2 MATERIAL APPROVAL FIRE ALARM APPROVED BY CEG 3 METHOD STATEMENT REVISE & RESUBMIT CEG UNDER COMPLIANCE AIGQ 4 HSE PLAN REVISE & RESUBMIT CEG UNDER COMPLIANCE AIGQ 5 QA/QC PLAN REVISE & RESUBMIT CEG UNDER COMPLIANCE AIGQ 3 SHOP DRAWING FIRE FIGHTING APPROVED BY CEG SUBMITTED TO GDI FOR QP SUBMISSION -30.04.2018 AWAITING APPROVAL 4 SHOP DRAWING FIRE ALARM APPROVED BY CEG SUBMITTED TO GDI FOR QP SUBMISSION -30.04.2018 AWAITING APPROVAL 5 INSTALLTION, T&C AWAITING DRAWING APPROVAL TO PROCEED