ID Task Name Duration Start Finish Resou % Notes

NamesComple Qtr 2, 2018


Apr May Jun
1 GE New Tank Layout at Cleaning Shop 0%
2 Preliminary Works 11 days Mon 02/04/18 Mon 16/04/18 0%
3 Domestic Water Supply to Line I & Line II 5 days Mon 02/04/18 Fri 06/04/18 EE 0% EE
4 CL24 & CL25 Overflow Pipe Modification 1 day Mon 09/04/18 Tue 10/04/18 EE 0% EE
5 Install CL27 heater element 1 day Mon 09/04/18 Tue 10/04/18 EE2 0% EE2
6 Two (2) units Air Regulator 1 day Thu 12/04/18 Thu 12/04/18 EE 0% EE
7 Two (2) units Wall Mounted Industrial Power Socket 2 days Wed 11/04/18 Thu 12/04/18 EE2 0% EE2
8 Install Hoist Crane 1 day Thu 12/04/18 Thu 12/04/18 ARG 0% ARG
9 Testing & Commissioning (Progressive) 0%
10 New Line II Arrangement 15 days Mon 23/04/18 Mon 14/05/18 0% (Tentative, subject to Crane PMA)
11 Dismantle CL20, CL22, CL23 wiring, piping, ducting 3 days Mon 23/04/18 Wed 25/04/18 EE 0% EE
12 Install CL19 heater element 1 day Thu 26/04/18 Thu 26/04/18 EE2 0% EE2
13 Dismantle CL10, CL11, CL12 wiring, piping, ducting 3 days Thu 26/04/18 Mon 30/04/18 EE 0% EE
14 Dismantle CL1 wiring, piping, ducting 2 days Mon 30/04/18 Wed 02/05/18 EE2 0% EE2
15 Hoist out CL20, CL21, CL22, CL23 for scrap 2 days Tue 01/05/18 Wed 02/05/18 EE 0% EE
16 Hoist out CL10, CL11, CL12 & position in Line II 2 days Thu 03/05/18 Fri 04/05/18 EE 0% EE
17 Hoist out CL1 & position in Line II 1 day Mon 07/05/18 Mon 07/05/18 EE 0% EE
18 Reconnect CL1, CL10, CL11, CL12 wiring, piping, ducting 5 days Mon 07/05/18 Fri 11/05/18 EE2 0% EE2
19 CL12 Piping Connection 1 day Mon 14/05/18 Mon 14/05/18 EE2 0% EE2
20 Testing & Commissioning (Progressive) 0% Quality Check 1
21 New Line I Arrangement 14 days Mon 14/05/18 Fri 01/06/18 0% (Tentative, subject to Crane PMA)
22 Dismantle CL32, CL33, CL34 wiring, piping, ducting 3 days Mon 14/05/18 Wed 16/05/18 EE 0% EE
23 Hoist out CL32 for scrap 1 day Thu 17/05/18 Thu 17/05/18 EE 0% EE
24 Install CL31 heater element 1 day Fri 18/05/18 Fri 18/05/18 EE2 0% EE2
25 Modify existing steel bar floor grating 1 day Fri 18/05/18 Fri 18/05/18 EE 0% EE
26 Modify existing 2" piping 2 days Mon 21/05/18 Tue 22/05/18 EE2 0% EE2
27 Install SS304 hollow section support 1 day Tue 22/05/18 Tue 22/05/18 EE 0% EE
28 Reposition CL33, CL34 2 days Thu 24/05/18 Fri 25/05/18 EE 0% EE
29 Dismantle CL18 wiring, piping, ducting 2 days Wed 23/05/18 Thu 24/05/18 EE2 0% EE2
30 Hoist out CL18 & position in Line I 1 day Mon 28/05/18 Mon 28/05/18 EE 0% EE
31 Install CL18 heater element 1 day Tue 29/05/18 Tue 29/05/18 EE2 0% EE2
32 Reconnect CL18, CL33, CL34 wiring, piping, ducting 3 days Wed 30/05/18 Fri 01/06/18 EE 0% EE
33 Testing & Commissioning (Progressive) 0% Quality Check 2
34 Remaining Works after Tank Relocation 5 days Mon 04/06/18 Fri 08/06/18 0%
35 Install CL34 heater element 1 day Mon 04/06/18 Mon 04/06/18 EE 0% EE
36 Install CL10 heater element 1 day Mon 04/06/18 Mon 04/06/18 EE2 0% EE2
37 Conductivity Meter c/w Beacon Light 1 day Tue 05/06/18 Tue 05/06/18 EE 0% EE
38 Install five (5) unit Countdown Timer c/w Yellow beacon light  2 days Tue 05/06/18 Wed 06/06/18 EE2 0% EE2
at CL12, CL24, CL25, CL28, CL33
39 Testing & Commissioning 0% Quality Check 3

Task Project Summary Manual Task Start-only Deadline

Project: GE_Tank Relocation_Sc Split Inactive Task Duration-only Finish-only Progress


Date: Fri 13/04/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

E/GE/806/P/S04(E) Page 1 Prepared by: Z. W. Leong