drone is not within 5 miles of an airport, or within a no-fly zone, and if f the FAA’s other restrictions are
followed, a drone may be flown for commercial purposes without contacting anyone. If the drone is
within 5 miles of an airport, the FAA requires the airport to be notified.

The rules for UAS flights are, again:

Must keep the aircraft in sight (visual line-of-sight)


Must fly under 400 feet
Must fly during the day
Must fly at or below 100 mph
Must yield right of way to manned aircraft
Must NOT fly over people
Must NOT fly from a moving vehicle

There is an exemption process if you need a waiver from the general rules.

The FAA has an app for smartphones called B4UFLY, an “…easy-to-use smartphone app that helps
unmanned aircraft operators determine whether there are any restrictions or requirements in effect at the
location where they want to fly.” (7a)

The FAA also provides a UAS data delivery site which provides shapefiles and maps of the National
Airspace of interest to drone operators. (7b)

Portions not credited © Sempco Surveying, Inc 2017


Page 119 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

Aeronautical Charts

The FAA publishes Sectional Aeronautical Charts which are the primary navigational reference medium
used by pilots of manned and unmanned aerial vehicles. They provide essential information for
navigation to and from airports, controlled space, restricted areas, obstructions and related data. (8)

The airspace in the DFW metroplex is very complex. Part of the FAA Remote Pilot Exam covers reading
these charts and understanding the airports shown, their airspace and flight restrictions, locations of
various hazards and special events status.

This section of the DFW chart shows a number of airports, airport towers and landing strips, Class B, C,
D & E airspace, cell towers, a variety of terrain and manmade obstructions, temporary restrictions,
weather radio frequencies and special flight patterns.

(9a)

The UAS pilot needs to understand the big picture when planning a flight. Locations of helicopter landing
pads and smaller unmanned or non-towered rural airports and knowledge of any unusual events or
emergencies should be part of the planning.

The FAA also works with Arcgis to provide local facility maps where the FAA may authorize UAS
operations without additional safety analysis. They can be used for informational purposes in requesting
waivers.

Portions not credited © Sempco Surveying, Inc 2017


Page 120 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

Applications for Drones

Applications are widespread. The professional engineer needs to acquire reliable data for proper design.
Using a fixed wing or quadcopter, one can obtain aerial images or LIDAR scans of areas of interest. What
once took a high altitude aerial flight can now be accomplished with a drone flight at a couple of hundred
feet high.

This application is of use in route design as well as in substation design. The concept is relatively simple.
Fly over a site at a certain altitude with a camera or LIDAR scanner, position the lens at a certain angle,
and program the software for overlap of photos, flying in a grid or crisscross pattern. The drone software
makes the actual flight semi-automatic.

With cameras, specialized software will stitch the photos together and convert the pixels to 3D scalable
points, providing a TIN or triangulated irregular network from which a contour map can be generated.
Connect the dots and you have your planimetric side of things. Download into a CAD drawing and you
can inverse between points or scale as necessary. With ground based control points, you will obtain a
georeferenced control diagram which can readily be used for design purposes.

LIDAR scanners, can penetrate ground cover as well as canopies from trees. Post processing software
will generate contours or planimetric drawings.

Utilizing infra-red cameras, drones can be used for inspection by capturing “hot spots” on transmission
lines or in substations. Various components of the electrical systems can be viewed in real time with
video flyovers.

This technology, coupling a drone with a camera set for single photo or video, or with a LIDAR scanner
with a GPS antenna, is readily adaptable for gathering data for substation rebuilds, for additions,
inspections, repair, for generating as-built surveys and for security.

The same technology works well for route design, gathering data for greenfield planning, vegetation
management, inspections, discovering or documenting encroachments or problem areas, emergency
repair, and gathering specific data for re-routing or replacement purposes.

One can conduct circular flights around towers, take shots from a nadir or oblique or 90-degree positions,
shoot video, conduct infra-red inspections for locating hot spots or potential failure areas. Image pattern
or CAD drawing overlay can be used to compare design with as-built conditions.

The drone industry is expanding on all fronts. Numerous companies provide turnkey solutions, and will
construct a drone with matching cameras, lenses and software customized for an individual need. Many
companies will rent drones, and others provide training and logistical support.

Portions not credited © Sempco Surveying, Inc 2017


Page 121 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

Key Elements of a UAS Program

Plan of Action-A plan to determine what the needs are, what the solutions are, establish financial costs,
estimate administrative and/or training hours, and establish goals to best achieve positive results.

Leadership-An individual or group to oversee the program and understand the formational needs,
structure, costs and development of the plan, as well as understand the overall regulations. Should also
track issues and revisions to rules at a local, state and federal level.

Structure-Determine how many individuals are needed for goals to be met. A UAS certified remote pilot
is required to be physically on site and part of the team. A visual observer is required whose sole task is
to focus on the drone path and watch for other aircraft, obstacles and anything that might affect the drone
flight. You need a person at the controls who understands the flight path, hardware and software and will
actually operate the flight controller. Field survey crew may be necessary to set ground control.

Operations Manual-Develop a manual to illustrate all the aspects of the drone program.

Safety Program-Part of the Operations Manual, and should include daily briefings as well as post-flight
analysis.

Insurance-Liability at the million-dollar range is common, plus a “hull” rider if the drone is to be covered.

Training Program-This should include FAA Certification as a remote pilot as well as training for all
members of the crew. Each crew member should have specific duties with safety as a priority.

Maintenance Manual-In addition to the manufacturer recommendations, this should include specific
additional steps for keeping all parts of the drone system in exceptional working order. Logs for battery
life and charging dates are necessary as well as an inspection calendar or Pilots Logbook to track flight
hours, intervals for cleaning, maintenance and repair.

Aircraft-Based on the perceived application, budget, and research. Fixed wing or rotary copter, number
and size of batteries, payload, length of flight, transport and storage should be considered.

Camera-Determine the character of the deliverable (photos, video, point cloud, chart), select a camera and
lens. Focal length and number of megapixels are important. Choose a matching gimbal package for
attaching to the drone. The entire package shall be less than 55 pounds.

Software-Determine what is compatible with the camera and what the flight software is included. You can
have multiple software packages operating the drone flight itself, the camera or LIDAR scanner. Flight
software includes establishing a grid pattern to cover the area at a certain elevation, the overlap of photos,
and points of beginning and ending for the flight.

Personnel-Number of field teams, number of crew members on each team. Office postprocessing as well
as administrative needs and ongoing inspection, maintenance and repair personnel.

Marketing-A plan and personnel to provide services to existing clients as well as obtain additional ones.

Portions not credited © Sempco Surveying, Inc 2017


Page 122 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

Types of Drones

There are two types of drones in use today, fixed wing and quadcopter. This paper will focus on
quadcopters as they provide more maneuverability when flying a crisscross or grid pattern. The
quadcopters of interest must have enough stability and payload capability to carry a good camera
or LIDAR scanner. All types listed are trademark proprietary brand Names.

The biggest drone manufacturer is DJI based in China. The top lines are the industrial Matrice
Pro, Dji Phantom and Dji Inspire Series.

Dji Matrice 600 Pro-20 lbs; Dji Phantom 4 Pro-4 lbs, Dji Inspire 2 -4 lbs,

A very good comparison chart is available from the heliguy.com website (10)

Parrott, based in France, has a package available called their Bebop Series. It uses Pix4D software and
provides 3D modeling. (11)
Parrot also owns the SenseFly brand, which offers the eBee fixed wing and albris rotor drone and
software packages. The Albris system has a triple view head with HD video, 38MP still, and thermal
cameras A comparison of the four eBee and single albris systems is available from their website. (12)

Parrott BeBop Pro-1 lb SenseFly Albris-1 lb

In 2015, Yuneec, based in China started a partnership with Intel after a sixty million dollar
investment and announced another partnership that same year with Best Buy. (13)
Their Typhoon Series provides a basis for 3D modeling. The H520 is currently in production. (14)
Yuneec 920 Plus 11 lbs Yuneec H520 ? lbs

Cameras and LIDAR Scanners

Portions not credited © Sempco Surveying, Inc 2017


Page 123 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

Cameras & LIDAR Scanners

As DJI is the biggest seller of drones, they have an extensive gimbal/camera configuration.

ZENMUSE Z15-A7 Gimbal; ZENMUSE Z30 Camera Ronin MX Gimbal


Sony Camera

Gimbals are the custom connections that mount the camera to the dron e.
Hasselbad, using the Ronin gimbal and Zenmuse, with its own gimbal are compatible with the
Matrice Pro lines. The Ronin MX Gimbal is designed for both the air and ground. (15)

Hassleblad Camera, 100 mp

For photographic quality purposes, the 16+ megapixel cameras


would be preferred. Many drones come complete with camera
mounted on custom gimbals or as part of the drone framework.

For LIDAR scanning the Riegel Line offers many choices. An IMU (Inertial Measurement Unit) needs to
be attached to the LIDAR Unit and an external GPS antenna, dedicated to the LIDAR package, is also
required. (16)

YellowScan provides a scanner for use with the DJI Matrice 600 among others. (17)

Infrared cameras are used for inspections for locating hot spots. Many companies offer turnkey
solutions. Flir offers several cameras for that purpose. (18)

Riegl VUX-1 LIDAR YellowScan LIDAR Flir Infra-red

Portions not credited © Sempco Surveying, Inc 2017


Page 124 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

Software

Pix4D Mapper Pro © – Photogammetry software for professional drone based mapping, purely from
images. Drone images are translated into x,y,z points with highly precise, georeferenced 2D maps and 3D
models as a result. They’re customizable, timely, and complement a wide range of applications and
software. (19)

Advantages:

 Intuitive
 Ease of Use
 Interoperability of File Types
 Quick Export of Contours/Surfaces
 3D Models
 Point Cloud
 Flexible Licensing
 Video Flythrough
 Easy Quality Control/Data Check

A link to the feature list for the Pix4D Mapper is provided in the references (20)

DatuSurvey™ turns drone and camera imagery into accurate, geo-referenced 2D maps and 3D models,
saving the need for expensive and risky field work and expediting deliveries. This 3D mapping software
features a survey-grade accuracy and an intuitive workflow, designed especially for land surveyors and
geospatial professionals. DatuSurvey™ multiple outputs include: orthophoto, projection on 2D planes,
volume calculation, point cloud, 3D texture and mesh model and more. (21)

Advantages:

 Easy to Use
 Fast Processing
 Point Cloud
 Epipolar Line projection for quick and accurate point creation
 Survey focused workflow
 Export Polylines and Points to DXF

Photomodeler © The PhotoModeler Software extracts 3D measurements and models from photographs
taken with an ordinary camera. A cost-effective way for accurate 3D scanning, measurement, surveying
and reality capture. (22)

Sensefly © – bundles with eBee © and albris © drones for seamless flight planning, capturing of images
and generation of data and maps ; final report/deliverable creation in third-party software. (23)

Dronedeploy © - A Software Platform for Drone Mapping; Capture imagery, process maps & 3D
models, and interpret data (24)

Portions not credited © Sempco Surveying, Inc 2017


Page 125 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

Conclusions

Drones are here to stay and will become an important tool in the acquisition of data. Use of UAV systems
allow an engineer to gather data for a variety of uses across a variety of disciplines. To be practical, the
design of a UAV system should be optimized so that each need is addressed. A drone set up for LIDAR
will need an additional GPS antenna permanently attached, in addition to the GPS antennas the drone uses
for location purposes. A drone dedicated for photography could be substantially lighter than one used for
LIDAR data gathering purposes.

A variety of cameras, still and/or infra-red, would provide flexibility in different applications. Purchasing
separate drones with appropriate gimbals or connecting braces for each system would allow versatility in
data collection.

Software is chosen to provide data processing as appropriate for each project and deliverables can match
the engineering or reporting needs.

The UAV technology, the advances in design and the practical applications are constantly changing as are
the regulations and social concerns. Safety is paramount, as is the protection of privacy. With a thorough
understanding of those issues, the knowledge of the elements in a drone program, and a good
understanding of what kind of applications and resources are available, an engineer can make best use of
this technology in theory and practice.

It is now practical to gather data for transmission route engineering, substation design, create as-built
drawings, view encroachments, conduct inspections and track operational issues using UAS technology.
The engineer or design professional has numerous opportunities to acquire this data. Options exist to
either retain a consultant that provides a UAS surveying service or create an in-house service.

There are several national and international organizations devoted to UAS theory, application and
practice, among them are:

AUVSI Association for Unmanned Vehicle Systems International provides


opportunities to network and track and address the emerging issues. (25)

AOPA Aircraft Owners and Pilots Association originally established for manned
flight, now has a drone pilot membership option, tracks safety,
regulations and similar issues. (26)

Know Before You Fly Organization between AUVSI and Academy of Model Aeronautics in
partnership with FAA as an educational campaign to enhances safety and
responsibility. (27)

Numerous magazines and periodicals are available providing valuable discussions and information on
current events in the UAS industry; including, Inside Unmanned Systems, Unmanned Systems
Technology, Flight International, Heights (xyHt) and Military Imbedded Systems. Websites are too
numerous to list, but provide additional resources, as do on-line forums, blogs and support groups.

Portions not credited © Sempco Surveying, Inc 2017


Page 126 of 284
SEMPCO SURVEYING, INC
GPS SURVEYING LIDAR SCANNING DRONE MAPPING
Fort Worth, TX 817-926-7876
www.sempcosurveying.com

References and links

(1) FAA data faa.gov/uas

(2) Ft L. near collision Flight International Mg, 2-8 May, 2017, Pg 14

(3) ASSURE purpose assureuas.org/about.php

(4) ASSURE 2016 Report assureuas.org/annual-reports/ASSURE_2016AR.pdf

(5) ASSURE info assureuas.org/partnersStatic.php

(6) National Airspace System ftstem.com/lessons/show/521

(7) FAA Sites

a. B4UFLY faa.gov/uas/where_to_fly/b4ufly/

b. UAS Map http://uas-faa.opendata.arcgis.com/

(8) FAA-Sectional charts faa.gov/air_traffic/flight_info/aeronav/productcatalog/vfrcharts/sectional/

(9) Aeronautical Charts/maps skyvector.com/

(10) DJI UAS comparisons heliguy.com/blog/2017/02/27/dji-matrice-200-vs-m600-pro-inspire-2/

(11) Parrott Bebop parrot.com/uk/business-solutions/

(12) SenseFly Chart sensefly.com/drones/compare.html

(13) Yuneec info en.wikipedia.org/wiki/Yuneec_Internationa

(14) Yuneec UAS photos us.yuneec.com/

(15) DJI Cameras dji.com/products/imagery

(16) Riegl VUX-1 LIDAR riegl.com/products/unmanned-scanning/riegl-vux-1uav/

(17) YellowScan yellowscan.fr/#uav-based-lidar

(18) Flir Infra-red flir.com/suas/content/?id=70733

(19) Pix4d description pix4d.com/product/pix4dmapper-pro/#

(20) Pix4Dmapper-Pro features pix4d.com/wp-content/uploads/2017/05/Pix4Dmapper-Pro-V3.2-Feature-List.pdf

(21) Datumate software datumate.com/products/datusurvey/

(22) Photomodeler software photomodeler.com/index

(23) Sensefly software sensefly.com/applications/surveying

(24) Dronedeploy dronedeploy.com/

(25) Assoc. for Unmanned Vehicles auvsi.org/home

(26) Aircraft Owners and Pilots Assoc. aopa.org/go-fly/aircraft-and-ownership/drones

(27) Know Before You Fly knowbeforeyoufly.org

Portions not credited © Sempco Surveying, Inc 2017


Page 127 of 284
Drones to the Rescue!
Airline to Holly – A case study on UAV based tower inspection

Grant T. Leaverton, Vice President – Business Development


Advanced Aerial Inspection Resources, Inc. 32628 Decker Prairie Rd., Suite 1, Tomball, TX 77355 (T)
832.500.3171 (M) 817.874.7800 Email: gleaverton@aairteam.com

Minh Nguyen – Transmission Line Engineer


AEP. 212 E 6th Street, Tulsa, Ok 74012 (T) 918-599-2165 (M) 918-260-8840 Email: mhnguyen@aep.com

Introduction

By now most everyone is familiar with the newest technology buzzword that has captivated
aviation enthusiast and industry professionals alike. DRONES! DRONES! DRONES! (The term used in
professional circles is Unmanned Aircraft Systems, or UAS for short). Perhaps you may have already
purchased one for yourself or your children as a present. It is true that the consumer markets have latched
onto UAS on an incredible scale. But the reality is that this amazing technology, though still very much in
its infancy, has already begun to transform a huge number of major industries and will continue to do so
with increasing pace. It seems innovations are announced almost daily that make drones smaller, smarter
and more valuable to those of us in the dull, dirty and dangerous areas of Utility O&M. But with so many
new ideas and opportunities lingering just around the corner, it is important to understand where the
technology is today and how it can best be used currently by utility industry professionals like you.
The Airline to Holly transmission line inspection and re-conductor project is a perfect example of
how drone based aerial inspection techniques can help improve the operational capabilities of a line
owner. In this case, an older line that has been in service for a number of years on the gulf coast is due
for installation of a second circuit. A conditional assessment of the structures is essential before
construction can begin. Corrosion, cracked or damaged welds and other structural deficiencies can be
identified and made known to the project engineers prior to crews arriving on site to begin work. This
operational insight can add tremendous value to the team responsible for maintaining the line. But what
is the best method for performing the assessment when the line is situated along a busy thoroughfare
with several structures located in someone’s back yard? In addition to the “urban” nature of the line
location, there is also an International Airport, Naval Air Station, and two private airstrips all in close
proximity to the project area. This case study presentation will outline the various challenges and
solutions related to conducting drone operations in this type of congested environment, including
obtaining FAA authorization. It will also address the critical needs experienced and expressed by the line
operator and the key areas where they found the most value in deploying drone technology on their
system.

Airline to Holly Project Summary

The Airline to Holly Transmission Line is a 2.2 mile double circuit (138kv/69kv) line segment that
was built in 1969. The 138kv circuit is still in service but the 69kv circuit was recently retired and AEP is in
the process of analyzing the feasibility of installing a new 138kv circuit on the existing structures to replace

Page 128 of 284


the retired equipment. The structures consist of single monopole towers with double circuit, vertical
configuration steel davit arms and suspension insulators. The proposed equipment for new installation is
1966 ACCC/TW Lapwing and 48 counts OPGW. The full 200C Maximum Operating Temperature (MOT) is
required for the ACCC conductor. The two critical factors that need to be evaluated as part of the
feasibility analysis of this project are the modeled and evaluated clearances of the line as well as the
calculated tensions and structural integrity of the existing monopoles and davit arms. Given the corrosive
environment that the line is situated in and its age, severe corrosion is a significant concern to the project
engineer. Figures 1 and 2 show a portion of the right of way and typical structure type.

Figure 1

Figure 2

Page 129 of 284


The load analysis of the existing monopoles was performed by calculating conductor tensions of
the existing 138kv line through PLS Cad sag models and temperature calculations from the IEEE738-GIGRE
207 Batch Thermal Calculator. The inputs for the thermal calculations included meteorological data
collected during an aerial survey and electrical loading data recorded by AEP operations at the time of the
survey.
The design loads for the new ACCC circuit were analyzed at both the existing tensions as well as
the highest possible tension while still meeting NESC limits utilizing the exception stated in NESC section
261. H.1.b EXCEPTION1. Based on the old design information, it was determined that the maximum
usages for the structures under the new loads were between 68.5% and 99.5%. However, there is
insufficient information on the current condition of the towers and whether or not they are still operating
at full design capacity. For this reason, it is critical that a detailed structural health assessment be
performed on the structures to confirm the integrity of the assets. It was subsequently determined by
the AEP standards and project management teams that a UAS platform would be the best option for
performing the inspection.

Why Deploy UAS?

With many options available to AEP to perform the inspections, there were several important
factors that made the use of drones the optimal choice for this project. The first reason is that parts of
the line segment were located in boggy wetland areas where access via bucket truck was not feasible.
With a UAS and a light footprint vehicle, access to the structures was increased significantly. Likewise,
other structures were located in property owners’ back yards and again access was limited. The fact that
UAS can be remotely operated and provide access to “hard to reach” areas is a major value proposition
for the technology.
The second and third factors in the decision to use UAS were the cost and resulting inspection
deliverable. For this type of targeted inspection, UAS operations tend to be much more cost effective that
helicopters, cranes and man lifts. And in addition to the cost of inspection, the deliverable is of higher
quality than what you would be able to capture from a walking inspection or aerial survey from a manned
aircraft. With a drone, the operator can position the craft only feet away from the tower, making it
possible to detect hairline cracks or other very small but potentially catastrophic defect. The Falcon 8 UAS
shown in Figure 3, which was used for this inspection project, caries a high resolution digital payload (Sony
A6000 DSLR) which is optimal for high detail inspections.

Figure 3

Page 130 of 284


All of this can be done while the line is energized, eliminating the need for the line owner to take
a costly outage. Of course, with a visual inspection you will only be able to see surface level cracks,
corrosion, or other defects. However, when you consider the elevated cost to climb towers, take outages,
and perform other forms of NDT (Ultrasonic, Magnetic Particle, Etc.), the overall value proposition of the
UAS based visual inspection make it the optimal choice for a project such as this. There are, of course,
challenges associated with the use of UAS that need to be considered as well.

UAS Operational Challenges

There are many aspects of line maintenance that make the operation challenging. Working at
heights, working in an around high voltage equipment, environmental conditions, and in some cases
regulatory requirements an all play a role. Each have some type of impact on the related work being
performed. As previously mentioned, UAS technology can help mitigate some of those risk factors such
as performing inspections remotely from the ground, keeping the technician safely away from hazardous
or potentially life threatening situations. It can also improve the quality of inspection data and drive up
the probability of defect detection so that small but critical deficiencies are not missed by the inspector.
And finally, it allows inspection work to be performed on energized lines which eliminates the need to
take costly outages. Like anything else, however, there are tradeoffs. UAS operations do present
challenges of their own such as onerous regulatory guidelines to follow, airspace challenges, and certain
risks inherent with flying in urban and congested areas.
The use of UAS for commercial purposes is heavily regulated by the Federal Aviation Agency (FAA).
In August of 2016 the FAA released what is known as “Part 107” of the Code of Federal Regulations (CFR).
In it there are very strict guidelines on how and where you can legally operate these types of aircraft.
Some of those include flying within visual line of site (VLOS), flying during daylight hours, flying under a
maximum altitude, restricting flights over people and only flying in class G or uncontrolled airspace.
The operator must always maintain visual line of site of the aircraft during flight. This means that
the craft must remain within a certain distance of the operator where it can be seen by the naked eye.
Aids such as scopes, binoculars or cameras are not permitted to satisfy the requirement. For small aircraft
such as the Falcon 8, our operators typically maintain VLOS out to approximately 1500 feet. It also means
that you cannot fly behind structures that would obstruct line of site from either the pilot or the observer.
In certain urban areas where ground access for the operator is limited this can present challenges to the
inspection team.
Additionally, all flights must be performed during daylight hours. This condition has less of an
impact since visual inspection would become more difficult in low light situations, however it does prevent
certain IR scans that would need to be performed at night when solar reflection and loading (factors that
negatively impact IR readings) are mitigated. The Airline-Holly inspection did not utilize IR imaging so this
requirement did not impact the project but should be considered on any IR inspection that would benefit
from night time flying.
The craft must also be kept below 400 feet above ground level (AGL) in class G airspace. A caveat
does exist for tower inspection that allows for UAS flights above 400 feet AGL if the craft remains within
400 feet vertically and laterally from the tower in question. The Airline-Holly poles being inspected were
all under 100 ft AGL so there was never any concern about satisfying this requirement. However, the pole
height did play a significant factor in the airspace waiver that will be discussed later.

Page 131 of 284


Part 107 also clearly stated that UAS operations cannot be performed over people that would not
be considered essential to the work being performed. Non-essential personnel would refer to any public
bystanders, people in moving vehicles, or land owners that might happen to be in the area. Since the
Airline-Holly line segment was located in the middle of urban Corpus Christi, this proved to be a very
challenging requirement. Fortunately, the towers were positioned roughly 20 feet away from the heavily
trafficked adjacent road. This allowed the pilot to perform the inspection without having to position the
craft directly over the road and any moving vehicles that may pass by or under during flight. Had the poles
been any closer, the team would have needed to acquire a permit to block at least one lane of traffic.
From a safety perspective, for both the public and the work crew on site, it is critically important to not
fly the aircraft over any moving vehicles at any time. Figure 4 shows the clearance between the structure
and the adjacent road.

Figure 4

To prevent pedestrians from encroaching the operational area, perimeters for each flight are also
established using cones, flags, and signs to clearly cordon off the area. It is important to remember that
despite the overt warning messages presented by these perimeters, often pedestrians will simply ignore
them and procedure through. This is especially true if the perimeter blocks a bike path or sidewalk. In
areas such as this, it is essential to have a third crew member present for “crowd control” during flights.
It is not safe or even functionally possible for the pilot or inspector to keep the perimeter secure while
they are flying the aircraft and performing the inspection. Typically, as was the case for this project, flight
times are only between five to seven minutes of duration. Any pedestrian can simply wait for the craft to
land or find another route around the perimeter.
Another feature of the Airline – Holly line that required consideration was the location of poles in
and around the property of local businesses and home owners. In rural areas this is not a major issue but

Page 132 of 284


the urban nature of this project in particular made it a concern. In some cases the poles were actually
located in a home owner’s back yard.

Figure 5

Figure 6

Communicating operations and maintenance activity to affected land owners and the public in
general is always a good practice. Keeping people informed is a proactive step in minimizing surprise or
concern when it comes time to perform the work. This is especially true when the work involves new
technology that can seem menacing to certain people who are not well informed of the intended
application. You can imagine the potential surprise of looking out your window to see a drone flying
around you back yard! If you are not aware of the work being performed and why, then you might become
agitated or alarmed. That is why on projects such as this, a well-coordinated notice to land owners that
outlines the type of work being done and by whom, as well as the appropriate licenses and permits
applicable will go a long way to ensuring a smooth project. For the Airline to Holly inspection, AEP agents
sent out notifications to all affected land owners prior to the scheduled work date which identified the

Page 133 of 284


UAS inspection and why they were being performed, as well as the appropriate authorizations and
contacts in case anyone had any questions. Ultimately the project was completed smoothly and there
were no adverse interactions with the local public.
The final challenge present by this project involved the prospect of flying in controlled airspace.
Per Part 107, no flight operations are currently permitted in controlled airspace by the FAA. In urban
locations where airports may be nearby, this restriction can have a significant impact on a line owner’s
ability to conduct UAS operations. Therefore, it is critical to understand the specifics of this requirement
and the steps necessary to gain FAA approval for UAS flights conducted in airspace other than Class G. In
certain circumstances these restrictions can be waived by the FAA if the operator can prove an equivalent
level of safety will be maintained. The steps required to secure such a waiver are constantly evolving
which makes it critical for any operator to check in frequently with the FAA UAS office in Washington, DC
to understand and follow the most up to date protocol.
The Airline to Holly Transmission line is in close proximity to the Corpus Christi International
Airport, Cabaniss Field, Waldron Field, and the Corpus Christi Naval Air Station. In fact, the nearest airport
was only two nautical miles away from the Holly Substation and all three were within six nautical miles of
the line. Figure 7 below shows the proximately of the airports and the controlled airspace map that the
line segment happens to fall in.

Figure 7

Because the project area fell squarely inside Class D airspace, in order to legally inspect the
transmission line we had to secure a waiver that granted the operator authorization to fly the UAS in
controlled airspace. There are two primary ways to receive this type of authorization from the FAA. The
first is to apply for what is known as an emergency certificate of authorization (ECOA). This will only be
granted for projects where loss of life is eminent or a public emergency has been declared. Any drone
operations that would take place following a major storm event would likely fall under this category. For
non-emergency situations, such as routine inspection, the operator is required to submit a request of
waiver to the FAA UAS office. In both cases, the application must show a very detailed map of the flight
area and the proposed altitude, time, and nature of the flight. Instructions on how to properly fill out this

Page 134 of 284


application are posted on the FAA website. If it is deemed that your proposed operation will not pose a
threat to manned aircraft in the area then you will likely be granted a waiver. Depending on the proximity
of your proposed operation to airports, the FAA will limit your maximum altitude and require the UAS
pilot to call into the local Air Traffic Control tower before and after flight operations. In extreme cases
they will require the pilot to carry a CTAF radio so that they can communicate directly with the tower or
be notified of emergencies by the tower or other aircraft in the area.
For the Airline to Holly project, the FAA did not require us to carry the CTAF radio but did instruct
us to check in with Air Traffic Control before and after daily operations. They also limited our operations
to 100 feet AGL. Fortunately all of the monopoles on this line segment had above ground heights less
than 100 feet so this limitation did not inhibit the inspection in any way.
It is important to note that these waiver request are currently taking two to three months to be
processed so operators should plan accordingly. The FAA does have plans to implement more streamlined
and timely waivers and authorizations but it is still unclear as to when those new procedures will be
implemented.

Inspection Results

Once the FAA granted the airspace authorization required to fly the UAS, the field work was
scheduled for April 6th of 2017. The weather that day was well within operational limits of the UAS with
winds holding steady around 12-15mph and partly cloudy skies. For reference, the maximum wind
threshold for the Falcon 8 aircraft is around 30mph. A total of 36 monopole structures where inspected
over approximately 9 hours of inspection work. The actual flight time for the UAS totaled 4.2 hours. The
inspection was focused on all of the structural elements of the towers including the foundation, slip
splices, seam welds, arm vangs, vang welds, davit arms, and arm shaft to bracket welds.
The findings from the inspection were consistent with what we would expect on a line of this age
and in this environment. There was a noticeable level of surface corrosion on the structure itself and the
hardware. The davit arms, which had already been identified as needing replacement, showed signs of
major corrosion at the arm shaft to bracket weld. In fact, some of the corrosion was so severe that certain
arms likely would not last until the proposed construction schedule and needed to be replaced
immediately for safety reason. On the surface, the pole structure and arm vangs appeared to be in decent
condition. There was no evidence of severe corrosion and/or weld cracks that would cause the structure
to fail at the vangs. However, the internal condition of the structures remains unknown. There were
several poles with missing pole caps which would allow further moisture ingress. The hand hole ports at
the base of the pole would likely need to be opened to ensure that there was not any standing or trapped
water at the base of the pole which would cause significant corrosion and wall thickness loss in the base
section at ground line. Figures 8-11 show the varying levels of corrosion found on the arms as well as the
general condition of the arm vangs, slip splices and ground line embedment.

Page 135 of 284


Figure 8

Figure 9

Page 136 of 284


Figure 10

Figure 11

Page 137 of 284


Closing Thoughts

The final outcome of the UAS inspection for Airline to Holly has yet to be determined. The
major takeaways from the data that was collected were focused primarily on the davit arms. While it
was already decided that the arms would need to be replaced before the reconductor work could begin,
the aerial inspection confirmed that several of the arms that were currently in service needed to be
replaced immediately due to sever corrosion. Visually, the other structural components of the poles
showed no defects. There were no visible cracks present in any of the arm bent brackets, vangs, vang
welds, or slip splices. The foundations appeared to be in adequate condition as well. However, the
internal condition of the structures and potential wall thickness loss due to corrosion cannot be
determined without a more through inspection (either straight beam UT at ground line or a visual
inspection through the hand hole ports). AEP is still in the process of analyzing the data to determine
whether the monopole structures will need to be replaced in addition to the arms, or if their life can be
extended further to support the new 138kv double circuit line.
It is clear, however, that UAS as an inspection tool added significant value to the line owner in
collecting the necessary conditional and structural assessment data on the Airline to Holly monopoles.
Despite the project being in a crowded, urban environment with controlled airspace near several major
airports, the inspections were completed safely and legally with the appropriate FAA approvals. The
costs of the inspection where minimized by eliminating the need for cranes, outages and climbing.
Overall, the Airline to Holly project proved that UAS can be deployed effectively in urban environments
and ultimately add significant value to the line owner and their operations team.

Page 138 of 284


Transmission Line Drilled Pier Design,
Limiting Rotation and Creating a Balanced
Performance Criteria
By Greg C. Parent, P.E., S.E.,
Senior Engineer
Greg.Parent@Ulteig.com

Transmission, Distribution, and Communications Department

5575 DTC Parkway, Suite 200


Greenwood Village, CO 80111

Page 139 of 284


ABSTRACT: Drilled pier foundations are major structural components of self-supporting transmission line
structures. Structural failures of transmission line foundations are rare. The structural success of drilled
piers could be attributed to a number of reasons, such as a well-defined and widely accepted foundation
design criteria and design process. It could also be attributed to a tight collaboration between the
Transmission Line Engineer, Steel Pole Fabricator, Geotechnical Engineer and Foundation Engineer. Or it
could be due to overly conservative foundation designs.
It is critical that these foundations be designed to ensure adequate structural capacity. However, the design
of the pier is often controlled by how the structure performs, that is, how much the foundation rotates and
deflects. The limits on foundation rotation and deflection are commonly referred to as foundation
performance criteria. None of the regulatory committees for Transmission Line design, NESC, RUS, IEEE,
or the ASCE standards and design manuals provide recommendations for foundation performance criteria.
Due to this lack of regulation, performance criteria varies greatly throughout the industry.
Designing a foundation to an overly stringent tip deflection limit may not significantly improve the
transmission line’s overall performance but it can lead to higher foundation construction costs. The design
engineer’s foremost responsibility is to ensure the public’s safety. However, an engineer also has a duty to
determine the most cost-effective foundation design that will safely support the transmission line structure.
INTRODUCTION (CURRENT STATE OF PRACTICE)
In 2012, the Deep Foundation Institute (DFI) created a survey for utility design professionals to assess the
state of the practice for transmission structure foundation design. A number of questions in the survey were
in regard to “What performance criterion is being used to design transmission line drilled piers?” The
survey results showed large variations in both rotation limits and tip deflections limits. The survey also
showed relatively stringent tip deflection limits while also allowing relatively liberal foundation rotation
limits. This can lead to foundation tip deflection limits controlling the design of the foundation, thus
requiring deeper foundations.
This paper will show that pier rotation plays a much larger role than pier tip deflection in causing additional
pole displacement. It also provides a method to create balanced performance criteria by putting an emphasis
on limiting rotations over limiting tip deflections.
PLS-CADD MODEL DESIGN ASSUMPTIONS
It is possible in PLS-Pole to model the effect of foundation rotation and tip deflection. It is even possible
to model a rotation stiffness and deflection stiffness of the soil that surrounds the foundation or pole to
determine how the foundation or embedded portion responds under varying load cases. However, in the
experience of this author, modeling foundation rotation and deflection within PLS-Pole, is not typically
performed when modeling transmission lines. The default settings of PLS-Pole apply a point of fixity at
ground line. This default assumption simplifies the PLS-CADD analysis, but it can lead to underestimating
the pole displacement due to the fact that all drilled piers and directly embedded structures experience some
amount of rotation and tip deflection. Figure 1 illustrates the effect of foundation rotation and tip deflection
on pole displacement.

Page 140 of 284


Figure 1: Pole Displacement Due to Foundation Deflection and Rotation
CONSEQUENCES OF EXCESSIVE ROTATION AND DEFLECTION OF TRANSMISSION LINE DRILLED PIER FOUNDATIONS:
As the foundation and pole rotate and deflect, the displacement at the top of the pole is greatest. Conductors
and shield wires that are attached towards the top of the pole could have larger increases in sag than the
conductors that are attached lower on the pole. Figure 2 illustrates the effects of excessive foundation
deflection and rotation in combination with large pole displacements.

Figure 2: Consequences of Large Foundation Deflections and Rotations


Larger than anticipated pole displacement can lead to a number of problems on the transmission line,
including:
• Reduced phase to shield wire clearance
• Reduced phase to Phase clearance
• Reduced phase to Ground Clearance
• Differential tensions of ahead and back spans in adjacent structures
Designing drilled pier foundations with appropriate performance criteria is critical to limit these
consequences.
LOAD REDUCTION DUE TO POLE MOVEMENT
There is a discrepancy between the design loads for pole and foundation design and the actual loads applied
to the pole and foundation. This discrepancy occurs because the conductor tensions reduce as the pole
deflects towards the adjacent structures. When a transmission line span experiences a design load the dead-
end structure deflects towards adjacent structures, the distance between the two structures reduces slightly.

Page 141 of 284


That is, the span length reduces but the conductor length remains the same. This has the effect of increasing
sag and decreasing design tensions. These reduced loads result in the pole and foundation deflecting and
displacing less than the “constant tension” assumption would predict. However, calculating the load
reduction is quite difficult because the analysis is highly iterative and dependent on numerous
interconnected components on the system, which include:
• Adjacent structure type (Tangent, running angle or dead-end)
• Adjacent structure insulator type (Post Insulator or suspension insulator)
• Design span to adjacent structure
• Ahead and back segment length (The distance to the adjacent dead-ends)
• Adjacent structures’ pole stiffness’s
• Foundation or embedment performance
PLS-CADD can perform a Level 3 analysis which accounts for all of the above items with the exception of
foundation or embedment performance. As stated above, PLS-CADD assumes the foundation or embedded
portion exhibits zero rotation or deflection at ground line. Even with a high-powered computer a Level 3
analysis significantly increases the analysis time from a matter of seconds up to a matter of hours. In all
cases the Level 3 analysis produces results that are less conservative. In many cases, the load reduction can
be relatively small. For these reasons a Level 3 analysis is not typically performed during transmission line
design and the load reduction due to pole movement is generally not calculated. For this reason, load
reduction due to pole movement was not performed as part of this paper.
LACK OF AN INDUSTRY STANDARD FOR PERFORMANCE CRITERIA
NESC does not have performance criteria for pier foundations. The Deep Foundation Institute [DFI]
created a task force to study the: “State of the Practice for Transmission Structure Foundation Design.” The
first step in defining the state of practice was creating a survey about transmission line structure foundations.
This Survey consisted of 45 questions and was sent to utilities and utility consulting engineers. As of
October 2014, 22 responses had been received. A paper was presented at the 2015 ASCE Electrical
Transmission and Substation Structures conference with the survey results.1 Figure 3 and Figure 4 illustrate
the survey results for pier rotation and pier tip deflection limits:
Number of Respondents using
particular deflection limit

1 1 1
0.5 1 0 1.5 2
Top of Pier Rotation Limits [Deg]
Weighted Average = 1.6 deg (Total 10 Respondents)
Figure 3: DFI Survey Results on Pier Rotation 1
Number of Respondents using

2
particular deflection limit

2
1
2
1
1 1 1
1 1
0.0 0.5 1.0 1.5 2.0
3.0 2.5 3.5 4.0 4.5 5.0 5.5 6.0
Deflection Limits [in]
Weighted Average = 2.55 in (Total 14 Respondents)

Figure 4: DFI Survey Results on Tip Deflection1 above 1

Page 142 of 284


As can be seen in Figure 3 & Figure 4 there is little consistency between different respondents’ performance
criteria for drilled piers. It should also be noted that out of the 22 respondents only 14, (64%), reported
deflection limits and only 10 respondents, (45%) reported a limit on pier rotation.
One important thing to note from Figure 3 is that the most common rotation limit is also the highest rotation
limit at 2 degrees of rotation. This limit may have originated from the Electric Power Research Institute
(EPRI) funded research studies in the late 1970’s and early 1980’s, in which full scale drilled piers were
tested. One conclusion of these tests was:
“2 degrees of rotation at the top of the shaft appears to be a reasonable way of defining
the ultimate lateral capacity of the test shafts.” 2
However, is it reasonable to have a performance limit on rotation occurring at the same point when the soil
around the pier is loaded to its ultimate capacity and experiences a highly non-linear load-deformation
relationship? Shouldn’t the performance rotation limit be held to a more stringent number?
Figure 4 shows that many respondents to the DFI survey have a range on tip deflection limits. It is not clear
if this range of values is due to the deflection limit being a percentage of pier diameter, or if there are
different deflection limits for different structure types, i.e. tangent, light angle, medium angle and heavy
angle.
DIFFERENT PERFORMANCE CRITERIA FOR DIFFERENT STRUCTURE TYPES
The consequences of additional pole movement due to foundation rotation and tip deflection vary according
to the structure type. The larger the line angle the greater the consequence of foundation rotation and tip
deflection. For this reason, different performance criteria can be assigned to different structure types.
Figure 5 illustrates the relationship of structure type to foundation performance criteria.

Figure 5: Different Foundation Performance Criteria for Different Structure Types

This paper will focus on the foundation performance criteria of dead-end structures since they exhibit the
highest consequence of large foundation rotations and tip defections. Some very good papers have been
written regarding different foundation performance criteria for different structure types. One that this
author highly recommends is “Recommendations for Steel Pole and Drilled Shaft Deflection Criteria Based
on a Parametric Study of a 138kV Double Circuit Transmission Line”. 3
LOAD CASES ANALYZED TO MEET PERFORMANCE CRITERIA

Table 1: DFI Survey Results on Load Type for Checking Performance Criteria 1

Page 143 of 284


Table 1, above, shows the “Load Types” that are analyzed to meet the performance criteria. This data was
also collected as part of the DFI survey. The term “Factored Load” was not clearly defined. That is,
“Factored Loads” could be Load Case 250B with the NESC Load Factors listed in NESC Table 253-1 or it
could be 250C & 250D with a 1.1 load factor, as RUS Bulletin 1724E-200 recommends in RUS Table 11-
7. The survey also did not define what constitutes a “Service Load”. Is a service load just a load case with
load factors of 1.0? Or is a service load an owner-specified operational load case?
In many non-coastal regions that are in NESC 250B Medium or Heavy regions, Load Case NESC 250B,
with load factors, often results in the largest foundation loads. As can be seen in Table 1, the most common
load type analyzed to meet performance criteria is “Factored Loads.” It is likely that the factored load case
is NESC 250B with load factors. Therefore, the main purpose of this paper is to provide a method to create
a reasonable and balanced performance criterion for the factored load cases which often control the pier
design.
COMMON TRANSMISSION LINE DRILLED PIER DESIGN SOFTWARE
The lateral geotechnical capacity of a drilled pier design can be determined using a variety of software
programs. The DFI survey, noted above, also asked what software programs were being used to design
drilled piers. Table 2 shows the different drilled pier design software programs that were used by the
respondents. The percentages shown in Table 2 strongly suggest that many of the respondents had access
to and design with multiple design programs.

Table 2: DFI Survey Results on Deep Foundation Software Used 1

Table 2, the two most used design software packages were:


• FAD TOOLS – MFAD– Managed by DiGioia Gray & Associates
• Lpile – by Ensoft
The two programs above can calculate how a drilled pier will deflect and rotate under an applied load.
However, the programs above use different assumptions and design methodologies to determine the piers’
geotechnical moment capacity and how the pier will perform.
This paper is not intended to promote one drilled pier foundation program over another. Both programs are
valid for different conditions. However, the recommendations for performance criteria that are stated in
this paper follow the same design assumptions that are used in the FAD TOOLS - MFAD analysis. For
this reason, it is important to state the design assumptions for both MFAD and Lpile and how the
assumptions differ.
MFAD

Figure 6: MFAD - Components of Lateral Resistance4 Figure 7: MFAD – Pier Deflection vs. Depth

Page 144 of 284


As can be seen in Figure 6, MFAD calculates total lateral capacity from four lateral resistance
components, including:
• p-y curves
• Base tip shear
• Base tip rotational reaction
• Shear resistance to pier rotation
For drilled piers with L/D ratios less than 10, these additional forms of resistance can be significant.
Another MFAD design assumption is that the pier experiences rigid body rotation. As illustrated in
Figure 6. This means there is constant rotation over the length of the pier. This ‘Rigid Body” assumption
is critical to MFAD program. Full-scale tests of drilled piers have shown that this assumption is valid for
piers with small L/D ratios. Please refer to Figure 10 for more information about these test results.

Lpile

Figure 8: Lpile - Components of Lateral Resistance Figure 9: Lpile - Pier Deflection vs. Depth

As can be seen in Figure 8, Lpile assumes that only p-y curves provide lateral resistance. For piers with
L/D ratios greater than 10, p-y curves make up the majority of the lateral capacity. Another Lpile
assumption is that the pier does not exhibit rigid body rotation. Lpile assumes that the concrete will flex
and crack when the applied moment exceeds the cracking moment capacity of the pier, as illustrated in
Figure 8 and Figure 9. This assumption creates a far more complex design model that requires numerous
iterations to converge upon a solution. This assumption results in pier rotation varying with pier depth.
This assumption can result in larger pier tip deflections and rotations than MFAD’s rigid body rotation
design assumption.
RIGID BODY ROTATION – FULL-SCALE TEST RESULTS
One paper that discusses in detail the Rigid Body
Rotation full scale test results is the Evaluation of
Performance Criteria for Short Laterally Loaded
Drilled Shafts.2 Much of the next paragraph refers
to the data presented in this paper. In the early
1980’s EPRI funded research to study laterally
loaded shaft design in the utility industry (Davison,
1982). This research program included field tests
to develop a database of high-quality full-scale
foundation tests in various soil conditions. 14
drilled piers of varying sizes were tested in a variety
of soil conditions. The L/D ratios for these 14 piers
ranged from 2.7 to 4.4.
Figure 10: Typical Shaft Deflected Shape

Page 145 of 284


The data collected from these 14 full-scale tests was supplemented with existing data from fifteen full-scale
laterally loaded drilled shaft tests conducted by various utilities. In ten of the EPRI test piers, slope
inclinometers were installed along the full length of the pier to evaluate how the loaded pier rotates under
load. Figure 10 displays a typical deflected shape below grade, indicating that the shaft behaves essentially
as a rigid body. The other test shafts also displayed near constant rotation over the embedded length.

From this full scale test data, the assumption appears valid that drilled piers with relatively small L/D ratios
display rigid body rotation under lateral loading.

DIFFERENT TYPES OF PERFORMANCE CRITERIA


There are four different types of performance criteria that can be calculated for a laterally loaded pier.
They include:
• Total tip deflection
• Total rotation
• Non-recoverable tip deflection
• Non-recoverable rotation
Figure 11 and Figure 12 illustrate these different types of performance criteria.

Figure 11: Total Deflection and Rotation Figure 12: Non-Recoverable Deflection and Rotation
EXAMPLE OF UNBALANCED PERFORMANCE CRITERIA
The DFI survey results, (See Figure 3 and Figure 4) show that limits on foundation tip deflection were more
common than limits on foundation rotation. Also, in the experience of the author, many utilities’
performance criteria specify relatively stringent limits on pier deflections as compared to the liberal limits
for pier rotation.
For example, two utilities familiar to this author specify a maximum tip deflection limit of 3 inches and a
maximum tip rotation of 1.5 degrees. It is worth noting that these utilities do not specify any limits on non-
recoverable rotation or deflection. It is also worth noting that total tip deflection limit of 3 inches and a
maximum tip rotation of 1.5 degrees is fairly close to the weighted average values for tip deflection and
rotation from the DFI survey. The DFI survey’s weighted average for tip deflection limit is 2.55 inches
and the weighted average tip rotation limit is 1.6 degrees. MFAD analysis assumes that a loaded pier
experiences rigid body rotation, as full-scale tests have shown. Please refer to Figure 10.
The point of rotation is very much dependent on the soil profile and the lateral capacity of the different
layers of the soil. The point of rotation usually occurs at a depth between ½ and ¾ of the embedment length
of the pier. For this example, it will be assumed that the point of rotation occurs at 2/3 of the embedment
length of the pier. If a typical pier has an 8ft diameter, the 3 inch tip deflection limit can be converted to a
percentage of the 8ft pier diameter.

Page 146 of 284


3
= = 3.1%
96
In other words, the tip deflection limit for this size
pier is 3.1% of the pier’s diameter, (3.1%)*D = 3
inch. By converting the deflection of the pier to a
percentage of the pier’s diameter, simple
trigonometry can be used to determine what L/D
ratio will cause the tip deflection limit and rotation
limit to occur simultaneously. Figure 13 illustrates
this example.
3.1% ∗
sin 1.5 =
2
3
Or
3.1%
= = 1.79
2
sin 1.5
3
Figure 13: Deflection vs. Rotation of an 8 ft Diameter Pier Equation 1: L/D Ratio from a 3" Tip Deflection and 1.5Deg
Rotation Limit

Table 3: L/D Ratios for 3in Tip Deflection and 1.5deg Rotation that Yield a Balanced Performance Criteria
In the experience of this author, the majority of foundations typically have L/D ratios between 3 and 5. The
required L/D ratios are highly dependent on the size of the transmission line structure that the foundation
is supporting and the lateral soil capacities which surround the pier. If the soil conditions are extremely
good or extremely poor, then the pier could have an L/D ratio outside of the 3 to 5 range but, in the
experience of this author, this is rare.
In Table 3 only the 4 foot diameter pier has an L/D ratio within this “3-5” range where either the rotation
or the deflection limit could be exceeded. Also shown in the bottom row of Table 3 is the pier length in
which a “balanced” performance criteria could occur. As can be seen, the length of the pier remains
constant at 14’-4” for all pier diameters. This is due to the single 3 inch tip deflection limit for all sizes of
pier diameter. It is highly unlikely to have an 8ft or greater diameter pier with only 14’-4” of pier length.
Table 3 shows that the performance criteria of 3 inch tip deflection and 1.5 degrees rotation has a relatively
stringent deflection limit and a relatively liberal rotation limit. This example of stringent tip deflection
limits and liberal rotation limits is not uncommon.
Figure 4 shows from the DFI survey the respondent’s weighted average for foundation tip deflection is 2.55
inches and Figure 3 shows that the weighted average for foundation rotation is 1.6 degrees. These small
deflection limits often result in pier tip deflection controlling the design of drilled piers.

EXAMPLE OF BALANCED PERFORMANCE CRITERIA


Instead of having a relatively large limit on pier rotation and a relatively small limit on pier tip deflection,
wouldn’t it be more reasonable to determine both a reasonable pier rotation limit and a tip deflection limit

Page 147 of 284


where either could potentially control the design of the pier? Pier tip deflections and rotations are linked
and a tight limit on one will cause an unintended limit on the other.
A technical paper the author highly recommends is: “Evaluation of Performance Criteria for Short
Laterally Loaded Drilled Shafts”.2 This paper goes into significant detail about the MFAD program, full-
scale tests, calibration of the MFAD program and provides recommendations for upper limits of pier
rotation and deflection.
“Based on both the test data and the MFAD 5.0 estimates, 1 degree is a reasonable value
for the upper limit of top of shaft rotation. On the average, this limit will keep shaft
movement within the elastic deflection during loading and produce deflection of about
3.5% to 4% of the shaft diameter.”2
In the next example, the performance criteria will set the limit on pier rotation to 1 degree and the foundation
tip deflection to 4 percent of the shaft diameter, as recommended in the paper above. As stated earlier, the
foundation’s rotation and tip deflection can result in additional pole displacements that are not accounted
for in the PLS-CADD analysis.

Figure 14 displays the pole displacement components from both foundation tip deflection and foundation
rotation. Four locations along the pole were selected to calculate the additional pole displacement from
foundation movement. The four locations represent the shield wire attachment point at the top of the pole
and the top, middle and bottom conductor attachment points on the pole. As examined above, this next
example will also analyze an 8-foot diameter pier. The limit for pier rotation is 1 degree and the tip
deflection is 4 percent of the pier diameter (4%*96 inches= 3.84 inches).
It is important to note that the 1 degree rotation limit
is significantly more stringent than the 1.6 degrees
weighted average limit shown in Figure 3 and the
3.84 inch deflection limit is far more liberal than the
2.55 inch weighted average limit shown in Figure
4. Using the same process as was stated in Figure
13 and Table 3 we can determine if this
performance criterion will be balanced in regard to
tip deflections and rotations. Once again, assuming
the point of rotation occurs at 2/3 of the embedment
depth then:
4%
= = 3.44
2
sin 1.0 $%
3

Figure 14: Additional Pole Displacement due to Foundation Tip Equation 2: L/D Ratio from a 4%*(D) Tip
Deflection and Rotation Deflection and 1deg Rotation Limit

Table 4: Foundation Tip Deflection & Foundation Rotation's effect on Displacement of a Pole.

Page 148 of 284


As can be seen, the 1-degree rotation limit and 4%*D deflection limit will be balanced when the L/D ratio
is around 3.5. The actual L/D ratio will be dependent on the soil profile and the different soil layers’
geotechnical lateral capacities but in the experience of this author, an L/D ratio of 3.5 is reasonable. Which
performance criteria will control the design will vary depending on the soils encountered and where the
point of rotation occurs below grade.
As can be seen in Figure 14 and Table 4, the additional pole displacement due to foundation tip deflections
is constant at 3.8 inches for all heights of the pole. The additional pole displacement due to foundation
rotation increases linearly with height above the top of the foundation. At 90 feet the additional pole
displacement due to foundation rotation consists of 83 percent of the total pole displacement due to
foundation movement. At only 50 feet, the additional pole displacement due to foundation rotation consists
of 73 percent of the pole displacement due to foundation movement. Table 4 shows that foundation rotation
has a much larger impact on additional pole displacement than foundation tip deflections.
As seen from Table 4, limiting the foundation rotation is key to limiting additional pole displacement. It is
also highly recommended to acquire geotechnical information early in the design process. Many
geotechnical firms provide desktop geotechnical reports that pull geotechnical data from private and public
databases of previously drilled borings. These desktop reports can provide highly educated estimations on
soil type, approximate layer thickness, soil layer density, soil layer cohesion or internal angle of friction
and depth to bedrock.
If a limit on foundation rotation has been selected, and if a preliminary geotechnical report can be provided,
then preliminary foundation designs can be produced that can achieve the desired limit on foundation
rotation. From these preliminary foundation designs an L/D ratio and point of rotation can be determined.
Using simple trigonometry an approximate deflection limit can be calculated that will create a balanced
performance criteria. It is recommended to normalize the deflection limits by stating the limit as a
percentage of the foundation diameter. In this way, the same deflection limit can be used for foundations
with different diameters.
NON-RECOVERABLE ROTATIONS AND TIP DEFLECTIONS
As stated previously, foundation rotation plays a much bigger role in pole displacement than foundation tip
deflection. For these reasons, a very important performance criterion is the limit for non-recoverable
rotation.
The likelihood of a truck, farm equipment, train, or sailboat passing underneath the transmission line at the
very moment when the transmission line is subjected to its MAXIMUM design load is relatively unlikely.
It is far more likely that the truck or farm equipment will pass under the transmission line days later when
the weather has improved and the transmission line is no longer subjected to a high design load.
However, now that the foundation has been fully loaded, it now has permanent, “non-recoverable” rotations
and deflections which can reduce phase to ground clearances.
Typically, the most common way of setting a non-recoverable rotation or deflection limit is to take a
percentage of the total rotation/deflection limits. The most common percentage this author has seen is to
set the non-recoverable rotation/deflection limit to 50 percent of the total rotation/deflection limit.
However, as stated above in “Evaluation of Performance Criteria for Short Laterally Loaded Drilled
Shafts” with the total rotation limited to only 1 degree;
“…this limit will keep shaft movement within the elastic deflection during loading…” 2
With the pier loaded within the elastic range, the majority of the total rotation/deflection will be recoverable.
Setting the non-recoverable rotation/deflection limit to 50 percent of the total rotation/deflection limit may
be too liberal and will end up never controlling the design of the pier. In the experience of the author,
setting the non-recoverable rotation/deflection limits to 33 percent of the total rotation/deflection limits is
generally a more appropriate limit when the total tip rotation is limited to only 1 degree.

Page 149 of 284


CONCLUSIONS
This paper focuses on the performance criteria for drilled pier foundations that support transmission line
structures. This paper demonstrates a lack of consistency in the performance criteria for drilled pier
foundations between designers, consultants and utilities. This paper discusses a number of the issues with
the current state of foundation design. The following conclusions serve as an outline on how to develop
balanced performance criteria for foundation design:
• Industry standards for design criteria of drilled pier foundations varies widely.
• Heavy angle structures are the most susceptible to negative consequences of large foundation
rotation and tip defection.
• Different structure types should be designed with different foundation performance criteria.
• Many utilities’ foundation performance criteria exhibit a very stringent limit on foundation tip
deflection and a relatively liberal limit on foundation rotation. This results in the foundation
tip deflection limit controlling the design of the foundations.
• The foundation rotation limit accounts for the majority of the additional pole displacement due
to foundation movement.
• The total foundation rotation limit should not exceed 1 degree under the largest design load.
• The limit on foundation tip deflection should be normalized in terms of pier diameter.
(Deflection Limit = % x Pier Diameter)
• It is highly recommended to acquire desktop geotechnical reports to perform preliminary
foundation designs and determine preliminary L/D ratios and the location of the point of
rotation.
• A balanced foundation tip deflection limit can be calculated using trigonometry knowing the
rotation limit, L/D ratio and the location of the point of rotation.
• If the total rotation limit is 1 degree or less, this will keep the shaft movement within the elastic
range. This will result in smaller non-recoverable rotations and deflections. The ratio of non-
Recoverable to total rotations and deflections can be generally reduced from the standard 50%
to 33%.

REFERENCES
1
Electrical Transmission and Substation Structures Conference SEI & ASCE (2015), Study of Electric
Transmission Line Deep Foundation Design. P.M. Kandaris, P.E., and Davidow, P.E.
2
GeoCongress 2012 ASCE 2012, Evaluation of Performance Criteria for Short Laterally Loaded Drilled
Shafts. P.M. Kandaris, P.E., A.M. DiGioia, Jr. Ph.D., P.E., and Z. J. Heim, P.E.
3
Electrical Transmission and Substation Structures Conference SEI & ASCE (2015), Recommendations for
Steel Pole and Drilled Shaft Deflection Criteria Based on a Parametric Study of a 138kV Double Circuit
Transmission Line. Adam G. Bowland, Ph.D., P.E.; Paul G. Class, P.E.; A.M. DiGioia, Jr. Ph.D., P.E
4
IEEE Std 691-2001 – IEEE Guide for Transmission Structure Foundation Design and Testing,
Transmission and Distribution Committee of the IEEE Power Engineering Society, December 6th, 2000.

Page 150 of 284


JASON SOUCHAK
Application Engineer | Megger

Deploying a New Fault Location


Strategy in a Large Utility- A Case Study

Page 151 of 284


Abstract
This paper will discuss the process used by a large utility to transition from a specialized core group of
fault locating personnel to a larger, more general group of personnel. During this transition, the size,
type, and capabilities of the fault location equipment needed to be considered to find the optimal
solution. Since a much larger group of personnel would be involved in fault location activities, the
training requirements, and the ease of use of the equipment was also a driving factor in the process.
This paper will discuss the costs, benefits, and challenges associated with this transition.

Introduction
Commonwealth Edison (ComEd) is large electric utility in Illinois, serving approximately 3.8 million
people, and encompassing approximately 12,000 square miles service area. This utility initiated a
project to update and improve the fault location process. The existing process relied on two or more
separate groups to repair any faulted cables.

First, the Distribution Testing (DT) group would be dispatched to locate the fault. This typically 2 person
crew would identify the faulted phase, identify the faulted section of cable, and finally pinpoint the
location of the fault on the isolated section of cable. Once the section was identified, this crew would
depart, and the next group would take over.

One of three groups would take over from the DT group. The Distribution Overhead (DO), Distribution
Underground (DU), or a contractor group would be assigned to repair the faulted cable. This work was
to be done at an unspecified future date, except in emergency conditions. The problems encountered
with this system of working are described below.

The new method of working will be to dispatch a single crew that is responsible to identify the faulted
phase, identify the faulted section, pinpoint the fault, repair the fault, and ultimately return the cable to
service. This method of working has some initial costs involved, but also substantial gains. These will be
described below.

Existing System
Figure 1 shows a block diagram of the existing process. This complicated process involved multiple
different crews and required handing off responsibility between them. The general workflow of the
existing system is described in Figure 1. In this system, the DT crew was a highly skilled group of fault
locators, consisting of 48 people equipped with truck mount fault location equipment ranging from 1600
to 3200 Joules, and up to 36 kV; sufficient to locate almost any fault.

Page 152 of 284


Figure 1 - Block diagram of the existing process. Highlighted areas were removed in the new process.

In this system, multiple crews were required to compete the work. First, Distribution Testing (DT) would
locate faults in the URD system with a 2-person crew. Once the fault was located, they would depart
the scene and turn responsibility for repair over to the Distribution Overhead (DO), Distribution
Underground (DU), or outside contractor crews. One of these crews would be dispatched to the fault
location at a later date. If it was an emergency, or important circuit, they would be dispatched quickly.
But for less critical faults, there may be some delay between DT locating the fault and a crew arriving to
repair the fault.

Occasionally, this delay would result in the repair crew being unable to locate the fault and they would
require DT to return to the fault and locate again. This duplicated work that was already done, and
prevented the DT crews from finding other, newer faults, and generally contributed to inefficiencies in
the process.

If the crew was able to successfully repair the fault, sometimes they would have a questionable result on
the pre-energization testing. In this case, the DT crew would again need to return to the scene to
perform a more thorough test and determine if the cable can be returned to service. This would again
increase inefficiency as the DT crew would need to return to a scene they already completed their work
at.

The five highlighted segments in Figure 1 were eliminated in the new system. This reduced the amount
of crews to one, and streamlined the entire process.

New System
Figure 2 shows a block diagram of the new process adopted by ComEd. Under this system, one
department has responsibility for the entire outage: from fault to fix. The new system would involve
over 1000 employees in the construction group. Prior to this project, this larger group had no fault
locating equipment and no previous fault location experience. One of the design considerations for this
project was to consider the training requirements of the new fault location equipment. Equipment that
was too difficult to learn and operate would not be effective in this system.

Page 153 of 284


Figure 2 - Block diagram of the new process.

The advantages this system has over the previous system are primarily due to the idea that only one
crew has responsibility for the fault from beginning to end. There would be no need to return to the
fault location because the repair crew was unable to locate the fault. There is no transfer of
responsibility from one group to another, simplifying operations and consolidating responsibility in one
group.

The challenge of implementing this system is due to the large number of personnel that are involved.
The new system needs to accommodate personnel with various skill levels, comfort levels, and
knowledge about fault location. In order to minimize this effect, it is necessary to consider the ease of
operation of the fault location equipment, and choose only those with a simple and easy to learn
interface.

Transition
The existing system had two distinct fault location groups: City and Suburban. The city groups were
equipped with 3200 Joule fault locators, and would locate mostly on main stem circuits of approximately
20,000 feet average. The suburban crews were equipped with 1600 Joule fault locators, and would
locate mostly on URD and main stem circuit of approximately 5,000 feet. Both crews utilized truck
mounted fault location equipment.

ComEd has 21 reporting centers where line crews reported day to day. After analyzing the activity at
each reporting center, it was determined that 3 to 5 fault location systems would be needed at each
location to keep up with the amount of faults in the system. All together this would mean about 40 new
fault location systems to fully outfit the construction crews.

If 40 new systems of the same specification as the existing equipment were purchased, it would cost
approximately $4 million: 40 units at a cost of about $100,000 per unit. This is just the purchase cost of
the equipment, training costs, and additional vehicles would be in addition to this cost. A better, more
cost efficient system was needed.

Page 154 of 284


ComEd reached out to vendors and sister utilities, and discovered that they were using smaller, less
powerful, and less expensive fault location systems for URD systems. A pilot program was started,
where the crews tried out these smaller units. They found that they were highly effective, finding every
fault they were used on. In addition, the pilot program revealed that despite the lower power available,
the crews found they preferred the portability and ease of use of the small units over the existing,
larger, truck mount systems.

By equipping all the crews with the portable systems, the cost of the transition was reduced to
approximately $600,000 for 40 units, and no additional vehicles would need to be purchased. Training
costs are not included in this figure, but due to the ease of use, the training time and expenses can be
kept to a minimum.

There is always a concern when using such small and portable units that the unit will not have enough
voltage or Joules to locate the fault, and this will happen from time to time. The strategy to mitigate
this risk is to deploy progressively more powerful but fewer units strategically throughout the system
(See “Satellite System” section below).

Work within ComEd continues with this transition. Training approximately 1000 inexperienced
personnel was completed in about 3 months, with the help of the vendor. Classes were held both in the
classroom and in the field to give theoretical and practical knowledge to the crews. Currently, the
construction crews are locating approximately 90% of all faults without the assistance of the
experienced Distribution Testing group.

Future work will address the necessity and viability of large portable units, and large truck mounted
units within the overall distribution system.

Benefits/Improvements
There have been many benefits of moving to the new system. The single largest improvement was in
reducing the amount of handoffs, which resulted in faults being repaired much more quickly. Wasted
time due to redoing previously completed work and travel has been reduced as well, as crews do not
need to revisit a fault multiple times. By having fault location equipment readily available, crews can
arrive at the scene of a fault quickly, and well prepared. This is expected to reduce the overall outage
durations, and work continues in tracking this information.

The disadvantages of these small system is the limited voltage and Joules available. However, these
units also have some particular strengths over the larger equipment. One of the biggest advantages is
that there is no need to dedicate a specialized vehicle to fault location activates. These small units can
fit into a more general purpose vehicle. Also, there is little need for long cable reels, as is common with
truck mount systems, as the small units can simply be placed where they are needed. Finally, the small
units typically cost considerably less than large units, and so more units can be purchased and spread
around the system, leading to decreased response times and high availability of equipment.

Page 155 of 284


Next Steps

Satellite System
This is an example of the start of a “satellite” system for deploying fault location equipment. No one
piece of equipment is best in every situation. The small, light, and portable equipment is ideal as a first
line of defense. This equipment can be deployed for relatively little money, and can be widely and
readily available to the crews that would most need it. For example, putting a portable unit on each
underground truck ensures that no matter which crew is dispatched, they can begin fault location
activities. It also means that a crew can be dispatched directly to a fault, without returning to the
service center to pick up fault location equipment. However, the drawback of these units is their
capabilities. In order to maintain the small size, they often sacrifice maximum voltage, or settle for a
lower amount of Joules. Some faults (On 15 kV systems, this may be less than 1 in 10 faults) will simply
require “more” than the portable equipment is able to provide. That could be more voltage, more
Joules, or more pre-location modes. So, while the small portable equipment will find the vast majority
of faults, especially on 15 kV class URD systems, it is important to have a back-up plan in place for the
more difficult faults.

This back-up system would be large portable units, or a small truck mount unit, depending on the
specific requirements of the end users. There might be only one of these types of equipment in a given
region, and they will typically be used far less often. They are most likely positioned at a convenient
service center, always fully charged and ready to go. These would be far less common in the system, but
would still be easily accessible. When the equipment is needed, someone from the crew would need to
return to the service center, collect the equipment, then return to the fault location, or have the
equipment brought out to them. This may take some hours, depending on the geography of the
distribution system, but it is much more capable than the rapid response, small units.

However, there will still be an occasional fault that even these large portable units will be unable to
locate. For example, a splice failure on a long 35 kV cable would likely be too much for even the larger
portable units. Similarly, the smaller units would be insufficient for faults in an underground network
system due to the large amount of cable-feet in such a system. For these conditions, it is necessary to
have a large, truck mount unit that is capable of finding almost any fault. There would only need to be a
small handful of these in a system, and they will take some time to deploy to any given fault, but once
they get there, it is very likely that they will be able to locate the fault. Strategic positioning of these
type of units can help reduce the deployment time. For example, a system like this is most likely to be
needed for a network fault, so it would be positioned in the closest service center to a downtown
network. It can then respond to the majority of its primary work quickly, but is also available if needed
for difficult fault location activates at more remote locations.

This “satellite” system then can be imagined as having the large truck mount unit in the center, with a
few of the large portable units “orbiting” around it, in various service centers. Each of these large
portable units would then have a few small portable units “in orbit” on the various trucks dispatched
from the service center. This system allows for a rapid response time to most faults, especially in the 15
kV system, but also accounts for the faults that the small units will not be able to locate, and positions
progressively larger units throughout the system (See Figure 3).

Page 156 of 284


Figure 3 - Diagram of "Satellite" fault location equipment distribution.

Conclusion
By contacting vendors and other utilities, and carefully considering the available options, ComEd was
able to cleverly transition their fault location crew from a small, but highly skilled group to a more
general, larger group. This was accomplished for less than 25% of the first-pass expected costs, while
also improving response time, decreasing time from fault to repair, and achieving the training objectives
easily.

ComEd is also positioned to deploy a full Satellite System, taking advantage of the relative strengths and
weaknesses of each type of fault location equipment to quickly and reliably find faults in the distribution
system, while maintaining a reasonable cost for deploying these systems and achieving a high
availability of equipment.

Page 157 of 284


Pollution of AC overhead transmission lines.
Definitions, mitigation methods and field experience

TSDOS Symposium September 2017, Frisco TX

Jean Marie George


Scientific Director

Abstract
When overhead transmission lines cross regions where either natural or industrial contamination prevail,
airborne dust or conductive contaminants can impact the electrical performance of insulator strings. The
global term « pollution » describing this phenomenon is very often assimilated to anything that comes on the
surface of an insulator, but such « pollution » should be defined precisely to allow for the most appropriate
counter measure selection. Among the solutions adopted by utilities the increase of leakage distance is the
most common method. Likewise, the use of a hydrophobic material such as silicone rubber has proven to be
an effective tool.
We will explain the key concepts and definitions related to insulator pollution problems and solutions
describing how they work and what their limitations can be.
When dealing with pollution problems, the first set of actions is to know what type of pollution the line is
facing. Terms such as ESDD and NSDD are defined. Sampling techniques are described as well as ranking and
classification charts established to determine the severity of the environment.
Once these concepts are clarified, it is possible to engage into the next phase by selecting the most
appropriate insulator type and design. The mechanism of dry band arcing and dynamics of arcing will be
examined showing that leakage distance is not the only parameter to take into consideration. Shape matters
greatly and we will show how different shapes with the same leakage distance can generate different
behaviors and withstand properties.
The use of silicone rubber on the surface of an insulator has proven to work well preventing flashovers from
occurring in a variety of contaminated environments. To better understand how hydrophobicity can help
mitigating pollution problems but also understand how such material can suffer and age prematurely in harsh
environments we will describe the physico-chemical processes at work.
Finally, and while polymers have shown their own limits in terms of resilience (especially in very challenging
environment) alternative solutions such as silicone coated toughened glass insulators will be discussed
including field experience for more than 20 years in extreme conditions with outstanding performance.

1. Introduction and definitions

Pollution is a very generic term when it comes to outdoor insulation contamination. A general approach
defines pollution like anything that comes and stays on the surface of an insulator which modifies the surface
conductivity, therefore increase the risk of an electrical arc bridging the insulator itself. The deposits are
usually airborne dust, sand, industrial airborne particles, soluble elements such a salt from the sea when a
line is near a coast…
The challenge for line design engineers and maintenance crews is to know how such electric flashovers can
be avoided by either using insulators catching less contaminants, more resistant to arcing or designed and
made with materials which will reduce the ability of an external arc to take place.
When dealing with pollution problems experts use several definitions which are listed hereafter:

Creepage distance: (sometimes the word “leakage distance” is being used). It is the distance an arc needs to
cover from one metal end fitting to the next following the surface of an insulator (figure 1).

Page 158 of 284


Arcing distance: the shortest distance between ground and energized side of an insulator (figure 1)

Figure 1: arcing distance (left) versus creepage distance (right)

ESDD is the acronym for Equivalent Salt Deposit Density. It represents the quantified value of the
contaminants which dissolve in water like salt. When salts dissolve in water the conductivity of the
humid/wet film on the surface of the insulator increases, and subsequently the risk of having a flashover
increases as well. The unit of measure is mg/cm²

NSDD is the acronym for Non-Soluble Deposit Density. It corresponds to the amount of deposit on the surface
of the insulator which does not dissolve in water and remains inert on the surface. Sand for example is a
typical component of NSDD. The non-soluble component of the pollution layer will work like a sponge
catching more humidity which in turn will facilitate the conductivity on the surface of the insulator

Leakage current: is the electric current flowing along the surface of an insulator along the leakage distance.
Each insulator type has a limit above which the leakage current will lead to arcing and possibly a complete
bypass of the insulator (this final stage of arcing is then called flashover).

Specific leakage distance: the ratio between the leakage distance of an insulator (or string of insulators) and
the phase to ground voltage. The unit is inch/ KV and referred to as USCD (Unified Specific Creepage Distance)

Dry band arcing: is a dynamic process by which an arc once initiated will dry the area where it takes place. By
drying a segment of the insulator, the arc will progressively have more and more difficulties to be sustained,
will self-extinguish until the surface is wet again, leading to currents which will generate new arcs, new dry
spots….

The evaluation of the pollution level in any given area on an insulator can be made by measuring both ESDD
and NSDD. The procedure consists in washing the surface of the insulator with deionized water which
conductivity is measured prior to washing. After washing, the conductivity is measured again, and tabulated
for conversion in equivalent salt weight. This number is then divided by the surface which was washed. Once
this is done, the washing water is filtered on a paper filter which needs to be dried in an over. The weight of
solid deposit is divided by the surface of the insulator to give the final NSDD in mg/cm². (figure 2)

Page 159 of 284


Figure 2: ESDD/NSDD evaluation method

Once ESDD and NSDD are defined, it is possible to establish the pollution class as per IEC 60815 (figure 3).

Figure 3: IEC 60815 pollution classification

For each class of pollution IEC gives an average USCD as a reference base value for selecting a leakage distance
in the environment under consideration (figure 4).

Page 160 of 284


Figure 4: Typical USCD values per pollution class as per IEC 60815

2. Insulator shapes and pollution

Insulators exist with different shapes and different leakage distances. Depending upon the local environment
one shape might be a best fit than another one. Some shapes will catch and retain more dust while others
are more adapted to fight arcing activity in moist, humid or foggy conditions. Figure 5 shows a selection
method based on shapes.

Figure 5: recommended shapes for various pollution environments (shapes as per SEDIVER catalog)

Another important aspect in pollution mitigation is the fact that shape will dictate the dynamics by which the
leakage current and the dry band arcing will behave. Figure 6 shows an example where insulators with the
same leakage distance have very different flashover values and very different ultimate leakage currents
threshold values. It is easy to understand that it is not possible to set a maximum reference leakage current
value without defining the type and shape of insulator under consideration.

Page 161 of 284


Figure 6: salt fog test with equal leakage distance values on different shapes of insulators

3. Silicone and pollution

Silicone is often described as an ideal material to reduce risks of flashover. This is the consequence of the
ability of this material to be water repellant. Hydrophobicity is the generic term used to describe this
property. A material is considered as hydrophobic if the contact angle on the surface of the material exceeds
90° (figure 7). A material with this property will remain dry, shed water droplets and therefore will keep the
leakage current at low values, preventing flashovers from happening. Silicone compounds have also the
ability to transfer this property to any contamination on its surface. This mechanism called “hydrophobicity
transfer” is the result of low weight molecules (LMW) inherently part of the silicone compound migrating to
the surface and embedding the pollutants on the surface. The surface can remain water repellant even with
surface contamination.

Figure 7: Hydrophobicity

While these properties seem extremely attractive, silicone shows also some weaknesses. Among those is the
fact that silicone is relatively sensitive to dry band arcing, leading to erosion and possible cracking of the
material (figure 8). Electric arcing under the form of dry band arcing or corona (result of the breakdown of
air under intense electric field) generates ozone which in turn reacts with nitrogen in air to form nitric acid.
To reduce such effects silicone can be designed with additives such as fillers (like Alumina Tri Hydrate, ATH)
slowing down the degradation process.

Page 162 of 284


However, failures of silicone polymer insulators are occurring mostly once the rubber housing is deteriorated
leaving moisture to penetrate inside the core. These degradation mechanisms are not easy to spot during
line inspection and failure modes such as brittle fractures, cannot be anticipated. This poses problems for
maintenance but more so for live line work.

Figure 8: Erosion of silicone rubber under the effect of electric activity

While in the past silicone polymer insulators were expected to last as long as porcelain or toughened glass,
reality from the field has proven otherwise with life expectancy down to 15 to 20 years, sometimes more,
sometimes less. Additionally, counter measures such as grading rings to reduce the electric field on the
silicone compound have been implemented at voltage levels much lower than initially thought (as low as 115
KV or even 69KV in some cases) reducing arcing distance and clearances.

4. Silicone coating over toughened glass insulators

Field experience has shown that extreme pollution can be handled with silicone, but at the same time it has
been established that more the contamination is severe the faster the degradation and risk of failure of
polymers. On the other hand, the resilience of toughened glass is known to be a major asset for overhead
lines stability. Combining both has been a concept introduced more than 20 years ago, with great success.
Silicone coatings work best when applied in an industrial controlled environment. In some cases, the
application is made in the field but thickness of the coating as well as adherence remain out of control. In a
factory environment both parameters are carefully controlled. Thicknesses in the range of 10 to 15 mils.
Adherence can be checked with EN ISO 2409 or through a water boiling test as described in IEEE 1523.
The performance under pollution has been established in laboratory tests either with salt fog conditions or
with solid deposits having an ESDD/NSDD under clean fog conditions (figure 9). It was shown during these
tests that toughened glass insulators work extremely well even when the coating is applied only on one side,
underneath the glass bell (figure 10). This is something some utilities might consider for handling purpose
(less damage to the coating when mishandled). Note however that the performance of the coated insulator
is not degraded even when small tears or damage occur to the coated insulators.

Field performance confirms these results with more than a million units used only in Italy along the coasts
removing the need for washing for more than 12 years. Likewise, in the Middle East, silicone coated glass
insulators have been successfully in service for about 20 years. Samples have been removed from the line for
a performance check and the results show that these units outperform after 20 years new non-coated
insulators tested with artificial pollution deposits equivalent to those measured on the line (figure 11). In the
USA the same trend exist, and large utilities are now using either fully coated or half coated units in
replacement of polymer insulators.

Page 163 of 284


Figure 9: Pollution performance of silicone coated toughened glass insulators

Figure 10: silicone coated toughened glass insulator and half coated version

Figure 11: Pollution performance of coated glass insulators after 20 years in service

Page 164 of 284


UTILIZING THE DESIGN OF HYBRID TRANSMISSION LINE STRUCTURES

IN FLOOD PLAIN REGIONS

Jessica McLarty, P.E.1 James R. Childs, P.E.2 John L. Webb, P.E.3

1
Engineer, Lower Colorado River Authority, Austin Texas; E-mail: Jessica.mclarty@lcra.org
2
Project Engineer, HDR Inc., Ann Arbor, Michigan; E-mail: james.childs@hdrinc.com
3
Assistant General Manager, Valmont Newmark, Bellville, Texas; E-mail: jwebb@valmont.com

50th Annual Transmission & Substation Design and Operation Symposium


The University of Texas at Arlington
Division for Enterprise Development

Page 165 of 284


TABLE OF CONTENTS

ABSTRACT ................................................................................................................................................ 3
INTRODUCTION ...................................................................................................................................... 3
DESIGN CONSIDERATIONS ................................................................................................................. 4
ACCESS .................................................................................................................................................. 5
FRAMING ............................................................................................................................................... 6
LOADS ..................................................................................................................................................... 6

FOUNDATIONS ...................................................................................................................................... 8

ADDITIONAL CONSIDERATIONS ...................................................................................................... 9

MANUFACTURING PROCESS .............................................................................................................. 9

INSTALLATION ..................................................................................................................................... 11

CONCLUSION ........................................................................................................................................ 12

REFERENCES ......................................................................................................................................... 13

Page 166 of 284


ABSTRACT

In 2016, LCRA TSC was in the process of upgrading their existing 69kV Goldthwaite to Lampasas
Transmission Line. A portion of the line between San Saba and Lampasas crosses the Colorado River.
Several structures were located in the predicted 100 year flood plain. In addition, the structures directly
adjacent to the banks of the river were potentially located in areas of higher water flow. The purpose of
this paper is to discuss how LCRA TSC, HDR, and Valmont all worked together to develop a hybrid H-
Frame structure, consisting of concrete bases and steel tops, which leverages the benefits of both concrete
and steel to provide an efficient structural design with limited conflicts to construction installation or
performance. The paper will provide insight on the design and construction considerations that took place.

INTRODUCTION

In 2016, the Lower Colorado River Authority Transmission Services Corporation (LCRA TSC) worked
with HDR, Inc. in 2016 to upgrade 33.4 miles of existing 69kV transmission line from Lampasas, TX to
San Saba, TX, see Figure 1. The line would begin at the existing Lampasas substation, enter and exit through
the existing Lometa substation and terminate at the existing San Saba substation. The project scope
included the complete tear down of the existing 69kV wooden H-frame transmission line, re-building it
with 138kV concrete and steel H-frames and single pole structures. This project utilized 795kcmil, “Drake”
ACSR conductor along with an Alcoa #52 OPGW and 3/8” HS shield wire.

Colorado River
Crossing

Figure 1 Lampasas to San Saba General Project Map Overview

The project was designed and constructed within existing centerline easements. A blowout analysis of the
existing line was completed, and the width of the existing ROW width was determined. Many existing
easements had structure type limitations, which specifically described what type of structures, mostly H-
frames, could be utilized in the easement. In order to comply with these easement limitations, H-frame
dead-end structures were used. Concrete structures were utilized where terrain and easement access
allowed, reducing costs and providing improved structure resiliency against flood waters commonly
experienced in the region.

The structural design parameters utilized for the project included NESC (2012) Rule 250B for light and
heavy loading districts in addition to Rule 250C, 90mph extreme wind, and Rule 250D concurrent ice and

Page 167 of 284


wind of ¾” and 40mph wind. The structures were also designed to maintain the LCRA TSC standard ground
and 100 year flood plain clearances.

The upgraded 138kV transmission line crosses the Colorado River at a single location. The river crossing
has a 100-year flood plain that affects three (3) H-frame structures. This crossing required a miscellaneous
easement permit from the General Land Office.

The general site conditions along the project required that structures exceeding 100ft of overall length to
be made of steel due to access constraints and shipping effort. A simple analysis was complete and it was
determined that two concrete poles less than 100 ft in length could be shipped on the same truck. In addition
due to erosion, differences in grade elevation, access paths, and other restrictions, a site specific
investigation was performed along the project to ensure the feasibility of concrete pole delivery. In areas
deemed unfit for concrete pole delivery, steel poles were utilized.

Texas often experiences heavy storm events that cause an elevated risk for flooding, due to the soil
characteristics and topography. LCRA TSC has design parameters that help to limit the number of outages
caused by flood waters. The 100-year flood clearance requirement is used in bodies of water, or low lying
areas, where water may improperly drain, or has been shown historically, by rain gauges and rainfall
intensity duration functions, to produce excessive runoff.

This paper will discuss the design and construction considerations that took place on LCRA TSC’s T138,
138kV Transmission Line Upgrade Project, for hybrid structures 201, 202, and 203, used within the 100-
year flood plain of the Colorado River.

DESIGN CONSIDERATIONS

Optimum structure spotting was performed utilizing PLS-CADD during the preliminary design efforts of
the T138 transmission line rebuild. This optimum spotting effort led to the reduction in the number of
structures impacted from the 100-year flood plain elevation from four (4) to three (3).

Figure 2 Profile of Existing alignment at Colorado River

Page 168 of 284


Due to the length of the span across the river, adjacent structures 201, 202, and 203 (formerly 78/5, 78/6,
and 78/7) remained in similar locations as to the existing 69kV wood h-frame structures, to maintain the
blowout clearances within the right-of-way (ROW).

Figure 3 Profile of New alignment at Colorado River

However, back span structures 78/3, 78/4, and 78/5 were optimized based off clearance, span length, cost
for structure type, and restricted zones to eliminate the need for structure 78/4 while still maintaining
blowout clearances within the (ROW).

ACCESS

The utilization of concrete structures was primarily determined by the overall structure height and site
access for construction activities. Overall, the transmission line structures were comprised of several
variations of structures; including concrete and steel H-frames, steel single poles, and concrete 3-pole
deadends. Over 80% of the transmission line structures were concrete h-frames. This number of concrete
structures is indicative of the terrain of the right of way and the number of structures whose length was less
than 100 ft. However, the access was deemed unacceptable for the use of concrete structures near the
Colorado River crossing after a field visit by LCRA TSC and their construction managers. The reasoning
for this determination included such observations as elevation changes, soil competency, water
encroachment, vegetation and maneuverability of the shipping vehicle. In addition to access, this region
required taller structures exceeding 100 ft in length, to achieve the minimum clearances above the ground
and the 100-year flood elevation. The decision was made to utilize a hybrid structure comprised of concrete
pole base sections and steel pole tops, in order to facilitate structure delivery to the site, and to improve
durability, considering the base of the structure may be frequently inundated by flood waters. The concrete
pole base sections extended to 5 ft above the predicted 100 year flood elevation. It was assumed that
concrete sections less than 40 ft in length were able to be shipped to the site.

Page 169 of 284


FRAMING

The hybrid concrete/steel pole H-frame structure, though different from the concrete or steel pole H-frames
used on the majority of the rest of the line, also meet the requirements of the existing easements that limited
the line to using H-frames. The hybrid pole framing can be found in Figure 4 below.

In order to help control the deflection at the tip of the


poles, it was determined that x-braces would be utilized.
The tallest of the hybrid h-frames were 115 ft in length,
40 ft of this was concrete and the other 75 ft was steel,
see Figure 4. With an 100 ft easement it was important
to limit the structure deflection as much as possible.

LCRA TSC requested that the framing of the hybrid


structure remain similar to the typical tangent H-frame
configuration. Utilizing this type of framing several
items were discussed and deliberated by LCRA TSC
and HDR for the proper load cases and failure modes
that may be considered for structural design.

LOADS

In summary, the following were considered for the H-


frame structures within the floodplain; flow loads,
impact loading caused by debris, potential scour, wave
loading, and uplift. To analyze these potential failure
modes, the American Petroleum Institute,
Figure 4 Hybrid H-Frame Pole Procurement Recommended Practice for Planning, Designing and
drawing Constructing Fixed Offshore Platforms – Working
Stress Design (API 2A-WSD) was consulted. Several
assumptions were made during HDR’s design efforts for the hybrid structure located within this floodplain.

Water flow assumptions would drive the effort in potential flow loads, impact loading, scour, and wave
loading experienced on the structures. LCRA TSC provided historical water data for a 100 year flood event
located along the Colorado River just upstream from the T138 transmission line crossing location at the
San Saba gauge. This data provided a flow rate of 224,000 cubic feet per second (cfs), which was used in
determining the flow velocity at the crossing location, as well as gauge datum and heights to derive the
flood elevation. Calculating the cross sectional area of the flow from the profile view of the PLS CADD
model and provided elevation of flood, it was determined that the average flow through the cross section
would be 2.78 ft/sec. However, this flow velocity needed further assumption across the flood region as it
is unreasonable that this average flow velocity remain consistent across the entire cross section. Due to the
variations in water depth and amount of vegetation present along the cross section, it was determined that
the water velocity at a distance away from the river bed would substantially decrease. HDR and LCRA
TSC assumed that the closest structure location, greater than 500ft from the everyday river bed location,
and due to the amount of vegetation in the area that there was negligible water flow at any of the hybrid
structure locations. This assumption allowed HDR and LCRA TSC to be comfortable with considering both

Page 170 of 284


wave loading and flow loads negligible and therefore would not be considered a factor for design. In
addition, negligible water flow and vegetation present allowed us to safely assume that the structures will
be sheltered sufficiently to ignore impact loading and wave loading on the structures.

The structural design of the hybrid structure was governed by NESC (2012) with all applicable load factors
and design requirements. Supplemental code, API 2A-WSD, would be used to develop the flow loads
within the flood plain of the Colorado River.

NESC (2012) loads cases were used in the structural design of the hybrid structures. In addition, LCRA
TSC standard load cases and overload factors were applied. The loading conditions for which loads were
applied include the following: NESC Rule 250B Heavy, NESC Rule 250B Light, NESC Rule 250C, NESC
Rule 250D, Broken Wire, and everyday 60 degrees Fahrenheit.

Additional assumptions were also made for uplift. The hybrid structure framing would utilize direct
embedment foundations. The subsurface soil conditions present near the Colorado River were
predominately hard lean clay (CL) and very stiff sandy silty clay (CL-ML). Geotechnical investigations at
the structure locations were important to analyze the foundations in bearing and uplift due to the additional
hydrostatic water pressure caused by the flood. It was assumed that this soil profile would drain freely and
the entire hydrostatic force cause by the flood waters would be utilized in the design of these structures.
The design flood elevation provided by LCRA’s TSC historical 100 year water data was 1160 ft, which
translated to 20 ft of standing water at the design structure location. This pressure head would translate to
a substantial additional uplift force on the H-frame structure. Discussions with LCRA TSC, HDR, and past
project experiences with Valmont concrete poles, allowed for acceptable assumptions to be made on the
concrete pole base diameters. These assumptions included a ground line diameter of three feet (3 ft), a butt
diameter of four feet (4 ft) and a hollow shaft with thickness equal to nine inches (9 in). These assumptions
drastically reduced the amount of uplift pressure present at the base of the structure due to hydrostatic
pressure.

The flood load weather condition was provided by LCRA TSC. This extreme weather condition was said
to occur at 60 degrees Fahrenheit, 30mph wind, and no ice. Furthermore, wind driven waves would not be
considered from this weather condition due to the nature of the river flow, which is negligible. The
Exposure Category of the structure was taken to be L-3 API (2002), since the structures are unmanned and
have low consequences of failure due to the rural location and probability of extreme weather event.
Therefore, the loading criteria of the hybrid structures should consider hydrostatic forces, wind loading on
the structure, and water pressure forces. These loads were provided within the issued for price quote
drawings to Valmont in the form of a load tree.

Pressure forces were resolved into transverse point loads based off the Static Wave Analysis using the
Morison Equation, API (2002):

= + = | |+ = 14.60 / Eqn. 2.3.1-1, API (2002)

Where,
F = Hydrodynamic Force Vector per unit length acting normal to the axis of the member
F = Drag force vector per unit length acting to the axis of the member in the plane of the member axis,
U, lb/ft

Page 171 of 284


F = 0; Inertia force Vector
C = 0.65; smooth circular cylinders as provided in 2.3.1.b.7, API (2002)
w = 62.4 lb/ft2
g = 32 ft/sec2
A = D for circular cylinders
V = πD2/4H for circular cylinders
D = Effective diameter of the circular cylinder members (no marine growth present) ~3ft (assumed ground
line diameter)
U = Current velocity vector (No waves) normal to the axis of the member, 2.78 ft/sec
|U| = Absolute value of U
C = 1.6, inertia coefficient as provided in 2.3.1.b.7, API (2002)
= 0, as provided in 2.3.3.c, API (2002)

Resultant Loads is therefore,

=( ) ( ) = (1.0) 292 ~0.3 (Each Pole)

Where,
d = Length of the submerged pole above ground = 20ft
= 1.0

Hydrostatic Pressures exerted on the pole will also be present as defined below:

=ϓ = 2215 /

Where,
F = Hydrostatic Pressure acting normal to the bearing area of the structure
ϓ = Unit weight of water, 62.4 lbs/ft3
L = 35.5ft (Depth of water ~20ft + embedment of 15.5ft of standard embedment)
And,
=( ) = (1.0) 9,460 ~9.5kip (Each Pole)

Where,
R = Hydrostatic Force acting upwards along the bearing area
π( )
A = = 4.27ft , bearing area structure
D = Effective outside diameter of the circular cylinder members ~4ft (assumed butt diameter)
"
d =D − = 3.25ft = Effective Inside diameter of the circular cylinder member
"
LF = 1.0

FOUNDATIONS

Foundation design of the hybrid structures followed LCRA TSC standard methodology utilizing Power
Line System module CAISSON (2016). LCRA TSC methodology includes independent leg design and

Page 172 of 284


analysis of H-frame structures for lateral capacity. Bearing and uplift capacities are validated utilizing
LCRA TSC standard tools and spreadsheets.

The directly embedded structures were designed to include a standard embedment equal to 10% of the total
pole length plus and additional 4ft. In addition, an increased depth of soil was neglected in the foundation
design to account for local scour. Select backfill was utilized for the hybrid structure foundations to limit
the possibility of local scour, and to reduce the bearing area exposed to the additional hydrostatic forces
that may otherwise be present if concrete backfill was specified. Special care was taken during the
foundation design to ensure the soil profile had enough embedment to limit the deflection and shear forces
exerted on the structure utilizing select backfill. Furthermore, fully saturated soil properties were utilized
for the required embedment determinations.

ADDITIONAL CONSIDERATIONS

In addition to the proximity of the structures to the Colorado River, there are also several airports in the
vicinity including, Lampasas Airport, San Saba County Municipal Airport, Lometa Air Strip and Birchfield
Ranch Airport. Therefore LCRA TSC was required to provide notice to the Federal Aviation
Administration of our proposed construction/alteration of the existing T138 San Saba to Lampasas
transmission line. It was determined that the proposed structure heights and locations did not pose a threat
to navigation, therefore and additional marking or lighting was not required.

MANUFACTURING PROCESS

Most concrete poles are manufactured and delivered as single piece


units. Spun poles can be manufactured in lengths from 25ft to
140ft.When line design requirements require taller poles, or delivery
Flange Plated
constraints preclude the delivery of longer members, steel/concrete Steel Pole Upper
hybrid pole solutions can offer the benefits of direct embedded spun Section

concrete poles while providing the flexibility of delivering shorter


sections. Right-of-way conditions and design requirements drove the Ground Wire
Jumper
decision to utilize flange connected steel/concrete hybrid structures
in the river crossing area. The flange connection, see figure 5 & 6,
was chosen due to the thrust and uplift forces applied to the structure Flange Plated
Concrete Pole
legs due to frame action and to eliminate the risk of fit-up Lower Section
complications due to slip-splices.

Figure 5 Diagram of Flange-Splice


Connection

Page 173 of 284


The pre-stressed spun concrete base sections
were chosen for their durability especially in
wet environments. The primary advantages of
the spun pre-stressed concrete members over
conventionally case and reinforced concrete
are:

a) The concrete section remains in


compression throughout the range of its
service load.
b) Plant produced concrete can be held to a
higher standard than traditional ready-mix
concrete allowing for much higher
compressive strengths to be used for design.
The concrete sections for these hybrid
sections were designed for 12,000psi
(82.6MPa) 28 day compressive strength.
c) The spinning process creates a dense,
almost impenetrable concrete matrix resistant
Figure 6 Flange Splice Connection
to water intrusion in wet environments.

With the equipment currently available in the


United States, concrete base sections can be fabricated with a maximum diameter of 60.75”(1.54m). Given
this restriction, the maximum bending strength that can be achieved is roughly 7,000ft*kip(9.49x106 N*m)

Typically, concrete poles are delivered on the right-of-way to the structure staking location. Due to
extremely wet weather in the winter of 2016/2017 the contractor requested that the poles be delivered to a
marshalling yard to allow for delivery to proceed even though ROW conditions did not allow for just-in-
time structure delivery to the staking location. The steel top sections were also delivered to the marshalling
yard. Once conditions allowed for access to the river crossing location the contractor was able to move the
sections to the ROW using their equipment.

INSTALLATION

The installation of these hybrid pole H-frames was essentially the same as a standard H-frame, with a few
modifications.

1. Concrete Base Installation


a. Precisely located holes were drilled 2 ft deeper than the required embedment.
b. The base of the excavations was then filled with compact select fill to give a solid and
level bearing surface for each of the concrete pole bases.
c. Once one of the concrete bases was installed a Digger Derrick was used to hold the
base in place.
d. The same process was complete on the other concrete base, see Figure 7.

Page 174 of 284


2. The digger Derricks were used to keep the concrete bases plumb which the steel frame was
erected on to it. Levels and other devices were utilized to measure plumbness and the elevation
of the top of the concrete bases. Once each of the concrete bases was plumbed, the steel frame
was set on them.
3. Steel Top Installation
a. A spreader bar was utilized to spread the load out and keep the frame plumb and level.
A 50 ton Mantis Crane was used to erect the steel structure with the spreader bar. The
base of the excavation was then filled with compact select fill to give a solid bearing
surface.
b. The crane and the spreader bars remained in place until the structure was stable and
the foundation was backfilled, see Figure 8.
c. The construction crew, while working from the bucket, aligned one of the steel bases
with the flange plate of the concrete pole and began inserting steel pins into the bolt
holes to align them. The crew worked around the pole base aligning holes on opposite
sides of the poles, until the pole was correctly centered. The crew then moved on to
the base of the other pole, and followed the same process.
d. After an adequate number of pins were installed the upper steel portion became stable,
and the process of setting the concrete bases began to take place
4. Foundation Installation
a. Compacted select fill was chosen as the backfill for the concrete poles, to allow for
drainage in the event of flood. Lifts of select fill were added to the excavation to
stabilize the concrete structure.
b. The crew worked on one pole at a time. After the concrete portion of the frame was
stabilized the temporary shoring provided by the digger truck was then removed
c. The last step in the erection was to insert the remaining connection bolts through the
flange plates.

One thing that was brought up early on in the process was maintaining the plumbness of the concrete
structures during erection. With the upper steel structure being completely assembled prior to erection,
some of the flexibility to adjust the structure was removed. It was essential to set the base of the structure
as best as possible, or the upper portion of the structure could possibly be off.

Page 175 of 284


Figure 7 Concrete Base Installation Figure 8 Steel Top Installation

CONCLUSIONS

The use of hybrid structures adjacent to or in flood plains have been considered for several projects since
their use on this project. Once of the reasons the hybrid structures have not been utilized is because the
potential for flowing water has not been present. The design and drawings have been added to our standard
design library. We have also given presentations internally discussing this design.

For LCRA TSC there was not a substantial cost increase with the hybrid h-frame structure, from the type
of structure that would usually be used in such a flood zone. In the past LCRA TSC has installed anchor
bolted steel dead end structure with concrete pier foundations, that utilize an additional reveal of
approximately 10-15 ft. An anchor bolted structures would have both additional cost for the foundation
and the structure itself. In addition getting a concrete truck to the structure would also be difficult which
would also lead to increased cost. After all of these consideration LCRA TSC determined that the hybrid
h-frame would be the most effective.

LCRA TSC’s mission statement is “To enhance the quality of life of the Texas we serve through water
stewardship, energy and community service.” One way we do this is by increasing the reliability of our
transmission lines. We believe that utilizing the hybrid h-frame structure and providing a minimum of 25’
of clearance above the high water elevation are pertinent in providing reliability to our customers. The
hybrid h-frame structure utilizes concrete bases in areas where water could be present for extended periods

Page 176 of 284


of time, which would prevent rust and structure deterioration. In addition the concrete bases would not be
damaged as easily, which would prevent potential outages to repair the structures after a storm event.

REFERENCES

NESC (2012) National Electric Safety Code, National Bureau of Standards, Washington, D.C.

API (2002) Recommended Practice for Planning, Designing and Constructing Offshore Platforms -
Working Stress Design, API Recommend Practice 2A-WSD, American Petroleum Institute, 21st Edition
200-2002.

CAISSON (2016), Power Line Systems, Inc., Madison Wisconsin

Page 177 of 284


Xcel Energy
AC Interference
Program: Metallic
Pipelines
Project Location: New Mexico and
Texas, USA

July 14, 2017

Page 178 of 284


AC Interference Program: Metallic Pipelines
Project Location: New Mexico and Texas, USA

July 14, 2017

Xcel Energy AC Interference Program:


Metallic Pipelines
Texas and New Mexico, USA

The primary objective of this report is to present the technical background of AC Interference as
well as to provide a summary and conclusions specific to the Xcel Energy AC Interference
Program. This report addresses AC interference modes and their effects on metallic pipelines
with respect to corrosion and safety hazards. In addition, this report summarizes the
methodology behind the AC Interference program as well as identifies additional potential risk
factors.

Several authors contributed to the development of this report. They are as follows:

Xcel Energy Josh Ross

HDR Engineering, Inc. Andrew Johnson, P.E.


Jack Grauman, P.E.
Cody Bingham
Carl Svard, P.E.
Brent Hanson, P.E.
Jeff Giddings, P.E.
Glen Adams, R.G.
Scott Marr, P.E.
Mandy Kondik

Mr. Ross is an employee of Xcel Energy Services Inc., the service company for the Xcel Energy
Inc. utility holding company system. XES provides engineering, siting and land rights, project
management and other services for the utility operating company subsidiaries of Xcel Energy
Inc., including Southwestern Public Service Company (SPS). In this paper, XES and SPS are
collectively referred to as “Xcel Energy”. Mr. Ross is employed in the Transmission business
unit of XES.

Page 179 of 284


Xcel Pipe Xcel Energy AC Interference Program: Metallic Pipelines

Contents
1 Introduction and Program Overview .................................................................................................... 1
2 Current Work Practices ....................................................................................................................... 2
2.1 Screening Criteria...................................................................................................................... 2
2.2 Notification ................................................................................................................................. 2
3 AC Interference Modes ....................................................................................................................... 2
3.1 Capacitive Coupling .................................................................................................................. 3
3.2 Inductive Coupling ..................................................................................................................... 3
3.3 Resistive Coupling..................................................................................................................... 4
4 AC Interference Program Methodology............................................................................................... 4
4.1 Task 1: Desktop Identification ................................................................................................... 6
4.2 Task 2: Field Delineation .......................................................................................................... 7
4.2.1 Pre-field Planning Effort ............................................................................................... 7
4.2.2 Field Delineation........................................................................................................... 8
4.2.3 Post-Field Data Processing and Development of Deliverables ................................... 8
4.3 Task 3: Initial Prioritization ........................................................................................................ 9
4.4 Task 4: Electrical Resistivity Data Collection ............................................................................ 9
4.5 Task 5: Final Data Gathering .................................................................................................. 10
4.6 Task 6: AC Interference Modeling........................................................................................... 11
4.7 Task 7: AC Interference Design Review ................................................................................. 12
4.8 Task 8: AC Interference Mitigation Construction .................................................................... 13
4.8.1 Surface and/or Near-Surface Grounding ................................................................... 13
4.8.2 Deep Grounding ......................................................................................................... 13
5 Additional Potential Risk Factors ...................................................................................................... 14
5.1 Increased or Decreased AC Interference Buffer Zones .......................................................... 14
6 Conclusions ....................................................................................................................................... 15
7 References ........................................................................................................................................ 16

Page 180 of 284


AC Interference Program: Metallic Pipelines
Project Location: New Mexico and Texas, USA

1 Introduction and Program Overview


At Xcel Energy, we are currently in the midst of rolling out our Power for the Plains
Transmission Program within the Southwestern Public Service Company (SPS) operating
company region. The Power for the Plains program is a series of electrical transmission projects
in SPS which will upgrade existing electrical transmission lines, as well as build new electrical
transmission lines, in Western Texas and Eastern New Mexico. The purpose of this program is
to improve electric reliability, strengthen the existing SPS transmission grid (System) and
provide an outlet for additional renewable generation facilities within the area.

The Southeast New Mexico (SENM) portion of the SPS System has a standalone transmission
expansion portfolio driven by major developments within the potash mining industry, increase in
oil and gas exploration and production efforts, and commercial growth within the area. SPS
worked closely with Southwest Power Pool (SPP) to develop cost effective solutions to address
the incremental oil and gas electrical load additions in the SENM region. In 2014, SPP approved
and issued Notices to Construct to SPS for the addition of 149 miles of 115kV electrical
transmission lines, and 245 miles of 345kV electrical transmission lines.

Throughout the years working within the SPS System, we have dealt with many challenges
specific to the existing oil and gas infrastructure within this area. Traditionally, our challenges
have stemmed from land access, easements, and load growth specifically related to the oil and
gas operators within the area. However, we now have a new challenge to consider, that being
issues surrounding potential AC Interference with coated metallic structures and specifically
buried metallic oil, gas, and water pipelines.

Recent studies conducted by oil and gas industry groups (i.e. Interstate Natural Gas Association
of America and American Gas Association) as well as corrosion engineering industry groups
(i.e. National Association of Corrosion Engineers) have provided documentation and examples
of the effects of AC Interference when electrical transmission and/or distribution infrastructure is
located adjacent to, crosses, and/or runs parallel to metallic structures. The AC Interference is
caused by the electromagnetic, capacitive, inductive, and conductive effects from the electrical
transmission and/or distribution infrastructure. In certain situations, this interference can cause
electrical arcing, step-current interaction and/or accelerated corrosion damage to metallic
structures such as above and below ground pipelines, metering and/or regulator facilities, well
heads, and storage tanks.

Specific to our Power for the Plains build-out within the SPS System, we have started a program
to better understand the potential effects of AC Interference caused by new electrical
transmission line projects on metallic oil, gas, and water pipeline infrastructure as well as to
define Xcel Energy’s risk profile specific to this topic.

Page 181 of 284


Xcel Pipe Xcel Energy AC Interference Program: Metallic Pipelines

2 Current Work Practices


In response to this new program to study potential AC interference on metallic pipelines at Xcel
Energy, there have been new work practices implemented for new electrical transmission
projects. These are still a work in progress but assist in determining whether there is potential
risk due to AC interference, as well as a procedure, which details the necessary subsequent
steps of identification and delineation should a perceived risk be identified. They are as follows:

2.1 Screening Criteria

When a new transmission line project is kicked off, the Engineers are aware to take
underground pipelines in to account when starting the design. If the project is in an area with
potential risk for AC Interference, then they reference the screening criteria. Within the criteria is
a buffer value that is used as an initial definition of extents during the process of investigating
the presence of metallic pipelines for a given electrical transmission line. Using different
evaluation criteria from industry published documents helps determine which pipelines identified
could potentially experience AC Interference.

2.2 Notification

If the screening procedure listed above identifies metallic pipelines that could have a potential
risk for AC Interference, the transmission engineer coordinates with the Sighting and Land
Rights agent to send a notification letter to that pipeline owner. The intent of the letter is to make
the owner aware of the construction that will take place and provide the owner with a point of
contact within Xcel Energy if they have questions.

3 AC Interference Modes
If the right set of circumstances exist, electrical interference from electrical transmission lines
can occur and may affect metallic structures in a variety of ways including developing shock
potential at or around a given metallic object and/or causing accelerated corrosion of the
metallic object. There are three generally accepted primary modes of AC interference (or
coupling):

 Capacitive Coupling;

 Inductive Coupling; and

Page 182 of 284


AC Interference Program: Metallic Pipelines
Project Location: New Mexico and Texas, USA

 Resistive Coupling.

The paragraphs below provide a brief description of each type of AC interference mode.

3.1 Capacitive Coupling


Capacitive coupling, or electrostatic interference, occurs when the electromagnetic field
produced by AC current flowing through an electrical transmission line induces a charge on an
above ground metallic structure, which is electrically isolated from the ground. For metallic
pipelines, capacitive effects are primarily a concern during construction when sections of the
metallic pipeline are above ground on insulating supports. However, after construction not all
metallic pipelines, or their associated facilities / components, are constructed below ground and
as such, in situations where they are constructed above ground; they may be at continuous risk
to capacitive coupling.

How capacitive coupling works is a metallic structure (like a metallic pipeline) builds a charge as
a capacitor with the surrounding air acting as the dielectric, which can maintain the electric field
with a minimum loss in power, resulting in a potential difference with the surrounding earth. The
magnitude of potential is primarily dependent upon the pipeline proximity to the electric
transmission line, the magnitude of electric transmission current, and the individual phase
arrangement. If the potential buildup due to capacitive coupling is significant, electrostatic
interference may present a risk of electric shock and/or arcing.

3.2 Inductive Coupling


Inductive coupling (or electromagnetic induction) is the primary interference effect of an electric
transmission line on a below ground metallic structure, such as a metallic pipeline, during
normal steady state operation. Inductive coupling occurs when AC current flowing along an
electric transmission line generates an electromagnetic field, which can couple with adjacent
buried metallic structures. When this coupling occurs, it induces an AC voltage and
corresponding current on the buried metallic structure. This induced AC potential can present a
safety hazard to personnel working on or around the buried metallic structure and can contribute
to AC corrosion on the buried metallic structure.

The inductive effects of an electrical transmission line on an adjacent buried metallic structure
are a function of geometry, soil resistivity, coating resistance of the buried metallic structure,
and the operating parameters of the electrical transmission line. The geometry characteristics
include separation distance between the pipeline and the electrical transmission line towers,
depth of cover for the buried metallic structure, angle between the buried metallic structure and
the electrical transmission line, and phase conductor configuration. These parameters remain
relatively constant over the service life of both the electrical transmission line and the buried
metallic structure. The coating resistance, power system resistance, and soil resistivity could
vary with the seasonal changes and as the structures begin to age. The operating parameters
of an electrical transmission line, such as phase conductor load, phase balance, voltage, and

Page 183 of 284


Xcel Pipe Xcel Energy AC Interference Program: Metallic Pipelines

available fault current, which all contribute to inductive coupling, can vary significantly. An
individual conductor current load and phase balance are dynamic and changes with load
requirements and switching surges. These variations in operating parameters contribute to
variations in levels of inductive coupling. During normal electrical transmission line operation,
the current load varies as the load demand changes both daily and seasonally. While normal
operating conditions are often referred to as steady state, the term is somewhat misleading as
the current loads and corresponding inducted AC potentials can be continuously varying, adding
further complexity to quantifying inductive coupling.

3.3 Resistive Coupling


Electrical current traveling through a soil mass to a buried metallic structure can cause resistive
coupling. As a grounded electrical transmission tower shares an electrolytic path with an
adjacent buried metallic structure through a soil mass, fault currents may transfer to adjacent
metallic structures if the metallic structure presents a lower resistance electrical path. Resistive
coupling is primarily a concern with a phase-to-ground fault that occurs in an area where a
buried metallic structure is in close proximity to an electrical transmission line and the
magnitude of the fault current within the ground is high.

During fault conditions, the primary concern is the resistive coupling being transferred through a
soil mass to a buried metallic structure. However, it should be noted inductive coupling can also
be a concern as the phase current and corresponding inductive coupling will most likely
increase. What this means is during a fault condition, the inductive effects during normal
operation increase due to the elevated electromagnetic interference during the fault period.

4 AC Interference Program Methodology


In order to begin developing Xcel Energy’s standard of care and safety plan as they relate to AC
induction on metallic pipelines, we believe we needed to become proactive in identifying and
disseminating pipeline infrastructure in and around our proposed SPS System projects. To
accomplish this task, we engaged HDR Engineering, Inc. (HDR) and specifically their Oil and
Gas Pipelines Practice to assist with this task. Through working with HDR, we developed
individual tasks which may need to be completed on each of our SPS System projects to begin
identifying instances giving risk to the aforementioned potential risk. Specifically, the tasks,
which we propose to complete for each project, are as follows:

 Task 1: Desktop Identification

 Task 2: Field Delineation

 Task 3: Initial Prioritization and Budgetary Cost Estimate

 Task 4: Electrical Resistivity Data Collection

 Task 5: Final Pipeline Owner Data Gathering

Page 184 of 284


AC Interference Program: Metallic Pipelines
Project Location: New Mexico and Texas, USA

 Task 6: AC Interference Modeling

 Task 7: AC Interference Design Review

The sections below provide a brief description of each task.

In addition to the tasks themselves, we needed to define the initial extents of our study for each
SPS System project. To develop these extents, we and HDR completed a literature review
specific to AC Induction which included studying reports commissioned and/or published by the
following:

 Interstate Natural Gas Association of America (INGAA);

 Canadian Energy Pipeline Association (CEPA);

 American Gas Association;(AGA)

 Standards Council of Canada

 Electric Power Research Institute (EPRI)

 Institute of Electrical and Electronics Engineers (IEEE)

 National Association of Corrosion Engineers (NACE)

 American Petroleum Institute (API)

A detailed list of the reports we examined during our literature review is provided in the
References section of this report. In addition to reviewing reports authored by others, we also
discussed this topic with HDR’s Corrosion Engineering Team as well as two other Corrosion
Engineering Firms, those being the Wood Group and Southern Cathodic Protection.

What we found consistent amongst all of the information we reviewed was the distance of
impact due to AC interference which was possible between an electrical transmission line and a
metallic pipeline varied markedly from project to project but relied on three basic elements:

 Characteristics of the electrical transmission line (i.e. voltage, conductors, line


sag, structure configuration, etc.);

 Soil conditions (i.e. whether a given soil mass was conductive for electrical
interference and if so, to what extent?); and

 Characteristics of the pipeline (type of pipe material, pipe coating, current AC


mitigation measures, etc.).

As such, to set initial extents or “buffers” for each SPS System project, we utilized those
recommended by INGAA. It should be noted while we recognize these initial buffer values to
likely be conservative, they are buffer values which are generally accepted by the oil and gas

Page 185 of 284


Xcel Pipe Xcel Energy AC Interference Program: Metallic Pipelines

pipeline industry as well as the corrosion engineering industry for conducting initial AC Induction
modeling. For reference, we are considering using the following buffer values:

 115 kV: 800 linear feet either side of centerline;

 230 kV: 1,200 linear feet either side of centerline; and

 345 kV: 1,500 linear feet either side of centerline.

4.1 Task 1: Desktop Identification


The first step with each SPS System project is to identify the existing pipeline and oil and gas
well pad infrastructure within the corresponding buffer. To do this, HDR gathers publically
available oil, gas, and water pipeline and well pad data, which is located adjacent to, parallel,
and/or within the corresponding buffer for each project. Examples of publically available data
sources include but are not limited to:

 Texas Railroad Commission;

 New Mexico Oil Conservation Division;

 New Mexico Energy, Minerals, and Natural Resources Division;

 New Mexico Public Regulation Commission;

 New Mexico and/or Texas 811;

 US Energy Information Administration;

 Bureau of Land Management;

 National Pipeline Mapping System; and

 Aerial Photography

In addition, HDR has access to the IHS Energy’s and PLATTS Pipeline Databases, which are
proprietary, subscription-based databases that provide additional pipeline and well pad data. As
such, for each project, HDR reviews data within the IHS Pipeline Database and includes any
corresponding pipeline and/or well pad data into the desktop maps. Also, any data which was
captured by Xcel Energy’s Siting and Land Rights group and/or project surveyors is included in
the initial desktop maps. At the end of Task 1, HDR produces desktop maps which include the
following:

 Centerline and ROW of the proposed electrical transmission line;

 Corresponding electrical substations and/or switching stations;

Page 186 of 284


AC Interference Program: Metallic Pipelines
Project Location: New Mexico and Texas, USA

 Corresponding buffer (which varies based on the voltage of the proposed

transmission line);

 Identified pipeline infrastructure; and

 Identified well pad infrastructure.

The produced maps are considered a 50% Draft map package and are provided to Xcel Energy
in Adobe (.pdf) ArcGIS (.shp), AutoCAD (.dxf), and Google Earth (.kmz) formats.

4.2 Task 2: Field Delineation


The second task with each SPS System project is to conduct a field delineation to confirm the
presence and location of oil, gas, and/or water infrastructure identified in Task 1, as well as to
locate and collect data on pipelines and other oil, gas, and or water infrastructure identified in
the field. The completion of Task 2 involves three areas of focus:

 Pre-field planning effort,

 Field delineation, and

 Post-field data processing and development of deliverables.

4.2.1 Pre-field Planning Effort


The first step of the pre-field effort is to identify the field delineation team. The field delineation
team generally consists of a Field Delineation Lead (Lead) and a Field Delineation Technician
(Technician), which are both skilled at map comprehension and spatial awareness/orientation,
and have strong experience and knowledge of oil, gas, and water infrastructure inclusive of
pipelines, well pads and associated facilities. Next, the field delineation team analyzes a
proposed electrical transmission route using publically available current and historical aerial
imagery, and identifies indicators of a pipeline’s presence such as a linear scar in the
landscape, visible aboveground facilities, or placards/casing vents. These features are digitized
in a geographic information system (GIS) platform and added to the maps produced in Task 1 to
create a set of field maps. The final step in the pre-field planning effort is to coordinate with
Xcel Energy representatives (inclusive of Transmission Engineering and Siting and Land Rights)
and other contractors (as necessary) for access, transportation, special concerns, and most
importantly to submit the utility locate One Call tickets. It is critical the utility locate one call
tickets are completed prior to the field effort, as many of the pipelines located during the field
delineation are identified by pin flags placed by utility locators while the utility locate One Call
ticket is open.

It has been HDR’s experience that while the utility locate One Call ticket identifies and flags the
majority of underground pipelines and utilities along the proposed electrical transmission route,

Page 187 of 284


Xcel Pipe Xcel Energy AC Interference Program: Metallic Pipelines

occasionally in remote or high-density areas, a pipeline is not identified by the utility locate One
Call ticket. Typically, these unidentified pipelines are older and at times, abandoned assets,
having been installed several decades earlier. These pipelines are often the most important to
locate, as pipeline engineering standards of the time did not require cathodic protection, and the
steel used in construction is usually of lower quality than what modern-day standards require.

4.2.2 Field Delineation


Upon deploying to the proposed electrical transmission line alignment, the field team traverses
the corresponding electrical transmission line buffer, usually in utility terrain vehicles (UTVs) and
observes the ROW for underground utility placards, pin flags, pipeline scars, valve boxes,
pigging facilities, or other indicators of pipeline infrastructure. At these locations, a GPS point,
photograph, and written description of an observation are recorded. At areas where oil and gas
well pads are located wholly or partially within the ROW, a GPS point is recorded at the well
head, and photographs and descriptions are recorded of the well pad placards. GPS points are
recorded in the NAD83 coordinate system using a Trimble Geo7x unit or equivalent with sub-
meter accuracy.

Within the transmission line ROW, other aboveground and belowground utilities such as high-
density polyethylene (poly) pipelines, telephone cables, fiber optic cables, are also
recorded. Outside of the transmission line ROW, the locations of poly lines and other utilities
are not recorded since they do not pose the same conductivity issue as metallic pipelines.

In areas where the presence of a pipeline is suspected, typically due to the identification of a
linear scar on aerial photographs, but no identifying information such as utility placards or pin
flags are available, a commercially available handheld utility locator is utilized to determine
whether a buried metallic structure is present. The Radio-detection Model 7100 utility locator is
used in several different modes to allow for reasonable certainty as to whether a buried metallic
object is present within a particular area.

4.2.3 Post-Field Data Processing and Development of Deliverables


Upon completing the field delineation effort, the collected GPS points are added to the GIS
digital files and post-processed to achieve a greater accuracy. With post-processing, GPS
points can be refined to within six (6) inches of real-world location. Using GIS, the field lead
then “connects the dots” to create the GIS representation of the inferred location of delineated
infrastructure.

It should be noted sub-meter accuracy is only present at the locations where the GPS points
were collected. HDR’s field crews make every effort to collect as many points as possible
where a pipeline may turn or bend, but surface indicators of a point of inflection are not always
present, and therefore may not be accurately captured. This generally is not a concern within
the transmission line ROW, as the majority of the pipelines are marked with pin flags, but
outside of the transmission line ROW this can become an issue. HDR can only be confident in

Page 188 of 284


AC Interference Program: Metallic Pipelines
Project Location: New Mexico and Texas, USA

the accuracy of the location of a pipeline where a GPS point was collected; the real-world
locations of pipelines and the inferred lines digitized in GIS to represent them may not correlate
exactly in a given location.

Once the pipelines have been digitized, the maps generated in Task 1 are updated to only
reflect metallic pipelines and other utilities which were captured during the field delineation. The
maps are then reviewed for quality control, and become Attachment A of a Technical
Memorandum. The Technical Memorandum identifies all metallic pipelines, well pads, or other
above and below-ground utilities along the route and lists them by closest electrical
transmission structure name or by mile post if electrical transmission structure locations are
unavailable. Occasionally, the presence of a pipeline is suspected due to some piece of data,
but unable to be identified in the field. These areas are highlighted on the maps and in the
Technical Memorandum as areas “Recommended for Further Investigation”.

HDR’s deliverables to Xcel Energy include the Technical Memorandum, and digital maps, which
can be considered a 95% map package, in GIS (.shp), AutoCAD (.dxf), and Google Earth
(.kmz). The Technical Memorandum includes the Pipeline Inventory Maps and a list of pipeline
and well pad operators and contact phone numbers collected along the transmission line
route. The final step is to upload all deliverables to the corresponding Xcel Energy electrical
transmission line ProjectWise folder.

4.3 Task 3: Initial Prioritization


At the culmination of Task 2, HDR performs an initial prioritization of the identified metallic oil,
gas, and water pipelines within a corresponding buffer for a given electrical transmission line.
This initial prioritization “sets the stage” for which metallic pipelines we believe will be at the
greatest risk to AC interference. During this process, the following parameters are evaluated:

 Separation Distance: distance between the electrical transmission line and a given
pipeline;

 Colocation / Crossing Angle: angle at which a given pipeline crosses and/or parallel’s an
electrical transmission line;

 Colocation Length: distance a pipeline is within the corresponding buffer distance for a
given electrical transmission line;

 Pipeline Owner: interstate oil and gas transmission operators versus midstream
operators

4.4 Task 4: Electrical Resistivity Data Collection


HDR’s services related to electrical resistivity (ER) data collection are for the purposes of
obtaining in-situ soil resistance values for corrosion analysis and modeling. The purpose of the

Page 189 of 284


Xcel Pipe Xcel Energy AC Interference Program: Metallic Pipelines

electrical surveys is to determine the subsurface resistivity distribution by making


measurements of the bulk resistivity between various spaced electrodes. The further the
electrode spacing the deeper and larger the volume of soil that is included in the measurement.
Electrical resistivity testing in the field is performed by a knowledgeable geophysical staff
utilizing equipment designed solely for the purpose of collecting soil resistivity data. The
Wenner 4-pin method is considered the industry standard for soil resistivity measurements for
electrical systems design. This test involves utilizing four (4) electrodes which are placed at
varying equal distances. The distances for each reading roughly correlate to a depth equal to
that distance and are commonly referred to as an “A”-spacing. With each reading, the A-
spacing is increased so as to obtain a logarithmic distribution of depth readings. A typical ER
field collection program includes but is not limited to the following:

 Selection of test locations based on geotechnical boring information, geomorphology,


terrain, planned route, existing pipeline infrastructure, and access

 Planning access routes and location groupings to most efficiently perform the testing;

 Mobilizing personnel and equipment to the site, performing quality equipment checks
including resistance test box calibration check;

 Collecting Wenner Array electrical resistivity data in general accordance with the
American Society of Test Materials (ASTM) Standard Test Method G57 and IEEE
Standard 81-2012 along two perpendicular arrays. Each array will consists of “A”-
spacings which include 0.5, 1.0, 3.0, 5.0, 10.0, 15.0, 20.0, 30.0, 50.0 and 100.0 feet.

 Performing onsite data quality checks including; standard deviation/error reporting for
internal meter readings, deviation check between arrays and data plotting for log/log
curve smoothness; and

 Tabulating reading and calculated apparent resistivity values per A-spacing to be


included in the data report and checking the calculated apparent resistivity values
against published typical values (if available).

4.5 Task 5: Final Data Gathering


AC interference modeling is dependent upon obtaining physical and operating parameters of the
electrical transmission line and pipeline within the corresponding electrical transmission buffers,
as well as converting and applying known soil resistivity data into acceptable model input.
Obtaining this available information requires a coordinated approach with pipeline owners and
Xcel Energy, resulting in developing and submitting Requests for Information (RFI) to each
pipeline owner in order to gather the necessary information needed for modeling. To aid in
developing a RFI, the field delineation maps, which are generated during Task 3, are used to
convey the extent of the RFI to each identified pipeline owner. Examples of types of information
requested from pipeline owners include but are not limited to:

 Pipeline diameter;

Page 190 of 284


AC Interference Program: Metallic Pipelines
Project Location: New Mexico and Texas, USA

 Depth to top of pipeline;

 Details on existing AC mitigation systems;

 Soil resistivity data; and

 In-line inspection and testing records (which provide an indication as to the remaining

service life of the asset).

Similarly, Xcel Energy is sent an RFI to obtain physical and operational parameters of the
proposed electrical transmission line. During the modeling process, if additional information is
needed, supplemental RFI(s) are developed and sent to the corresponding project stakeholder.

As expected, not all pipeline owners are able to provide all of the requested information. When
this occurs, assumptions about the unknown information are made. Prior to executing Task 6:
AC Induction Modeling, all input parameters are confirmed and agreed to by all project
stakeholders (which include all pipeline owners and Xcel Energy). The software used for this
modeling has the ability to print the input data of all three basic elements (electrical transmission
line, soil resistivity, and pipeline characteristics) so both the known data provided and assumed
input values are shared to confirm their validity.

4.6 Task 6: AC Interference Modeling


Upon receiving information from project stakeholders as described in Task 5, HDR then
proceeds forward with AC Induction modeling. HDR’s AC Induction analysts utilize a software
package named CDEGS (Current Distribution, Electromagnetic Fields, Grounding and Soil
Structure Analysis) distributed by Safe Engineering Services & Technologies ltd. Specifically
within the CDEGS software, HDR’s team utilizes both the SES Right-of-way (ROW) and SES
Multi-fields (HiFREQ) modules. Using separate models has an additional value as the ROW and
HiFREQ packages complement each other’s weakness. In addition, the benefit of using two
models is the identification of errors as the two methods should provide similar results, but not
identical.

The CDEGS ROW system model for a given project is constructed by using typical cross-
sectional configurations of the corridor in question. This includes all transmission and metallic
pipeline facilities. The ROW model can analyze the system under steady state, fault, and
lightning strike conditions. Additionally, the soil type can vary throughout an electrical
transmission line alignment, which is something the HiFREQ model does not easily allow.

The CDEGS HiFREQ system model is built using the same information as the ROW model.
Unlike ROW, HIFREQ allows for above ground conductors (valve locations in this case) to be
modeled. Additionally, HiFREQ allows more modeling options for energizing conductors. The
limitation of HiFREQ is the limitation of a single soil structure for the entire electrical
transmission line alignment, resulting in the possible need for multiple models to be developed.

Page 191 of 284


Xcel Pipe Xcel Energy AC Interference Program: Metallic Pipelines

After completing the CDEGS modeling, HDR compiles the results in a report with sections for
each specific pipeline associated with a given Xcel Energy electrical transmission line. These
results are the basis identifying areas of AC Induction risk along a given metallic pipeline asset
as well as developing strategies for mitigating the AC Induction risk.

4.7 Task 7: AC Interference Design Review


Generally speaking, today’s pipeline coating systems are very good at providing effective
corrosion control and are continuing to improve at providing a barrier from corrosive electrolyte
and also preventing the flow of AC corrosion current leaving the pipe. This bonded dielectric
coating system has also been found to limit the discharge or dissipation of AC current, which
tends to accumulate along portions of a metallic pipeline. As a result, AC voltage and current
accumulate and can cause many different forms of corrosion damage from producing small
pinholes (referred to as holidays) to failure at joint welds to full degradation at a given section of
pipeline. Given a pipeline coatings varied effectiveness, alternate means may be necessary to
safely discharge AC current from a given metallic structure to avoid electrical shock potential
and accelerated corrosion related to elevated current densities per industry guidelines.

Using the CDEGS software, modeling the interaction of an electrical transmission line’s steady
state, peak, and fault condition effects on nearby metallic structures in a given media (soil
resistivity), as described in Task 6, provides the AC voltage and current predictions along the
length of a metallic pipeline. If AC voltage is shown to exceed 15V at a given location, USDOT
Pipeline and Hazardous Material Safety Administration (PHMSA) and National Association of
Corrosion Engineers (NACE) design guidelines dictate mitigation methods must be utilized to
dissipate AC effectively while preventing valuable cathodic protection current (DC) loss, all the
while maintaining safety. The specific PHMSA and NACE design guidelines are as follows:

 USDOT Pipeline and Hazardous Materials Safety Administration (PHMSA) Regulations

o 49 CFR Part 195 Subpart H: Corrosion Control; and

o 49 CFR Part 192 subpart I: Requirements for Corrosion Control

 NACE Design Guideline SP0169-2013

Examples of mitigation methods may include but are not limited to utilizing discharge locations,
isolation, continuity, decoupling, equalization, and dissipation, all of which are elements which
need to be designed specific to a given pipeline asset.

For this program, potential AC Mitigation design is being led by the individual pipeline
companies and/or their consultants because any mitigation would typically be installed on the
pipelines rather than the electrical transmission line. Through this process, Xcel Energy and
HDR will be reviewing the AC Mitigation designs developed by others to confirm their

Page 192 of 284


AC Interference Program: Metallic Pipelines
Project Location: New Mexico and Texas, USA

effectiveness in reducing voltage and current to acceptable levels as prescribed by PHMSA and
NACE.

4.8 Task 8: AC Interference Mitigation Construction


Although the program has not progressed to the point on any given project where AC mitigation
has been or will be constructed, we expect this will likely be the case as we progress through
the project portfolio. Within the corrosion protection industry, there are many different measures
which could be designed and implemented to mitigate the affects of AC interference. Such
mitigation strategies may include:

 Surface and/or Near-Surface Grounding; and

 Deep Grounding

4.8.1 Surface and/or Near-Surface Grounding


Surface and/or near-surface grounding generally refers to one of several types of mitigation
ground installed at or near the ground surface or at metallic structure burial depth. Typical
designs may consist of bare copper cable, zinc ribbon, or shallow anodes. During new metallic
structure construction, surface and/or near surface grounding can be installed directly in the
metallic structure excavation or laid parallel to the metallic structure in an adjacent excavation,
pit, or bore. Connecting additional surface and/or near-surface mitigation, such as additional
ribbon and/or shallow anodes, can further reduce the effects of AC induction. Installation of this
type of mitigation at targeted locations along a metallic structure, which are determined from the
AC induction modeling process, can further reduce the effects of AC induction along the metallic
structure.

For project sites which have surficial soils that display a high resistivity, one downside for
surface and/or near surface grounding is the length of mitigation ribbon and/or the number of
shallow anodes which may be required to achieve the desired mitigation results. This method
situation can prove to be problematic in areas where rights-of-way (ROW are constrained such
as in urban areas or ROW’s which contain multiple utilities.

4.8.2 Deep Grounding


Deep grounding generally refers to mitigation elements which are installed deep into a soil
mass, such as deep drilled ground wells (deep wells). Deep wells generally consist of one or
more anodes drilled vertically into the ground in order to achieve the desired mitigation results.
The actual depth of deep wells can vary significantly based on need, but they generally extend
to depths greater than 100 feet.

Page 193 of 284


Xcel Pipe Xcel Energy AC Interference Program: Metallic Pipelines

In general, construction costs are generally higher for deep well grounding than for comparable
surface and/or near-surface grounding. However, deep well grounding can be a viable option in
specific applications where one or both of the following criteria are true:

 The soil resistivity at the ground surface is significantly greater than the soil resistivity at
lower depths; and/or

 Horizontal surface grounding is not feasible due to construction constraints (i.e. limited
ROW)

For typical AC induction mitigation systems, where surface and/or near surface and deep
grounding are both viable options, surface and/or near surface grounding generally proves to be
more efficient and economical because it can achieve a lower resistance to ground for lower
overall cost. The table below provides a comparison of three different mitigation options: zinc
ribbon and copper cable, which are both surface to near surface mitigation options, and the
deep well, which is a deep grounding mitigation option.

Effective in Effective
Effective Soils with
Ease Cost History in Areas
Mitigation as Extremely
of of of with
Option Fault High
Construction Construction Effectiveness Resistivity Limited
Mitigation
Values ROW
Zinc
Moderate Low Yes Likely Unlikely Unlikely
Ribbon
Copper
Yes Moderate Yes Likely Likely Unlikely
Cable
Deep
No High Yes Unlikely Likely Unlikely
Well

5 Additional Potential Risk Factors


Throughout this program, we have identified additional items or risk factors which may positively
or negatively impact Xcel Energy’s risk profile specific to this program. Identified additional
potential risk factors include:

 Increased or Decreased AC Interference Buffer Zones.

5.1 Increased or Decreased AC Interference Buffer Zones


In this program, we are currently using the following buffer zones to limit Tasks 1 through 3:

Page 194 of 284


AC Interference Program: Metallic Pipelines
Project Location: New Mexico and Texas, USA

Voltage Buffer Zone (either side of centerline)


115 kV 800 feet
230 kV 1,200 feet
345 kV 1,500 feet

These values were utilized as our buffer values because they are generally accepted within the
Oil and Gas and Corrosion Engineering industries. However, we now know the impact of AC
interference from an electrical transmission line onto a metallic pipeline is influenced by soil
resistivity, voltage of the electrical transmission line, geometry between the electrical
transmission line and a given pipeline, and the existing cathodic protection system on a given
pipeline. As such, there could be scenarios where the utilized buffer zone underestimates the
actual impact distance of AC Interference. For example, in the situation of a 345 kV electrical
transmission line, which is constructed in extremely high conductive soils conditions and which
parallels a metallic pipeline for several miles, the AC Interference impact distance could extend
greater than 1,500 feet.

6 Conclusions
Given the continued transmission build out within the SPS region, this program was tasked to
investigate the potential impact to new transmission line projects sited near metallic pipelines.
After more than a year of investigation, there is one clear finding: AC Interference from high
voltage transmission lines onto metallic pipelines needs to be analyzed in order to be
understood. With the continued construction of electrical transmission lines within the SPS
region, as well as the dense existing infrastructure of the Oil & Gas industry within this same
area, it is not practical for Xcel Energy to site its transmission lines to completely avoid all risk
specific to AC Interference.

Historically, AC Interference has not been a “hot topic” within either the electrical or oil and gas
industries. However, given the increased events (i.e. ruptures, leaks, etc.) associated with the
oil and gas pipeline industry over the last several years, there is now Federal regulation reform
within the oil and gas pipeline industry which highlights AC Interference and associated AC
Corrosion.

Xcel Energy Engineering is positioned to be an industry leader specific to understanding


potential AC Interference and has the opportunity to take a proactive approach to better
understand and work with pipeline owners to mitigate the risk AC Interference presents, while at
the same time upgrading its electrical transmission grid to better serve the owners of those
pipelines. The current program has helped in numerous ways on new transmission line projects
and has been met with great positivity from oil and gas pipeline owners in which we have
interacted with. Xcel Energy Engineering believes it is useful to analyze the effects of new Xcel

Page 195 of 284


Xcel Pipe Xcel Energy AC Interference Program: Metallic Pipelines

Energy electrical transmission line projects on existing pipelines to ensure we are taking
reasonable measures to understand and address AC interference.

7 References
 B. Tribollet, “AC Induced Corrosion of Underground Pipelines”, Underground Pipeline Corrosion
Conference, June 2014.

 CAN/CSA-C22.3 No.6 – 13 “Principles and Practices of Electrical Coordination between Pipelines


and Electric Supply Lines”, Standards Council of Canada, June 2014.

 CAN/CSA C22.3 No.1 – 06 “Overhead Systems”, Standards Council of Canada, July 2007.

 EL-904 Research Project 742-1 “ Mutual Design Considerations for Overhead AC Transmission
Lines and Gas Transmission Pipelines, Volume 1: Engineering Analysis”, Electric Power
Research Institute (EPRI), September 1978.

 EL-3106 “Power Line Induced AC Potential on Natural Gas Pipelines for Complex Rights-of-Way
Configurations, Volume 1: Engineering Analysis”, Electric Power Research Institute (EPRI) and
American Gas Association (AGA), May 1983.

 Fletcher, K. C., “Issues Affecting Co-Location of Energy Infrastructure”, Governor’s Office of


Energy Independence and Security, State of Maine, May 2011.

 Giddings, J., Marshall, D., and Moore, C., “Shocking News – Analyzing AC Inducted Potentials on
Buried Pipelines”, American Society of Civil Engineers (ASCE) Pipelines Conference, Portland,
Oregon, May 2014.

 Gummow, R.A. “A/C Interference Guideline Final Report”, Canadian Energy Pipeline Association,
June 2014

 INGAA Report No. 2015-04, “Criteria for Pipelines Co-Existing with Electric Power Lines”,
Interstate Natural Gas Association of America (INGAA), October 2015.

 Johar, U.M. and Shwehdi, M.H., “Transmission Line EMF Interference with Buried Pipelines:
Essential and Cautions”, Proceedings from the International Conference on Non-Ionizing
Radiation, October 2003.

 NACE SP0169, “Standard Practice – Control of External Corrosion on Underground or


Submerged Metallic Piping Systems”, National Association of Corrosion Engineers (NACE)
Report SP-0169-2013, May 2013.

Page 196 of 284


AC Interference Program: Metallic Pipelines
Project Location: New Mexico and Texas, USA

 NACE TG327, “AC Corrosion State-of-the-Art: Corrosion Rate, Mechanism and Mitigation
Requirements, National Association of Corrosion Engineers (NACE) Report 35110, October
2010.

 Prinz, W. “AC Induced Corrosion on Cathodically Protected Pipelines”, Proceedings of National


Association of Corrosion Engineers (NACE) Nashville Conference, April 2010.

Page 197 of 284


Considerations for a Comprehensive Review
of Temporary Protective Grounding
Procedures

Kevin G. Verett David T. Chessmore


Transmission Operations System Protection
Oncor Electric Delivery Oncor Electric Delivery
Waco, TX, USA Fort Worth, TX, USA
kevin.verett@oncor.com david.chessmore@oncor.com

Page 198 of 284


Considerations for a Comprehensive Review of
Temporary Protective Grounding Procedures

Kevin G. Verett David T. Chessmore


Transmission Operations System Protection
Oncor Electric Delivery Oncor Electric Delivery
Waco, TX, USA Fort Worth, TX, USA
kevin.verett@oncor.com david.chessmore@oncor.com

Abstract—Temporary Protective Grounding (TPG)


procedures for protecting personnel working on de-energized II. INTRODUCTION
transmission lines and substation equipment have been used De-energizing transmission lines and substation equipment
since the early days of the electric utility business. TPG for construction and maintenance activities allows work to be
procedures and TPG equipment recommendations have evolved performed without the hazards associated with working on
over the years due to accident investigations, advancements in
energized equipment. Electric utility experience, various
scientific research, additional computer modeling of work
industry standards[1]–[4], and the U.S. Occupational Safety &
scenarios, and higher fault currents. Oncor performed a
comprehensive review of their TPG procedures and TPG Health Administration (OSHA)[5], all recognize that even
equipment used in Transmission Operations to ensure workers with the lines and equipment de-energized there can still be
are protected when work is being performed on de-energized shock hazards for personnel unless proper TPG procedures are
transmission lines and substation equipment. The knowledge followed and TPG equipment is properly applied. This
acquired during the review will be used to revise Oncor’s TPG requires a thorough understanding of the electrical hazards that
procedures and develop an updated list of approved TPG may be present when performing work on de-energized lines
equipment for different applications in Oncor’s service areas. and equipment and how to mitigate or eliminate those hazards
through the proper use of TPG equipment, work procedures,
This paper includes an overview of hazards associated with insulated tools, and other protective devices. A lack of proper
work on de-energized lines and substation equipment, an understanding can lead to a false sense of protection. An
examination of applicable OSHA, IEEE, NESC, and ASTM example of a false sense of protection is the phrase that many
standards, and summarizes the best practices interviews with electrical utility workers have been taught, “If it is not
other utilities that were performed by Oncor. Additionally, the grounded, then it is not dead”. This is a true statement, but it
paper presents an engineering analysis methodology that takes implies something that is not true, that being “If it is grounded,
into account the available short circuit current and associated then it is dead and safe to work on”. Compliance with a
X/R ratio, three-phase versus single-phase accidental company’s TPG procedures will be greatly enhanced if the end
energization, location and configuration of TPG equipment, and
users of the procedures have a thorough understanding of the
clearing time of the source of accidental energization. Using this
methodology, a computer program was developed that can
electrical hazards that may be present when performing work
determine the maximum current rating of TPG cables for on de-energized lines and equipment, and how to mitigate or
different scenarios. eliminate those hazards.

Keywords—Temporary Protective Grounding, Temporary III. SOURCES OF ELECTRICAL HAZARDS WHEN WORK IS
Protective Grounding Equipment, Equipotential Zone, PERFORMED ON DE-ENERGIZED LINES AND EQUIPMENT
Transmission Operations
A. Accidental Closing of a Circuit’s Isolating Device
I. NOTICE Procedures to de-energize and isolate lines and equipment
The content of this paper is for discussion purposes only are well established in the electric utility business and are
and is not intended to be a substitute for the work and safety required by the U.S. OSHA [6] when work is to be performed
policies and procedures that may be in place or appropriate for on de-energized lines and equipment. These procedures
other companies. The views expressed therein are those of the include a means of ensuring that the lines and equipment are
authors and not intended to be advice or substitutes for other not energized until the work is completed and the workers are
companies’ rules, etc. or advice as to compliance with U.S. in the clear of the lines or equipment. Failure to follow these
procedures can result in the intentional but erroneous closing of
OSHA rules and regulations.
the circuit’s isolating device.

Page 199 of 284


B. Contact Between a De-energized Circuit and an Energized IV. EFFECTS OF ELECTRIC CURRENT ON THE HUMAN BODY
Circuit Charles Dalziel performed extensive research and
It is a common occurrence that de-energized lines pass published numerous papers [9], [10] on the effects of electric
over, pass under, or are located in close proximity to energized current on humans in the 1940s, 1950s, and 1960s. His work is
circuits. Contact can occur between the de-energized and the basis for several industry standards for minimizing the
energized circuits due to failure of the supporting structures of effects of electrical shocks [1]–[3] and is the starting place for
either circuit, movement of the conductors during planned understanding the hazards associated with work on de-
work, or high winds. When contact occurs the voltage applied energized lines and equipment. Dalziel’s research on the effect
to the de-energized circuit will be a function of the voltage of of electric current on men and women is summarized in Table
the energized circuit. Therefore, it may be more or less than 1 [11].
the rated voltage of the de-energized circuit. The location of
the contact between the two circuits may be miles away from Ventricular fibrillation is a condition where the heart does
the worksite of the de-energized work. not beat properly such that normal blood flow is interrupted
which can lead to death unless action is taken to restore the
heart to its normal rhythm [12]. Table 1 indicates that
C. Backfeed from Secondary Sources
ventricular fibrillation is possible when the body current is 670
De-energized circuits that are connected to transformers mA or more for short durations of 0.03 s or 67 mA or more for
can be energized at full normal voltage from the secondary of a longer durations up to 3.0 s. TPG procedures must be designed
transformer. The secondary could become energized due to the to limit a worker’s exposure to electrical current such that the
application of test voltages during maintenance procedures on risk of ventricular fibrillation is eliminated. Equation (1) was
a transformer, by a generator or by human error. derived by Dalziel from his research [11] which gives the limit
for body current to prevent ventricular fibrillation from
D. Ground Potential Rise occurring if a worker is exposed to a hazardous voltage.
A Ground Potential Rise (GPR) will occur anytime current
k
is injected into the earth by the energization of a ground I= (1)
electrode by neutral currents, faults, or lightning. The t
magnitude of the GPR will be dependent upon the amount of
where
current injected into the earth, the resistance of the ground
electrode, the resistivity of the soil, and the proximity of the I is the body current, in mA
worker to the ground electrode.
k is the Dalziel body weight constant
E. Electric Field and Magnetic Field Induction k = 116 for a worker weighing 110 lb
Capacitance exists between two conductors which are k = 157 for a worker weighing 155 lb or more
separated by some distance. When one of the conductors is
energized a voltage will be impressed upon the other de- t is the current flow time, in seconds
energized conductor by electric field induction. The induced
voltage with respect to the earth is a function of the voltage of TABLE 1. EFFECT OF ELECTRIC CURRENT
the energized conductor, the separation distance of the
conductors, and their height above the earth. If a worker Men Women
Effect
(mA) (mA)
makes contact with the de-energized conductor then they may
No sensation on the hand 0.4 0.3
be subjected to current flowing through their body due to the Slight tingling (perception threshold) 1.1 0.7
charging current of the capacitance between the circuits [7]. Shock, not painful and muscle control not lost 1.8 1.2
Painful shock, painful but muscle control not
Conductors that run parallel to each other can also be lost
9.0 6.0
magnetically coupled together due to inductive coupling. Painful shock (let-go threshold) 16.0 10.5
Current flow in one of the conductors will create a magnetic Painful and severe shock, muscles contract,
23.0 15.0
field that can induce a voltage onto the other conductor. The breathing difficult
level of induced voltage is a function of the current flowing in Possible ventricular fibrillation from short
670.0 670.0
the energized conductor, the separation distance between the shocks (0.03 s)
lines and the distance that they run parallel to each other [7]. Possible ventricular fibrillation from longer
67.0 67.0
shocks (3.0 s)

F. Lightning
The hazards at a worksite associated with lightning are V. BODY CURRENT EXPOSURE LIMITS
significant but difficult to predict. The use of TPG procedures
and equipment may not be sufficient to protect workers from A. For Cases of Accidental Energization with Exposure Time
those hazards [8]. of 0.03 s to 3.0 s
Equation (1) indicates that the body current limit for
preventing ventricular fibrillation is a function of the time to
which a worker is exposed to current flowing through their
body. In the case of accidental energization of a de-energized

Page 200 of 284


and grounded line or device, the exposure time is a function of Ve is the exposure voltage across the body, in V
the fault current clearing scheme associated with the source of
the accidental energization. Consideration should be given to Rb is the body resistance, in Ω
using a clearing time in (1) that includes the operating time of The total body resistance can vary depending upon several
the primary and backup protective schemes plus the opening factors including moisture on the surface of the skin. A value
time of the protective device [13]. It is common utility practice of 1000 Ω [14] is commonly used as the average body
to use fault clearing times in (1) of 0.25 s (15 cycles) or less for resistance for hand to hand, hand to foot and foot to foot
substation buses with differential protective relay schemes and contact. This value assumes that the hand and foot contact
0.25–0.50 s (15–30 cycles) for transmission lines. Using these resistances and the glove and shoe resistances are equal to zero
clearing times in (1) yields the body current exposure limits [14], [15]. Some utilities choose to use a lower value of 500 Ω
shown in Table 2. [14] in order to be conservative in their engineering analysis of
shock hazards in the workplace. It should be noted that the
TABLE 2. BODY CURRENT EXPOSURE LIMITS U.S. OSHA recommends a value of 500 Ω by pointing out that
the internal body resistance of 500 Ω better represents the
Body Current Limit (mA) minimum resistance of a worker’s body in actual work
conditions [16].
Fault Clearing Time 110 lb Worker 155 lb Worker

0.25 s (15 cycles) 232 314


VII. HAZARDOUS DIFFERENCES OF ELECTRICAL POTENTIAL
0.50 s (30 cycles) 164 222
The electric utility industry recognizes the need and the
U.S. OSHA requires employers to protect workers from
hazardous differences of electrical potential when working on
B. For Cases of Accidental Energization with Exposure Time
de-energized and grounded lines and equipment [17]. The
that Exceeds 3.0 s method for determining what constitutes a hazardous voltage is
Equation (1) is not valid for exposure times that exceed 3.0 dependent upon whether the source of energization is due to
s. This can be the case when buses do not have differential accidental energization, a fault on a nearby circuit, or from
relay protection schemes or when fuses are used as the fault induction.
clearing device. An example is a 138-12.5 kV load serving
substation where the 12.5 kV bus is protected by overcurrent A. For Cases of Accidental Energization with Exposure Time
relays that must be coordinated with the feeder breaker of 0.03 s to 3.0 s
overcurrent relays. The type of fault clearing device may
further lengthen the clearing time. This can result in fault Equation (1) is valid for exposure time of 0.03–3.0 s and
clearing times that exceed 3.0 s (180 cycles). can be used with (3) to calculate the exposure voltage limit to
prevent ventricular fibrillation only if the employer protects
workers from hazards associated with involuntary muscle
C. For Cases of Induction with Indefinite Exposure Time
reactions from electric shock (for example, the hazard to a
In the case of exposure to currents resulting from electric worker from falling as a result of an electric shock) [16]. If
field and/or magnetic field induction on a de-energized and workers are not adequately protected from the hazards
grounded line or device there is no protective relay scheme or associated with involuntary muscle reactions then the exposure
fuse that will detect and remove the source of current. voltage should be limited to 0.5 V [16].
Therefore, (1) is not applicable for exposure currents from
induction that exceed the let-go threshold given in Table 1. If Ve = I b ⋅ Rb (3)
the let-go threshold is exceeded then there is no definite
exposure time. If the exposure time exceeds 3.0 s (180 cycles) where
then ventricular fibrillation can occur with body currents as Ve is the exposure voltage limit across the body, in
low as 67 mA [12]. V
Ib is the exposure body current limit, in A
VI. BODY RESISTANCE
When a worker’s body is in contact with a difference in Rb is the body resistance, in Ω
electrical potential across two body points then they are subject
to electrical current flowing in their body. The amount of B. For Cases of Accidental Energization with Exposure Time
current that will flow is a function of the applied voltage and that Exceeds 3.0 s
the resistance of the path through the body. This relationship is Equation (1) is not valid for exposure times that exceed 3.0
expressed by solving Ohm’s Law in (2). s. Therefore, it should not be used in (3) to calculate the
exposure voltage limit. A conservative approach to
Ve
Ib = (2) determining an exposure voltage limit is to limit the exposure
Rb current to the let-go threshold of 10.5 mA from Table 1 as long
as the workers are adequately protected from the hazards
where associated with involuntary muscle reactions. This approach
Ib is the body exposure current, in A will result in an exposure voltage limit of 10.5 V from (3) with
a body resistance of 1000 Ω. An exposure voltage limit of this

Page 201 of 284


magnitude may be difficult to achieve when fault currents can occur when working at ground level and making contact
exceed 10,000 A. This is due to the short lengths of TPG cable with grounded structures, vehicles or work equipment.
that would be necessary to not exceed the exposure voltage
limit of 10.5 V as shown in Table 3[18]. B. Step Voltage (Potential)
A more practical approach is to limit the exposure voltage “Step voltage is the difference in surface potential that
to what various industry and regulatory standards indicate as could be experienced by a person bridging a distance of one
not being hazardous. A search of industry literature indicated meter with the feet without touching any grounded object.”
that an exposure voltage of 25 V or less is not considered [20] This can occur when working at ground level around but
hazardous [19]. This will result in body currents less than 67 not in contact with grounded structures, vehicles or work
mA which will not cause ventricular fibrillation as per Table 1. equipment.
C. Transfer Voltage (Potential)
TABLE 3. MAXIMUM LENGTH 4/0 COPPER TPG CABLE TO LIMIT
EXPOSURE VOLTAGE TO 10.5 V “Transfer voltage is a special case of touch voltage where
a conductive element brings the potential from an energized
Based Upon ASTM F 2249 Section 7.5.3 Equation 3 point to a remote point some distance away. This special type
Fault Maximum Cable Maximum Cable of touch voltage increases as the distance from the grounded
Current (A) Resistance (mΩ) Length (ft) structure or equipment increases.” [20] Some examples are:
• Working on conductors at or near ground level when
5000 2.100 32.7 TPG equipment is installed some distance from the
actual work.
10000 1.050 13.4
15000 0.700 7.0
• Making or breaking connections in structure ground
wires, phase conductors, or shield wires.
20000 0.525 3.8
• Making contact with grounded work equipment and
vehicles.
C. For Cases of Induction With Indefinite Exposure Time
Cases of induction in de-energized and grounded IX. METHODS FOR PROTECTING WORKERS FROM
transmission lines and equipment are very similar to those HAZARDOUS DIFFERENCES OF ELECTRICAL POTENTIAL
where the exposure time exceeds 3.0 s since there is no definite
exposure time and (1) is not applicable for calculating an A. Creation of Equipotential Zone to Reduce the Hazardous
exposure voltage limit. The induced voltages and currents are Differences of Electrical Potential
dependent upon several factors. These include the voltage of An Equipotential Zone (EPZ) is a “state of maintaining a
the nearby energized circuit, the amount of current flowing in near identical electrical potential between two or more items”
the circuit, the geometry of the conductors of each circuit and [20]. For de-energized and grounded work an EPZ is created
the spacing between the circuits. by the proper use of TPG equipment to bond all conductive
objects together such that any two points a worker touches are
VIII. TYPES OF HAZARDS ASSOCIATED WITH DIFFERENCES at the same potential or are reduced to a non-hazardous level.
IN ELECTRICAL POTENTIAL
When the work requires structure components to be removed,
care must be exercised to maintain the integrity of the EPZ or
Hazardous differences in electrical potential can occur at a additional methods to insulate or isolate the employee from the
worksite during de-energized and grounded work. This can hazards may be required. It is particularly challenging to
occur due to accidental energization of the de-energized and maintain an effective EPZ for workers on the ground.
grounded line, a fault occurring on an energized circuit that
shares the same structures as the de-energized line, from B. Insulation from the Hazardous Differences of Electrical
induction of nearby energized lines, or lightning. When this Potential
occurs the grounded line or equipment can be energized at
some voltage with respect to remote earth. This creates the Insulating devices such as rubber gloves and a variety of
possibility for a hazardous voltage between any two objects at devices made to cover up and work on energized lines and
the worksite that are grounded, a grounded point and another equipment in the electric utility business have been used for
point on the earth’s surface, or two points on the earth’s many years and their use is well understood. These same
surface. devices can be used to insulate workers from hazardous
differences in electrical potential that can exist when work is
A. Touch Voltage (Potential) being performed on de-energized and grounded lines and
equipment. When these devices are used for this purpose their
“Touch voltage is the voltage difference between an rating need only be for “the highest voltage that can be
energized metallic structure or equipment and a point an arm’s impressed upon grounded objects under fault conditions” or
reach away (approximately one meter). The separation may be from induction [21].
from one normal horizontal reach to a much larger distance due
to a conductive element extending the energization.” [20] This Electrical Hazard (EH) rated footwear [22], dielectric rated
footwear [23], or insulated mats can be used to insulate

Page 202 of 284


workers from hazardous touch, step, and transfer voltages. EH as possible. Listed below are possible fault current return paths
rated footwear may not be effective in wet or muddy in order of lowest impedance to the highest [25].
conditions if the depth of the water or mud exceeds the
• Multi-grounded distribution neutral conductor
thickness of the soles. This is due to the insulation qualities of
the footwear being part of the sole or foot pad inside the • Grounded overhead shield wire
footwear. Dielectric rated footwear is made from an insulating
material that is used for the whole boot or shoe. In wet or • Structure ground
muddy conditions, dielectric rated footwear is effective as long • Anchor rod
as the depth of the water or mud does not exceed the height of
the top of the footwear. • Temporary ground rod

C. Isolation from the Hazardous Differences of Electrical XI. ENGINEERING ANALYSIS METHODOLOGY FOR
Potential DETERMINING THE LEVEL OF HAZARDOUS DIFFERENCES IN
Some companies use the term isolation different than it will ELECTRICAL POTENTIAL
be used in this paper. For purposes of this paper, isolation is An engineering analysis is necessary to create TPG
the practice of isolating a worker or the public from sources of procedures and methods that will protect workers from
hazardous differences in electrical potential that can occur hazardous differences of electrical potential. This analysis
when de-energized and grounded work is being performed. must include determining the fault current and its X/R ratio at
The restricted area must be large enough to exclude the area of the worksite and the clearing time for sources of accidental
hazardous levels of ground potential rise. Examples include: energization. This information can be provided through the
use of fault modeling software in use at most electric utilities.
• Restricting access to grounded structures where TPG
This information is typically readily available for substation
equipment has been installed.
buses due to the need for such values for calculating the
• Restricting access to locations where TPG equipment settings of protective relay systems, sizing fuses, and
has been installed at some distance away from a calculating arc flash exposure levels. Therefore, the analysis is
structure and a temporary ground rod is used. fairly straight forward for worksites at substations. However,
for worksites on transmission lines the information may not be
• Restricting access to grounded vehicles or work readily available and may require significant resources to
equipment. obtain this information for the worksite for any planned or
unplanned work. Factors to be considered for the engineering
X. PURPOSE OF TEMPORARY PROTECTIVE GROUNDING analysis methodology are discussed below.

A. Limit Worker Exposure Voltage A. Use of Impedance Versus Resistance for TPG Equipment
Workers engaged in de-energized and grounded work must The exposure voltage across a worker when working on a
be protected from hazardous differences of electrical potential grounded line is a function of the voltage drop (4) across the
that can occur at a worksite due to accidental energization or TPG equipment that is installed in parallel with the worker
induction. This protection is provided by TPG equipment [26]. The exposure voltage limit from (3) can be used in (5) to
installed on lines and equipment to limit currents through a determine the maximum impedance of the TPG equipment
worker by limiting the exposure voltage at the worksite [24]. such that the exposure voltage limit will not be exceeded. The
The proper application of TPG equipment will create a low reactance component of the impedance is a function of the
impedance path in parallel with the worker that will limit the geometry of the installation of TPG equipment. On some
body current to acceptable levels. worksites the configuration changes as the work progresses. It
can be a difficult task to determine the impedance unless
B. Limit the Exposure Time modeling software is used for each configuration. A simplified
Equation (1) indicates that levels of body current that may approach to take into account the inductive reactance is given
result in ventricular fibrillation are a function of the time that a in [27] where correction factors have be developed to
worker is exposed to the current. For cases of accidental approximate the inductance as a function of the cable
energization of de-energized lines and equipment the proper resistance of a limited number of TPG equipment
use of TPG equipment will ensure that the fault clearing configurations. This approach works fairly well for substation
protective device associated with the source of accidental worksites where the TPG equipment configuration is more
energization will clear the fault as quickly as possible. For predictable for the different phases of the work. It is more
cases of accidental energization of two or three phases this is difficult to apply this method for line work where the
accomplished by using TPG equipment to create a multi-phase configuration of the TPG equipment is dynamic as the work
short circuit that is connected to the best ground electrode at progresses at a worksite. Some utilities use only the resistance
the worksite. For cases of single-phase accidental of the TPG equipment for both line and substation work and
energization, there must be a low impedance fault current include a safety factor to compensate for not using the
return path that will ensure sufficient current flows during the impedance.
fault to operate the fault clearing protective devices as quickly

Page 203 of 284


C. Thermal Rating of Single TPG Cables
Ve = (R + j ⋅ X L ) ⋅ I f (4)
The electric utility business has historically used ASTM F
855-15 Table 1 or Table 2 [29] to determine the fault current
rating for TPG cables and equipment. The ratings given in
where
ASTM F 855-15 Table 1 are valid only for fault current source
Ve is the exposure voltage across the body, in V X/R ratios of 1.8 or less. The values given in ASTM F 855-15
Table 2 are based upon values from EPRI RP2446 computer
R is the resistance of the TPG equipment, in Ω program RGTC “A Desktop Computer Program for
XL is the inductive reactance of the TPG equipment, Calculating Ratings of Temporary Protective Ground Cables”
in Ω and are valid for X/R ratios that do not exceed 30. The values
calculated by this computer program were verified by EPRI by
If is the fault current at the worksite, in A conducting high current destructive testing of various TPG
cables [30].
The X/R ratio for most of the transmission and distribution
substation buses in the Oncor system is greater than 1.8.
= (R + j ⋅ X L )
Ve Therefore, the values given in ASTM F 855-15 Table 2 or the
ZTPGmax = (5) EPRI RGTC must be used to calculate the values. The values
If given in ASTM F 855-15 Table 2 are calculated at X/R ratio of
30 and only for 0.25 s (15 cycles) or less clearing time. The
where
use of the ASTM ratings will be conservative for worksites
ZTPGmax is the maximum allowed impedance of the with X/R less than or equal to 30 and will not be adequate for
TPG equipment in parallel with the worker, in Ω worksites where the X/R ratio exceeds 30. In addition, the
ASTM ratings are not valid for worksites where the fault
Ve is the exposure voltage limit across the body, in current clearing time exceeds 0.25 s (15 cycles). For this
V reason, Oncor has chosen to use the theoretical approach
If is the fault current at the worksite, in A suggested by V.T. Morgan [31] that was the basis for the EPRI
RGTC. Since the computer program itself is no longer
R is the resistance of the TPG equipment, in Ω available from EPRI, Oncor developed a Python script based
XL is the inductive reactance of the TPG equipment, upon [31] that can calculate the ultimate rating of a standard
in Ω cable size using any X/R ratio and clearing time input
variables. The accuracy of the output of the script has been
B. Location of TPG Equipment verified against the output of the EPRI RGTC program. The
script also calculates a withstand rating based upon a user
The location where TPG equipment is installed with respect defined de-rating factor similar to that used in ASTM F 855-15
to the actual worksite will affect the exposure voltage. A Table 1.
simple and very effective method of limiting the exposure
voltage at a worksite is for the TPG equipment to be installed The use of an accurate cable rating methodology is
at the worksite where workers will be contacting the lines, imperative for worksites where the fault current clearing time
structures, or equipment. This is referred to as worksite exceeds 0.25 s (15 cycles). Table 4 shows an example of the
grounding [28]. However, the physical presence of TPG effect of the clearing time on the rating of TPG cables. The
equipment at the worksite may interfere with the work when values in Table 4 are based upon an X/R ratio of 30, 40° C
the work requires the removal of structure components. Some ambient temperature, and a withstand de-rating factor of 70%
utilities allow the TPG equipment to be located a short distance of the ultimate rating.
away from the worksite to allow room for the work to take
place. This should not be done unless an engineering analysis D. Thermal Rating and Use of Parallel TPG Cables
has been performed to determine the effect on the exposure When the fault current exceeds the thermal rating of a
voltage. The combination grounding method [28] can be used single TPG cable then consideration must be given to either
to allow the worksite TPG equipment to be moved out of the paralleling two or more cables together or to increasing the size
way of the work and limit the worker exposure voltage to non- of the cable. The best protection is obtained by the use of one
hazardous levels. Industry standards [28] included a few other cable of sufficient capacity [32], [33]. Use of parallel cables
methods of grounding with TPG equipment that have differing may be preferred when there are concerns about the weight of
levels of protection for the worker. An engineering analysis copper cables larger than 4/0. When parallel cables are used it
should be performed for whatever method of grounding is used is imperative that measures be taken to help ensure that the
to determine if the method will provide adequate protection for cables equally share the fault current [32], [33]. This is best
workers for the planned work scenario. Several computer accomplished by using parallel cables with the same length, of
modeling programs are available that can be used to perform the same material, with the same TPG clamps on all of the
the analysis. cables, having the same impedance, and being located as close
as possible to each other [32]–[34]. In addition, the thermal
rating of each cable in the parallel combination should be de-
rated by 10–20% [32], [34]. It is highly recommended that

Page 204 of 284


cables and clamps used in parallel combination be subjected to Some utilities have chosen to only consider the case of
the test criteria in ASTM F855-15 Table 2 for the actual three-phase accidental energization based upon historical
planned configuration and usage rather than rely upon a de- events indicating that the probability of a single-phase
rating factor [33]. accidental energization at full fault current is minimal.

E. Three-Phase Versus Single-Phase Accidental Energization TABLE 4. TPG CABLE CAPACITY


Exposure voltage that results from a three-phase accidental
Copper
energization can be significantly different than that for a Cable Size
2/0 4/0
single-phase event at the same worksite. This is illustrated by
the comparison of a three-phase versus a single-phase Duration Ultimate Withstanda Ultimate Withstanda
energization in Fig. 1. (cycles) (A) (A) (A) (A)

• For the three-phase case, the resultant current flowing


15 33879 23715 53785 37650
into the grounded overhead shield wire, the structure
grounds, and the temporary ground rod is near zero. 30 25547 17883 40558 28391
Therefore, the resistance component, R, used in (4) to
calculate the worker exposure voltage includes only the 60 18721 13105 29721 20805
resistance of RTPG phase 1-2 and RTPG phase 2-3. Since the 90 15478 10834 24572 17201
current injected into the earth at the worksite is much
less than the three-phase fault current, the exposure of 180 11086 7760 17599 12320
workers on the ground to hazardous touch, step, and 200 10530 7371 16718 11703
transfer voltages is reduced.
300 8632 6042 13704 9593
• For the case of energizing only phase 1, the resistance
component, R, used in (4) to calculate the worker 400 7490 5243 11891 8324
exposure voltage includes the resistance of RTPG phase 1-2, 500 6707 4695 10648 7454
RTPG phase 2-3, the parallel combination of all the other
a.
TPG cable resistances, and the structure grounds. The Ultimate/Withstand ≈ 70 %
total resistance for this case can be significantly greater
than the three-phase case which results in a higher
exposure voltage for the same fault current. Due to XII. SELECTION AND USE OF TPG EQUIPMENT
current being injected into the earth at the worksite,
workers on the ground may be exposed to hazardous A. TPG Equipment Industry Standard
touch, step, and transfer voltages. The industry standard in the U.S. for TPG equipment is
ASTM F855-15 [29]. Table 1 of that standard is only
applicable when the X/R ratio of the fault current source does
not exceed 1.8. TPG equipment meeting the requirements of
Table 1 of the standard should not be used at worksites where
the X/R ratio exceeds 1.8. This is due to increased heating and
mechanical force on the TPG cables and equipment that occur
when the fault current is asymmetrical. The application of
TPG equipment meeting the criteria of ASTM 855-15 Table 1
at worksites with an X/R ratio greater than 1.8 may result in
their failure. Such failures may result in the complete loss of
protection of the workers from hazardous differences in
electrical potential [35].
Only equipment meeting ASTM F855-15 Table 2 should
be used for worksites where the fault current X/R ratio exceeds
1.8. It is important to verify if existing TPG equipment in use
meets the requirements of ASTM F855-15 Table 2. This may
be difficult since not all manufacturers of TPG equipment
permanently mark their clamps with a catalog number.

B. Use of Flat Face Clamps


Clamps that are designed to attach to flat surfaces are
widely used by some utilities for the grounded end of a TPG
assembly. Industry testing of these devices has indicated that
most of the clamps will not meet the criteria of ASTM F855-15
for use in applications where the X/R ratio exceeds 1.8.
Fig. 1. Unbalanced Chain TPG Scenario

Page 205 of 284


C. Use of Welded Studs and Bolts for TPG Attachment Point TPG procedures. Summarized below are some of the pertinent
The installation of TPG equipment on aluminum tubular items from the meetings.
bus of a diameter of 4” or greater requires the use large clamps • All of the companies had performed a detailed
which can be heavy when used with 4/0 copper cables. This engineering analysis that was the basis of their TPG
has led to the use of welded aluminum grounding studs that are procedures. Three of the companies used a consulting
installed on the bus during construction. This allows an engineering firm and two performed the analysis with
attachment point that is small enough to allow smaller TPG their own resources.
clamps to be used. Industry testing has indicated that unless
the diameter of the stud is 1.5” or greater the stud will not pass • The TPG procedures used by each company were in
the requirements of ASTM F855-15 Table 2 grade 5H or some instances significantly different from the other
higher. Therefore, these devices should not be used as companies while each was based upon an engineering
attachment points for TPG equipment where the fault current analysis methodology consistent with good engineering
level requires the use of grade 5H or greater TPG assemblies and electric utility practices.
unless they have been tested to meet ASTM F855-15 Table 2 • Compliance with TPG procedures and their acceptance
requirements. Several manufacturers of TPG equipment offer by the end users increased when end users were taught
bus clamps rated 5H or greater with a stud attachment point as about the electrical hazards associated with de-
part of the clamp. This allows the bus clamp to be installed energized and grounded work and were shown how to
without the weight of the cable and gives a suitable attachment eliminate or reduce those hazards through proper
point for smaller size clamps. application of TPG equipment. All of the companies
It is a common practice for two or four hole pad connectors had a TPG subject matter expert that was involved in
to be used for attaching bus or conductor to substation the development of training for employees.
equipment. Some utilities have the practice of using a long • All of companies require the use of TPG equipment that
bolt as part of the attachment hardware to provide a place for meets the requirements of ASTM F855-15 Table 2.
attaching TPG equipment. This should not be done unless high
current testing has been performed to verify that the attachment • Four of the companies allow the use of parallel TPG
point is sufficient for the fault current at the worksite. Several cables for high current applications. It was emphasized
manufactures offer threaded studs that meet ASTM F855-15 that consideration should be given to performing high
grade 5H or higher that can be used to provide a suitable current tests to confirm the performance of parallel TPG
attachment point for such applications. cable assemblies for the actual planned use and
configuration.
D. Use of TPG Components from Muliple Manufacturers
ASTM F855-15 requires specific testing criteria and B. Oncor Present Status
arrangement of TPG equipment assemblies in order for Oncor has chosen to develop an engineering analysis
manufacturers to state that their TPG equipment meets the methodology that combines practices learned from the best
requirements of the standard [36]. This means that the practices meetings. The methodology for determining the
components of a TPG assembly are not tested as individual thermal rating of TPG cables and for evaluating the
components but rather the whole assembly is tested as a unit. effectiveness of the worksite grounding method has been
Therefore, when a manufacturer offers equipment meeting the developed. Modeling of the effect of the location of TPG
standard it is for the whole assembly using specific clamps, equipment when using worksite grounding and combination
cable, ferrules, crimping method, and length. Some utilities grounding are presently being conducted. When these studies
allow the use of clamps from different manufactures to be used are completed TPG procedures will be revised based upon
in the same TPG assembly. The practice of using components those results.
or crimping methods in an assembly that have not been tested
as an assembly may result in the failure of an assembly during XIV. CONCLUSIONS
fault conditions. Such practices may occur when utilities
assemble TPG equipment assemblies or third party vendors • Protection of workers from hazardous differences in
assemble and sell TPG assemblies from components obtained electrical potential when engaged in de-energized and
from different manufactures. There can be justification for this grounded work requires a thorough understanding of
practice due to user preferences in components, but those hazards and how to eliminate or mitigate those
consideration should be given to performing high current hazards.
testing to ensure that the assembly will not fail if subjected to • An engineering analysis is required to understand the
fault currents in the planned use of the assemblies. source, nature and level of hazardous differences in
electrical potential at a worksite.
XIII. METHODOLOGY FOR DEVELOPMENT OF TPG WORK • TPG work procedures should be based upon an
PROCEDURES engineering analysis of the hazards at a worksite.
A. Best Practices Meetings • TPG equipment should be rated and tested for fault
Oncor conducted best practices meetings with five electric current for a particular application.
utilities that are known as industry leaders on the subject of

Page 206 of 284


• Training and education of the end users of TPG work [24] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines,
procedures concerning the hazards of and methods for section 4.1
eliminating or mitigating the hazards will result in [25] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines,
section 6.5
acceptance and compliance with the procedures.
[26] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines,
• Ongoing participation in best practices meetings with section 4.6
other utilities can help ensure proper understanding of [27] IEEE Std 1246-2011, Guide for Temporary Protective Grounding
how to protect employees from hazardous differences in Systems Used in Substations, Annex C
electrical potential. [28] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines,
section 7.4
[29] ASTM F 855-15, Standard Specification for Temporary Protective
REFERENCES Grounds Used on De-energized Electric Power Lines and Equipment.
[30] J. Riechman, J. Kuffel and M. Vainberg, “Fusing Research on Personnel
[1] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines Ground Cables” EPRI, EL-5258, Research Project 2446-1, final report ,
[2] IEEE Std 1246-2011, Guide for Temporary Protective Grounding July 1987
Systems Used in Substations [31] V.T. Morgan, “Rating of Conductors for Short-Duration Currents”,
[3] IEEE Std 80-2013, Guide for Safety in AC Substation Grounding Proceedings of IEE, Vol. 118, No. 3|4, March|April 1971.
[4] National Electrical Safety Code® NESC® C2-2017 Edition [32] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines,
section 5.2
[5] US Department of Labor OSHA 1910.269(n) and 1926.962, Federal
Register volume 79, No. 70, dated April 11, 2014 [33] ASTM F 855-15, Standard Specification for Temporary Protective
Grounds Used on De-energized Electric Power Lines and Equipment,
[6] US Department of Labor OSHA 1910.269(m) and 1926.961 section X5
[7] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines, [34] Gary Zevenbergen, “Developing Fault Current Withstand Ratings for
section 4.2 Personal Protective Ground Cables for High X/R Ratios”, Western Area
[8] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines, Power Administration, December 2011
section 4.4 [35] ASTM F 855-15, Standard Specification for Temporary Protective
[9] Charles F. Dalziel, “Deleterious Effects of Electric Shock”, 1961, Grounds Used on De-energized Electric Power Lines and Equipment,
presented at a Meeting of Experts on Electrical Accidents and Related section X4
Matters, Sponsored by the International Labour Office, World Health [36] ASTM F 855-15, Standard Specification for Temporary Protective
Office and International Electrotechnical Commission, Geneva, Grounds Used on De-energized Electric Power Lines and Equipment,
Switzerland, October 23-31, 1961. Reproduced by the Hazards Control section 12
Department, Lawrence Radiation Laboratory, Livermore, California
with permission of the author.
[10] Charles F. Dalziel, “Effects of Electric Shock on Man”, IRE
Transactions on Medical Electronics (Volume: PGME-5 ), pp. 44-62,
July 1956.
[11] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines,
section 6.1
[12] Charles F. Dalziel, “Deleterious Effects of Electric Shock”, 1961,
presented at a Meeting of Experts on Electrical Accidents and Related
Matters, pp. 20. Sponsored by the International Labour Office, World
Health Office and International Electrotechnical Commission, Geneva,
Switzerland, October 23-31, 1961. Reproduced by the Hazards Control
Department, Lawrence Radiation Laboratory, Livermore, California
with permission of the author.
[13] IEEE Std 1246-2011, Guide for Temporary Protective Grounding
Systems Used in Substations, section 4.3.2
[14] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines,
section 6.2
[15] IEEE Std 80-2013, Guide for Safety in AC Substation Grounding,
section 7.1
[16] US Department of Labor OSHA 1910.269, Appendix C, section III.D.1
[17] US Department of Labor OSHA 1910.269(n)(3)
[18] ASTM F 2249-03(2015), Standard Specifications for In-Service Test
Methods for Temporary Grounding Jumper Assemblies Used on De-
Energized Electric Power Lines and Equipment, section 7.5.3
[19] Doug Dorr, “Determining voltage levels of concern for human and
animal response to AC current”, Power & Energy Society General
Meeting, 2009, PES 2009, IEEE
[20] IEEE Std 1048-2016, Guide for Protective Grounding of Power Lines,
section 3
[21] US Department of Labor OSHA 1910.269, Appendix C, section III.C.2
[22] ASTM F 2413-11, Standard Specification for Performance
Requirements for Protective (Safety) Toe Cap Footwear
[23] ASTM F 1117-03, Standard Specifications for Dielectric Footwear

Page 207 of 284


Design and Installation of Tubular Steel Poles 200 Feet and Taller

By:

Kent Lam, Transmission Engineer


Thales Ramier, P.E., Transmission Engineer
Leidos Engineering, LLC

June 30, 2017

Page 208 of 284


Table of Contents

Abstract ......................................................................................................................................................... 3

1. Background ............................................................................................................................................... 4

2. Clearance Considerations.......................................................................................................................... 4

3. Structure Type Selection for Ultra-Tall Structures ................................................................................... 7

4. Special Considerations and Limitations for Ultra-Tall Tubular Steel Poles ............................................. 8

5. Design Topics for Ultra-Tall Transmission Structures .......................................................................... 11

6. Lessons Learned From Recently Completed Project ............................................................................. 13

7. Conclusion ............................................................................................................................................. 14

8. References .............................................................................................................................................. 15

Page 209 of 284


Leidos Engineering, LLC Page 2
Design and Installation of Tubular Steel Poles 200 Feet and Taller

Abstract
Due to Houston’s rapidly growing population, the Texas Department of Transportation (TxDOT) is
consistently rebuilding and adding roadways to their extensive network of highways. Transmission lines
crossing these expanding TxDOT roads are often required to be raised or relocated to accommodate the
expanding infrastructure. At some TxDOT interchanges with highly dense vertical stacking of roadways,
transmission structures can exceed 200 feet in height in order to meet both National Electric Safety Code
(NESC) and TxDOT clearance requirements.
Tubular steel poles (TSP) have been selected for several recent projects involving TxDOT expansions
requiring new crossing structures of 200 feet or more. TSPs have a smaller footprint when compared to
the traditional lattice tower structures. As these projects are often located in parts of the city with very
limited space to spot the new structures, a single foundation for a TSP is more favorable than the four
foundations and wider base required for a lattice tower structure. Additionally, TSPs result in shorter
construction times as they require less assembly when compared to lattice towers.
Although TSPs are quickly becoming the preferred structure type for these applications, they do not come
without their own set of considerations and design limitation challenges. This paper will explore key
design concepts and lessons learned from installing TSPs 200 feet and taller, such as setting deflection
limits, cambering vs raking, constructability concerns, foundation design considerations, and Federal
Aviation Administration (FAA) lighting requirements.

Page 210 of 284


Leidos Engineering, LLC Page 3
Design and Installation of Tubular Steel Poles 200 Feet and Taller

1. Background
Texas is home to 10 of the top 15 fastest growing cities in the United States with populations of 50,000
residences or more according to the United States Census Bureau[1]. Number one on the list is Conroe,
Texas, a northern suburb of Houston, Texas. Newly released United States census shows that Conroe had
a growth rate of 11 times that of the United States from 2015 to 2016. Other list toppers are Frisco and
Georgetown, Texas, suburbs to Dallas and Austin respectively. With the spike in population and growth
seen in these Texas cities and their suburbs, huge demand increases for resources and infrastructure are
required to sustain the rapidly growing population.
Like any major metropolitan area in the United States, a large percentage of employment is located in the
heart of Texas’ major cities, such as Houston and Dallas. While corporation’s offices are located
downtown, most of the employees reside in the suburbs and commute to work daily. Due to overly
congested roadways from this rapidly growing population, the Texas Department of Transportation
(TxDOT) is required to increase the capacity on their roadways by adding to or expanding the existing
interstate and highway systems in these rapidly growing areas.
To help alleviate congested highways, rehabilitate bridges, and improve connectivity in and around the
state’s metropolitan areas, Texas voters approved $5 billion in bonding. The Texas legislature authorized
the bonding in 2007, under Proposition 12[2]. The first $2 billion in projects were approved in 2010 and
the remaining $3 billion was approved in 2011. In 2015, voters approved Proposition 7[3], which allocated
portions of the state’s revenue to the State Highway Fund for non-tolled projects. These substantial
budget allocations have allowed for large scale and fast-paced projects which are often centered on
expanding existing interchanges, but, due to the established city build-up in these areas, there is often
limited physical space for any new transportation infrastructure. As a result, new roadways connecting
suburbs to city centers typically need to be stacked vertically at interchanges.
Existing transmission lines, which often run parallel to major roadways, frequently cross these congested
interchanges. As TxDOT projects result in the vertical expansion of interchanges, existing transmission
line crossings at or near these interchanges are also required to be raised. To meet National Electric Safety
Code[4] (NESC) clearance standards and TxDOT clearance requirements, the new designs can result in
structures that exceed 200 feet in height. Structures exceeding 200 feet in height are referred to as ultra-
tall structures throughout this paper.
This paper is focused on how the rapid increase of population affects transmission line design
considerations in highly congested major Texas cities. This paper explores the methodology for designing
transmission lines in highly congested areas with limited physical space that require ultra-tall structures.

2. Clearance Considerations
In designing transmission lines crossing over interchanges in Texas’ major metropolitan areas, many
challenges arise. The lack of available physical space and the high costs associated with rerouting
transmission line alignments often make raising them the best option to deal with the increasing
interchange heights.
For transmission lines, determining the correct electrical clearance requirements for a given line is the
first major design consideration to tackle. The NESC is often the basis for determining the minimum
clearance requirements for transmission lines in Texas. In some cases, state or local codes can be more
stringent, therefore it is important to investigate all project specific requirements prior to finalizing a
clearance criteria. For the purposes of this paper, the NESC and the Texas Administrative Code[5] (TAC)
will be assumed as the only applicable clearance requirements.

Leidos Engineering, LLC Page 4


Page 211 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

NESC Rule 232 provides the vertical clearances for communication cables, shieldwires and conductors to
roads, streets and other areas subject to truck traffic. While NESC Rule 234 provides the clearances for
communication cables, shieldwires and conductors to bridges. The NESC clearances for Rules 232 and
234 for phase to phase operating voltages of 0 kV, 34.5 kV, 69 kV, 138 kV and 345 kV are summarized
in Table 1.
Table 1. NESC Rules 232 & 234: Wires, Conductors, or Cables to Bridges, Roads, Streets and
Other Areas Subject to Truck Traffic

Communication

Shieldwires (ft)

34.5 kV (ft)

138 kV (ft)

345 kV (ft)
69 kV (ft)
Nature of surface underneath wires, conductors, or

(ft)
cables

Roads, streets and other areas subject to truck traffic 18.5 18.5 18.5 19.1 20.6 24.8
Bridges - where wires are attached 5.5 5.5 5.5 6.1 7.6 11.8
Bridges - where wires are not attached 12.5 12.5 12.5 13.1 14.6 18.8
Bridge structure - where wires are not attached,
7.5 7.5 7.5 8.1 9.6 13.8
accessible to pedestrians
Bridge structure - where wires are not attached, no
6.5 6.5 6.5 7.1 8.6 12.8
pedestrian access

In addition to the general electrical gap clearances over bridges and roads, the NESC also specifies a
requirement to account for the effects of the electric field for voltages above 98 kV phase to ground.
NESC section 232D3C, states that the electro static effects on the largest expected vehicle to cross the
electric filed are to be limited to 5 mA or less when the transmission line is operating at 120 degrees
Fahrenheit. Depending on the voltage, conductor type and configuration, this rule has the potential to
control the design clearance for a given interchange crossing.
The TAC Section 21.41 Overhead Electrical and Communication Lines provides the TxDOT clearance
requirements of overhead electrical and communication lines, under maximum operating temperatures, to
roadways and bridges owned and operated by the State of Texas. Table 2 summarizes the requirements
outlined in Section 21.41.
Table 2. TAC Section 21.41 Overhead Electrical and Communication Lines
Communication

Shieldwires (ft)

34.5 kV (ft)

138 kV (ft)

345 kV (ft)
69 kV (ft)

Nature of surface underneath wires, conductors, or


(ft)

cables

Roads, streets, and other areas subject to truck traffic 18 22 22 22 22 22


Bridge pavement and retaining wall 30 30 30 30 30 30

After the minimum clearances to the roadway are accounted for, an additional height buffer is typically
added to accommodate potential changes in the TxDOT design that could result in increasing the final
height of the new roadway as well as field changes during the installation of the transmission line and
construction tolerances. This is important because the transmission work is typically completed well in
advance of the final roadway designs and the buffer helps to mitigate potential redesign efforts including
re-fabricating structure portions which can be very costly depending how far along the structure is in

Leidos Engineering, LLC Page 5


Page 212 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

production and the extent of the changes that are required. This buffer may also be increased to account
for the construction equipment needed to build the interchange. The TxDOT construction crews may not
be certified to work around electric circuits and so larger approach distances (see OSHA 29 CFR, §1910.
269[6]) may be needed between the construction equipment and the electrified conductors.
In addition to the roadway height, code clearances and buffers, the configuration, conductor and line
voltage will also add to the final structure height. Adequate phase spacing is required and will vary based
on the voltage class of the transmission line. Conductor sag can increase or decrease depending on the
conductor size and type used as well as the maximum ampacity rating of the line. The structure
configuration is often based on a mix of the special limitations in the area as well as the utility
preferences.
Roadway on and off ramps can be stacked two to three decks high to allow uninterrupted traffic at
interchanges. Typically, clearance between road decks is 20 feet or more with deck thickness at
approximately eight to ten feet. Transmission structures are spotted as close to the roadway as possible to
avoid crossings around the maximum sag of the conductors, but may still encounter ten feet of sag or
more. Assuming 345 kV vertical configuration with phase spacing of 25 feet with shield wires above the
top phases, structure lengths can quickly exceed 200 feet or more. Figure 1 illustrates the potential
required pole height at an interchange with 3 road decks stacked vertically.
Figure 1. Example Clearance Factors*

* The dimensions shown here are general and do not necessarily represent
minimum clearances or spacing. It is the responsibility of the project designer
to verify and determine these dimensions based on each specific project’s
parameters.

Leidos Engineering, LLC Page 6


Page 213 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

Clients often request transmission lines to be raised using the existing conductor types and operational
voltages but require the structures to be designed to handle an increased numbers of circuits, different
attachment configurations and/or an increase in voltage class. Future buildout considerations can
significantly increases the height of the structures.

3. Structure Type Selection for Ultra-Tall Structures


Once clearances and general configurations are established, determining the most appropriate structure
type for the project becomes the next task. In transmission line design, structures such as lattice towers,
tubular steel poles (TSP), wood poles, concrete poles or hybrid structures are often utilized depending on
the project specifics. Wood and concrete poles are not typically able to be manufactured for the heights
required for these interchange crossings and in the rare cases were they could be, the excessive heights
make them too costly to be viable options. While lattice towers and hybrid structures may be viable for
ultra-tall applications, often other project limitations disqualify them. As a result, many newer
transmission line projects crossing TxDOT interchanges and roads, especially for crossings that require
structures of 200 feet or more, utilize TSPs.
Steel lattice towers, also known as truss towers, are freestanding structures that consists of steel members
arranged to form interlocking trusses in a geometric pattern. Steel lattice towers are very typical structure
types utilized for transmission line designs, especially on projects without spatial limitations. This
structure type is very advantageous for applications requiring ultra-tall structures because lattice towers
experience minimal structural deflection regardless of height. Additionally, standard steel lattice towers
are typically less expensive to fabricate and require smaller caisson foundations. Although they have
many advantages and may be the obvious choice for certain applications, they also come with many
limitations and disadvantages. For transmission projects with very limited land and aerial space, the
overall large footprint of lattice towers may not be the ideal choice. Because of the splayed legs, as the
height of a lattice tower increases so does the width of the base in a linear relationship, resulting in
excessively wide tower bases. Narrow based lattice towers can be designed with increased cost but the
base would still be much wider than a TSP. In addition, the cost to design and perform full scale load
testing for non-standard steel lattice towers may exceed budgetary requirements if standard lattice designs
cannot be utilized. Lastly, steel lattice towers typically are more costly to install due to the assembly of
the lattice members and the multiple foundation installations. While steel lattice towers may have many
advantages, for applications with spatial limitations, budget constraints, and tight schedules, this structure
type is typically not selected.
Hybrid steel and concrete poles are also offered by vendors for transmission line applications. Typically,
these structures will have a direct embedded concrete base section with tubular steel sections on top. The
direct embedded concrete base section eliminates the need for a concrete foundation, base plate and
anchor bolt cage. This significantly reduces the costs for material and labor associated with structures
requiring caisson foundations. Although hybrid structures may cost less to fabricate and install, projects
requiring ultra-tall structures typically have very high applied loads that require caisson foundations to
transfer the load adequately, making the direct embed hybrid structure unsuitable.
TSPs are often the most viable structure type for applications requiring ultra-tall structures to be installed
in the limited physical space near congested inner-city roadways. TSPs can be designed to achieve the
required heights of 200 feet or more. In contrast to lattice towers, individual structure designs for location
specific loading can be quickly produced using design software and then manufactured without requiring
expensive full scale load testing. Although TSPs often experience larger deflections, designs can be
tailored to meet client specific deflection limits by adjusting the wall thickness or pole taper. This same
design variability allows for limiting the pole base diameters to accommodate highly confined setting
locations. Base diameters of poles can typically be 10 to12 feet with 15 foot foundation diameters. Due to

Leidos Engineering, LLC Page 7


Page 214 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

the multi-section design approach, TSPs are easy to ship on standard trailers and straightforward to
construct. Some of the constraints placed on the pole design can result in very expensive structures, but
the overall design benefits often outweigh the potential cost adders. For these reasons, TSPs are not only
the more favorable option, but sometimes they are the only option.

4. Special Considerations and Limitations for Ultra-Tall


Tubular Steel Poles
TSPs may be the most viable option for transmission line designs requiring ultra-tall structures, but they
also come with design limitations and challenges. Structural load capacity, foundation load transfer
design, steel section joint design, deflection considerations, material lead time and availability are just
some of the critical elements to consider during design.
Transmission line projects requiring high cost structures, such as ultra-tall TSPs, may be designed to the
maximum expected future electrical capacity for the intended circuit(s). In these cases, design loads on
the structures may be very high to account for a future buildout condition potentially requiring larger
conductors with higher tensions. Also, as spans crossing major roadways or interchanges are generally
considered critical crossings, dead-end structures are typically designed for full dead-end loads (i.e. all
wires down on one side) under NESC extreme weather conditions. Even where future conditions may not
be a design concern, these projects often require increased tension on the existing conductor to help limit
sag while crossing over the raised roadways. This practice helps to minimize structure height while
maximizing the clearance over the interchange. The extreme pole heights combined with large design
loads result in robust and often costly structure designs which require equally robust foundation designs.
Direct embedded foundations, caisson foundations with anchor bolts, and any client specific special
foundation types are typically used for transferring loads from TSPs into the ground. For the purpose of
this paper, client-specific special foundation types will not be discussed. Direct embedded foundations are
normally used for tangent and light angle structures where overturning moment is minimal. Caisson
foundations with anchor bolts are most commonly utilized for the heavily loaded TSPs exceeding 200 feet
since they are best suited to handle the large ground line reactions. The diameter of the drill pier is always
larger than the pole base as it needs to accommodate the anchor bolt cage plus accommodate the
reinforcing steel cage and the minimum concrete cover requirements. As a general rule, the minimum
concrete pier diameter is around two feet larger than the anchor bolt ring diameter. It is important to
consider this when spotting a pole in a highly confined area, as it may require limiting the overall pole
taper to allow for a smaller foundation diameter. Limiting the pole base diameter is usually achieved by
increasing the wall thickness of the sections, but this can be very costly and may not be an option because
of budgetary reasons.
The steel section’s joints can be designed as either slip joints or flange joints. There are several
advantages and disadvantages for both types of joint design and the engineer should specify the joint type
based on project specific needs. Slip joints are typically used in situations where setting tolerances are not
critical and uplift is not expected. Flange joints are more suitable for poles that require tighter setting
tolerances, where uplift may be a concern or where a pole taper is so limited that the sections are not able
to overlap. Typically, flange joint poles are only utilized when absolutely required as they have a higher
cost for fabrication, often have longer lead times and require more time to install.
The lead time for custom TSPs can be up to 26 weeks, depending on the vendors’ availability to fabricate.
This lead time is critical for engineering and construction scheduling and should be considered at the
beginning of the project to avoid any delays in delivery of the TSPs. Delivery delays will cause downtime
for construction crews and therefore risk putting the project over budget. Lead times can be even larger
for projects where all material is required to be manufactured in America. Only a limited number of steel

Leidos Engineering, LLC Page 8


Page 215 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

mills in America have the capacity to mill some of the larger size base plates and often they have
extensive back logs that can extend lead times well beyond 26 weeks. In these instances, the base plate
size may be reduced by using multiple bolt circles, however, this practice can create additional issues
since the inner bolt circle is often located on the inside of the pole. To tighten the anchor nuts inside the
pole, a worker must have access to the interior of the pole which often means a special access door must
be designed and fabricated into the side of the base section. Special detailing for these requirements adds
cost and production time to the structure order. It is best to discuss any potential procurement and design
concerns with perspective TSP vendors as early in the design process as possible to avoid critical delays
later in the project schedule.
Not all considerations are critical to the structural design or construability of a project. For projects that
are located along heavily trafficked areas, pole aesthetics can play a large role in how the public reacts to
a new transmission installation. Pole deflection is often the most visually apparent of these concerns
especially on ultra-tall TSPs. For instance, Figure 2 shows that even a minor deflection of five percent
results in over 12 feet of deflection at the tip of a 250 foot TSP. Although this amount of deflection may
not be a structural issue, it is visually identifiable and may raise concerns from the public. To control the
deflection and alleviate potential concerns, a designer can specify a deflection limit, design stiffeners,
design a pole camber or rake the pole during installation.
Figure 2. Visual Tubular Steel Pole Deflection

As shown in the figure above, deflection in TSPs is nonlinear. The tip deflection is best approximated
using the deflection equation for a cantilevered beam:

=
3

Leidos Engineering, LLC Page 9


Page 216 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

Where:
δ = deflection
P = the resultant load at the structure tip
L = the length of the pole
E = the modulus of elasticity of steel
I= the moment of inertia of the pole itself
For a given project, P, L and E are all constant, therefor adjusting I becomes the only way to vary the tip
deflection. For projects with a set deflection limit, the equation can be rearranged to determine the
required moment of inertia:

=
3
In practice, the desired value of I can be achieved by adjusting the section diameters and/or increasing the
thickness of the section walls. The option to limit deflection will generally cause an increase in costs or
result in larger base diameters, potentially making a pole design unsuitable for a project. Designing pole
stiffeners along the length of the pole shaft to increase the moment of inertia of the pole may be another
option to control deflection, but this option will also increase costs.
Cambering is also used to counteract the visual effects of deflection without making special adjustments
to the overall pole design. Cambering is the process of fabricating the TSP with a preset curve to offset
anticipated deflection that will occur once the load is applied. If applied correctly, the pole will appear
plumb under typical “every day” conditions after all the wires are installed and tensioned. However,
fabricating curved sections can increase structure cost and it is difficult to accurately camber the pole to
match the actual installed loading. Because cambering is not an exact science, after the pole is installed
and placed under load, the applied load may not be high enough to “straighten” out the camber, the
distribution of the camber along the pole may not be even, or the pole camber may be less than
anticipated and the pole ends up deflecting toward the ultimate loading regardless. The results of an
unsuccessful camber design is a higher cost pole that still shows a visual deflection.
Raking is the process where the pole is tilted away from the direction of anticipated deflection before the
pole is placed under load. The pole can be raked by adjusting leveling nuts below the baseplate on the
anchor bolts. The amount of rake is usually based on the anticipated deflection under normal everyday
loading, but its success heavily depends on the installation crew both installing the conductors to the
specified tensions and tilting the pole to the correct angle. If the pole is not cambered, a straight, raked
pole will still deflect and appear curved along its length. Poles of this length can still be visually
unappealing due to the deflection.
Beyond the aesthetic effects, deflections this large can also create issues with the wire sag and tension.
During construction, the pole will deflect as each wire is brought up to the specified design tension. If
each wire is tensioned individually, each successive wire being strung will result in an increase in the
overall pole deflection. This in turn will cause the reduction in tension (increase in sag) for each of the
already tensioned wires. This effect is illustrated below in Figure 3. To avoid potential clearance issues
after the wires are installed, it is important to discuss this effect with the construction crews and verify
that the final sag/tension measurements were checked after all the wires were installed.

Leidos Engineering, LLC Page 10


Page 217 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

Figure 3. Deflection Effects on Sag/Tension

5. Design Topics for Ultra-Tall Transmission Structures


There are several aspects to consider when designing ultra-tall structures, including FAA requirements,
constructability, temporary construction requirements, transferring and stringing conductors, uplift on
adjacent structures, and future line maintenance. The design topics mentioned in this section may vary
based on project or location specific requirements, therefore meeting with all primary stake holders prior
the start of every project will help facilitate a smoother design process.
The FAA requirements for aerial obstacles can be found on the agency’s obstruction evaluation website at
https://oeaaa.faa.gov/oeaaa/external/portal.jsp. The website provides links and information for
determining the design requirements for structures that are considered obstruction to aircrafts. Based on
the new structure’s proposed height and location, specific permits may be required to be obtained prior to
the installation or the agency may deny the proposed structure and require alternative heights or locations
be considered. For structures exceeding 200 feet, the FAA requires special lighting and/or paint to be
installed or applied on the structures regardless of proximity to airports. This is to help pilots identify
obstructions and guide them away from potential collisions. Unless specialty self-powering light units are
able to be used, installing lighting may require distribution service be routed to the project area prior to
construction. This must also be considered during structure detailing so that proper attachments are
included in order to bring the electric service up the structure to the lights. Additionally, marker balls are
typically installed on the highest wires to make them more visible to pilots. There may be additional

Leidos Engineering, LLC Page 11


Page 218 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

requirements if the structures are located proximal to an airport. The specific requirements for each
project are detailed in the permits once they are approved by the FAA and are generally required to be
installed as well as active during the construction process.
The constructability of a design is a critical aspect that must be considered during the initial project
planning. Items such as site access, equipment weight limitations, current versus future grading plans and
clearances to the surrounding environment both above and below ground have to be factored into the
design. When exploring potential structure locations, the available physical space above ground is not the
only concern. Foundations must be placed so as to avoid underground conflicts, such as pipelines or other
burred infrastructure. To identify these potential obstructions, underground investigations should be done
prior to starting any engineering as finding them during construction can result in costly delays and
extensive redesign efforts. To avoid constructability issues in the field, it is best to discuss design
decisions with the construction team early on, as they are able to provide insight on how they will stage
and execute the build process.
Transmission line construction often requires a temporary or staged work plan to help accommodate
limited line outages, shorten overall construction schedules or to accommodate a phased construction of
the roadway. Although temporary construction is a typical practice in transmission line work, it is
especially crucial for projects involving the permanent installation of ultra-tall TSPs as construction over
major roadways must not create significant disruption to the daily traffic patterns. For higher voltage or
critical lines, outages cannot be scheduled for a long duration and usually can only be arranged for
specific times in short durations not long enough to remove existing structures and completely install the
permanent structure and foundation. Temporary structures are generally set slightly off of the existing
alignment and the existing conductors transferred from the existing structures to the temporary locations
during scheduled short outages. Once the conductors are properly installed in a temporary configuration
and the outage expires, the transmission service is restored. This allows the construction of the permanent
ultra-tall TSPs on the existing alignment to continue while the line remains in service. Although
temporary designs may not need to handle the final loading, they still must physically fit within the given
area of the rebuild while not obstructing the accessibility of construction equipment during the installation
of the permanent structures.
Depending on the specific project scope, installing all new conductors and wires may not be ideal and
instead reusing the existing cables could be preferred. When transferring conductors and wires as part of a
rebuild, additional lengths must be spliced in to maintain the specified catenaries and tensions. Once the
splices are made, typical wire pulling methods are utilized to string the line. It is crucial for the
construction crew to understand the intended tensions for both the final configuration and any temporary
work so that wire length and splice locations can be properly arranged to avoid rework between the
construction stages. The designer must also provide enough spare cable and splices in the bill of material
to accommodate the construction process as well as the final intended design. Not accounting for the
additional wire or splices can create shortages in the field resulting in construction delays and re-work or
potentially even cause deviations from intended design and excessive line tension.
Installing ultra-tall TSPs often will cause uplift issues on the adjacent structures, this is due to the abrupt
increase of height between the existing and new structures. Depending on the span lengths and the
difference in height, several adjacent structures may need to be replaced in order to create a gradual rise
in the line that eliminates uplift on adjacent tangent assembles. To properly estimate a construction
schedule and budget, it is important to review the structures beyond the immediate rebuild area for uplift
concerns as replacing adjacent structures will increase the cost and construction duration of the overall
project significantly.
Long term maintenance issues should also be considered during the design process. To perform
maintenance items such as inspections, hardware and conductor work, repainting rusted portions of the
pole with galvanizing paint and replacing FAA lighting will require very extremely tall bucket lifts or

Leidos Engineering, LLC Page 12


Page 219 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

other specialized equipment. In situations where this equipment may not be readily available to the utility
crews, it may be possible to add special design details to the pole such as permanent ladders and tie off
points that can be used for future maintenance operations.

6. Lessons Learned From Recently Completed Project


A recent transmission line rebuild project utilizing several TSPs with maximum height of 240 feet was
completed successfully in 2017. Although the project was installed successfully, construction issues were
encountered, resulting in several lessons learned. Table 4 details some of the issues during construction
and at final installation of the project.
Table 4. Lessons Learned

Construction Cause(s) Corrective Action(s) Lessons Learned


Issue for Future Projects
Deflection visible Deflection limit was not Specify a deflection Final pole deflection is a
under load specified and deflection limit and/or design critical serviceability issue
causing counteraction methods deflection counteraction and should not be lower
unappealing were not specified. such as camber and/or priority than other factors
aesthetics and rake. such as costs or pole footprint.
public concerns. Deflection controls or
Stringing operation
counteractions should be a
relied solely on Stringing operations
critical consideration for
dynamometer readings should not rely only on
ultra-tall TSPs.
for conductor tensions. dynamometer readings
for installation line
tensions, but rather
Stringing charts did not
crosscheck readings with
include structure
engineer stringing charts
deflection considerations
and/or return wave
which affected the final
times.
tensions/sags
Poles requiring Limited space for None. Note, OSHA Larger foundation pier
multiple anchor foundation footprint, confined space standards diameters to be designed
rings have inner which limited size of were specified for the where possible in order to fit
rings inside of required baseplate, installation of the inner larger baseplates that will
the pole shaft. resulted in multiple bolt rings inside of the allow for all anchor bolts to
anchor rings with inner pole shaft. be located on the outside of
rings inside of the pole the pole shaft.
shaft.

Leidos Engineering, LLC Page 13


Page 220 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

Table 4. Lessons Learned (cont.)

Construction Cause(s) Corrective Action(s) Lessons Learned


Issue for Future Projects
Use of dead-end Due to the large Specify through vangs On large diameter poles, it
pull-off plates diameter of the pole instead of pull-off plates can be difficult to line up and
mounted with shaft, the through bolts for high tension and place through bolts without a
through bolts were excessively long, large shaft diameter guide. This creates delays and
causing difficulty making the installation poles. difficulty during the
installing long difficult. construction process.
through bolts.
If pull-off plates are
used, specify steel pipes
to be cut and welded
inside of the pole shaft
at the bolt-hole locations
for ease of installing
through bolts and
increasing local stiffness
at bolt-hole locations.
Gap between High conductor tension Specify through vangs Attached conductors to come
dead-end pull-off causing the plate to be instead of pull-off plates along to take tension off of
plates and pole pulled away from the for high tension and the dead-end pull-off plates
surface after pole surface due to hex large shaft diameter and tightened down the hex
conductors were nuts on through bolts not poles. nuts properly.
tensioned. being tightened
adequately.
Specify minimum torque
for hex nut(s).

7. Conclusion
As the population in Texas continues to grow, increasing the demand on TxDOT roadways, the need for
ultra-tall transmission structures will continue to become more and more common. Similar growth
patterns are occurring in many other metropolitan areas through the country. For these extremely
congested areas with limited rerouting options, rebuilding transmission lines around TxDOT interchanges
will require structures with footprints that minimize ground and aerial conflicts. TSPs are being utilized
more frequently for these applications as they are better suited to meet the design constraints when
compared to other traditional structure options like lattice towers. Although TSPs may provide the best
solution for a given project, they still have many limitations and require a great deal of consideration by
the designer. To achieve critical milestones and eliminate costly delays, project stakeholders such as
TxDOT personnel, design team members, construction leads, and the TSP vendor should meet at the early
stages of the project and continue regular meetings throughout. This open and continuous communication
between the project members will ultimately lead to a more effective and successful installation.

Leidos Engineering, LLC Page 14


Page 221 of 284
Design and Installation of Tubular Steel Poles 200 Feet and Taller

8. References
[1] “The South Is Home to 10 of the 15 Fastest-Growing Large Cities.” US Census Bureau, 25 May
2017, https://www.census.gov/newsroom/press-releases/2017/cb17-81-population-estimates-
subcounty.html
[2] “Proposition 12 (General Obligation Bond Projects).” Texas Department of Transportation,
http://www.txdot.gov/inside-txdot/projects/prop12.htm. Accessed 22 June 2017.
[3] “Proposition 7 - Constitutional Amendment for Transportation Funding.” Texas Department of
Transportation, http://www.txdot.gov/government/legislative/state-affairs/ballot-proposition-
7.html. Accessed 22 June 2017.
[4] National Electric Safety Code C2-2017, Institute of Electrical and Electronics Engineers. 26 April
2016.
[5] “Texas Administrative Code Title 43.1.21.C Rule 21.41.” Texas Registrar,
http://texreg.sos.state.tx.us/public/readtac$ext.TacPage?sl=R&app=9&p_dir=&p_rloc=&p_tloc=
&p_ploc=&pg=1&p_tac=&ti=43&pt=1&ch=21&rl=41. Accessed 22 June 2017.
[6] “Occupational Safety and Health Standards 1910.269.” US Department of Labor,
https://www.osha.gov/pls/oshaweb/owadisp.show_document?p_table=STANDARDS&p_id=986
8. Accessed 22 June 2017.

Leidos Engineering, LLC Page 15


Page 222 of 284
Substation Grounding and Step Over Native Concerns

Molli Dooley, P.E.


Project Engineer
POWER Engineers, Inc.
Fort Worth, TX

Prepared for the


th
50 Annual Transmission & Substation Design & Operation Symposium
Dallas, TX
September 6-8, 2017

Page 223 of 284


ABSTRACT
Substations are designed with grounding systems with one function, to reduced touch and step voltages
inside the substations. IEEE Std 80 is most often used to determine compliance for step and touch
voltages and clearly applies within a substation fence. Outside of the substation fence, there is a
breakpoint where substation surfacing is no longer installed. For that area beyond the substation
surfacing, additional step over native analysis may need to be performed. While IEEE Std 80 focuses on
human safety, it is vague about the analysis and mitigation required beyond the substation fence. The
methodology in the guide does not analyze voltages outside the grounding system area, but the guide
discusses the need to consider other areas. In a survey conducted by the IEEE Std 80 working group,
roughly 50% of utilities evaluate step over native beyond the substation fence. While step over native
concerns are rare, they can be incredibly costly to mitigate.

This paper focuses on the basics of substation grounding as well as providing back ground on step over
native soil (outside the station). With this knowledge the decision of whether to study and mitigate for
these conditions can be made by individual utilities.

INTRODUCTION
IEEE Std 80-2013 focuses on the safety of personnel within a substation. Calculations are performed to
evaluate a substation grounding system for IEEE Std 80 compliance against two measures, touch voltage
and step voltage.

Touch voltage is the voltage difference between a person’s feet and an object they touch. Step voltage is
the voltage difference between a person’s feet.

Touch Voltage Step Voltage

When evaluating a grounding system for IEEE Std 80 compliance, a tolerable touch and step limit is
determined. This tolerance limit takes factors such as the backup clearing time, soil properties, and any
material between the grounding system and the person’s feet. That compliance limit is then compared
to the calculated touch and step value. A grounding system can be declared IEEE compliant if the touch

Page 224 of 284


and step voltages are below the compliance limits. Note that touch voltage limits may apply only in
areas where there is something to touch.

Importance of a Grounding System


Before beginning the design and analysis of a grounding system, one first needs to understand why
grounding systems are important. There are four major purposes to a grounding system:

• Provide personnel protection under fault and normal loading conditions.


• Protect equipment from high voltages and currents seen by the system during fault conditions.
• Allow for proper system and equipment operation under both normal and fault scenarios,
including arrester and ground relaying operation.
• Dissipate the current from surges and lightning strikes in order to reduce the frequency of
outages.

Grounding plays an important role throughout the entire power system, protecting equipment and
personnel from normal and abnormal system conditions. IEEE Std 80 is the IEEE Guide for Safety in AC
Substations Grounding and is used to provide guidance on limits based on scenarios presented in a
substation environment and behavior of the human body when subjected to an electric shock. Through
an understanding of the body’s response to electric shock, calculations can be performed to determine
compliance, or safety, limits for both step and touch voltage.

Behavior of a Substation Under Fault Conditions


Under fault conditions, a grounding system will experience a ground potential rise (GPR). GPR is a
function of the fault magnitude and the grounding system resistance as defined by Ohms Law, V = I * R.
The resulting voltage magnitude determines grounding system performance in regards to personnel
safety compliance and, in some cases, equipment damage thresholds.

The resistance of the grounding system can be referred to as the resistance to remote earth as shown in
the figure below.

Transmission Line

SLG Source
Fault Substation
(I)

Resistance
to Remote
Earth
(R)

Page 225 of 284


As the current attempts to return to remote earth, it will travel through the earth in varying paths
through the soil. Depending on the soil, the current may travel closer to the surface or ideally deeper
into the earth. The highest GPR will be at the grounding system, as the distance from the grounding
system increases, the GPR will decrease. IEEE 367 further explains the concept of Zone of Influence
(ZOI). In relation to IEEE Std 80, the primary concern is the rate at which the potential decreases. A large
difference in potential over a small distance, such as 3 feet, can be concerning and will be discussed in
following sections on step over native.

The graph below is a representation of the potential on the surface of the earth as the distance from the
station increases. While the exact rate of decay and magnitude of the potential will be different for each
station depending on the fault magnitude, grounding system resistance, and soil type, it is known that
the largest difference in potential will be seen right outside of the substation.

Analysis Methodology
The analysis of a grounding system’s performance under fault conditions requires these basic steps:

• Characterizing the soil and developing a model that represents an electrical equivalent of the
soil in which the grounding system is installed.
• Determining the amount of current that will flow through the substation grounding system to
return to the source through the earth.
• Determining IEEE Std 80-2013 touch and step voltage compliance levels.
• Analyzing the actual touch and step voltage values throughout and three feet beyond the
substation.
The following sections discuss the general methodology of each step. Multiple software packages are
used throughout the industry. This paper does not focus on a specific software or analysis tool.

Page 226 of 284


Soil Analysis
The performance of the grounding system is greatly dependent on the soil structure in which the
grounding system is installed. Soil structures typically consist of a few distinctive horizontal layers over a
given area, with each layer having its own electrical characteristics based on soil composition and
moisture content, as well as several other factors. The layering and characteristics of the soil are
determined by performing soil resistivity measurements using one of the methods recommended by
IEEE Std 80-2013.

IEEE Std 81-2012 (“IEEE Guide for Measuring Earth Resistivity, Ground Resistance, and Earth Surface
Potentials of a Grounding System”) indicates that “probe spacings on the order of the ground grid
dimension should give sufficient model accuracy for computing touch and step voltages”. If the soil
resistivity data maximum probe spacing for a substation is much less than the maximum substation
dimensions, the grounding analysis accuracy may be impacted.

Fault Current Split Factor Analysis


The most conservative approach for substation grounding analysis is to assume that all of the fault
current will enter the grounding system and return to the source through the ground via the substation
grounding system. In practicality, there are often numerous other return paths to the fault source
through shield wires and distribution neutrals attached to the substation grounding system, including
the associated structure grounds. Various methods exist for computing an equivalent current split of the
fault current, allowing the true amount of fault current returning through the substation grounding
system to be determined. As a result, the maximum calculated touch and step voltages within the
substation will decrease to a more realistic value.

Faulted Substation

IEEE Std 80-2013 Compliance Limits


One of the main design objectives of a substation grounding system is to reduce touch and step voltages
throughout a substation to a value that is below the IEEE Std 80-2013 tolerable compliance limits. The
limits presented in IEEE Std 80-2013 reduce, but do not eliminate, the risk of fatalities associated with

Page 227 of 284


heart fibrillation caused by current flowing through the body because of contact with grounded objects
within the substation during a fault condition. The compliance limits are determined primarily by the soil
surfacing layer (and its relationship to the underlying soil), and the maximum fault duration. Compliance
limits are typically based on a 50 kg person with no additional impedance (such as boots or gloves) as
the general public can typically access the substation fence, which is part of the grounding system.

The maximum fault duration, a.k.a. backup clearing time, can be calculated or a conservative value
assumed. Commonly, 0.5 seconds (30 cycles) is used as typical maximum fault duration for transmission
voltages. As the maximum fault duration decreases, the compliance limits increase.

Soil surfacing can have the greatest impact on the compliance limits. Surfacing varies from crushed
gravel to asphalt and many other options. Each surfacing will have its own electrical properties
depending on the material and the thickness. While the intent of the substation surfacing is to insulate
personnel from the ground, the type and depth of material will vary based on utility needs and the
function of the substation. For example, driving a vehicle in 6 inches of crushed gravel is often not
feasible, so a maximum of 4 inches is used or a different surfacing is applied for driveways. Occasionally,
there may be areas of substations where there is no surfacing; this is referred to as step-over native. The
overall compliance limits are a function of both the resistivity of the surfacing and the thickness. As the
thickness increases, the compliance limits will increase; as the resistivity of the surfacing increases, the
compliance limits will also increase.

Grounding System Analysis


Computations are then performed for the touch and step voltages within areas defined by the user.
Typically this area is within the substation and three feet beyond the substation fence and the swing of
outward opening gates. The calculated tolerable step and touch voltage thresholds can be used to
identify areas within the substation that exceed step and touch voltage thresholds. IEEE Std 80-2013
generally recommends a maximum reach and step of three feet.

Step Over Native – Back ground


As previously discussed, a significant factor in a grounding system analysis is the substation surfacing. In
areas where there is no surfacing, only native soil, the term step-over native applies. Essentially, step
over native is simply the same step voltage as discussed previously but in an area with no surfacing.

Since step voltage is the potential difference between a person’s feet, any current would flow through
the person’s feet and leg. As noted in IEEE Std 80 Clause 16.1, “step voltages are inherently less
dangerous than [touch] voltages” based on the fact that the majority of the body current will not flow
through the heart (Clause 7.2); yet the guide does not provide details on how the compliance limit could
be increased to account for this aspect. It should also be noted that touch potential violations are far
more common than step.

Page 228 of 284


Step Voltage Step-Over Native Voltage

Certain conditions may increase the likelihood of having step over native issues. One such condition is
where the soil has high resistivity and few return paths for the fault current distribution. Another is
when the soil model reveals a low resistivity layer on top of a high resistivity layer. Below is the example
from a station in western Texas where step over native issues were calculated. As can be seen, the
second layer of soil has a significantly higher resistivity than the first.

Due to the high resistivity of the second layer, the voltage will remain near the surface longer since the
path of least resistance is in the top layer of soil. The plot below shows the potential along the surface
from the station fence going out 1,000 feet. With a station fault current of 10,000 Amps applied, the
GPR at the station is as 15,000 volts. At 500 feet from the station, there is still a GPR of over 3,000 volts.
Not only is that a high GPR, but the rapid decay of potential on the surface leads to step voltages in
excess of the IEEE compliance limits.

Page 229 of 284


Step Over Native – Industry Standards
Some utilities are starting to look at step over native outside of the substation fence as common practice
for grounding analysis, other are choosing to limit the grounding analysis to the substation area. IEEE Std
80-2013 does not provide direct guidance on the need to meet step voltage limits beyond the area of
the grounding system. The design calculation methodology in Clause 16 of the guide limits the
calculations to the area within the grounding system area; however, nearly all commercially available
grounding software does allow for this calculation outside of the grounding system area. IEEE Std 80
Clause 4.1 indicates that one objective of the design is “To reduce the risk of a person in the vicinity of
grounded facilities…” but does not define “in the vicinity”. Based on a 2009 survey by the IEEE Working
Group for this guide, there is no industry consensus if step voltages beyond the grounding system
should be considered, and if so, how far beyond. However, IEEE Std 80 methodology does calculate step
voltages within the full grounding system area and Clause 16.1 indicates this area should be analyzed if
the surfacing does not extend outside the fence.

Due to the vague nature of the standard at this time, it is up to the individual utility to determine what
their best practice is.

Step Over Native – Mitigation Techniques


Since step voltage is the potential difference between a person’s feet, assumed to be 3 feet apart, the
rate of change along the surface is of interest. Often, the most likely place to encounter step over native
issues is at the point where the substation surfacing stops. If a person were standing with one foot on
the surfacing and the other on native soil the potential between their feet could be significant. As
discussed previously, the largest potential difference will be right outside of the substation grounding

Page 230 of 284


system. Therefore, the methods for mitigating step over native concerns focus primarily on either
extending the grounding system or the surfacing, or decreasing the grounding system resistance.

While step over native concerns are uncommon, they can be costly to mitigate. One of the quickest
options for mitigating step over native is to extend the surfacing father than normal. Due to property
lines, and topography that is not always an option. It is not uncommon for stations with issues to see
that the station surfacing would need to be extended as far 15 and 20 feet from the station fence.

Extending the grounding system can be the most effective mitigation method. An outer grounding loop
is often installed 3 feet beyond the substation fence. Extending the grounding system would be adding
additional grounding runs deeper than the rest of the grounding system. This method is referred to as
stair stepping. The intention is to push the voltage further into the earth, away from the surface. This
option is also depend on the property lines and often not an option.

An additional mitigation technique is to take measures to decrease the station grounding resistance.
That can be accomplished by adding additional grounding, ground rods, and ground wells. Enhancing
fault current distribution

When step over native issues are discovered, any combination of the above mentioned mitigation
techniques can be used. While mitigation can occasionally be simple, it can also be extravagant. In the
example from above, analysis techniques were employed to reduce the fault current by applying fault
current split and using a realistic fault clearing time as opposed to a conservative value. Even with a
reduced fault current and faster clearing time, step over native issues were still present. The image
below is the output from grounding software where the color areas denote non-compliance.

To mitigate the step over native issues, an additional ground loop was added around the outside of the
station and a total of seven (7) 80 ft deep, 6 inch diameter ground wells were added to the station.

Page 231 of 284


Step Over Native Example
In a 220 kV station in Pennsylvania, the soil model indicates that the resistivity increases with depth, see
below. After fault current split, a total fault current of 15,000 Amps is applied to the grounding system.
With a clearing time of 0.5 seconds the IEEE step compliance limit goes from 2,190 volts with surfacing
to 358 volts without surfacing. Combining the soil model with the high fault current lends to the ideal
environment for step over native issues.

The grounding analysis indicated step over native concerns directly outside of the fence extending as far
as 25 feet from the station fence. Due to property limitations, extending the surfacing and adding
additional loops outside of the station were not an option. The image on the left shows the existing
station grounding while the image on the right is the ground grid design required for step over native
compliance.

The following was required to bring the station to IEEE Std 80 compliance including step over native
outside of the station fence:

• Approximately 9,000 feet of existing 500 kcmil bare stranded copper conductor buried 18 inches
below structural grade.
• Approximately 24,000 feet of new 500 kcmil bare stranded copper conductor buried 36 inches
below structural grade.
• Approximately 7,200 feet of existing 4/0 bare stranded copper conductor buried 18 inches
below structural grade.
• Approximately 280 feet of #4 AWG bare stranded copper conductor for the connection of the
fence to the grid
• 331 ground rods (194 new), each 5/8 inches in diameter and 10 feet long.
• Shift northern fence in 3 feet and taper corners for step voltage over native compliance
considerations

Page 232 of 284


Conclusions
Substation grounding is an important part of equipment and personnel safety. Analysis should be
performed to determine IEEE Std 80 compliance of the substation. In addition to the traditional touch
and step potential compliance, utilities should consider if evaluating step over native outside of the
station surfacing is the correct approach for them. While public safety should be considered, analysis
techniques may be overly conservative leading to overdesigned grounding systems.

Page 233 of 284


Asset Management Analytics for a Sustainable Grid

Qasim Aziz & Gautam Sonde


CenterPoint Energy, Houston Texas

Abstract— This paper discusses the need and use I. INTRODUCTION


of substation related analytics in formulation of asset
management strategy that would help support a
sustainable power grid. CenterPoint Energy is a combination of gas and
This paper focuses on presenting methodology electric utility and is part of the Electric Reliability
around development of analytics for substation Council of Texas (ERCOT) Region. It serves around
related assets including transformers, circuit breakers 5.2 million electric customers across roughly 5,000
and protective relaying. It discusses use of substation square miles in the Greater Houston Area. Major
analytics to assess system risk associated with facilities of CenterPoint Energy’s electric
electric assets based on condition and system impact. transmission and distribution network include 3,718
It describes application of substation analytics in miles of transmission lines, 233 substations and
developing long-term asset management strategy 52,639 miles of distribution lines as of 2017. These
encompassing electric asset replacements, facilities form an electric network that connects in-
maintaining adequate levels of Capitalized area generation sources and bulk energy transmission
Emergency Material (CEM) and best maintenance from various in-state and out of state sources to
strategies. Opportunity to use substation analytics as deliver energy to CenterPoint Energy’s customers.
a building block for development of a future asset
health center is addressed in this paper as well.
II. ASSET REPLACEMENT STRATEGY
Substation analytics discussed in this paper were
developed around electric assets owned and/or
maintained by CenterPoint Energy, an electric CenterPoint Energy uses planned replacements
transmission provider in the Greater Houston Area. for several types of substation assets including
CenterPoint Energy’s electric assets comprise of transformers, breakers, switches etc. Assets are
substations and transmission & distribution lines identified and prioritized for replacement based on
serving the Greater Houston area. Houston area, one risk of failure. Annual capital budget dollars are then
of the major load centers in ERCOT, interconnects to allocated for targeted pro-active replacements.
the transmission grid at 345 kV and 138 kV voltage Station assets are prioritized for replacement based
levels. A combination of local generation and import on analytics information using factors such as
power from external sources serves the extremely vintage, diagnostic test results, probability & impact
dense load of around 18,000 MW in this area. of failure, Operational & Maintenance (O&M) cost,
design and most importantly condition or health of
The methodology and information related to life the asset. This intelligent information helps company
cycles used for development of analytics is based on asset managers make right decisions regarding
discussions held at Electric Power Research replacements versus repairs.
Institute’s (EPRI) member utilities platform,
contribution from CenterPoint Energy’s subject Pro-active replacement of substation assets
matter experts and have been presented at various before they reach the end of their useful life, or as a
industry forums. result of inspections is an important modernization
This paper discusses the use of data integration strategy of the company. However, more equipment
methodology, smart algorithms and application of of all types installed on CenterPoint Energy’s electric
latest Information Technology (IT) capabilities as network is identified for replacement that can be
building blocks used during the development of replaced in any given year. As such, the strategy at
substation analytics. CenterPoint Energy is to balance resources, outage
availability, reliability and system impact to prioritize
work that will be accomplished in a given year.
Without continued implementation of planned capital

Page 234 of 284


replacements, equipment failure rates could rise in protection and control equipment varies significantly
response to aging infrastructure, higher loads and from electromechanical to microprocessor relays.
rising fault levels. Electromechanical relays have a typical life span of
30 to 40 years, which matches the life span of
equipment, such as circuit breakers. Microprocessor
relays on the other hand have a much shorter life
expectation than their predecessors and is in the
range of 10-15 years. Therefore, a substation may
require replacing microprocessor relays two to three
times during the 40-year life cycle of high-voltage
equipment such as a power transformer. A holistic
asset replacement strategy that takes into account
mismatched life cycles for various substation assets
could be a possible solution in order to resolve this
type of life cycle issues.

Use of analytics information to support


replacement strategy formation is described below
for transformers, breakers and protective relays:

1. Substation Transformers
Figure 1: A typical substation showing circuit
breakers and high voltage bus work. Substation transformers are important asset in an
electric substation. These are essentially static
Besides asset condition, CenterPoint Energy also devices that operate at primary voltages ranging from
replaces substation assets proactively based on 12 kV to 345 kV. They are used to step down
capacity constraints. System planning engineers at electricity from high voltage down to a lower voltage
CenterPoint Energy conduct steady-state, short level that is more appropriate for distribution to local
circuit and dynamic analyses based on load areas. They consist of insulated windings installed
forecasting. Based on results of such planning studies on laminated steel cores and immersed in oil that
the company continually and routinely replaces insulates and cools the equipment.
substation equipment to maintain safety and grid
reliability. As three-phase banks, transformer assemblies
can include either three single-phase units or one
CenterPoint Energy has developed in-house asset three-phase unit. Transformer assemblies consist of
life cycle systems. These systems provide following key components:
intelligence in the form of analytics to asset
management, operations and engineering to help  Core and Coils
prioritize assets for replacement based on condition  Insulation & Bushings
and system risk. Since timing of this work is usually  Tanks
not driven by a specific event, such as a projected  Cooling system
summer – peak demand, this work is sometimes
 De-energized/On-Load Tap changers
shifted forward or backward by few months to meet
outage windows and manage resources needed to  Foundations & spill containment
address time critical work. However, occasionally it  Protection & Controls
becomes necessary to replace failed substation
Transformers have no preset life expectancy, but
equipment that has resulted in a significant outage or
utilities generally expect transformers to have a
has created an unsafe condition. Such replacements
useful life span of 40 to 50 years, assuming normal
are performed on an emergency basis just prior to or
loads and operating conditions. In a typical electric
immediately after an asset failure.
system, transformers operate under many extreme
conditions, both normal and abnormal, which affect
Substation equipment, such as a power
their aging and breakdown. Overloads cause above
transformer or a circuit breaker, typically has an
expected life span of 40 years or even longer if normal temperatures, through-faults can cause
maintained properly. In contrast, the life span of displacement of coils and insulation.

Page 235 of 284


degradation etc. It is anticipated that in the near
future, analytics related to on-line monitoring will
help electric service providers develop new smarter
maintenance programs and extend maintenance
intervals with confidence based on analytics
information.

Figure 2: Industry-wide age profile of in-service


substation class transformers at all voltage levels [1]

The condition of cores and coils typically dictate


the useful life of a transformer. These components
undergo operating stresses like overloading, short
circuit, thermal and electro-magnetic effects plus
transient and dynamic over-voltages. These stresses
cause cumulative and non-reversible degradation to Figure 3: A transformer installed inside a typical
paper insulation inside the transformer. Moisture substation.
from high humidity levels and particles and acids
from surrounding industrial environment degrade Presently, the industry-wide annual failure rate
transformer insulation as well. Conditions degrading for substation class power transformers is 0.5%. For
transformer insulation could eventually lead to auto transformers, the observed annual failure rate
equipment failures. presently sits at 0.5% as well. The source for this
information is EPRI’s Industry-Wide Database for
Load Tap Changers (LTC’s) are dynamic transformers (IDB) based on information as of first
components of transformers with several moving quarter 2015.
parts subject to wear and stress. LTCs frequently
make and break high currents and undergo arcing that
accompanies such operations. Excessive arcing
causes overheating, contact burning, insulating oil
contamination and short circuit failures. In many
cases, LTC’s have shorter life than the useful life
expectancy of their transformer core assembly.
Accumulation of coking on the LTC’s is an issue of
major concern from a failure perspective. Asset life
cycle operational analytics provides alerts regarding
LTCs that have not crossed neutral for extended
periods of times. This helps ensure that necessary
corrective actions are taken by exercising the LTC’s
so as to prevent coking on the contacts which could Figure 4: Industry-wide age profile of substation
lead to LTC driven transformer failures. class transformer failures [1]

As mentioned earlier, CenterPoint Energy’s


Another means of operational data collection,
transformer replacement strategy is to prioritize and
namely the on-line monitoring of substation assets, is
proactively replace deteriorated transformers based
not a new concept in the electric power industry.
on their condition prior to failure. Present criteria
Electric service providers however, have recently
used to determine health of transformers includes:
started using the real-time data for operational and
condition determination such as insulation

Page 236 of 284


 Fault levels & vintage require custom specification and design, highway
 Alarms & Maintenance Activity permitting, fabrication and testing. Since these types
 Financials such as (O&M) expense of assets are deployed on need basis only, they
 Peak Loading & duration experience longer life cycle and require different
 Dissolved Gas Analysis (DGA) intervals of maintenance as compared with substation
transformers. Mobile transformers would require a
While determining the condition of transformers, different set of criteria for determining their condition
there is a heavy emphasis placed on level of for pro-active replacements which is out of the scope
degradation of insulation which in turn is based on of this paper.
DGA results. DGA determines the quantities of
various gases dissolved in transformer oil. It serves as 3. Circuit Breakers
a primary means to assess insulation condition and
identifies faults such as overheating, arcing in oil and Circuit breakers are also an important substation
partial discharge damage. CenterPoint Energy uses asset from a reliability perspective. A circuit breaker
EPRI’s PTX diagnostic system to interpret levels of is a device designed to automatically interrupt flow
transformer insulation degradation and any abnormal of electricity in the event of a problem such as a short
thermal, core or electric faults [2]. circuit or circuit overload. A circuit breaker can be
reset manually or automatically to resume normal
Besides prioritizing the transformers for operation and restore customer service.
replacement, availability of resources including
capital dollars, outage availability and long lead time
material availability also plays an important role in
deciding the timing for pro-active transformer
replacements.

2. Mobile Transformers

Electric service providers maintain adequate


supply of mobile transformers and capitalized
emergency transformer stock for emergency
response. Mobile transformers can be described as
transformers on wheels.

Figure 6: An SF6 dead tank type circuit breaker


installed inside a typical substation.

While this asset class consists of several different


technologies, they may have many common
degradation issues. For example, all circuit breakers
undergo some contact degradation every time they
open to interrupt an arc. Also, arcing produces heat
and decomposing products that degrade surrounding
insulation materials, nozzles, interrupter chambers
and grids. Circuit breakers failure rate and severity of
Figure 5: Typical mobile substations that can be degradation depends on several factors including but
deployed on an emergency basis. not limited to insulating medium, operating
environment and breaker duties.
They are capable of being deployed system-wide
in response to transformer failure events and enable At CenterPoint Energy, breaker replacements are
service restoration typically within 24 to 72 hours. triggered not only by breaker condition but also by
Mobiles are also used during planned transformer projects associated with improvement of bus
replacements where outage is difficult to obtain and reliability such as conversion of existing transmission

Page 237 of 284


class buses to Breaker and a Half (BAAH) or ring targeting oil breakers for pro-active replacements
bus configuration to enhance bus reliability and under breaker replacement program. In some cases,
support compliance of regulatory requirements. breakers have become overstressed or overloaded due
to system modifications, or have become unreliable
or uneconomical to maintain and repair.

Figure 7: Transmission class breakers age versus all


transmission class voltage levels

Council on Large Electric Systems (CIGRE) Figure 9: Typical mix of circuit breakers based on
studies on circuit breaker reliability have confirmed operating medium, at all transmission voltages
that mechanical degradation presents greater end-of-
life concerns than electrical degradation. Even for In order to prioritize breakers for replacement,
modern SF6 gas breakers, mechanical degradation CenterPoint Energy conducts evaluation of its assets
causes 80% of observed problems. Generally, based on maintenance assessment that includes
operating mechanisms, bearings, linkages and drive following factors:
rods represent components that experience most
mechanical degradation problems. Gas, oil and air  Bus fault levels & misoperations
leakage also occur. Newer classes of breakers use  Tank and breaker type
simpler operating mechanisms and have seals and  O&M expense & Maintenance Activity
fittings that help minimize leaks. Shown below is a  No. of Operations & vintage
typical relationship between number of years a  Operating mechanism & manufacturer
beaker remains in-service and the unit maintenance
cost.

Figure 10: Probability of failure versus age for


Figure 8: O&M expense for breakers versus age for
typical transmission class breakers
all transmission class voltage levels - typical
Whenever possible, circuit breakers planned for
Oil circuit breakers require more maintenance
replacement within a substation are grouped together
than SF6 breakers. Oil breakers involved in switching
for replacement to capture efficiencies.
operations have an even higher maintenance needs.
CenterPoint Energy breaker strategy involves

Page 238 of 284


4. Protective Relays [3]

The Protection & Control systems (P&C) are an


important component of the primary circuit elements
of the T&D system, and are a critical component with
respect to preserving the life of the circuit elements
and maintaining the overall reliability of the system.
Mix of protective relays by type for a typical electric
service provider is shown below.

Figure 12: Electro-mechanical relay panels installed


inside a typical substation control house.

b) Solid-State Relays

Developed during the 1970’s, solid state relays


Figure 11: Mix of different types of relays for a have fewer moving parts than electro-mechanical
typical electric transmission provider. relays. These are also known as static relays. These
types of relays have several analogue parts such as
In the electric utility industry, many of the capacitors, diodes, op-amps etc. Relay components
existing electro-mechanical and solid state relays are are mounted on printed circuit boards (PCB’s).
functional but nearing obsolescence. Presently,
electric industry protective relay assets comprise of Root cause of failure/malfunction for majority of
following types of relays described below: these relays is due to input card failure due to over
voltage and over current conditions. Output contacts
a) Electro-mechanical Relays may also wear out and eventually fail. Power supply
card failures may also lead to relay
Electro-mechanical relays function based on failure/malfunctions.
physical and electromagnetic properties using
rotating disks, springs and other mechanical parts.
Majority of Electro-mechanical relays have heavy
burdens and have direct input from secondary
instrument transformers such as Current
Transformers (CTs) and Potential Transformers
(PTs).

Since electro-mechanical relays depend on


electro-magnetic properties and several mechanical
parts, any wear, corrosion or dust accumulation on
moving parts can affect relay accuracy and
calibration. Additionally, aging of mechanical springs
may cause changes in spring constants and affect
relay accuracy and calibration. Repeated making and
breaking of electric current leads to deterioration of
relay output contacts and may lead to relay
malfunction. Regular visual inspections, test results Figure 13: Solid state relay panels also known as
calibrations and historical performance are indices static relays installed inside a typical substation
for assessing health and condition of electro- control house.
mechanical relays.

Page 239 of 284


c) Microprocessor-Based Relays Just like its predecessors, visual inspections and
test results and historical performance are important
Microprocessor-based relays are computer based indicators of the health and condition of
system with software based algorithms for detection microprocessor-based relays. Industry-wide, obsolete
and clearance of electrical faults. These are the most P&C assets are being replaced with proven protective
modern category of protective relays. This category relaying and SCADA RTU digital microprocessor
of relays has much broader capabilities than electro- based hardware and software technology. Electric
mechanical or solid-state relays. Presently in the service providers would expect to see a reduction in
electric power industry, most of the new protection O&M costs as a result of P&C capital investment in
scheme installations and replacements are utilizing
micro-processor based technology. The new
microprocessor-based relays.
technology offers the opportunity to apply revised
P&C maintenance strategies with increased intervals
which would reduce O&M cost. It will also help
increase the penetration of micro-processor based
relays with enhanced fault identification and location
capabilities.

Figure 14: Microprocessor based relay panel

Main difference between microprocessor-based


relays and solid-state relays is the use of software
algorithms and numerical processing. As a result, Figure 16: Heat map showing probability of failure
aging processes and failure modes are more difficult on y-axis and station impact on the x-axis for
to define and predict for microprocessor-based relays protective relays for a typical electric transmission
as compared to the other two types of relays. provider.
However, microprocessor-based relays often have
self-diagnostic capabilities that can assist in assessing Replacement of obsolete relays with micro-
their health. processor based relays will also enable electric
providers to reduce system events and provide
increased post event analysis and availability for
testing and maintenance. The newer relays are
expected to provide enhanced electric system
analytics data for quicker and better decision making
during service restoration providing opportunities to
integrate functions and take advantage of mature
technology.

CenterPoint Energy’s relay replacement strategy


is identical to transformers and breakers replacement
strategy whereby protective relays are prioritized and
proactively replaced prior to failure.
Figure 15: Typical life cycle curves for different
types of relays [4]

Page 240 of 284


CenterPoint Energy’s relay health prioritization system. System reliability and safety dictates the
criteria include: levels of spares maintained at strategic locations.
Spare levels are evaluated on periodic basis and
 Vintage capital dollars allocated on annual basis for purchase
 Mean Time Between Failures (P) of Capitalized Emergency Material (CEM). Due
 Financials (O&M) expense (P) diligence is exercised in maintaining adequate levels
 Misoperations (P) of spares at strategic locations e.g. CEM transformers
 Relay Type & Obsolescence (P) which risk expiration of manufacturer’s warranties
are rotated and installed under ongoing capacity and
 Station Bus Configuration (I)
replacement projects. New spares are then ordered to
 Station Impact (I)
back fill the CEM stock.
 Protection Scheme (I)
 No. of Operations (P) Almost all electric service providers maintain
inventories of spare substation equipment to mitigate
P: Performance I: Impact
the effects of equipment failures. Onsite spares
Impact Score = {(X% Station Impact) improve service reliability and customer satisfaction
+ (Y% Protection Scheme) by reducing outage times during emergency
+ (Z% Bus Configuration)} conditions. Without available spares, replacement
times could get extended due to unforeseen
Health Score = A% ∑Performance Indices + B% Age procurement and delivery delays. In particular,
substation transformers may take months to replace,
Total Score = (C% Impact) + (D% Health Score) [4] potentially prolonging outages and creating
significant challenges for utilities striving to maintain
Risk Index = Probability of failure x System Impact reliability and control O&M costs.

Weightages assigned to the individual terms are


variables depending on the system configuration and
electric utility’s requirements.

Figure 18: Spare assets need to be shipped to their


Figure 17: Mix of different transmission protective destinations based on manufacturer’s guidelines in
relays and their age for a typical electric transmission order to prevent events such as shown here.
provider.
Maintaining spares incur significant O&M costs
III. ASSET SPARES STRATEGY such as capital, storage, maintenance and testing on
periodic basis. Costs associated with maintaining
spares inventory are dependent upon the different
A spare strategy could be set of actin based
types of spares kept at hand e.g. transformers,
decisions relating to purchase and utilization of spare
breakers, CCVT’s etc. Maintaining fewer spares
assets in case of emergency conditions. At
could cause prolonged system outages while too
CenterPoint Energy, substation spare strategy is
many spares could increase O&M cost associated
based on maintaining a safe and reliable electric
with maintaining these spare assets.

Page 241 of 284


North American Electric Reliability Corporation IV. ASSET MAINTENANCE STRATEGY
(NERC) has made available with input from various
electric utilities an online Spare Equipment Database
(SED). The inventory of spare equipment will be The need for development of an efficient asset
helpful industry resource should an emergency maintenance strategy is due to various reasons such as
condition warrant deployment of a spare. Information aging electric infrastructure, retiring workforce and
collected in the spares database is voluntary flat O&M expenditures. Despite an increased need for
information from participating electric utilities bound maintenance, majority of electric utility companies
by a mutual confidentiality agreement. At this time plan decreased or flat O&M spending. Electric service
the SED contains spares related to High-voltage providers are exploring options such as looking into
transmission and generator step-up transformers changing the traditional approach of sending
which are necessary for operation of integrated bulk maintenance crew to substations to ascertain whether
power systems [5]. a particular asset needs maintenance or not. Using
analytics information, predictive maintenance
techniques can be developed to determine condition of
in-service equipment to ascertain timing of
maintenance. Predictive maintenance approach helps
save cost as compared with routine or time based
preventive maintenance. In this approach,
maintenance tasks are performed on need basis.
Advantages of predictive maintenance using
analytics include:

 prevents unexpected failures


Figure 19: Spare transformers stored temporarily  reduces corrective maintenance
inside a typical substation ready to be energized in  increased asset life cycle
case of a failure.
Electric Power Research Institute (EPRI) has Concept of use of predictive analytics in
initiated a project e to investigate and assess available maintenance of substation assets comes from the
methods for determining spares strategies, identify electric power generation industry. Preventative
strengths and weaknesses and develop an enhanced maintenance is a time-based approach whereby
analytical methodology for determining spares equipment undergoes maintenance or replacement at
strategies. The methodology will take advantage of pre-determined intervals e.g. replacement of a circuit
other EPRI developments in the areas of fleet breaker based on certain number of operations under
management and industry-wide data bases and hazard fault, switching or a combination of both conditions.
rate analyses.

Some of the parameters that could be considered Predictive maintenance based on analytics
during development of analytics based spare strategy involves using software technology for real time
include: monitoring of equipment condition and comparing its
current operational state to its initial state under
 spare levels and their strategic locations normal and emergency operating conditions e.g.
 asset installed base & its condition predictive maintenance strategy can be developed for
 system impact and lead times a substation transformer based on infra-red
 compliance requirements, if any inspections. Infra-red model can be developed and
 O&M costs and failure rates then compared using advanced algorithms with the
initial state model to determine any variances or
Future failure rates can be calculated based on invisible thermal signatures of impending damage
past historical failure information and condition before the damage occurs such as rapid deterioration
based asset health scores [6]. of insulation.

Page 242 of 284


Dashboards with tiles layout provides an efficient
way to drill down and access detailed analytics
results. This platform provides user functionality by
providing the capability to create downloadable
WEBI reports as well.

VI. TECHNOLOGY – HANA PLATFORM

CenterPoint Energy’s analytics utilize SAP


HANA platform. This platform provides several
advantages over conventional platforms which were
previously used as traditional data analytics
technology. It eliminates several layers of analytics
Figure 20: Typical substation class transformer infra-
processing allowing in-memory processing. It allows
red inspection signature under normal operating
conditions data processing at speeds x1000 times faster providing
quicker business intelligence. Because of its speed,
Alerts and notifications can be sent to simple analytics programs can be built that rely on
maintenance crew based on any remarkable findings. single copy of information.
By leveraging the right data, power utilities can
develop smart and efficient asset maintenance Traditional data analytics technology relied on
strategies. This will help free up their resources so layers of information which were copied at different
they can spend more time taking actions instead of levels of detail in order to present analytics results in
spending time looking for potential issues. the required format. In-memory data analytics
technology does not require any optimizations
allowing more data processing in less space and time.
V. DATA INTEGRATION

Analytics development triggered integration of


operational data stored in various databases into a
consumable form for analytics development purposes.
In-memory data integration from various databases on
state of the art SAP HANA platform allows faster data
processing.

Figure 22: Snapshot of a typical SAP HANA platform


used for analytics development purposes
New data analytics technology is not as
expensive nor infrastructure intensive like its
predecessor and there are no unnecessary time gaps
involved between data creation and analytics
reporting and its subsequent usage. At the core of
the SAP HANA platform is the HANA database. It is
a super-fast information storage and retrieval engine
Figure 21: SAP HANA data platform architecture – which can store and retrieve information in real-time.
typical [7] Integrated inside the platform are several functions
which fit into a number of categories. This platform

Page 243 of 284


has data transformation, streaming and batch load Electric power industry as of today is facing
capabilities. In addition there are a set of engines that complex market challenges and emerging issues
sit inside the HANA platform and run in-memory. relating to transmission and distribution of electrical
These include predictive libraries, business function energy. Some of these challenges include tighter
libraries, a text, sentiment and search engine, a spatial compliance environment, reduced and/or flat O&M
and a graph engine. This means the business budgets, retiring workforce all with pressures to
applications including substation analytics can reuse improve reliability targets and tighter rate case
information over and over again without duplication interventions. In order to meet these challenges the
or any transfer of information. industry is embracing the role of analytics to extract
actionable intelligence and push it back into utilities
processes as part of their business transformations.
VII. CONCLUDING REMARKS

Electric power industry is not new to application


of analytics. Analytics applications have been used in
the power industry since its birth though in various
forms and at different levels. These applications
ranged from as simple as spreadsheets to manually
record asset nameplate and diagnostic information to
complex condition based maintenance schedules. In
fact, predictive analytics, which is a form of
advanced analytics, has been used in the power
industry for the past several decades in the forms
ranging from simple a-c calculating boards to state of
the art software to conduct system planning studies Figure 24: Current positioning of electric power
and protective relay settings. Power system engineers industry in adopting asset related analytics as means
and protection engineers use these applications to to improve safety and system reliability and at the
predict system behavior under normal and emergency same time budget & spend Capital and O&M dollars
conditions based on system analytics. wisely.
An opportunity still exists though to incorporate
asset analytics information such as condition and The electric power industry has been collecting
probability of failures into T&D system planning and storing Big Data relating to their assets for a long
arena. This incorporation which might take place in period of time. It is only very recently that the
the future will help improve system visibility for industry has developed sophisticated platforms and
electric system providers which will in turn make the other necessary tools to derive insights hidden inside
system safer and more reliable. the data by converting it to actionable intelligence.
In general, substation analytics in the electric power
industry is in innovation and early adoption stage of
the technology adoption lifecycle curve. It is
struggling to cross “The Chasm”. Some of the
challenges being experienced by majority of electric
power providers that is preventing them to cross the
chasm and move forward are listed below:

 Limited availability of electric system


operational data in a consumable form and
data integration at enterprise level
 Existence of “silos” and limited working
relationship between electric business and
their technology departments
 Absence of dedicated teams to think and
Figure 23: Planning studies using modern day devise long-term asset management
software – an application of predictive analytics strategies using analytics due to limited
resources

Page 244 of 284


 Limited desire within the electric power The asset analytics industry has several software
operational units to “change” and explore applications to offer to the power industry. These
newer and smarter ways to carry out their applications are designed to increase asset reliability
operational activities by providing information relating to:
 Aggressive marketing techniques exhibited
on the part of technology companies to
 asset health based on condition
secure business which may cause the electric
providers to shy away from adopting this  reliability management and
technology  maintenance optimization
 Limited understanding on the part of
technology service providers regarding the Asset analytics applications provide holistic
needs of electric providers relative to asset view of asset health and status by providing online
analytics applications access and remote condition monitoring such as
 Limited availability of industry guidelines online DGA, load tap change (LTC) operation counts
and specifications regarding selection and etc. These applications provide accurate diagnosis
purchase of analytics applications and helps operators respond before any asset related
 Limited regulatory pressures or incentives at system disturbance occurs. Analytics information
federal and/or state levels for electric service also provides information that helps formulate asset
providers to adopt assets analytics maintenance and financial strategies for optimal
technology utilization of assets based on budget and system risk
 Relatively shorter technology life cycles constraints.

Advancements in asset inspection, assessment Analytics development at CenterPoint Energy


and diagnostics have resulted in a wide variety of was a combined effort between subject matter experts
data that can be used in assessing asset performance. of various departments including Substation
Asset performance data in turn can be used to make Operations, Engineering, System Protection, Asset
risk based financial and operational decisions as well. Management, Technology Operations, T&D Planning
Below is a conceptual view showing relationship and Standards & Materials. CenterPoint Energy
between analytics, asset strategies and capital & leadership also played a critical role in development
O&M budgeting. of substation analytics and asset management
strategy by providing their vison & insight and
making sure necessary resources are in place to
develop asset analytics.

Lastly, EPRI task force committee meetings


provided necessary platform for sharing analytics and
strategy development and feedback during
development stage.

VIII. REFERENCES

[1] EPRI, “Industry-Wide Transformers Database


Key Findings and Case Studies”, Product ID:
3002007831, 2016.
[2] EPRI, “PTX Transformer Fleet Management
Software”, Product ID: 3002005971, 2016.
Figure 25: Conceptual view showing relationship
[3] Q. Aziz, G. Sonde, “Protection & Controls
between asset analytics, strategies and capital &
Analytics for a Reliable Grid”, 2015.
O&M budgeting.
[4] A. Feathers, A. Mubaraki, A. Nungo and N. Paz,
“Relay Performance Index for a Sustainable

Page 245 of 284


Relay Replacement Program,” presented during
EPRI P&C Task Force Meeting held at
Charlotte, NC, 2015.
[5] NERC, “Spare Equipment Database”, Available:
http://www.nerc.com/pa/RAPA/sed/Pages/Spare-
Equipment-Database-(SED).aspx.
[6] EPRI, “Development of Substation Equipment
Spares Strategy Methodology, Analysis and
Guidelines”, Product ID: 3002008655, 2016.
[7] SAP, Available: http://sap.com

IX. BIOGRAPHY

Qasim Aziz is a Consultant in the Asset Management


department at CenterPoint Energy. He has around
eighteen years’ experience in the electric power
industry in various fields including engineering,
protection, operation & maintenance, planning and
project management in electric power generation,
transmission and distribution fields. His current job
responsibilities include development of asset life
cycle analytics for CenterPoint Energy’s assets. He
has a Bachelor’s degree in electrical engineering, MS
Engineering and an MBA from San Jose State
University, California. He is a member of EPRI’s
task force committees relating to asset management,
P&C, transformer and circuit breakers. He is
registered as a Professional Engineer in the states of
Texas and California.
Gautam Sonde is a Solution Architect for the
Operational & Corporate Analytics team
at CenterPoint Energy with a combined experience
of over twenty years in Information
Technology. He has been charged with the delivery
of innovative solutions in several areas such
as finance, asset management and smart meter
analytics. He has led his team through architecture
development to implementation of business solutions
which includes the delivery of data models,
reconciliations, and value added self-service
solutions using various state-of-the-art technologies.

Page 246 of 284


Comparative Analysis of Drilled Shafts using LPile and MFAD

By:

Sanchit Chitre, Transmission Line Engineer

Joel Coker, P.E., Transmission Line Engineer

Brian Sedgwick, P.E., Transmission Line

Engineer Leidos Engineering, LLC

July 21, 2017

Page 247 of 284


Table of Contents

PAGE

Abstract ......................................................................................................................................................... 3

1. Introduction .............................................................................................................................................. 3

2. Design Methodologies ............................................................................................................................. 4


A. MFAD, part of FAD Tools International, LLC Design Software ................................................................... 4
B. LPile ................................................................................................................................................................ 6

3. Design Example Showing Variation in Geotechnical Inputs ................................................................... 7

4. Design Example Showing Variation in Geometric Inputs ..................................................................... 12

5. Key Observations ................................................................................................................................... 15

6. References .............................................................................................................................................. 15

Page 248 of 284


Abstract
The electric transmission line utility industry predominately utilizes two design software suites for
concrete drilled shaft foundation design. The objective of this study was to conduct a comparative
analysis of drilled pier foundations, subject to transmission line steel monopole structure loading
conditions, designed using the programs LPile by Ensoft, Inc. and Moment Foundation Analysis and
Design (MFAD) by Electric Power Research Institute (EPRI), maintained by DiGioia Gray and
Associates. When properly designed, a drilled pier foundation effectively transfers axial, lateral, and
torsional loads in combination with shear forces and bending moments to the soil or rock supporting it.
This interactive relationship between the pier and the surrounding earth is a key variable in the algorithms
of pier design software programs such as MFAD and LPile.

While the programs’ main difference is the modeling of the drilled pier behavior (MFAD as rigid and
LPile as flexible member), this study focused on how each program accounted for the interaction of the
foundation shafts with the surrounding subsurface media. As there is a wide variety of subsurface
materials and conditions with various characteristic distinctions, a review of existing p-y (lateral load
transfer) models and non-linear spring parameters was completed to determine the appropriate soil
parameters to be utilized for the analysis. Multiple foundation shaft sizes, with varying aspect ratios, were
analyzed for a combination of different subsurface material engineering properties and structural loads
using both LPile and MFAD. The performance of each of the foundation designs was assessed based on
the strength and deflection criteria.

By comparing the resulting designs, this study provides basic guidelines to help determine which program
would yield the most optimized solution for a given set of parameters and eliminate potentially over-
conservative designs.

1. Introduction
Drilled shaft and direct embedded foundation types have been widely utilized to support transmission line
structures subjected to line loads. In general, any transmission line structure can be categorized into a
rigid or rotational structure based on the system’s resistance to deformations. In contrast to rigid
structures such as lattice towers and braced H-frames where uplift, compression and shear demands are of
significance, foundations of rotational structures such as monopoles and unbraced H-frames need to be
resisted for large overturning moment and shear demands. While direct embedded foundation designs are
mostly limited to lightly loaded tangent pole structures, drilled shaft foundations are more applicable for
resisting heavier transmission line loads. This study is limited to the analysis and design of drilled shaft
foundations of rotational structures (e.g.: steel monopoles).

There is a variety of software tools that perform the analysis and design of drilled shaft foundations of
rotational structures (moment-governed), of which, MFAD and LPile are the most commonly utilized
packages in the transmission line industry. The design outputs of both foundation software packages are
dependent on a set of user-specified inputs that can be categorized based on geotechnical conditions,
geometry of the shaft and applied loads. Based on the structural specifications of different utilities and the
geography of the project-site, these input parameters can fluctuate significantly, thus resulting in vastly
different output designs. The primary objective of this study is to assess the drilled shaft foundation
design outputs generated by MFAD and LPile for a given set of controllably varied input parameters.

Page 249 of 284


The following sections of this paper not only detail the design methodologies of both programs but also
delve into several design examples showcasing the effect of design parameters on program outputs. This
paper also focusses on comparing the output results between LPile and MFAD while considering the
impact of spring contributions utilized within MFAD. With the results obtained and the observations
made, this paper thereby acknowledges the differences in the methodologies of both programs.

2. Design Methodologies
It is crucial to have an understanding of how the subsurface material and shaft capacities are computed
within each program in order to determine the appropriate applicability and degree of conservatism. As in
the case of foundation engineering, soil-structure interaction becomes significant because of the
difference in mobilization of the structure with respect to the soil. Both LPile and MFAD utilize nonlinear
Winkler-spring mechanisms to model the appropriate nonlinear response of the subsurface material.
These responses are then calibrated using results of full-scale lateral load tests.

A. MFAD, part of FAD Tools International, LLC Design Software


i. Spring Models

MFAD uses a four-spring load-deflection model to reflect the interaction between the drilled shaft and the
surrounding subsurface, as shown in Figure-1 below.

Figure 1- Free-body Diagram (left) and Schematic Diagram (right) [5] of Spring Model used in MFAD

These four types of springs relate the resisting forces acting on the drilled shaft with the resulting
deformations, as follows:

Page 250 of 284


 Lateral translational springs associates the horizontal subsurface reaction on the side of the shaft.
The degree of stiffness of these translational springs depends on the stiffness of the layer and is
quantified using the Deformation Modulus input specified by the user in MFAD. In short, the
lateral resistance offered by the subsurface material layer is a measure of its stiffness.
 Base shear translational spring associates the horizontal shearing force imposed at the base of the
shaft because of the relative translation of the shaft and the material underneath.
 Base moment rotational spring associates the bending moment imposed at the base of the shaft
because of the relative rotation of the shaft and the material underneath.
 Side shear spring associates the vertical shear force that the shaft experiences due to the shear
friction at the interface.
The capacity of a drilled shaft is a combination of contributions of all these four springs, of which, the
contribution of lateral translational spring in providing resistance is generally the most significant. MFAD
further allows users to turn off the three remaining springs (base shear, base moment and side shear) to
account for conservatism or to further customize the design scenario (smooth casing, etc.).
Deformation Moduli utilized by MFAD to compute lateral resistance offered by the soil, is a measure of
the consistency and the unconfined compressive strength of the resisting material. In general, soil
consistency is determined by resistance tests performed in the field such as the Standard Penetration Test
(SPT). Depending on the type of soil, the MFAD technical manual provides charts correlating
Deformation Moduli with Standard Penetration Resistance.

ii. Reliability-Based Design

Recently, reliability-based design methods have been developed for different designs in foundation
engineering to account for uncertainties that exist in loading, geometry and geotechnical aspects of any
foundation. The traditional deterministic approach to account for such uncertainties is to include
conservative values of uncertain quantities and safety factors which often yield over-conservative designs.

Figure 2- Combined Probability Density Function representing limit state of a system [3]

In reliability-based design, g is the limit state function that divides the design space into two regions, the
safety region (g > 0) and the failure region (g < 0). The limit state function corresponds to the safety
margin measured as a difference between resistance, R, and load effect, Q, as illustrated in Figure-2.
Because of the input uncertainties, g in itself, is treated as a random variable with an assumed normal
distribution.

Page 251 of 284


In the calibration procedure of MFAD, full-scale foundation load tests were performed on drilled shafts in
soil and rock subsurface profiles. Based on its in-built four-spring model, geometry of the shaft and the
loading, MFAD predicts the ultimate nominal capacity (Rn) of each test whereas the test capacity (RT) is
predicted from field tests. This developed data is then plotted and a least square fit line is established. For
a full-scale load testing performed in MFAD, the least square fit line corresponds to a constant coefficient
of variation of 23.1 percent and a slope of 0.99 [5]. With an attempt to attain maximum target reliability,
5 percent lower exclusion limit is considered which results in a strength factor of 0.63, complying to the
reliability-based approach.

B. LPile
i. Spring Models

The subsurface surrounding the pile is modeled as a set of nonlinear springs in LPile to reflect that the
soil resistance p is a nonlinear function of pile deflection y.

Figure 3- Free-body Diagram (left) and Schematic Diagram (right) of Spring Model used in LPile

Unlike MFAD, the subsurface model in LPile only utilizes lateral translational springs for different
subsurface material layers, as shown in Figure 3. The p-y curve corresponding to the top translational
spring is to indicate that the pile is subject to a finite deflection with no subsurface resistance.

Derivation of p-y curve models in LPile is based on the results of full-scale foundation load tests. During
a load test on a laterally loaded pile, strain gauges are installed along the length of the pile that records
strains at gauge locations. From the direct measurement of strain and curvature, bending moment values
can be further derived. Evaluation of mobilized subsurface resistance along the length of the pile requires
two differentiations of bending moment curves with respect to depth. The experimental p-y curves are
then plotted showing the distribution of deflection and subsurface resistance.

ii. Finite Differences Analysis Method

For the implementation of the p-y method, the beam-column differential equation is solved in LPile using
the finite differences analysis method. The foundation shaft is divided into n intervals with a node at

Page 252 of 284


either end of the interval. For each interval, flexural stiffness EI is appropriately defined. The subsurface
is divided into a series of nonlinear springs located at each node, as shown in Figure 3.

Following the full-scale load testing procedure described above, strain values are recorded for increments
of the applied structural loads. The results of the full-scale load tests determine the boundary conditions
for each of the nodes of the n intervals. Applying these boundary conditions, the program evaluates a
condition of static equilibrium and computes the shear, moment and lateral deflection at each interval.

3. Design Example Showing Variation in Geotechnical Inputs


Maximum internal reactions (bending moment and shear force) and the degrees of deformation
(deflection and rotation) of the drilled shaft directly depend on the input parameters (geotechnical,
geometric and loading). This section covers design examples showing a systematic variation of
geotechnical input conditions while maintaining the geometric and loading inputs constant. Based on their
interaction with the foundation shaft, most subsurface materials can be categorized into – cohesive and
cohesion-less types. Cohesive soils are fine-grained in nature and provide resistance due to shear strength
developed. Cohesion-less soils are coarse-grained in nature and provide resistance due to internal friction.

Problem Statement
A double circuit 150 feet, 90 degree, dead-end 138 kV steel monopole is considered in a National
Electrical Safety Code (NESC) light loading district. Maximum base reactions provided by the vendor
shall be utilized for the drilled shaft design. Consistent shaft geometry is used in this design example as
tabulated in Table 1. Geotechnical input parameters that are subject to variation as parts of this example
are tabulated in Table 2. Monolithic soil profiles with depths of 75 feet for cohesive and cohesion-less soil
types are utilized. Soft clay (Matlock) p-y curve is selected In LPile for poor clay profile. Stiff clay
without free water (Reese) is selected in LPile for average and good clay profiles. Sand (Reese) is
selected in LPile for all sand profiles. A constant water table depth of 33 feet is assumed for all profiles.

Loading Inputs Geometric Inputs


Moment 26631 k-ft Diameter 10ft
Shear 266 k Depth 67ft
Axial 189 k Reveal 2ft
Table 1 - Geometric and Loading Inputs for Geotechnical Variation Design Example

Unit Weight Undrained Internal Angle


Soil (pcf) Shear Strength of Friction
Profile
Total Effective (ksf), c (degrees), ϕ
Poor 110 47 0.7 30
Average 125 62 1.2 33
Good 135 72 4 40
Table 2 - Geotechnical Variation

Page 253 of 284


a) Results for cohesive soils –

Maximum
Maximum Maximum Maximum Total Total
Input Pier
Pier Internal Moment Shear Rotation Deflection
Variation Internal
Moment (k-ft) Depth (ft) Depth (ft) (deg) (in)
Shear (k)
28757 13.1 940.6 42.8 2.13 17.8
Poor Clay 28324 8.9 707.5 39.6 0.68 5.6
28582 9.8 791.5 39.4 0.84 6.9
28563 12.4 916.5 42.8 0.44 2.8
Average Clay 27903 6.2 656.6 38.8 0.23 1.9
28073 6.5 732.4 37.1 0.29 2.2
27833 6.9 1061.2 31.1 0.19 0.6
Good Clay 28120 7.7 699.0 40.2 0.06 0.5
28131 7.3 762.0 38.1 0.07 0.6

LPILE
MFAD
MFAD - Springs OFF
Table 3- Results for Variation in Cohesive Soils

0 0 0
-20000 0 20000 40000 -1500 -1000 -500 0 500 -20 0 20
-10 -10 -10

-20 -20 -20

-30 -30 -30


Depth (ft)

Depth (ft)

Depth (ft)

-40 -40 -40

-50 -50 -50

-60 -60 -60

-70 -70 -70

-80 -80 -80


Moment (kip-ft) Shear (kip) Deflection (in)

Figure 4- Moment (left), Shear (center) and Deflection (right) Plots for Poor Clay Profile

Page 254 of 284


0 0 0
-20000 0 20000 40000 -1000 -500 0 500 -4 -2 0 2 4
-10 -10 -10

-20 -20 -20

-30 -30 -30

Depth (ft)

Depth (ft)
Depth (ft)

-40 -40 -40

-50 -50 -50

-60 -60 -60

-70 -70 -70

-80 -80 -80


Moment (kip-ft) Shear (kip) Deflection (in)

Figure 5- Moment (left), Shear (center) and Deflection (right) Plots for Average Clay Profile

0 0 0
-20000 0 20000 40000 -1500 -1000 -500 0 500 -1 -0.5 0 0.5 1

-10 -10 -10

-20 -20 -20

-30 -30 -30


Depth (ft)

Depth (ft)

Depth (ft)

-40 -40 -40

-50 -50 -50

-60 -60 -60

-70 -70 -70

-80 -80 -80


Moment (kip-ft) Shear (kip) Deflection (in)

Figure 6- Moment (left), Shear (center) and Deflection (right) Plots for Good Clay Profile

Page 255 of 284


b) Results for cohesion-less soils –

Maximum
Maximum Maximum Maximum Total Total
Input Pier
Pier Internal Moment Shear Rotation Deflection
Variation Internal
Moment (k-ft) Depth (ft) Depth (ft) (deg) (in)
Shear (k)
28931 12.4 794.2 39.3 0.27 1.2
Poor Sand
28741 10.5 757.4 43.7 0.24 2.2
28896 10.5 828.2 42.3 0.29 2.6
28730 11.0 845.7 33.1 0.23 0.9
Average Sand
28632 10.3 745.6 42.5 0.12 1.1
28757 10.2 808.0 41.4 0.15 1.3
28464 9.0 1004.3 28.3 0.19 0.6
Good Sand
28543 10.0 718.6 40.7 0.06 0.5
28627 9.9 775.0 39.5 0.07 0.5

LPILE
MFAD
MFAD - Springs OFF
Table 4- Results for Variation in Cohesion-less Soils

0 0 0
-20000 0 20000 40000 -1000 -500 0 500 -2 0 2 4

-10 -10 -10

-20 -20 -20

-30 -30 -30


Depth (ft)

Depth (ft)
Depth (ft)

-40 -40 -40

-50 -50 -50

-60 -60 -60

-70 -70 -70

-80 -80 -80


Moment (kip-ft) Shear (kip) Deflection (in)

Figure 7- Moment (left), Shear (center) and Deflection (right) Plots for Poor Sand Profile

Page 256 of 284


0 0 0
-20000 0 20000 40000 -1000 -500 0 500 -1 0 1 2

-10 -10 -10

-20 -20 -20

-30 -30 -30


Depth (ft)

Depth (ft)

Depth (ft)
-40 -40 -40

-50 -50 -50

-60 -60 -60

-70 -70 -70

-80 -80 -80


Moment (kip-ft) Shear (kip) Deflection (in)

Figure 8- Moment (left), Shear (center) and Deflection (right) Plots for Average Sand Profile

0 0 0
-20000 0 20000 40000 -1500 -1000 -500 0 500 -0.5 0 0.5 1

-10 -10 -10

-20 -20 -20

-30 -30 -30


Depth (ft)

Depth (ft)
Depth (ft)

-40 -40 -40

-50 -50 -50

-60 -60 -60

-70 -70 -70

-80 -80 -80


Moment (kip-ft) Shear (kip) Deflection (in)

Figure 9- Moment (left), Shear (center) and Deflection (right) Plots for Good Sand Profile

Page 257 of 284


4. Design Example Showing Variation in Geometric Inputs
As specified in the FAD tools user guide, the ratio of foundation depth to drilled shaft diameter, also
termed as the aspect ratio (AR), shall be equal to or less than 10 as a geometric constraint within the
program. Limiting the AR to 10 essentially ensures that the shaft will behave as a rigid body, which is a
primary consideration within MFAD. By analyzing drilled shafts with differing aspect ratios (between
two to ten), and maintaining consistent geotechnical and loading parameters, we can assess the design
outputs across the bending flexibility spectrum.

Problem Statement
A single circuit, 150 feet tangent 345 kV steel monopole is considered in an NESC light loading district.
Maximum base reactions provided by the vendor are utilized for drilled shaft design. A consistent average
clay soil profile is considered for this example as documented in Table 5. A constant pier length of 30 feet
inclusive of a two feet reveal is considered for this design example.

Geotechnical Inputs
Depth Unit Weight Internal
Undrained
to Angle of
Layer p-y curve selection Shear
Bottom Total Effective Friction
No. in LPile Strength
of Layer (pcf) (pcf) (degrees),
(ksf), c
(ft) ϕ
Soft Clay
1 5 90
(Matlock)
Soft Clay
2 6 120 0.8
(Matlock)
Soft Clay
3 18 125 1
(Matlock)
Stiff Clay w/o
4 53 Free Water 125 62 2.5
(Reese)
5 69 Sand (Reese) 120 57 32
Stiff Clay w/o
6 75 Free Water 125 62 1.5
(Reese)
Loading Inputs
Load Shear Axial
Moment
Case Load Case Name Load Load
No. [kips] [kip-ft] [kips]
1 Vendor Outputs 16.436 1358.17 14.727
Table 5 – Geotechnical and Loading Inputs for Geometric Variation Design Example

Diameter of Shaft
Shaft Aspect Ratio Pier Length (ft)
(ft)
AR = 10 3 30
AR = 5 6 30
AR = 2 15 30
Table 6 - Geometric Variation

Page 258 of 284


Maximum
Maximum Maximum Maximum Total Total
Input Pier
Pier Internal Moment Shear Rotation Deflection
Variation Internal
Moment (k-ft) Depth (ft) Depth (ft) (deg) (in)
Shear (k)
1498 9.3 149.6 23.4 1.20 2.2
Shaft w/
Aspect Ratio 1482 6.2 102.4 20.2 0.31 1.5
= 10
1484 6.3 110.1 19.6 0.37 1.7
1495 9.3 147.6 23.1 0.15 0.6
Shaft w/
Aspect Ratio 1485 6.7 95.2 22.3 0.14 0.7
=5
1485 6.3 113.0 19.8 0.27 1.3
1496 9.3 142.1 22.8 0.02 0.1
Shaft w/
Aspect Ratio 1478 6.0 69.3 21.2 0.05 0.2
=2
1486 6.5 113.8 20.2 0.11 0.5

LPILE
MFAD
MFAD - Springs OFF
Table 7- Results for Variation in Aspect Ratio

0 0 0
-1000 0 1000 2000 -200 -100 0 100 -2 0 2 4

-5 -5 -5

-10 -10 -10

-15 -15 -15


Depth (ft)

Depth (ft)

Depth (ft)

-20 -20 -20

-25 -25 -25

-30 -30 -30

-35 -35 -35


Moment (kip-ft) Shear (kip) Deflection (in)

Figure 10- Moment (left), Shear (center) and Deflection (right) Plots for Shafts with Aspect Ratio of 10

Page 259 of 284


0 0 0
-1000 0 1000 2000 -200 -100 0 100 -1 0 1 2

-5 -5 -5

-10 -10 -10

-15 -15 -15

Depth (ft)
Depth (ft)

Depth (ft)
-20 -20 -20

-25 -25 -25

-30 -30 -30

-35 -35 -35


Moment (kip-ft) Shear (kip) Deflection (in)

Figure 11- Moment (left), Shear (center) and Deflection (right) Plots for Shafts with Aspect Ratio of 5

0 0 0
-1000 0 1000 2000 -200 -100 0 100 -0.5 0 0.5 1

-5 -5 -5

-10 -10 -10

-15 -15 -15


Depth (ft)

Depth (ft)
Depth (ft)

-20 -20 -20

-25 -25 -25

-30 -30 -30

-35 -35 -35


Moment (kip-ft) Shear (kip) Deflection (in)

Figure 12- Moment (left), Shear (center) and Deflection (right) Plots for Shafts with Aspect Ratio of 2

Page 260 of 284


5. Key Observations
1. Strength-based observations depict consistent internal moment values calculated across both
programs, with very small percentage differences (less than 3 percent). Comparing the internal
shear results calculated by MFAD and LPile, we observe larger differences in maximum shear
and location (on average 25-30 percent difference). In general, LPile calculates larger design
capacity outputs than MFAD.

2. Performance-based observations depict vast differences in the total deflection and rotation values
calculated by LPile and MFAD. LPile typically calculates larger performance outputs than
MFAD. This is due to LPile’s primary modeling assumption of considering a flexible behavior of
a drilled shaft which, in contrast, is assumed as rigid behavior in MFAD.

3. The effect of springs is demonstrated by observing the close resemblance of results in clay
between LPile and MFAD with springs turned off. When springs are turned off in MFAD, side
shear, base shear and base moment contributions are eliminated and only lateral pressure
contribution is in effect. This is very similar to the LPile program’s methodology of solely
considering lateral pressure contribution in calculating soil capacity.

4. Comparing results in clay and sand profiles depict large conservatism in clay type p-y curve
models considered in LPile. We can infer that the p-y curve for ‘Sand’ model selection (Reese) in
LPile comply with the empirical test results utilized in MFAD. Cohesive soils develop more side
friction resistance than cohesion-less soils which has an apparent effect on the conservatism.

5. A very high aspect ratio of 10 (upper limit in MFAD) yields lower deflection results in MFAD
compared to LPile which treats the shaft as rigid. In contrast, a very low aspect ratio of 2 (lower
limit in MFAD) yields lower deflection results in LPile due to the limiting length of the shaft
which restricts the flex displacement of the physical pile. An average aspect ratio (4-8), which is
typically observed for transmission line structures, yields comparable results in MFAD and LPile
pertaining to its respective design philosophy.

6. References
[1] Nikos Gerolymos, George Gazetas. Development of Winkler model for static and dynamic
response of caisson foundations with soil and interface nonlinearities. Greece; 2005.
[2] David Bonhoff, Ph.D., P.E. Modeling Soil Behavior with Simple Springs. USA.
[3] Samuel G. Pakowsky. Standards and Reliability Based Design. USA.
[4] William M. Isenhower, Ph.D., P.E., Shin-Tower Wang, Ph.D., P.E., L. Gonzalo Vasquez, Ph.D.,
P.E. Technical Manual for LPile 2016. USA; 2016.
[5] Electric Power Research Institute, FAD Tools, FAD 5.1 User’s Guide. USA; 2015.
[6] Donald P. Coduto, Foundation Design Principles and Practices Second Edition. USA; 2001.

Page 261 of 284


WHITE PAPER / SUBSTATION SECURITY SYSTEM COMMISSIONING

START SOONER TO GET MORE


OUT OF COMMISSIONING
BY Terry Harless

When you are tasked with implementing a new


substation security system, the commissioning process
may seem like a time-consuming, but necessary, final
step. For optimal success, the time to begin verifying
that a security system operates as designed should
start long before the system is handed over.

Page 262 of 284


WHITE PAPER / SUBSTATION SECURITY SYSTEM COMMISSIONING

INTRODUCTION
Commissioning of substation security systems commonly
WHAT IS COMMISSIONING?
starts just weeks before the system is to be handed over
to the security operation center. But that can be a mistake. The commissioning process is designed to verify
that a substation security system operates in a
An integrator that doesn’t pre-test a system prior to manner consistent with the design documents.
commissioning, for example, may find the number of It involves testing all the security points on a
punch list items to be overwhelming, often preventing system and validating the integration between
the system from passing the commissioning test. security systems. This reduces the risk of system
errors and minimizes or avoids time and capital
Experience suggests that outcomes are far better expenses associated with fixing problems.
when commissioning is treated as an ongoing process
that spans multiple stages in a security system’s
design and installation. That process begins during
the security system design phase with the development should also address how the item integrates with other
of a commissioning plan. Following this step-by-step security systems.
approach is a recipe for successful outcomes with minimal
disruptions during the process. Site and floor plans — These plans should identify
the initial placement of and field of view for each security
camera. Those details will help an agent determine
STEP ONE: THE COMMISSIONING PLAN
if the cameras are installed correctly.
The security designer or commissioning agent can start
creating commissioning forms and schedules as soon as
Network schedule — This document, which lists the IP
the substation security system design is issued for bid or
address for each security device and piece of equipment
construction, depending on the project delivery method.
attached to the network, should be distributed to the
owner’s IT department to coordinate IP addresses,
These documents provide a commissioning agent with
subnets and other details. This schedule also can be
the tools needed to precheck the security system during
used to help verify if existing switches have the needed
factory testing and other early testing opportunities.
capacity or if additional network switches are needed.

Commissioning documents that should be created


during a project’s design phase typically include: STEP TWO: FACTORY TESTING
While factory tests are rarely required by designers
Commissioning schedule — This schedule, which includes or owners, they can be valuable in solving integration
dates for document reviews, factory tests, site visits and issues prior to installation. For this reason, a savvy
acceptance testing, enables the commissioning agent commissioning agent will take an active role in
to plan for pre-commissioning tasks. The schedule should factory testing.
include some flexibility, as dates may need to fluctuate
to accommodate changes in the project’s timeline. Performed at the system integrator’s offices, factory
testing involves setting up a security system, including
Inspection checklist — This checklist covers all the cameras, card readers, door locks and other devices.
security devices, video recorders, card readers, servers, Then, using the current version of the commissioning
door panels, cabling and other equipment and operating checklist as a guide, each device is tested at its connection
scenarios that require inspection. Using a pass-fail format, point on the system.
the checklist is a tool the commissioning agent can use
to verify and document that an item is installed correctly, For these tests, all security equipment should be
labeled, cleaned and operating properly. This checklist installed, and most security devices should be connected

© 2017 Page 263 of 284


WHITE PAPER / SUBSTATION SECURITY SYSTEM COMMISSIONING

to it. Some devices, such as fence detection systems the commissioning checklist. Proper cable management
and vehicle gate motors, can’t be installed in a factory and device installation should be verified during each visit.
test setting. The integrator should create scenarios
that simulate alarms for these devices. Once installation is complete, the commissioning agent
should verify that the as-built drawings and operation
The integrator also should set up a security workstation and maintenance manuals correspond with the
to verify that each point on the security equipment commissioning checklist.
matches the device shown on the workstation.
STEP FOUR: SECURITY
After individual device testing is complete, integration SYSTEM PRE-TESTING
testing between the security systems begins. This involves Pre-testing is performed to make sure a security system
testing alarm points to verify that the correct cameras are is operating properly so that acceptance testing can
activating, alarms are properly labeled and other security begin. This testing is typically performed by the integrator,
systems are initiating the correct response to an alarm. with the commissioning agent making periodic site visits
to the substation to observe.
STEP THREE: SECURITY
SYSTEM INSTALLATION Pre-testing begins with troubleshooting the system to
A smart commissioning agent will likewise conduct confirm that all security devices have been connected
periodic site visits during security system installation. to the correct points on the security equipment, and
The agent can use these visits to verify that security that all programming is finalized. A sizable portion of
equipment, devices and cabling are being installed troubleshooting issues are traced to incorrect labeling
according to the construction documents. While of cables and minor programming errors. A mislabeled
the agent’s role during these visits is to advance motion detector or camera, for example, will bring up
the commissioning process, rather than to perform the wrong location when an alarm activates.
construction administration duties, it is the agent’s duty
to inform the design team if it appears that guidelines Other tasks performed by the integrator during pre-
are not being followed. testing include cleaning equipment cabinets, equipment
filters and security devices so they perform optimally.
During installation, the agent also should verify that the By this stage, the integrator should use the final
equipment, cabinets, devices and cabling are labeled as commissioning checklist to perform a commissioning
prescribed in the design documents, which should match test of the entire security system.

STEP FIVE: SECURITY SYSTEM BURN-IN


The purpose of burn-in is to give a security system time
— often two to four weeks — to operate in real-world
conditions, during which time the equipment might
“learn” from analytics and integrators can detect system
anomalies. This period usually, but not always, takes place
prior to acceptance testing. Weather events during burn-
in, for example, can bring to light vulnerabilities that can
be corrected before acceptance testing begins.

Burn-in is important because it helps make sure the


system is operating correctly using normal operating
procedures. Substation personnel should use the system
during burn-in as if it has been accepted.

© 2017 Page 264 of 284


WHITE PAPER / SUBSTATION SECURITY SYSTEM COMMISSIONING

During this phase, the security system alarm report is used Installation verification — The commissioning agent
to create a punch list. The integrator uses this list to verify should have verified that equipment, devices and
false alarms using video the system has recorded. If an cabling was properly installed during installation.
alarm is determined to be a nuisance, the integrator can During acceptance testing, the commissioning agent
take corrective action to solve the issue. should perform spot checks of the installation.

Punch list items should be resolved as they occur. If issues Penetration tests — Time permitting, the commissioning
persist, the owner should consider extending the burn-in team should perform random penetration tests during
period until the system is ready for acceptance testing. both day and night to find vulnerabilities an attacker
could exploit.
STEP SIX: ACCEPTANCE TESTING
Acceptance testing — the final tests before a security If the integrator and commissioning agent have worked
system is turned over to the owner — should be scheduled well together in resolving issues throughout the project,
by the integrator and commissioning agent prior to the acceptance testing should be relatively simple and
burn-in phase. At a minimum, the commissioning agent, trouble-free.
owner representative and integrator should be involved
in the final acceptance test. Most work will be performed CONCLUSION
from the substation, where they will activate alarms, verify Commissioning a substation security system is no small
device installation and perform other tests. One person is undertaking. The theoretical simplicity of checking things
typically stationed at the Security Operations Center to off a list can belie the importance of the process. Getting
verify that the system is functioning properly. better results and performing the process efficiently is
best achieved by making commissioning an ongoing
While performing the acceptance test, the commissioning element of the project.
agent should verify alarm naming conventions, map and
floor plan symbol locations, and network connectivity. Taking a step-by-step approach, beginning with a
Acceptance testing should include: comprehensive plan during design development, lays
a foundation for successful commissioning. Multistage
Alarm testing — Each alarm should be tested by testing, installation and burn-in time set the table for
simulating the conditions that would set off the alarm. acceptance testing, owner satisfaction and timely
To verify the alarm, the agent should confirm that it calls handover of the system to the owner.
up the correct camera. In some situations, more than one
camera may be used to verify alarms. BIOGRAPHY

Security system device verification — The agent should TERRY HARLESS is a senior physical security
verify that card readers, cameras, fence detection and specialist at Burns & McDonnell, with more than
other security devices are operating properly. 18 years’ experience in electronic security system
design and commissioning. In addition to writing
Camera views and fence zones — The agent should specifications for commissioning processes and
compare camera views and fence zones against design procedures, attending factory tests and assisting
documents to verify that the devices are correctly integrators with pre-commissioning tests, he has
mounted and aimed. tested and commissioned security systems on many
complex security projects in electric utility markets.
Labeling — The accuracy of labels on equipment in
cabinets and field devices should be verified through
comparisons to design documents, security workstation
02372-COM-0817

symbols and alarms.

© 2017 Page 265 of 284


Reducing Misoperations through Improved
Quality Control in Protection System Design

50th Annual Transmission and Substation Design and Operating Symposium


September 6-8, 2017

Tim Farrar
Chief Engineer-Protection and Controls
E: TFarrar@trcsolutions.com
P: (207) 621-7027
Page 266 of 284
Introduction
The protection system design for a typical substation involves many interrelated drawings, calculations,
studies and development of specific protective relay settings. Their accuracy has long been recognized
as critical to the successful, safe and secure construction, commissioning and operation of a utility
substation. This technical paper identifies a process that will improve the quality of protection system
design and protective relay settings to reduce the potential for protection system misoperations.
Refocusing attention on the Quality Control (QC) of protection system design and relay settings
development can achieve that goal.
Protection System Misoperations Defined
The North American Electric Reliability Corporation (NERC) is the regulatory authority whose mission is
to assure the reliable operation of the Bulk Electric System (BES) in North America. Under NERC’s
currently effective mandatory standard PRC-004-5(i) 1 effective April 1, 2017, utilities are obligated to
review all protection system operations in order to identify, report and correct those operations that
qualify as misoperations.
NERC has defined the term misoperation 2 as the failure of a Composite Protection 3 System to operate as
intended for protection purposes and lists six categories as described in Table 1 below.
The following is a general definition of misoperations:
• Any failure of a Protection System element to operate within the specified time when a fault
or abnormal condition occurs within a zone of protection.
• Any operation for a fault not within a zone of protection (other than operation as backup
protection for a fault in an adjacent zone that is not cleared within a specified time for the
protection for that zone).
• Any unintentional Protection System operation when no fault or other abnormal condition has
occurred unrelated to on-site maintenance and testing activity.
This definition is based on the IEEE Power System Relaying Subcommittee (PSRC) Working Group I3
“Transmission Protective Relay System Performance Measuring Methodology.”

1
The misoperations reporting standard PRC-004-5(i) may be found at this link:
http://www.nerc.com/_layouts/PrintStandard.aspx?standardnumber=PRC-004-
5(i)&title=Protection%20System%20Misoperation%20Identification%20and%20Correction&jurisdiction=United%2
0States
2
See the NERC Glossary of Terms for the full definition of the term misoperation:
http://www.nerc.com/pa/Stand/Glossary%20of%20Terms/Glossary_of_Terms.pdf
3
Composite Protection System - The total complement of Protection System(s) that function collectively to protect
an Element. Backup protection provided by a different Element’s Protection System(s) is excluded.

Page 267 of 284


NERC Requirements and Measures
The requirements of each Transmission Owner, Generator Owner, and Distribution Provider that owns
BES equipment must meet the following objectives:
• Review all Protection System operations on the BES to identify those that are Misoperations
of Protection Systems for Facilities that are part of the BES.
• Analyze Misoperations of Protection Systems for Facilities that are part of the BES to identify
the cause(s).
• Develop and implement Corrective Action Plans to address the cause(s) of Misoperations of
Protection Systems for Facilities that are part of the BES.
• Submission of Protection System Misoperation data to NERC’s Protection System Misoperation
Data Collection System.
NERC’s Protection System Misoperation Data Collection
The purpose of this data collection is to continue consistent reporting of Misoperation data to NERC
through a standardized template for performance analysis. NERC will analyze the data to:
• Develop meaningful metrics to assess Protection System performance.
• Identify trends in Protection System performance that negatively impact reliability.
• Identify remediation techniques to reduce the rate of occurrence and severity of
Misoperations.
• Provide focused assistance to entities in need of guidance.
• Publicize lessons learned to the industry.
NERC began mandatory collection of this data in the fourth quarter of 2012 and has been involved in
formal misoperation statistical analysis since at least 2009, if not earlier. NERC continues to conduct and
report misoperation performance results on an annual basis through its annual State of Reliability
Report 4 and its Reliability Assessment and Performance Analysis Portal 5.
To facilitate uniform information gathering in this area, in 2016 NERC moved to an online system called
the Misoperations Information Data Analysis System (MIDAS) 6. This tool requires specific data entries
including the following Misoperation Categories and Cause(s) of Misoperation as outlined in Tables 1
and Table 2 below:

4
NERC’s Annual State of Reliability Reports may be found at this link:
http://www.nerc.com/pa/RAPA/PA/Pages/default.aspx
5
NERC Reports on outages due to Failed Protection systems through its portal at:
http://www.nerc.com/pa/RAPA/ri/Pages/AutomaticTransOutagesInitiatedbyFailedProtSysHErr.aspx
6
NERC MIDAS information may be viewed at this link: http://www.nerc.com/pa/RAPA/Pages/Misoperations.aspx

Page 268 of 284


Table 1: Misoperation Category

Failure to Trip - A failure of a Composite Protection System to operate for a Fault condition
During Fault for which it is designed. The failure of a Protection System component is not a
Misoperation as long as the overall performance of the Composite Protection
System is correct.
Failure to Trip - A failure of a Composite Protection System to operate for a non-Fault
Other than Fault condition for which it is designed, such as a power swing, undervoltage,
overexcitation, or loss of excitation. The failure of a Protection System
component is not a Misoperation as long as the performance of the
Composite Protection System is correct.
Slow Trip - A Composite Protection System operation that is slower than intended for a
During Fault Fault condition if the duration of its operating time resulted in the operation
of at least one other Element’s Composite Protection System.
Slow Trip - A Composite Protection System operation that is slower than required for a
Other than Fault non-Fault condition, such as a power swing, undervoltage, overexcitation, or
loss of excitation, if the duration of its operating time resulted in the
operation of at least one other Element’s Composite Protection System.
Unnecessary Trip – An unnecessary Composite Protection System operation for a Fault condition
During Fault on another Element.

Unnecessary Trip - An unnecessary Composite Protection System operation for a non-Fault


Other than Fault condition. A Composite Protection System operation that is caused by
personnel during on-site maintenance, testing, inspection, construction or
commissioning activities is not a Misoperation.

Page 269 of 284


Table 2: Cause(s) of Misoperation

AC System This category includes Misoperations due to problems in the ac inputs


to the Protection System. Examples would include Misoperations
associated with CT saturation, loss of potential,
or rodent damaged wiring in a voltage or current circuit.
As-Left Personnel Error This category includes Misoperations due to the as-left condition of the
Protection System following maintenance or construction procedures.
These include test switches left open, wiring errors not associated with
incorrect drawings, carrier grounds left in place, or settings placed in
the wrong relay, or incorrect field settings left in the relay that do not
match engineering approved settings.
Communication Failures This category includes Misoperations due to failures in the
communication systems associated with protection schemes inclusive
of transmitters and receivers. Examples would include Misoperations
caused by loss of carrier, spurious transfer trips associated with noise,
Telco errors resulting in malperformance of communications over
leased lines, loss of fiber optic communication equipment, or
microwave problems associated with weather conditions.
DC System This category includes Misoperations due to problems in the dc control
circuits. These include problems in the battery or charging systems, trip
wiring to breakers, or loss of dc power to a relay or communication
device.
Incorrect Settings This category includes Misoperations due to issued setting errors,
including those caused by modeling errors, associated with
electromechanical and solid state relays, and the protection element
settings in microprocessor-based relays (excluding logic errors
discussed in the Logic error cause code).
Logic Errors This category includes Misoperations due to issued logic setting errors
associated with programming microprocessor relay inputs, outputs,
custom user logic, or protection function mapping to communication or
physical I/O points.
Design Errors This category includes Misoperations due to incorrect physical design.
Examples would include incorrect configuration on ac or dc schematic
or wiring drawings, or incorrectly applied protective equipment
(hardware or firmware).

Page 270 of 284


Relay This category includes Misoperations due to improper operation of the
Failures/Malfunctions relays themselves. These may be due to component failures, physical
damage to a device, firmware problems, or manufacturer errors.
Examples would include Misoperations caused by changes in relay
characteristic due to capacitor aging, misfiring thyristors, relay power
supply failure, or internal wiring/logic error. Failures of auxiliary
tripping relays fall under this category.
Unknown/Unexplainable This category includes Misoperations where no clear cause can be
determined. Requires extensive documentation of investigative actions
if this cause code is utilized. Do not use this cause code if the analysis is
still in progress.
Other/Explainable This category includes Misoperations that were determined to have an
identified cause but they do not fit into any of the above categories.
For example, temporary changes in network topology that because of
their low probability of occurrence are not accounted for in the design
of the Protection System, or environmental issues such as damage due
to water from a leaking roof or animal intrusion.

Misoperations Reporting from the NERC 2017 State of Reliability Report

The NERC 2017 State of Reliability Report states that while protection system misoperations rate
continue to decline, misoperations as a risk to reliability remains a priority. Figure 1 shows the total
correct operations rate for NERC through the first three reporting quarters of 2016.

Figure 1: Correct Protection System Operations Rate; NERC 2017 State of Reliability Report

Page 271 of 284


Figure 2 shows the regional misoperation rates and summarizes results of the statistical tests on
misoperation rate comparisons. The dark blue bars show the rates that are statistically significantly
higher than NERC’s rate of 9.5 percent. The rate of misoperations, as a percentage of total operations, is
just under 10% (i.e., roughly one in 10 protection system operations involves a misoperation).

Figure 2: Four-Year Misoperation Rate by Region (Q4 2012 – Q3 2016); NERC 2017 State of Reliability
Report

Figure 3 shows misoperations by cause code as a percentage to the total. The most common causes of
misoperations have remained the same through the past few years with over 60% percent of
misoperations caused by settings/logic/design errors, communication failures, and relay malfunctions.

Page 272 of 284


Figure 3: NERC Misoperations by Cause Code (Q2 2012 – Q3 2016); NERC 2017 State of Reliability Report
NERC lists the Protection System Misoperations Rate as a Key Finding in this report and is a priority area
of focus. NERC recommends the following:
• Identify protection system misoperations as a primary focus for industry: Protection system
misoperations should remain an area of focus as it continues to be one of the largest
contributors to the severity of transmission outages.
• Expand seminars on protection misoperations topic: Continue with and expand upon Regional
efforts on education, outreach and training with industry and stakeholders to reduce
protection system misoperations and continue the downward trend.
• Form partnerships to broaden message on misoperations: Continue collaboration with the
North American Transmission Forum, vendors, manufacturers, and others to understand,
mitigate, and reduce the protection system misoperation rate and impact on the BES. Seek
new venues for understanding the challenges associated with the top causes of
misoperations and broaden data sharing and information outreach where possible.

Page 273 of 284


NERC also reported that these misoperations often make system disturbances even more severe than if
the protection system had operated correctly.
Incorrect Relay Settings, Logic and Design Errors
Since the most significant source of misoperations is a result of incorrect relay settings, logic and design
errors, improvements in this area will provide the most near term benefit because they can be
controlled and improved with process changes. Reduction of incorrect relay settings, logic and design
error will move the industry toward reliable operation of the Bulk Electric System.
Industry Changes
The typical electric utility workforce, including protection engineers, technicians, etc., is aging and
retiring at an increased rate. These experienced, knowledgeable senior-level employees are commonly
being replaced with more junior staff, and so having a solid and up-to-date QC plan is important to
achieve effective knowledge transfer maintaining a high level of excellence and avoiding re-learning
lessons from past mistakes.
Engineering consultants are being used not only to develop the protection system design and relay
settings but also to act as the owners’ engineer and to carry out the utility’s QC plan, among other
important engineering roles. This again demonstrates the necessity of having a solid and up-to-date QC
plan for use within your company and by contract technical experts.
Technology changes in utility substations including the new IEC-61850 communication standard also
require us to refocus on quality. These automated substation architectures have changed the protection
system physical designs considerably. Some utilities now rely on extensive development and utilization
of logic diagrams for these platforms. Therefore, expanding the QC plan to the software and other
supporting documentation for these platforms is also crucial.
Design Standards
Having detailed and well-thought-out design standards is an important element in the QC plan. The
design standards are typically developed for common substation equipment (for example, line
protection, transformer protection and bus protection) and include a set of standard drawings
(schematic diagrams, wiring diagrams, layout drawings, materials lists, etc.) and relay setting
documentation (settings, basis documents, philosophy documents, etc.). These standard standards can
be used as a template to develop the site-specific drawings, documents and settings that are modified
to accommodate the individual application.
The design standards are part of the QC process. The checking team uses them as a tool to verify that a
new design meets the utility’s requirements. Quality improvement is a big benefit of design standards,
but other upsides also include consistency of designs among multiple design teams and/or consultants,
improved design efficiency, and the elimination of differences strictly due to personal preferences.
Design standards also can have operational and maintenance improvements by reducing the number of
unique designs that operators and maintenance personnel need to work with and understand.

Page 274 of 284


Peer Reviews and Point-to-Point Checks
Peer reviews and point-to-point wiring checks are the most important elements of a good QC plan. The
peer review process for both protection system designs and relay settings involve one or more
competent and qualified people (in the engineering topic) to review and evaluate the design and
identify any errors or omissions.
A common practice is to perform a peer review of protection system schematic diagrams for the
functional accuracy of the design. This can be performed before the point-to-point wiring and
interconnection diagrams are developed, therefore capturing any errors early in the design process.
When possible it is preferred to have the protection engineer perform this peer review to provide
overlap between the protection system design and relay settings.
Point-to-point checking is the process of verifying that all wiring points on schematic diagrams are
developed accurately (and equivalent) on the wiring diagrams. Typically this is done by tracing and
highlighting each circuit on each drawing. This process must be included on all design components to
ensure the accuracy of the entire design.
Checklists and Sign-off Lists
To ensure all aspects of the protection system design and relay settings are complete and accurate,
meet the client’s scope of work and design standards and have been peer-reviewed with all point-to-
point wiring checks, an additional step in the QC process is required. This step is typically implemented
with checklists and/or sign-off lists.
A common practice is to use a checklist of very specific tasks that must be completed as part of the
process. These tasks can be technical in nature (for example, use only one ground per current
transformer and voltage transformer circuit) or non-technical (for example, make sure the proper
border, revision block, text size, font, blocks/cells and client CADD standards have been followed).
It is also a common practice to require a signature or the initials of the person performing the QC task.
This provides a record of who performed the specific checking task and also assigns personal
accountability to the QC task.
The sign-off procedure is most effective if presented in a multi-step closed-loop process as described
below:
Step 1: The designer signs off, indicating the document is complete and self-checked.
Step 2: The checker signs off, indicating the peer review or checking is complete.
Step 3: The designer again signs off, indicating all checking corrections and comments have been
resolved or included in the document.
Step 4: The checker again signs off, indicating all checking corrections and comments have been
resolved or included in the document.

Page 275 of 284


Industry Resources
The IEEE/PSRC develops standards, guides and recommendation practices to assist the industry in
applying best practices. These technical documents are essential reference information to any
protection system design and relay setting development. A list of the protection related standards and
guides are available on the IEEE website.
In addition to the technical guideline in the NERC Standard, the IEEE/PSRC has published working group
reports to provide additional technical guidance for QC of both protection system design and protective
relay settings. These documents are also available on the IEEE website as follows:
• Quality Control for Protection and Control Design
• Processes, Issue, Trends and Quality Control of Relay Settings
As part of NERC’s mission to assure the reliability of the Bulk Electric System, it also provides technical
information useful to the whole industry. One very useful service provided by NERC is its lessons learned
resource, which features published documents that clearly identify common problems that have been
experienced, as well as the corrective actions taken, and of course the lessons learned during the
process. A quick reference guide to these documents is available on the NERC website as well.
Other Quality Control Elements
Below is a list of additional QC elements that also should be incorporated in a good QC plan:
• The role of cost, scope and schedule
• Communication with the entire design team including other engineering disciplines
• Communication with the client
• Establishing qualifications for the roles in the design and QC process
• Document control
• As-built documentation
• Monitoring and measuring the effectiveness of the QC process to provide feedback and
improvement
• Ongoing training program
Conclusions
The paramount goals of a Quality Control Plan are to provide high-quality protection system design and
relay settings that meet client scope and standards, without errors and omissions. The potential for
successful implementation and achievement of reliability objectives will be greatly improved through
this approach. Resources available from IEEE, NERC, including the checklists and guidance referenced in
this technical paper will help you to understand and apply all the elements necessary in a Quality
Control Plan to achieve this goal.

Page 276 of 284


50th Annual Transmission & Substation Design & Operation
Symposium

Building Information Modeling (BIM) Technology in


Substation Construction Progress Visualization – BIM 4D

Wolfgang EYRICH
entegra eyrich + appel gmbh
Germany

SUMMARY
Electrical power systems including substations have to be newly built and expanded continuously because
of the growing demand for energy. Due to this, a new philosophy for substation planning is necessary - the
Building Information Modeling (BIM) philosophy. The transition from conventional design to Building
Information Modeling presents a similar challenge to the engineers as it did for the transition to Computer
Aided Design (CAD) in the past. The Power industry is looking for the product -with capabilities beyond
that of existing CAD solutions - that allows for BIM solutions. BIM means new investments in software
and different approaches to projects. BIM is a design process that relies on an intelligent model - as the
basis for design, simulation and collaboration at each stage of the project life span. It provides quality, quick
and accurate execution of a wide range of different tasks including modeling, simulations, coordination,
and documentation.
This paper describes using of BIM models to simulate the timeline of the construction progress. It describes
the BIM 4D method - how a smart 3D model from an intelligent substation BIM software can be used to
simulate and check the construction progress. With the BIM 4D method, it is possible to visualize different
phases of the construction and define the necessary tasks and their duration on a timeline. With this BIM
4D method, different types of substation projects like extension projects or upgrades of already existing
substations can be handled and simulated comfortably.

KEYWORDS
Substation design, BIM 4D, 3D, substation BIM, construction progress, simulation, visualization

Page 277 of 284


1. INTRODUCTION
The transition to Building Information Modeling (BIM) presents a similar challenge to the engineers as it
did for transition to Computer Aided Design (CAD) in the past. The power industry is looking for the
product - with capabilities beyond that of existing CAD solutions - that allows for BIM solutions. The
implementation of BIM includes new investments in software and introducing different approaches to
project management. The BIM models of Air Insulated Substations (AIS) projects can then be further
developed by using, not only 3D models, but by also using the BIM 4D method. BIM 4D gives the
possibility to visualize and simulate the different phases of the construction progress and define the
necessary tasks and their duration on a timeline.

2. BIM
BIM is a design process that relies on an intelligent model as the basis for design, simulation and
collaboration at each stage of the project life span. It provides quality, quick and accurate execution of a
wide range of tasks including modeling, simulations, coordination, and documentation. [1] The BIM
workflow and philosophy – in the substation design context - means using one integrated information data
model in all the disciplines that are involved in the process. This means all included team members of the
substation design department, the building modeling, the building service engineering, the steel
construction, the terrain modeling and the electrical design work team. [2]
The core idea of BIM systems is a 3D model. In additional to the 3D visualization of the model (see
Figure 1), the model contains also a lot of other information e.g. quantities of materials, object properties as
shown in Figure 2 as well as other information that is necessary for the project documentation and
construction. If changes are made to the objects in an intelligent 3D model, these changes are reflected in
every element of the design where this object is used. With this, the designers can work more collaboratively
in one model. [3]

Figure 1. 3D substation model

Page 278 of 284


Figure 2. BIM 3D model of disconnector with linked information

3. BIM 4D – TIME DIMENSION


BIM, as a process method, is still in the development phase, so definitions are constantly being revised and
extended. One of those definitions is BIM 4D that refers to the time component.
BIM 4D modeling is a term related to the linking of the 3D model to the timeline of the construction progress
[2]. BIM 4D is used e.g. in the upgrading of existing substation models to simulate the different upgrading
or refurbishment construction phases. The 4D simulation shows the construction activities in relation to the
time in 3D.

The timeline itself defines all the tasks. A timeline, as is well known from Gantt charts, illustrates a project
schedule as well as the start and finish dates of the elements of a project. The construction timeline can
therefore be defined for new substation projects (greenfield projects) as well as for extensions or upgrades
of existing objects (brownfield projects) - (see an example for a substation construction timeline in Figure 3).
Using only the traditional Gantt chart is difficult and time consuming – since that would make it necessary
to develop alternative schedules and to identify challenges and find the best way to achieve the best
construction progress solutions.

Page 279 of 284


Figure 3. Example of Gantt chart (timeline with tasks)

However, to handle the challenge of the replacement of equipment in substations or extensions of the
substations the following points need to be considered: “1) Construction has to be done around energized
equipment; 2) Offline time needs to be kept at a minimum; 3) Increase in performance and 4) Integration of
new technologies in to the existing state. The fourth point especially refers to older substations whose
electrical components do not comply with today´s standards or are no longer manufactured. Usually, in this
case, all electrical components should be replaced.
In order to perform some of the before-mentioned actions it is necessary to define the time intervals in order
to define de-energized state. Also, it is necessary to define switching operations of circuit
breakers/disconnecting switches for the purpose of physical enabling of de-energized state on the part of the
substation of interest. So the challenge is always to define the best way to handle the project to save time
and costs.” [2]. For these challenges, BIM 4D offers the perfect method to simulate and analyze the critical
time intervals.

4. BIM 4D – SIMULATION
As described before, BIM 4D enables designers in different disciplines to visualize the progress of
construction activities throughout the lifetime of the project. This approach has the very high potential to
improve project management and shorten the delivery times of construction projects, as well as being
scalable to any project size. The process of creating 4D models (BIM 4D) is be simple using a previously
created BIM 3D model - as smart models with all the necessary objects and project information. Those
objects or groups of objects in a BIM 3D model must then be linked to the tasks (construction activities) in
the predefined timeline. A simplified schematic representation of the 4D simulation process is illustrated in
Figure 4.

Page 280 of 284


Figure 4. Simplified schematic representation of the 4D simulation process

With a substation BIM based software (e.g. like primtech 3d) the foundation of a BIM 4D simulation is set.
A specialized 3D software export offers an optimized BIM collaboration with Autodesk Navisworks by
transferring - within the export - the BIM 3D substation structure (part stations, bays, modules, assemblies,
project symbols, etc.). The structure of such a BIM 3D substation model is described in a previously
published IEEE paper, [3]. In addition to the structure, it is necessary to transfer all the object types as well.
To prepare such a BIM 3D model, a 3D export (including layer conversion if necessary) is carried out and
then imported into Autodesk Navisworks. The next step - in Autodesk Navisworks - is to import the
predefined project plan (or newly created) from e.g. Microsoft Project Management to the TimeLiner in
Navisworks and to define Search Sets for each object. The final step is to attach the Search Set to the tasks
from the project plan. A BIM 4D simulation picture of such a workflow is shown in Figure 5.

Page 281 of 284


Figure 5. BIM 4D simulation in Autodesk Navisworks

As mentioned, the following actions are needed for the creation of the BIM 4D substation construction
model (see Figure 4 and 5):

1) Creation and export of a BIM 3D model with linked information in a substation BIM software
2) Definition of a timeline with tasks (Gantt chart) (see Figure 3)
3) Import of BIM 3D model in the BIM 4D simulation software
4) Linking of the intelligent CAD objects or structures to certain tasks.

CONCLUSION
As mentioned, BIM 4D offers the substation project team the possibility to 1) simulate the substation
construction progress, 2) test different possibilities to construction phases, 3) keep the offline time needs at
a minimum - through simulation, 4) control the time management and logistic of the substation construction
progress.

To simulate BIM 4D, a smart BIM substation model with linked information is needed - as is created in
primtech 3d – as well as the definition of construction phases and tasks. Finally, the smart 3D substation
model with the timeline and tasks can then be simulated and visualized in a simulation software.

Page 282 of 284


BIBLIOGRAPHY

[1] C. Eastman, P. Teicholz, R. Sacks, K. Liston, “BIM Handbook, A Guide to Building Information,
Modeling for Owners, Managers, Designers, Engineers, and Contractors” (Ed. 2. Hoboken, N.J.: John Wiley
& Sons, 2011).

[2] S. Heuser, W. Eyrich, M. Kokorus, “Smart substation information model - challenges in the
development of a Building Information Modeling (BIM) based software for substation design”, (CIGRÉ
Mexico International Colloquium, Mexico City, Oct. 2016).

[3] M. Kokorus, W. Eyrich, R. Zacharias “Innovative Approach to the Substation Design using
Building Information Modeling (BIM) Technology” (IEEE/PES May 2016, pages 1ff).

BIOGRAPHY

Wolfgang Eyrich is managing director and head of the software development department of the company -
Entegra eyrich + appel gmbh. He founded Entegra in 1991 and since then has further built a profound
expertise in the field of substation design while working together with a wide range of customers including
utilities, manufacturers and engineering companies. Furthermore, he has registered several patents. His main
areas of research are substations, optimization of substation design processes and integrated calculations.
He has published several technical papers.

Page 283 of 284

S-ar putea să vă placă și